Keywords

Acts of the institutions – Directives – Implementation by Member States (Art. 249 EC) (see paras 9-10)

2. Member States – Obligations – Implementation of directives – Failure to fulfil obligations – National system pleaded as justification – Not permissible (Art. 226 EC) (see para. 13)

3. Actions for failure to fulfil obligations – Examination of merits by the Court – Situation on expiry of the period laid down in the reasoned opinion (Art. 226 EC) (see para. 14)

Subject of the case

Re:

Failure of a Member State to fulfil obligations – Failure to adopt, within the prescribed period, the provisions necessary to comply with Directive 2004/17/EC of the European Parliament and of the Council of 31 March 2004 coordinating the procurement procedures of entities operating in the water, energy, transport and postal services sectors (OJ 2004 L 134, p. 1).

Operative part

Operative part

The Court:

1. Declares that, by failing to adopt, within the prescribed period, the laws, regulations and administrative provisions necessary to comply with Directive 2004/17/EC of the European Parliament and of the Council of 31 March 2004 coordinating the procurement procedures of entities operating in the water, energy, transport and postal services sectors, the Grand Duchy of Luxembourg has failed to fulfil its obligations under that directive;

2. Orders the Grand Duchy of Luxembourg to pay the costs.