Commission Regulation (EC) No 4/2004 of 23 December 2003 laying down detailed rules for the application of Council Regulation (EEC) No 4045/89 on scrutiny by Member States of transactions forming part of the system of financing by the Guarantee Section of the European Agricultural Guidance and Guarantee Fund
Consolidated text: Commission Regulation (EC) No 4/2004 of 23 December 2003 laying down detailed rules for the application of Council Regulation (EEC) No 4045/89 on scrutiny by Member States of transactions forming part of the system of financing by the Guarantee Section of the European Agricultural Guidance and Guarantee Fund
Commission Regulation (EC) No 4/2004 of 23 December 2003 laying down detailed rules for the application of Council Regulation (EEC) No 4045/89 on scrutiny by Member States of transactions forming part of the system of financing by the Guarantee Section of the European Agricultural Guidance and Guarantee Fund
No longer in force
2004R0004 — EN — 16.01.2006 — 001.001
This text is meant purely as a documentation tool and has no legal effect. The Union's institutions do not assume any liability for its contents. The authentic versions of the relevant acts, including their preambles, are those published in the Official Journal of the European Union and available in EUR-Lex. Those official texts are directly accessible through the links embedded in this document
COMMISSION REGULATION (EC) No 4/2004 of 23 December 2003 (OJ L 002 6.1.2004, p. 3) |
Amended by:
|
|
Official Journal |
||
No |
page |
date |
||
L 8 |
4 |
13.1.2006 |
COMMISSION REGULATION (EC) No 4/2004
of 23 December 2003
laying down detailed rules for the application of Council Regulation (EEC) No 4045/89 on scrutiny by Member States of transactions forming part of the system of financing by the Guarantee Section of the European Agricultural Guidance and Guarantee Fund
CHAPTER I
SUBJECT MATTER
Article 1
This Regulation lays down detailed rules for the application of Regulation (EEC) No 4045/89.
CHAPTER II
APPLICATION FOR REDUCTION OF THE MINIMUM NUMBER OF SCRUTINIES
Article 2
The request for a reduction of the number of scrutinies referred to in the third subparagraph of Article 7(1) of Regulation (EEC) No 4045/89 shall contain detailed information as set out in Annex I to this Regulation.
Article 3
The decision to grant a reduction of the minimum number of scrutinies as provided for in the third subparagraph of Article 7(1) of Regulation (EEC) No 4045/89 shall be based on an assessment of the benefits in respect of the protection of the Communities' financial interests and shall take into account the following criteria:
(a) the risks identified;
(b) the approach adopted;
(c) the rate of completion of the minimum number of scrutinies for the previous three scrutiny periods and the number and rate of timely completion of mutual assistance requests for the previous three scrutiny periods;
(d) the feasibility of the proposed approach and any particular scrutiny experience of the Member State(s) concerned with the approach or in the sector concerned;
(e) the extent to which scrutineers of one Member State may participate in the scrutinies under the joint exercise in the other Member State(s);
(f) the confirmation that the other Member State(s) participate, to the extent required, in the joint exercise, if that exercise is not included in the other Member State(s) programme handed in under Article 10(1) of Regulation (EEC) No 4045/89;
(g) the extent to which scrutiny in third countries is envisaged and considered feasible;
(h) any other information considered necessary to support the request.
Article 4
The decision referred to in Article 3 shall fix the rate and number of the reduction on the minimum number of scrutinies required under Article 2(2) of Regulation (EEC) No 4045/89.
CHAPTER III
THE CONTENT OF DOCUMENTS
Article 5
1. The annual report referred to in Article 9(1) of Regulation (EEC) No 4045/89 shall include detailed information on each of the aspects of the application of that Regulation as set out in part I of Annex II to this Regulation and shall include detailed information in accordance with the specimen forms set out in part II of that Annex.
2. The annual programme of scrutinies referred to in Article 10 of Regulation (EEC) No 4045/89 shall be drawn up in accordance with the specimen form shown in Annex III to this Regulation.
3. The list of undertakings referred to in Article 7(2) of Regulation (EEC) No 4045/89 shall be drawn up in accordance with the specimen form set out in Annex IV to this Regulation and shall include transaction data in a format specified under Article 6(3).
