Choose the experimental features you want to try

This document is an excerpt from the EUR-Lex website

Document 52025SC0093

COMMISSION STAFF WORKING DOCUMENT Updated climate tracking and digital tagging of the Recovery and Resilience Plan of Slovakia Accompanying the document Proposal for a COUNCIL IMPLEMENTING DECISION amending Implementing Decision (EU) (ST 10156/21 INIT; ST 10156/21 ADD 1) on the approval of the assessment of the recovery and resilience plan for Slovakia

SWD/2025/93 final

Brussels, 11.4.2025

SWD(2025) 93 final

COMMISSION STAFF WORKING DOCUMENT

Updated climate tracking and digital tagging of the Recovery and Resilience Plan of Slovakia






Accompanying the document

Proposal for a COUNCIL IMPLEMENTING DECISION

amending Implementing Decision (EU) (ST 10156/21 INIT; ST 10156/21 ADD 1) on the approval of the assessment of the recovery and resilience plan for Slovakia




{COM(2025) 175 final}


Updated climate tracking and digital tagging of the Recovery and Resilience Plan of Slovakia

The table below presents the detailed application of the climate tracking and digital tagging methodologies set out respectively in Annex VI and VII to Regulation (EU) 2021/241 in the modified Slovak recovery and resilience plan.

Int. Field = intervention field.

Coeff. = Coefficient for the calculation of support to climate change objectives and to digital transition, on the basis of Annex VI and Annex VII of the RRF Regulation.

New or revised measures are highlighted to distinguish them from the unchanged measures in the RRP.

 

 

 

 

Climate 

Digital 

Measure/ Sub-Measure ID

Measure/Sub-Measure Name

Budget

(EUR million)

Int. Field

Coeff.%

Int. Field

Coeff.%

SK-C[C1]-I[I1.a] 

Investments in the construction of new sources of electricity from RES (a) 

102.74 

029  

100% 

 

 

SK-C[C1]-I[I1.b] 

Investments in the construction of new sources of electricity from RES – Administrative costs 

2.10 

029  

100% 

 

 

SK-C[C1]-I[I2.a] 

Investments in upgrading existing RES electricity sources (repowering) (a) 

34.74 

032 

100% 

 

 

SK-C[C1]-I[I2.b] 

Investments in upgrading existing RES electricity sources (repowering) - Administrative costs 

0.80 

032  

100% 

 

 

SK-C[C1]-I[I2.c] 

Modernising the existing renewable electricity sources (repowering) and tranformation to biomethane production - biomethane 

17.00 

030 

40% 

 

 

SK-C[C1]-I[I2.d] 

Modernising the existing renewable electricity sources (repowering) and tranformation to biomethane production - biomethane - Administartive costs 

0.46 

030 

40% 

 

 

SK-C[C1]-I[I3.a] 

Investments in increasing flexibility of electricity systems for greater RES integration - excluding Hydropower 

35.76 

033  

100% 

033 

40% 

SK-C[C1]-I[I3.b] 

Investments in increasing flexibility of electricity systems for greater RES integration - excluding Hydropower - Administrative costs 

1.00 

033 

100% 

033 

40% 

SK-C[C1]-I[I3.c] 

Investments in increasing flexibility of electricity systems for greater RES integration - Hydropower 

11.80 

032 

100% 

 

 

SK-C[C1]-I[I3.d] 

Investments in increasing flexibility of electricity systems for greater RES integration - Hydropower - Administrative costs 

0.26 

032 

100% 

 

 

SK-C[C2]-I[I1.a] 

Improving the energy efficiency of family homes 

424.46 

 

025bis 

100% 

 

 

SK-C[C2]-I[I1.b] 

Improving the energy efficiency of family homes - administrative cost 

22.12 

025bis 

100% 

 

 

SK-C[C2]-I[I2.a] 

Renovation of public historical and remembrance buildings 

173.19 

026bis 

100% 

 

 

SK-C[C2]-I[I2.b] 

Renovation of public historical and remembrance protected buildings - administrative cost 

5.38 

026bis  

100% 

 

 

SK-C[C2]-I[I2.c] 

Renovation of public historical and remembrance buildings - information campaign 

1.04 

 

026bis 

100% 

 

 

SK-C[C2]-R[R2] 

Increasing transparency and streamlining decisions of the Monuments Board of the Slovak Republic 

6.69 

025bis 

100% 

 

 

SK-C[C3]-I[I1.a] 

