Choose the experimental features you want to try

This document is an excerpt from the EUR-Lex website

Document 62017TB0423

    Case T-423/17 R: Order of the President of the General Court of 23 November 2017 — Nexans France and Nexans v Commission (Interim relief — Competition — Power cables — Rejection of the request for confidential treatment of certain information contained in a decision establishing an infringement of Article 101 TFEU — Application for interim measures — Lack of urgency)

    OJ C 22, 22.1.2018, p. 41–42 (BG, ES, CS, DA, DE, ET, EL, EN, FR, HR, IT, LV, LT, HU, MT, NL, PL, PT, RO, SK, SL, FI, SV)

    22.1.2018   

    EN

    Official Journal of the European Union

    C 22/41


    Order of the President of the General Court of 23 November 2017 — Nexans France and Nexans v Commission

    (Case T-423/17 R)

    ((Interim relief - Competition - Power cables - Rejection of the request for confidential treatment of certain information contained in a decision establishing an infringement of Article 101 TFEU - Application for interim measures - Lack of urgency))

    (2018/C 022/57)

    Language of the case: English

    Parties

    Applicants: Nexans France (Courbevoie, France), Nexans (Courbevoie) (represented by: G. Forwood, A. Rogers, A. Oh and M. Powell, lawyers)

    Defendant: European Commission (represented by: H. van Vliet, G. Meessen and I. Zaloguin, acting as Agents)

    Re:

    Application based on Articles 278 TFEU and 279 TFEU, seeking, first, a suspension of operation of Commission Decision C(2017) 3051 final of 2 May 2017 relating to a request for confidential treatment (Case COMP/AT.39610 — Power Cables) in so far as that request is refused in respect of the material seized from the applicants and another economic operator and, second, an order requiring the Commission to refrain from publishing a version of its Decision C(2014) 2139 final of 2 April 2014 (Case COMP/AT.39610 — Power Cables), which contains that material.

    Operative part of the order

    1.

    The application for interim measures is rejected.

    2.

    The order of 12 July 2017, Nexans France and Nexans v Commission (T-423/17 R) is set aside.

    3.

    The costs are reserved.


    Top