Document 62006CJ0480

Summary of the Judgment

Keywords
Summary

Keywords

Approximation of laws – Procedures for the award of public service contracts – Directive 92/50 – Scope

(Council Directive 92/50, Art. 1)

Summary

A contract which forms both the basis and the legal framework for the future construction and operation of a facility intended to perform a public service, namely thermal incineration of waste, in so far as it was concluded solely by public authorities, without the participation of any private party, and does not provide for or prejudice the award of any contracts that may be necessary in respect of the construction and operation of the waste treatment facility does not fall within the scope of application of Directive 92/50 relating to the coordination of procedures for the award of public service contracts.

A public authority has the possibility of performing the public interest tasks conferred on it either by using its own resources or in cooperation with other public authorities, without being obliged to call on outside entities not forming part of its own departments. In that connection, first, Community law does not require public authorities to use any particular legal form in order to carry out jointly their public service tasks. Secondly, such cooperation between public authorities does not undermine the principal objective of the Community rules on public procurement, that is, the free movement of services and the opening-up of undistorted competition in all the Member States, where implementation of that cooperation is governed solely by considerations and requirements relating to the pursuit of objectives in the public interest and the principle of equal treatment of the persons concerned, referred to in Directive 92/50, is respected, so that no private undertaking is placed in a position of advantage vis-à-vis competitors.

(see paras 44-45, 47)