This document is an excerpt from the EUR-Lex website
Document 62010TO0252
Order of the President of the General Court of 29 July 2010.#Cross Czech a.s. v European Commission.#Application for interim measures – Sixth Framework Programme for research, technological development and demonstration activities – Letter confirming the findings of a financial audit – Application for suspension of operation of a measure – Disregard of formal requirements – Inadmissibility.#Case T-252/10 R.
Order of the President of the General Court of 29 July 2010.
Cross Czech a.s. v European Commission.
Application for interim measures – Sixth Framework Programme for research, technological development and demonstration activities – Letter confirming the findings of a financial audit – Application for suspension of operation of a measure – Disregard of formal requirements – Inadmissibility.
Case T-252/10 R.
Order of the President of the General Court of 29 July 2010.
Cross Czech a.s. v European Commission.
Application for interim measures – Sixth Framework Programme for research, technological development and demonstration activities – Letter confirming the findings of a financial audit – Application for suspension of operation of a measure – Disregard of formal requirements – Inadmissibility.
Case T-252/10 R.
European Court Reports 2010 II-00157*
ECLI identifier: ECLI:EU:T:2010:323
Order of the President of the General Court of 29 July 2010 – Cross Czech v Commission
(Case T-252/10 R)
Application for interim measures – Sixth Framework Programme for research, technological development and demonstration activities – Letter confirming the findings of a financial audit – Application for suspension of operation of a measure – Disregard of formal requirements – Inadmissibility
1. Application for interim measures – Suspension of operation of a measure – Interim measures – Conditions for granting – Prima facie case – Urgency – Serious and irreparable damage – Cumulative nature – Discretion of the judge dealing with the application for interim relief (Arts 278 TFEU and 279 TFEU; Rules of Procedure of the General Court, Art. 104(2)) (see paras 7-8)
2. Application for interim measures – Formal requirements – Submission of applications – Brief summary of the pleas in law on which the application is based – Pleas not set out in the application and pleadings – General reference to documents – Inadmissibility (Arts 278 TFEU and 279 TFEU; Rules of Procedure of the General Court, Arts 44(1)(c) and 104(3)) (see paras 9-16)
Re:
APPLICATION for suspension of operation of the Commission’s letter of 12 March 2010 confirming the findings of the audit of financial statements submitted by the applicant for the period from 1 February 2005 to 30 April 2008 in respect of the eMapps.com, CEEC IST NET and Transfer-East projects. |
Operative part
1. |
The application for interim measures is dismissed. |
2. |
Costs are reserved. |