Development of low-carbon transport infrastructure: railway lines 

431.50 

069bis 

100% 

 

 

SK-C[C3]-I[I1.b] 

Development of low-carbon transport infrastructure:rail digitalisation 

96.34 

070 

40% 

070  

100% 

SK-C[C3]-I[I1.c] 

Development of low-carbon transport infrastructure:cycling paths 

85.04 

075 

100% 

 

 

SK-C[C3]-I[I1.d] 

Development of low-carbon transport infrastructure: administrative costs 

5.80 

069bis  

100% 

 

 

SK-C[C3]-I[I2] 

‘Promoting clean passenger transport

79.30 

072bis  

100% 

 

 

SK-C[C3]-I[I3] 

Development of intermodal freight transport 

16.10 

079 

40% 

 

 

SK-C[C3]-I[I4] 

Support for the construction of alternative propulsion infrastructure 

51.60 

077 

100% 

 

 

SK-C[C3]-R[R2] 

Public passenger transport 

26.60 

084bis 

40% 

084bis 

100% 

SK-C[C3]-R[R4] 

The introduction of new policies for the long-term promotion of alternative fuels in the transport sector 

1.00 

077 

100% 

 

 

SK-C[C4]-I[I1] 

The operation of the industry decarbonisation scheme 

35.88 

024ter 

100% 

 

 

SK-C[C4]-I[I2.a] 

Ensuring the functioning of SIŽP processes linked to decarbonisation - excluding vehicles 

2.70 

027  

100% 

 

 

SK-C[C4]-I[I2.b] 

Ensuring the functioning of SIŽP processes linked to decarbonisation – vehicles 

2.50 

 

ADHOC6 

40% 

 

 

SK-C[C5]-I[I1.a] 

Adaptation of regions to climate change with an emphasis on nature conservation and biodiversity development – renaturing watercourses 

62.36 

 

037 

100% 

 

 

SK-C[C5]-I[I1.b] 

Adaptation of regions to climate change with emphasis on nature conservation and biodiversity development – property settlement with private landowners 

0.094 

037  

100% 

 

 

SK-C[C5]-I[I1.c] 

Adaptation of regions to climate change with emphasis on nature conservation and biodiversity development – soft tourism development plans in the NP Muránska Plain and NP Poloniny 

15.92 

 

037  

100% 

 

 

SK-C[C5]-I[I1.d] 

Adapting regions to climate change, focusing on nature conservation and biodiversity development: administrative capacity 

1.71 

 

037  

100% 

 

 

SK-C[C5]-I[I2] 

Building forests resilient to climate change 

40.00 

 

037  

100% 

  

  

SK-C[C6]-R[R1.a] 

Providing conditions for the implementation of compulsory pre-primary education for children from the age of 5 and introducing a legal entitlement to a place in kindergarten or other pre-primary education providers from the age of 3 - energy efficiency renovation 

45.21 

026bis 

100% 

 

 

SK-C[C7]-I[I1.a] 

Digital infrastructure in schools (a) 

187.18 

 

 

012  

100% 

SK-C[C7]-I[I2.a] 

Completion of the school infrastructure (a) 

112.39 

 

NA  

0% 

 

 

SK-C[C7]-I[I2.b] 

Completion of the school infrastructure - administrative costs for climate tagging 

0.00 

NA 

0% 

 

 

SK-C[C7]-I[I2.c] 

Completion of the school infrastructure - administrative costs 

8.39 

NA 

0% 

NA 

0% 

SK-C[C7]-I[I2.d] 

Completion of the school infrastructure (d) - energy efficiency renovation 

12.49 

 026bis 

 100% 

  

  

SK-C[C7]-R[R1.b] 

Education content and form reform (curricular and textbook reform) – Digital testing and digital tools 

19.55 

 

0% 

 012 

100% 

SK-C[C7]-R[R2.b] 

Preparing and developing teachers for new content and form of teaching – development teachers in digital skills 

16.74 

 

 

108  

100% 

SK-C[C8]-I[I1.b] 

Investment support for the strategic development of universities – energy efficiency renovation 

48.49 

026bis 

100% 

 

 

SK-C[C8]-R[R2.a] 

Introduction of a system of periodic scientific performance evaluation – IT system 

6.73 

 

 

011 

100% 

SK-C[C9]-I[I2.b] 

Supporting cooperation between companies, academia and R & D organisations – digital 

14.02 

 

 

009bis  

100% 

SK-C[C9]-I[I4] 

