Summary of the Order

Keywords
Subject of the case
Operative part

Keywords

Non-contractual liability – Damage – Damage for which compensation due (Art. 288, second para., EC) (see paras 15-16)

2. Non-contractual liability – Conditions – Actual and certain damage – Burden of proof (Art. 288, second para., EC) (see paras 20, 27, 33, 36)

Subject of the case

Re:

ACTION for damages for the loss allegedly suffered by the applicant as a result of the decision of the Commission of 12 February 2004 rejecting the complaint brought by the applicant against Eurocontrol in respect of alleged infringements of the provisions of the EC Treaty on competition.

Operative part

Operative part

The Court:

1. Dismisses the action as in part manifestly inadmissible and in part manifestly without foundation in law;

2. Orders SELEX Sistemi Integrati Spa to pay the costs.