Document 62011CA0231
Joined Cases C-231/11 P to C-233/11 P: Judgment of the Court (Fourth Chamber) of 10 April 2014 — European Commission v Siemens AG Österreich, VA Tech Transmission & Distribution GmbH & Co. KEG, Siemens Transmission & Distribution Ltd, Siemens Transmission & Distribution SA, Nuova Magrini Galileo SpA (Appeals — Competition — Agreements, decisions and concerted practices — Market in gas insulated switchgear projects — Joint and several liability for payment of the fine — Concept of an ‘undertaking’ — Principle of personal liability and the principle that the penalty must be specific to the offender and the offence — Unlimited jurisdiction of the General Court — The ultra petita rule — Principles of proportionality and equal treatment)
Asuntos acumulados C-231/11 P a C-233/11 P: Sentencia del Tribunal de Justicia (Sala Cuarta) de 10 de abril de 2014 — Comisión Europea/Siemens AG Österreich, VA Tech Transmission & Distribution GmbH & Co. KEG, Siemens Transmission & Distribution Ltd, Siemens Transmission & Distribution SA, Nuova Magrini Galileo SpA (Recurso de casación — Competencia — Práctica colusoria — Mercado de los proyectos relativos a conmutadores con aislamiento de gas — Responsabilidad solidaria para el pago de la multa — Concepto de empresa — Principios de responsabilidad personal y de individualización de las penas y de las sanciones — Competencia jurisdiccional plena del Tribunal General — Principio ne ultra petita — Principios de proporcionalidad y de igualdad de trato)
Asuntos acumulados C-231/11 P a C-233/11 P: Sentencia del Tribunal de Justicia (Sala Cuarta) de 10 de abril de 2014 — Comisión Europea/Siemens AG Österreich, VA Tech Transmission & Distribution GmbH & Co. KEG, Siemens Transmission & Distribution Ltd, Siemens Transmission & Distribution SA, Nuova Magrini Galileo SpA (Recurso de casación — Competencia — Práctica colusoria — Mercado de los proyectos relativos a conmutadores con aislamiento de gas — Responsabilidad solidaria para el pago de la multa — Concepto de empresa — Principios de responsabilidad personal y de individualización de las penas y de las sanciones — Competencia jurisdiccional plena del Tribunal General — Principio ne ultra petita — Principios de proporcionalidad y de igualdad de trato)
DO C 175 de 10.6.2014, p. 2–3
(BG, ES, CS, DA, DE, ET, EL, EN, FR, HR, IT, LV, LT, HU, MT, NL, PL, PT, RO, SK, SL, FI, SV)
10.6.2014 |
ES |
Diario Oficial de la Unión Europea |
C 175/2 |
Sentencia del Tribunal de Justicia (Sala Cuarta) de 10 de abril de 2014 — Comisión Europea/Siemens AG Österreich, VA Tech Transmission & Distribution GmbH & Co. KEG, Siemens Transmission & Distribution Ltd, Siemens Transmission & Distribution SA, Nuova Magrini Galileo SpA
(Asuntos acumulados C-231/11 P a C-233/11 P) (1)
((Recurso de casación - Competencia - Práctica colusoria - Mercado de los proyectos relativos a conmutadores con aislamiento de gas - Responsabilidad solidaria para el pago de la multa - Concepto de empresa - Principios de responsabilidad personal y de individualización de las penas y de las sanciones - Competencia jurisdiccional plena del Tribunal General - Principio ne ultra petita - Principios de proporcionalidad y de igualdad de trato))
2014/C 175/02
Lengua de procedimiento: alemán
Partes
Recurrentes: Comisión Europea (representantes: A. Antoniadis, R. Sauer y N. von Lingen, agentes) (C-231/11 P), Siemens Transmission & Distribution Ltd (C-232/11 P), Siemens Transmission & Distribution SA, Nuova Magrini Galileo SpA (C-233/11 P) (representantes: H. Wollmann y F. Urlesberger, Rechtsanwälte)
Otras partes en el procedimiento: Siemens AG Österreich, VA Tech Transmission & Distribution GmbH & Co. KEG, Siemens Transmission & Distribution Ltd, Siemens Transmission & Distribution SA, Nuova Magrini Galileo SpA (representantes: H. Wollmann y F. Urlesberger, Rechtsanwälte), Comisión Europea (representantes: A. Antoniadis, R. Sauer y N. von Lingen, agentes)
Objeto
Recursos de casación interpuestos contra la sentencia del Tribunal General (Sala Segunda) de 3 de marzo de 2011, Siemens Österreich y otros/Comisión (asuntos acumulados T-122/07 a T-124/07), mediante los que se solicita, con carácter principal, la anulación parcial de la Decisión C(2006) 6762 final de la Comisión, de 24 de enero de 2007, relativa a un procedimiento de aplicación de los artículos 81 CE y 53 del Acuerdo EEE (asunto COMP/F/38.899 — Conmutadores con aislamiento de gas), y, con carácter subsidiario, la reducción de la multa impuesta a las demandantes.
Fallo
1) |
Anular el punto 2 del fallo de la sentencia del Tribunal General de la Unión Europea de 3 de marzo de 2011, Siemens Österreich y otros/Comisión (T-122/07 a T-124/07), en la medida en que anula el artículo 2, letras j) y k), de la Decisión C(2006) 6762 final de la Comisión, de 24 de enero de 2007, relativa a un procedimiento de conformidad con el artículo [81 CE] y con el artículo 53 del Acuerdo EEE (asunto COMP/F/38.899 — Conmutadores con aislamiento de gas). |
2) |
Anular el punto 3, primer guión, del fallo de la sentencia del Tribunal General de 3 de marzo de 2011, Siemens Österreich y otros/Comisión (T-122/07 a T-124/07). |
3) |
Anular el punto 3, guiones segundo a cuarto, del fallo de la sentencia del Tribunal General de 3 de marzo de 2011, Siemens Österreich y otros/Comisión (T-122/07 a T-124/07) en la medida en que implica la fijación de las cuotas de las demandantes en primera instancia de los importes de la multa a los que fueron condenadas solidariamente. |
4) |
Desestimar los recursos de casación en todo lo demás. |
5) |
Condenar a Siemens AG Österreich, VA Tech Transmission & Distribution GmbH & Co. KEG, Siemens Transmission & Distribution Ltd, Siemens Transmission & Distribution SA y Nuova Magrini Galileo SpA a cargar con las costas del recurso de casación en el asunto C-231/11 P. |
6) |
Condenar a Siemens Transmission & Distribution Ltd a cargar con las costas del recurso de casación en el asunto C-232/11 P. |
7) |
Condenar a la Comisión Europea a cargar con las costas del recurso de casación en el asunto C-233/11 P. |
8) |
Se mantiene el reparto de las costas relativas al procedimiento de primera instancia establecido en los puntos 5 a 7 del fallo de la sentencia del Tribunal General de 3 de marzo de 2011, Siemens Österreich y otros/Comisión (T-122/07 a T-124/07). |