Choose the experimental features you want to try

This document is an excerpt from the EUR-Lex website

Document 62023TA1033

Case T-1033/23: Judgment of the General Court of 5 February 2025 – Poland v Commission (Law governing the institutions – Partial failure to comply with an order of the Court of Justice imposing interim measures in the context of an action for failure to fulfil obligations – Periodic penalty payment – Recovery of amounts receivable by offsetting – Article 101(1) and Article 102 of Regulation (EU, Euratom) 2018/1046 – Jurisdiction of the General Court)

OJ C, C/2025/1643, 24.3.2025, ELI: http://data.europa.eu/eli/C/2025/1643/oj (BG, ES, CS, DA, DE, ET, EL, EN, FR, GA, HR, IT, LV, LT, HU, MT, NL, PL, PT, RO, SK, SL, FI, SV)

ELI: http://data.europa.eu/eli/C/2025/1643/oj

European flag

Official Journal
of the European Union

EN

C series


C/2025/1643

24.3.2025

Judgment of the General Court of 5 February 2025 – Poland v Commission

(Case T-1033/23)  (1)

(Law governing the institutions - Partial failure to comply with an order of the Court of Justice imposing interim measures in the context of an action for failure to fulfil obligations - Periodic penalty payment - Recovery of amounts receivable by offsetting - Article 101(1) and Article 102 of Regulation (EU, Euratom) 2018/1046 - Jurisdiction of the General Court)

(C/2025/1643)

Language of the case: Polish

Parties

Applicant: Republic of Poland (represented by: B. Majczyna and S. Żyrek, Agents)

Defendant: European Commission (represented by: P. Van Nuffel, O. Verheecke and K. Herrmann, Agents)

Re:

By its action under Article 263 TFEU, the Republic of Poland seeks the annulment of three decisions of the European Commission, contained in the two letters of 4 August 2023 and in the letter of 9 August 2023, to recover by way of offsetting the amounts payable by the Republic of Poland in respect of the daily penalty payment ordered by the Vice-President of the Court of Justice in the order of 27 October 2021, Commission v Poland (C-204/21 R, EU:C:2021:878), for the periods between 29 October and 31 December 2022, between 1 January and 28 February 2023 and between 1 March and 4 June 2023, respectively.

Operative part of the judgment

The Court:

1.

Dismisses the action;

2.

Orders the Republic of Poland to pay the costs.