Case C-835/19: Order of the Court (Ninth Chamber) of 26 November 2020 (request for a preliminary ruling from the Consiglio di Stato — Italy) — Autostrada Torino Ivrea Valle D’Aosta — Ativa S.p.A. v Presidenza del Consiglio dei Ministri, Ministero delle Infrastrutture e dei Trasporti, Ministero dell'Economia e delle Finanze, Autorità di regolazione dei trasporti (Reference for a preliminary ruling — Article 99 of the Rules of Procedure of the Court of Justice — Award of concession contracts — Directive 2014/23/EU — Article 2(1), first subparagraph — Article 30 — Freedom of awarding authorities to define and organise the procedure leading to the selection of the concession holder — National legislation prohibiting the use of project financing for motorway concession contracts)
Case C-835/19: Order of the Court (Ninth Chamber) of 26 November 2020 (request for a preliminary ruling from the Consiglio di Stato — Italy) — Autostrada Torino Ivrea Valle D’Aosta — Ativa S.p.A. v Presidenza del Consiglio dei Ministri, Ministero delle Infrastrutture e dei Trasporti, Ministero dell'Economia e delle Finanze, Autorità di regolazione dei trasporti (Reference for a preliminary ruling — Article 99 of the Rules of Procedure of the Court of Justice — Award of concession contracts — Directive 2014/23/EU — Article 2(1), first subparagraph — Article 30 — Freedom of awarding authorities to define and organise the procedure leading to the selection of the concession holder — National legislation prohibiting the use of project financing for motorway concession contracts)
Case C-835/19: Order of the Court (Ninth Chamber) of 26 November 2020 (request for a preliminary ruling from the Consiglio di Stato — Italy) — Autostrada Torino Ivrea Valle D’Aosta — Ativa S.p.A. v Presidenza del Consiglio dei Ministri, Ministero delle Infrastrutture e dei Trasporti, Ministero dell'Economia e delle Finanze, Autorità di regolazione dei trasporti (Reference for a preliminary ruling — Article 99 of the Rules of Procedure of the Court of Justice — Award of concession contracts — Directive 2014/23/EU — Article 2(1), first subparagraph — Article 30 — Freedom of awarding authorities to define and organise the procedure leading to the selection of the concession holder — National legislation prohibiting the use of project financing for motorway concession contracts)
OJ C 44, 8.2.2021, p. 11–12
(BG, ES, CS, DA, DE, ET, EL, EN, FR, HR, IT, LV, LT, HU, MT, NL, PL, PT, RO, SK, SL, FI, SV)
8.2.2021 |
EN |
Official Journal of the European Union |
C 44/11 |
Order of the Court (Ninth Chamber) of 26 November 2020 (request for a preliminary ruling from the Consiglio di Stato — Italy) — Autostrada Torino Ivrea Valle D’Aosta — Ativa S.p.A. v Presidenza del Consiglio dei Ministri, Ministero delle Infrastrutture e dei Trasporti, Ministero dell'Economia e delle Finanze, Autorità di regolazione dei trasporti
(Case C-835/19) (1)
(Reference for a preliminary ruling - Article 99 of the Rules of Procedure of the Court of Justice - Award of concession contracts - Directive 2014/23/EU - Article 2(1), first subparagraph - Article 30 - Freedom of awarding authorities to define and organise the procedure leading to the selection of the concession holder - National legislation prohibiting the use of project financing for motorway concession contracts)
(2021/C 44/16)
Language of the case: Italian
Referring court
Consiglio di Stato
Parties to the main proceedings
Applicant: Autostrada Torino Ivrea Valle D’Aosta — Ativa S.p.A.
Defendants: Presidenza del Consiglio dei Ministri, Ministero delle Infrastrutture e dei Trasporti, Ministero dell'Economia e delle Finanze, Autorità di regolazione dei trasporti
Intervening parties: Autorità di bacino del Po, Regione Piemonte
Operative part of the order
Must the first subparagraph of Article 2(1) of Directive 2014/23/EU of the European Parliament and of the Council of 26 February 2014 on the award of concession contracts, read in conjunction with Article 30 and recitals 5 and 68 of that directive, be interpreted as not precluding a national provision prohibiting awarding authorities from granting expired or expiring motorway concessions using the project financing procedure laid down in Article 183 of decreto legislativo n. 50 — Codice dei contratti pubblici (Legislative decree No 50 establishing the public procurement code), of 18 April 2016.