Corrigendum to Commission Implementing Decision 2012/119/EU of 10 February 2012 laying down rules concerning guidance on the collection of data and on the drawing up of BAT reference documents and on their quality assurance referred to in Directive 2010/75/EU of the European Parliament and of the Council on industrial emissions ( OJ L 63, 2.3.2012 )
Corrigendum to Commission Implementing Decision 2012/119/EU of 10 February 2012 laying down rules concerning guidance on the collection of data and on the drawing up of BAT reference documents and on their quality assurance referred to in Directive 2010/75/EU of the European Parliament and of the Council on industrial emissions ( OJ L 63, 2.3.2012 )
Corrigendum to Commission Implementing Decision 2012/119/EU of 10 February 2012 laying down rules concerning guidance on the collection of data and on the drawing up of BAT reference documents and on their quality assurance referred to in Directive 2010/75/EU of the European Parliament and of the Council on industrial emissions ( OJ L 63, 2.3.2012 )
OL L 328, 2012 11 28, p. 27–28
(BG, ES, CS, EN, PT)
ELI: http://data.europa.eu/eli/dec_impl/2012/119/corrigendum/2012-11-28/oj
28.11.2012 |
EN |
Official Journal of the European Union |
L 328/27 |
Corrigendum to Commission Implementing Decision 2012/119/EU of 10 February 2012 laying down rules concerning guidance on the collection of data and on the drawing up of BAT reference documents and on their quality assurance referred to in Directive 2010/75/EU of the European Parliament and of the Council on industrial emissions
( Official Journal of the European Union L 63 of 2 March 2012 )
On page 39, Appendix 2, the workflow should read as follows:
Typical workflow for the drawing up and review of BREFs
New BREF or BREF review with major scope expansion
Activation call of TWG (new BREF)
or
TWG reactivation and call for ‘wishes’ (BREF review)
3 months (new BREF)
5 months (BREF review)
TWG kick-off meeting
6 months
Information
6 months (new BREF)
4 – 6 months (BREF review)
RAI
Draft 1 (D1)
2 – 3 months
TWG comments
RAI
5 – 7 months
(revised) draft
BAT conclusions
Draft 2 (D2)
RAI
2 – 3 months
TWG comments
RAI
3 – 5 months
Chap. 3, 4, 5
Final TWG meeting
4 months
Final draft
Total: 31 – 39 months
1st review of a BREF without major scope expansion
TWG reactivation and call for ‘wishes’
5 months
TWG kick-off meeting
6 months
Information
4 – 6 months
RAI
Draft 1 (D1)
(revised) draft
BAT conclusions
RAI
2 – 3 months
TWG comments
Draft 2?
yes
RAI
3 – 7 months
no
Draft 2 (D2)
2 – 3 months
3 – 5 months
TWG comments
3 – 5 months
RAI
Chap. 3, 4, 5
Final TWG meeting
4 months
Final draft
Total: 29 – 39 months (with D2)
24 – 29 months (without D2)
subsequent review of a BREF without major scope expansion
TWG reactivation and call for ‘wishes’
5 months
TWG kick-off meeting
6 months
Information
RAI
4 – 6 months
Draft 1 (D1)
(revised) draft
BAT conclusions
RAI
2 – 3 months
TWG comments
RAI
3 – 5 months
Chap. 3, 4, 5
Final TWG meeting
4 months
Final draft
Total: 24 – 29 months
Rai: request for additional information from the EIPPCB to the TWG (if this is considered necessary)
Chap. 3, 4, 5: Update of at least Chapters 3, 4 and 5