This document is an excerpt from the EUR-Lex website
Document 62008TO0373
Order of the General Court (Seventh Chamber) of 24 May 2011. # Nuova Agricast Srl v European Commission. # Non-contractual liability - Aid scheme under Italian legislation - Scheme declared compatible with the common market - Transitional measure - Exclusion of certain undertakings - Principle of the protection of legitimate expectations - Sufficiently serious breach of a rule of law conferring rights on individuals - None - Clear lack of jurisdiction - Action manifestly devoid of any basis in law. # Case T-373/08.
Order of the General Court (Seventh Chamber) of 24 May 2011.
Nuova Agricast Srl v European Commission.
Non-contractual liability - Aid scheme under Italian legislation - Scheme declared compatible with the common market - Transitional measure - Exclusion of certain undertakings - Principle of the protection of legitimate expectations - Sufficiently serious breach of a rule of law conferring rights on individuals - None - Clear lack of jurisdiction - Action manifestly devoid of any basis in law.
Case T-373/08.
Order of the General Court (Seventh Chamber) of 24 May 2011.
Nuova Agricast Srl v European Commission.
Non-contractual liability - Aid scheme under Italian legislation - Scheme declared compatible with the common market - Transitional measure - Exclusion of certain undertakings - Principle of the protection of legitimate expectations - Sufficiently serious breach of a rule of law conferring rights on individuals - None - Clear lack of jurisdiction - Action manifestly devoid of any basis in law.
Case T-373/08.
European Court Reports 2011 II-00147*
ECLI identifier: ECLI:EU:T:2011:237
Order of the General Court (Seventh Chamber) of 24 May 2011 – Nuova Agricast v Commission
(Case T-373/08)
Non-contractual liability – Aid scheme under Italian legislation – Scheme declared compatible with the common market – Transitional measure – Exclusion of certain undertakings – Principle of the protection of legitimate expectations – Sufficiently serious breach of a rule of law conferring rights on individuals – None – Clear lack of jurisdiction – Action manifestly devoid of any basis in law
1. Non-contractual liability – Conditions – Unlawfulness – Damage – Causal link – One of the conditions not satisfied – Claim for compensation dismissed in its entirety (Art. 288, second para., EC) (see paras 50, 92-93)
2. Non-contractual liability – Conditions – Sufficiently serious breach of a rule of law intended to confer rights on individuals – Discretion of the institution when adopting the measure – Need to be taken into consideration when examining liability (Art. 288, second para., EC) (see para. 72)
3. State aid – General aid scheme approved by the Commission – Identification of individual aids falling within the temporal scope of that scheme – Date of the legally binding measure requiring the competent national authority to grant the aid – Strict interpretation of derogations from the prohibition of State aid precluding the extension of the temporal scope of an approved aid scheme (Art. 87 EC) (see paras 76-78)
4. State aid – Commission decision not to raise objections to an aid scheme – Limitation of the temporal effects of the decision – Breach of principle of the protection of legitimate expectations – None – Breach of principle of equal treatment – None (Art. 87 EC) (see paras 84, 88)
Re:
ACTION for non-contractual liability seeking compensation for damage allegedly suffered by the applicant as a result of the Commission’s adopting the decision of 12 July 2000 not to raise objections to a State aid scheme in the form of aid for investment in disadvantaged regions of Italy (Aid No 715/99 – Italy (SG 2000 D/105754) and by reason of the Commission’s conduct prior to the adoption of that decision. |
Operative part
1. |
The action is dismissed. |
2. |
Nuova Agricast Srl is ordered to pay the costs. |