Choose the experimental features you want to try

This document is an excerpt from the EUR-Lex website

Document 52017XC1215(01)

    Communication from the Commission — Updating of data used to calculate lump sum and penalty payments to be proposed by the Commission to the Court of Justice in infringement proceedings

    C/2017/8720

    OJ C 431, 15.12.2017, p. 3–5 (BG, ES, CS, DA, DE, ET, EL, EN, FR, HR, IT, LV, LT, HU, MT, NL, PL, PT, RO, SK, SL, FI, SV)

    15.12.2017   

    EN

    Official Journal of the European Union

    C 431/3


    COMMUNICATION FROM THE COMMISSION

    Updating of data used to calculate lump sum and penalty payments to be proposed by the Commission to the Court of Justice in infringement proceedings

    (2017/C 431/02)

    I.   INTRODUCTION

    The 2005 Commission Communication on the application of Article 228 of the EC Treaty (1) (now Article 260(1) and (2) of the TFEU) established the basis on which the Commission calculates the amount of the financial sanctions (either lump sum or penalty payments) that it requests the Court of Justice to apply when the Commission brings a case before the Court under Article 260(2) TFEU, in the context of infringement proceedings against a Member State.

    In a subsequent Communication of 2010 (2) on the updating of the data used for this calculation, the Commission established that these macroeconomic data be subject to revision every year, in order to take into account inflation and GDP movements.

    The 2011 Commission Communication on the implementation of Article 260(3) TFEU (3) and the 2017 Commission Communication ‘EU law: Better results through better application’ (4) emphasise that the same method as established by the 2005 Communication applies for the calculation of the financial sanctions which the Commission requests the Court of Justice to apply under Article 260(3) TFEU.

    The yearly update provided in this Communication is based on developments in the inflation and GDP of each Member State (5). The relevant rate of inflation and GDP statistics to be used are those established two years prior to the update (‘t-2 rule’), as two years is the minimum period of time necessary for gathering relatively stable macroeconomic data. This Communication is therefore based on economic data for nominal GDP and the GDP deflator for 2015 (6) and the current weighting of Member State voting rights in the Council.

    II.   COMPONENTS OF THE UPDATE

    The list of economic criteria to be revised is as follows:

    the standard flat-rate amount for the penalty payment (7), currently fixed at EUR 680 per day, to be revised in line with inflation;

    the standard flat-rate amount for the lump sum payment (8), currently fixed at EUR 230 per day, to be revised in line with inflation;

    the special ‘n’ factor (9), to be revised in line with the GDP of the Member State in question taking into account the number of voting rights it has in the Council; the ‘n’ factor is identical for the calculation of lump sum and daily penalty payments;

    minimum lump sum payments (10) to be revised in line with inflation.

    III.   UPDATES

    The Commission will apply the following updated figures to calculate the amount of the financial sanctions (lump sum or penalty payments) when it brings a case to the Court of Justice under Article 260(2) and (3) TFEU:

    (1)

    the standard flat-rate amount for calculating the penalty payment is fixed at EUR 700 per day,

    (2)

    the standard flat rate for the lump sum payment is fixed at EUR 230 per day.

    (3)

    The special ‘n’ factor and the minimum lump sum for the 28 EU Member States are set as follows:

    Member State

    special factor ‘n’

    Minimum lump sums

    (EUR 1 000 )

    Belgium

    4,85

    2 799

    Bulgaria

    1,47

    848

    Czech Republic

    3,09

    1 783

    Denmark

    3,01

    1 737

    Germany

    20,50

    11 832

    Estonia

    0,62

    358

    Ireland

    2,92

    1 685

    Greece

    3,17

    1 830

    Spain

    11,78

    6 799

    France

    17,43

    10 060

    Croatia

    1,21

    698

    Italy

    15,10

    8 715

    Cyprus

    0,58

    335

    Latvia

    0,68

    392

    Lithuania

    1,12

    646

    Luxembourg

    1,00

    577

    Hungary

    2,51

    1 449

    Malta

    0,36

    208

    Netherlands

    6,48

    3 740

    Austria

    4,03

    2 326

    Poland

    7,45

    4 300

    Portugal

    3,21

    1 853

    Romania

    3,27

    1 887

    Slovenia

    0,86

    496

    Slovakia

    1,62

    935

    Finland

    2,65

    1 529

    Sweden

    4,62

    2 666

    United Kingdom

    18,90

    10 908

    (4)

    The Commission will apply the updated figures to decisions it takes to bring a case before the Court of Justice under Article 260 TFEU as from the adoption of this Communication.


    (1)  SEC(2005) 1658 (OJ C 126, 7.6.2007, p. 15).

    (2)  SEC(2010) 923/3. This Communication has been updated in 2011 (SEC(2011) 1024 final), in 2012 (C(2012) 6106 final), in 2013 (C(2013) 8101 final) and in 2014 (C(2014) 6767 final), in 2015 (C(2015)5511 final) and in 2016 (C(2016)5091 final) for the yearly adaptation of economic data.

    (3)  OJ C 12, 15.1.2011, p. 1.

    (4)  OJ C 18, 19.1.2017, p. 10.

    (5)  According to the general rules set out in the communications of 2005 and 2010.

    (6)  The GDP price deflator is used as a measure of inflation. The uniform amounts for lump sum and penalty payments are rounded to the nearest multiple of ten. The minimum lump sums are rounded to the nearest thousand. The ‘n’ factor is rounded to two decimal places.

    (7)  The standard or uniform flat-rate amount for daily penalty payments is defined as the fixed basic amount to which certain multiplier weightings are applied. The weightings are the coefficients for the seriousness and the duration of the infringement and the special factor ‘n’ corresponding to the Member State concerned that are to be applied for the calculation of a daily penalty payment.

    (8)  The flat-rate amount is to be applied when calculating the lump sum. As regards Article 260(2) TFEU, the lump sum will result from multiplying a daily amount (resulting from multiplying the standard flat-rate amount for lump sum payments by the coefficient for seriousness and the result of this calculation being multiplied by the special factor ‘n’) by the number of days the infringement persists between the date of the first judgment and the date that the infringement comes to an end or the date of delivery of the judgment under Article 260(2) TFEU. As regards Article 260(3) TFEU, according to point 28 of the Commission Communication on ‘Implementation of Article 260(3) of the Treaty’ (SEC (2010)1371 final; OJ C 12, 15.1.2011, p. 1), the lump sum will result from multiplying a daily amount (resulting from multiplying the standard flat-rate amount for lump sum payments by the coefficient for seriousness and the result of this calculation being multiplied by the special factor ‘n’) by the number of days from the day after the time limit for transposition set out in the directive expired until the date that the infringement comes to an end or the date of delivery of the judgment under Articles 258 and 260 (3) TFEU. The lump sum calculated on the basis of the daily amount should apply when the result of the above-mentioned calculation exceeds the minimum lump sum.

    (9)  The special factor ‘n’ takes into account the capacity of the Member States to pay (gross domestic product (GDP)) and the number of votes it has in the Council.

    (10)  The minimum fixed lump sum payment is determined for each Member State according to the special ‘n’ factor. The minimum fixed lump sum will be proposed to the Court when the summed up daily lump sum payments do not exceed the minimum fixed lump sum.


    Top