Research and innovation to decarbonise the economy 

78.66 

022 

100% 

 

 

SK-C[C9]-I[I5] 

Research and innovation for the digitalisation of the economy 

134.05 

 

 

009bis  

100% 

SK-C[C11]-I[I2.a] 

New hospital network – construction – green costs 

800.68 

025ter  

40% 

 

 

SK-C[C11]-I[I2.c] 

New hospital network – reconstruction – green costs & other costs (merged) 

026bis  

 

100% 

 

 

 

SK-C[C11]-I[I3] 

Digitalisation in health 

41.20 

 

 

095  

100% 

SK-C[C11]-I[I4.b] 

Construction and rehabilitation of ambulance stations (emergency ambulance services) – reconstruction – green costs 

0.84 

 

026bis 

100% 

 

 

SK-C[C12]-I[I3.b] 

Community Centres (covers I3, I4, I5) – Reconstructions – energy efficiency renovation costs 

0.35 

026bis  

100% 

 

 

SK-C[C12]-I[I6.b] 

Establishment of a repository of psychodiagnostic methods -- IT costs 

NA  

0% 

NA 

0% 

SK-C[C12]-I[I7.b] 

Humanisation of institutional psychiatric care - energy efficiency renovation costs 

2.08 

NA 

0% 

 

 

SK-C[C12]-R[R1.c] 

Coordinated inter-ministerial cooperation and regulation - IT part 

0.52 

 

 

095 

100% 

SK-C[C13]-I[I1.a] 

Enhancing community-based social care capacities – green investment 

13.94 

026bis 

100% 

 

 

SK-C[C13]-I[I2.a] 

Extension and renewal of after-care and nursing capacities – green investments 

1.87 

 

N.A 

0% 

 

 

SK-C[C14]-I[I1.d] 

Capacities for reforms to reduce regulatory burden - Anti-bureaucratic packages – work-flow tool 

0.20 

 

 

011 

100% 

SK-C[C14]-I[I2] 

Digitalisation of insolvency processes 

5.99 

 

 

011quater  

100% 

SK-C[C15]-I[I1.a] 

Buildings for the reorganised court system - renovation of buildings (green part) 

29.81 

026bis  

100% 

 

 

SK-C[C15]-I[I2.a] 

Digitalisation and analytical capacities - Commercial Register and Centralised System of Judicial Governance 

4.69 

 

 

011quater 

100% 

SK-C[C15]-I[I2.b] 

Digitalisation and analytical capacities - Upgrading of IT equipment 

26.71 

 

 

011quater 

100% 

SK-C[C16]-I[I1.a] 

Investment 1:Making the fight against corruption and AML more effective – development of tools (Central Accounts Register) 

3.33 

 

 

011 

100% 

SK-C[C16]-I[I1.b] 

Investment 1:Streamlining the fight against corruption and AML – development of tools (GoAML) 

1.65 

 

 

 

011 

100% 

SK-C[C16]-I[I1.e] 

Investment 1:Streamlining the fight against corruption and AML – technical equipment for efficient financial investigations (digital investment) 

3.44 

 

 

 

011 

100% 

SK-C[C16]-I[I2.a] 

Investment 2:Modernisation and capacity building of the police force – training of staff and technical equipment of new units (digital investment) 

5.57 

 

 

 

011 

100% 

SK-C[C16]-I[I2.c] 

Investment 2:Modernisation and professional capacity building of the Police Force – new Aliens Registration Information System (IS ECU) 

3.31 

 

 

011 

100% 

SK-C[C16]-I[I2.d] 

Investment 2:Modernisation and capacity building of the police force – Automated system for detecting road traffic offences 

24.79 

 

 

011 

100% 

SK-C[C16]-I[I2.f] 

Investment 2:Modernisation and capacity building of the police force – reconstruction of buildings (green investment) 

10.13 

026bis 

100% 

 

 

SK-C[C16]-I[I3.a] 

Investment 3:Modernisation of the fire and rescue system – building a network of Integrated Safety Centres (digital investment) 

47.67 

 

0% 

011 

100% 

SK-C[C16]-I[I3.c] 

Investment 3:Modernisation of the fire and rescue system – renovation of fire station buildings (green investment) 

0.46 

026bis 

100% 

 

 

SK-C[C16]-I[I4.b] 

Reform/Investment 4:Strengthening administrative capacity at different levels of government – creation of a National Implementation and Coordination Authority 

