Choose the experimental features you want to try

This document is an excerpt from the EUR-Lex website

Document 62014TA0475

    Case T-475/14: Judgment of the General Court of 12 July 2018 — Prysmian and Prysmian Cavi e Sistemi v Commission (Competition — Agreements, decisions and concerted practices — European market for power cables — Decision finding an infringement of Article 101 TFEU — Single and continuous infringement — Illegal nature of the inspection decision — Reasonable time — Principle of sound administration — Principle of personal responsibility — Joint and several liability for payment of the fine — Sufficient proof of the infringement — Duration of the infringement — Fines — Proportionality — Equal treatment — Unlimited jurisdiction)

    IO C 328, 17.9.2018, p. 40–41 (BG, ES, CS, DA, DE, ET, EL, EN, FR, HR, IT, LV, LT, HU, MT, NL, PL, PT, RO, SK, SL, FI, SV)

    17.9.2018   

    EN

    Official Journal of the European Union

    C 328/40


    Judgment of the General Court of 12 July 2018 — Prysmian and Prysmian Cavi e Sistemi v Commission

    (Case T-475/14) (1)

    ((Competition - Agreements, decisions and concerted practices - European market for power cables - Decision finding an infringement of Article 101 TFEU - Single and continuous infringement - Illegal nature of the inspection decision - Reasonable time - Principle of sound administration - Principle of personal responsibility - Joint and several liability for payment of the fine - Sufficient proof of the infringement - Duration of the infringement - Fines - Proportionality - Equal treatment - Unlimited jurisdiction))

    (2018/C 328/55)

    Language of the case: English

    Parties

    Applicants: Prysmian SpA (Milan, Italy) and Prysmian Cavi e Sistemi Srl (Milan) (represented by: C. Tesauro, F. Russo, L. Armati and C. Toniolo, lawyers)

    Defendant: European Commission (represented initially by: C. Giolito, L. Malferrari, P. Rossi and H. van Vliet, and subsequently by C. Giolito, P. Rossi and H. van Vliet, acting as Agents, and by S. Kingston, Barrister)

    Intervener in support of the applicants: The Goldman Sachs Group, Inc. (New York, New York, United States) (represented by: W. Deselaers, J. Koponen and A. Mangiaracina, lawyers)

    Intervener in support of the defendant: Pirelli & C. SpA (Milan) (represented by: M. Siragusa, G. Rizza, P. Ferrari, F. Moretti and A. Fava, lawyers)

    Re:

    Application under Article 263 TFEU for the annulment of Commission Decision C(2014) 2139 final of 2 April 2014 relating to a proceeding under Article 101 [TFEU] and Article 53 of the EEA Agreement (Case AT.39610 — Power cables) in so far as it concerns the applicants and, in the alternative, a reduction of the fine imposed on the applicants.

    Operative part of the judgment

    The Court:

    1.

    Dismisses the action;

    2.

    Orders Prysmian SpA and Prysmian Cavi e Sistemi Srl to bear their own costs and to pay those of the European Commission;

    3.

    Orders The Goldman Sachs Group, Inc. and Pirelli & C. SpA to bear their own costs.


    (1)  OJ C 315, 15.9.2014.


    Top