This document is an excerpt from the EUR-Lex website
Document 62008TO0401
Order of the President of the Court of First Instance of 14 November 2008.#Säveltäjäin Tekijänoikeustoimisto Teosto ry v Commission of the European Communities.#Interim measures - Commission decision ordering the termination of a concerted practice in relation to the collective protection of copyright - Application for suspension of operation of a measure - No urgency.#Case T-401/08 R.
Order of the President of the Court of First Instance of 14 November 2008.
Säveltäjäin Tekijänoikeustoimisto Teosto ry v Commission of the European Communities.
Interim measures - Commission decision ordering the termination of a concerted practice in relation to the collective protection of copyright - Application for suspension of operation of a measure - No urgency.
Case T-401/08 R.
Order of the President of the Court of First Instance of 14 November 2008.
Säveltäjäin Tekijänoikeustoimisto Teosto ry v Commission of the European Communities.
Interim measures - Commission decision ordering the termination of a concerted practice in relation to the collective protection of copyright - Application for suspension of operation of a measure - No urgency.
Case T-401/08 R.
European Court Reports 2008 II-00267*
ECLI identifier: ECLI:EU:T:2008:501
Order of the President of the Court of First Instance of 14 November 2008 – Säveltäjäin Tekijänoikeustoimisto Teosto v Commission
(Case T-401/08 R)
Interim measures – Commission decision ordering the termination of a concerted practice in relation to the collective protection of copyright – Application for suspension of operation of a measure – No urgency
1. Applications for interim measures – Suspension of operation of a measure – Interim measures – Conditions for granting – ‘Prima facie case’ – Urgency – Cumulative nature – Order of examination and method of verification (Arts 225(1) EC, 242 EC and 243 EC; Rules of Procedure of the Court of First Instance, Art. 104(2)) (see paras 21-24)
2. Applications for interim measures – Suspension of operation of a measure – Interim measures – Conditions for granting – Urgency – Serious and irreparable damage – Financial loss (Arts 242 EC and 243 EC; Rules of Procedure of the Court of First Instance, Art. 104(2)) (see paras 34-37, 40)
Re:
APPLICATION for suspension of the operation of Article 3 in conjunction with Article 4(2) and (3) of Decision C(2008) 3435 final of the Commission of 16 July 2008 relating to a proceeding pursuant to Article 81 EC and Article 53 of the EEA Agreement (Case COMP/C2/38.698 – CISAC), to the extent that the applicant is affected. |
Operative part
The Court:
1. |
Dismisses the application for interim measures; |
2. |
Reserves the costs. |