7.65 

 

 

011 

100% 

SK-C[C17]-I[I1.a] 

Better services for citizens and businesses (a) 

177.53 

 

 

 011 

100% 

SK-C[C17]-I[I1.b] 

Better services for citizens and businesses - administrative capacity 

2.34 

 

 

011 

100% 

SK-C[C17]-I[I2.a] 

Digital transformation of public service delivery (a) 

103.28 

 

 

 011 

100% 

SK-C[C17]-I[I2.b] 

Digital transformation of public service delivery - administrative capacity 

1.83 

 

 

011  

100% 

SK-C[C17]-I[I3.a] 

Engaging in multi-country European projects related to the digital economy – EDIHs 

16.87 

 

 

010 

100% 

SK-C[C17]-I[I3.b] 

Engaging in multi-country European projects related to the digital economy - supercomputing, other 

85.09 

 

 

021quater 

100% 

SK-C[C17]-I[I3.c] 

Engaging in multi-country European projects related to the digital economy - EDIHs - administrative capacity 

0.53 

 

 

010 

100% 

SK-C[C17]-I[I3.d] 

Digital Slovakia – Engaging in multi-country European projects related to the digital economy - supercomputing, other - administrative capacity 

1.50 

 

 

021quater 

100% 

SK-C[C17]-I[I4.a] 

Support for projects aiming at the development and application of top digital technologies (a) 

70.25 

 

 

010  

100% 

SK-C[C17]-I[I4.b] 

Support for projects aiming at the development and application of top digital technologies - administrative capacity 

1.29 

 

 

010  

100% 

SK-C[C17]-I[I5.a] 

Fast grants – hackathons (a) 

2.80 

 

 

009bis 

100% 

SK-C[C17]-I[I5.b] 

Fast grants – hackathons - administrative capacity 

0.63 

 

 

009bis  

100% 

SK-C[C17]-I[I6.a] 

Strengthening preventive measures, increasing the speed of incident detection and resolution 

34.63 

 

 

 

011  

100% 

SK-C[C17]-I[I6.b] 

Strengthening preventive measures, increasing the speed of incident detection and resolution  – Reconstruction and completion of secured areas of critical infrastructure 

2.99 

 

 

 

021quinquies 

100% 

SK-C[C17]-I[I6.c] 

Strengthening preventive measures, increasing the speed of incident detection and resolution - administrative capacity 

1.00 

 

 

 011 

100% 

SK-C[C17]-I[I6.d] 

Strengthening preventive measures, increasing the speed of incident detection and resolution  – Reconstruction and completion of secured areas of critical infrastructure - administrative capacity 

0.27 

 

 

021quinquies 

100% 

SK-C[C17]-I[I7.a] 

Improving the digital skills of seniors and the distribution of Senior Tablets - pilot project 

4.14 

 

 

012 

100% 

SK-C[C17]-I[I7.b] 

Improving the digital skills of seniors and the distribution of Senior Tablets - completed project 

38.21 

 

 

012 

100% 

SK-C[C17]-I[I7.c] 

Improving the digital skills of seniors and the distribution of Senior Tablets - pilot project - administrative capacity 

0.15 

 

 

012 

100% 

SK-C[C17]-I[I7.d] 

Improving the digital skills of seniors and the distribution of Senior Tablets - completed project - administrative capacity 

2.22 

 

 

 012 

100% 

SK-C[C17]-R[R4.a] 

Standardisation of technical and procedural cybersecurity solutions (a) 

4.15 

 

 

011 

100% 

SK-C[C17]-R[R4.b] 

Standardisation of technical and procedural cybersecurity solutions - administrative capacity 

0.27 

 

 

011  

100% 

SK-C[C17]-R[R5.a] 

Improving cybersecurity training and skills (a) 

9.35 

 

 

021quinquies 

100% 

SK-C[C17]-R[R5.b] 

Improving cybersecurity training and skills - administrative capacity 

0.27 

 

 

021quinquies 

100% 

REPowerEU Chapter

SK-C[C19]-I[I1.a] 

Transformation of the PS/RDS 

45.25 

033 

100% 

033  

40% 

SK-C[C19]-I[I1.b] 

Transformation of the  PS/RDS –  Administrative costs 

0.91 

033 

100% 

033 

40% 

SK-C[C19]-I[I1.c] 

Upgrading of transmission lines 

38.62 

033 

100% 

033  

40% 

SK-C[C19]-I[I1.d] 

