Case T-544/15: Order of the General Court of 13 September 2016 — Terna v Commission (Action for annulment — Union list of projects of common interest — EU financial aid in two projects in the area of trans-European energy networks — Reduction of the financial aid initially granted following an audit — Preparatory measure — Measure not open to challenge — Inadmissibility)
Case T-544/15: Order of the General Court of 13 September 2016 — Terna v Commission (Action for annulment — Union list of projects of common interest — EU financial aid in two projects in the area of trans-European energy networks — Reduction of the financial aid initially granted following an audit — Preparatory measure — Measure not open to challenge — Inadmissibility)
Case T-544/15: Order of the General Court of 13 September 2016 — Terna v Commission (Action for annulment — Union list of projects of common interest — EU financial aid in two projects in the area of trans-European energy networks — Reduction of the financial aid initially granted following an audit — Preparatory measure — Measure not open to challenge — Inadmissibility)
IO C 402, 31.10.2016, p. 46–46
(BG, ES, CS, DA, DE, ET, EL, EN, FR, HR, IT, LV, LT, HU, MT, NL, PL, PT, RO, SK, SL, FI, SV)
31.10.2016 |
EN |
Official Journal of the European Union |
C 402/46 |
Order of the General Court of 13 September 2016 — Terna v Commission
(Case T-544/15) (1)
((Action for annulment - Union list of projects of common interest - EU financial aid in two projects in the area of trans-European energy networks - Reduction of the financial aid initially granted following an audit - Preparatory measure - Measure not open to challenge - Inadmissibility))
(2016/C 402/54)
Language of the case: Italian
Parties
Applicant: Terna — Rete elettrica nazionale SpA (Rome, Italy) (represented by: A. Police, L. Di Via, F. Covone and D. Carria, lawyers)
Defendant: European Commission (represented by: O. Beynet, L. Di Paolo and A. Tokár, acting as Agents)
Re:
Application based on Article 263 TFEU and seeking annulment of the decision which contained the Commission’s letter, of 6 July 2015, reducing the financial aid initially granted in the context of two projects (projects 2009-E255/09-ENER/09/TEN-E-S12.564583 and 2007-E 221/07/2007-TREN/07TEN-E-S07.91403) in the area of trans-European energy networks.
Operative part of the order
1. |
The action is dismissed. |
2. |
Terna — Rete elettrica nazionale SpA shall pay the costs. |