Modernisation of transmission lines - administrative costs 

0.77 

033  

100% 

033  

40% 

SK-C[C19]-I[I1.e] 

Modernisation of distribution systems 

80.31 

033  

100% 

033  

40% 

SK-C[C19]-I[I1.f] 

Modernisation of distribution systems - administrative costs 

0.83 

033  

100% 

033  

40% 

SK-C[C19]-I[I1.g] 

Energy Data Centre 

3.28 

 

 

011 

100% 

SK-C[C19]-I[I1.h] 

Energy Data Centre - administrative costs 

0.07 

 

 

011 

100% 

SK-C[C19]-I[I2.a] 

Improving the energy performance and efficiency of public buildings 

20.02 

026  

40% 

 

 

SK-C[C19]-I[I2.b] 

Improving the energy performance and efficiency of public buildings - administrative costs 

0.40 

026 

40% 

 

 

SK-C[C19]-I[I3] 

Complementing the allocation of Investment 2 Component 2 Restoration of Public Historical and Historical Buildings 

50.17 

026bis 

100% 

 

 

SK-C[C19]-I[I4.a] 

Comprehensive renovation scheme (Top-up investment 1 Component 2 SK-C[C2]-I[I2]-T[C2.4]) 

0.0 

NA  

100% 

 

 

SK-C[C19]-I[I4.b] 

Light renovation scheme 

40.00 

025 

40% 

 

 

SK-C[C19]-I[I4.c] 

Administrative costs 

1.31 

025  

40% 

 

 

SK-C[C19]-I[I4.d] 

Technical assistance to support the renovation of single-family houses 

9.79 

025  

40% 

 

 

SK-C[C19]-I[I5] 

Development of low-carbon transport infrastructure, SCALE UP measure SK-C[C3]-I[I1a] 

18.00 

069bis  

100% 

 

 

SK-C[C19]-I[I6] 

Promoting environmentally friendly passenger transport, SCALE UP measures SK-C[C3]-I[I2] 

66.50 

072bis 

100% 

 

 

SK-C[C19]-I[I7.a] 

Learning and skills development conditions for the green transition 

14.45 

001  

100% 

 

 

SK-C[C19]-I[I7.b] 

Learning and skills development conditions for the green transition - administrative costs 

0.29 

001  

100% 

 

 

SK-C[C19]-R[R1.a] 

Legislative and procedural changes speeding up the issuing of environmental permits 

9.07 

032 

100% 

 

 

SK-C[C19]-R[R1.b] 

Improving the use of geothermal energy 

0.66 

032  

100% 

 

 

SK-C[C19]-R[R1.d] 

Establishment of BAT centre and provision of BAT reference documents 

1.71 

027 

100% 

 

 

SK-C[C19]-R[R1.e] 

Preparation of an assessment of the trajectories of sustainable use and supply of biomass in Slovakia for period 2025-2035 

0.23 

030bis 

0% 

 

 

SK-C[C19]-R[R1.f] 

Developing and promoting the production of sustainable bio-methane, organic fertilisers and the circular bio-economy 

2.46 

030bis  

100% 

 

 

SK-C[C19]-R[R2.a] 

Development of methodologies and establishment of pilot 'go-to areas' suitable for wind energy development 

2.80 

028 

100% 

 

 

SK-C[C19]-R[R2.b] 

Action Plan of the National Hydrogen Strategy of the Slovak Republic and enabling conditions for the development of hydrogen economy in Slovakia 

0.66 

032 

100% 

 

 

SK-C[C19]-R[R2.c] 

Integration of renewables into the electricity grid 

0.55 

033 

100% 

 

 

SK-C[C19]-R[R3] 

Supporting the creation of a database and data exchange system on the energy performance of buildings 

25.82 

011bis  

40% 

011bis  

100% 

SK-C[C19]-R[R4] 

Management of central government buildings 

2.23 

143  

0% 

143 

0% 

SK-C[C19]-R[R6] 

Supporting education and skills development for the green transition 

0.69 

001 

100% 

 

 

 

While the estimated cost of Slovakia’s recovery and resilience plan exceeds the country’s total allocation of non-repayable financial support, Slovakia will ensure that all spending related to the measures mentioned in this table as contributing to climate objectives are fully financed by the funds from the RRF.

* Reforms and investments in the REPowerEU chapter are not taken into account when calculating the plan’s contribution to the digital target requirement set by Regulation (EU) 2021/241.

Top