4. The list of undertakings referred to in Article 7(3) of Regulation (EEC) No 4045/89 shall be drawn up in accordance with the specimen form shown in Annex V to this Regulation.
5. A request by a Member State for a priority inspection of an undertaking in another Member State, as referred to in Article 7(2) and (4) of Regulation (EEC) No 4045/89, shall be drawn up in accordance with the specimen form shown in Annex VI to this Regulation.
6. The information on the results of the scrutinies referred to in Article 7(2) and (4) of Regulation (EEC) No 4045/89 shall be drawn up in accordance with the specimen form shown in Annex VII to this Regulation.
7. The information on the requests and the results of the scrutinies referred to in Article 7(2) and (4) of Regulation (EEC) No 4045/89, to be communicated to the Commission in quarterly reports as provided for in the second subparagraph of Article 7(4) of that Regulation, shall be drawn up in accordance with the specimen form shown in Annex VIII to this Regulation.
8. The risk analysis referred to in Article 2(2) of Regulation (EEC) No 4045/89 shall be drawn up in accordance with the specimen form set out in Annex IX to this Regulation.
Article 6
1. The information to be submitted pursuant to Article 5(1) to (4) and (7) and (8) shall be communicated in electronic form in the format to be specified by the Commission.
2. The information to be submitted pursuant to Article 5(5) and (6) shall be communicated on paper or in electronic form, in a format to be agreed between the sender and the recipient. Confirmation of receipt of each request/reply received pursuant to Article 5(5) and (6) should be sent to the sender.
3. Transaction data pursuant to Article 7 of Regulation (EEC) No 4045/89 shall be communicated in electronic form in the format specified in Annex I, Annex II, point 2 and in Annex III to Commission Regulation (EC) No 2390/1999 ( 5 ).
CHAPTER IV
JOINT ACTIONS
Article 7
1. The Commission, acting on its own initiative or on the basis of a proposal by a Member State, and with the agreement of the Member States concerned, may decide to coordinate joint actions involving mutual assistance between two or more Member States, as provided for in Article 7(1) of Regulation (EEC) No 4045/89.
For its decision the Commission shall take into account the following points, in particular:
(a) the level of risk involved;
(b) the extent of operations, in particular the frequency of intra- and extra-Community trade, and their financial scale;
(c) the need to achieve a uniform approach.
2. In agreement with the Member States concerned, a Member State shall be designated to be responsible for the management of the joint action.
However, each Member State shall remain responsible for carrying out the scrutinies required by Regulation (EEC) No 4045/89.
3. Each Member State concerned shall:
(a) designate those persons or services responsible for carrying out the joint action on its behalf;
(b) ensure that a sufficient number of adequately experienced officials is made available for the conduct of the joint action;
(c) ensure that within set time limits the scrutiny is carried out and the report finalised and made available to all participating Member States and to the Commission.
CHAPTER V
FINAL RULES
Article 8
Regulation (EEC) No 1863/90 is repealed.
Article 9
This Regulation shall enter into force on the third day following that of its publication in the Official Journal of the European Union.
This Regulation shall be binding in its entirety and directly applicable in all Member States.
ANNEX I
ANNEX II
PART I
Information to be contained in the annual report provided for in Article 9(1) of Regulation (EEC) No 4045/89
1. Administration of Regulation (EEC) No 4045/89
Information shall be provided concerning the administration of Regulation (EEC) No 4045/89, including changes to the organisations responsible for controls and to the special department responsible for monitoring the application of that Regulation, as referred to in Article 11 thereof, and to the competences of those organisations.
2. Legislative changes
Information shall be provided regarding any national legislative changes relevant to the application of Regulation (EEC) No 4045/89 that have intervened since the previous annual report.
3. Amendments to the scrutiny programme
A description shall be provided of any amendments or modifications that were made to the scrutiny programme submitted to the Commission under Article 10(2) of Regulation (EEC) No 4045/89 since the date of submission of that programme.
4. Execution of the scrutiny programme covered by the present report
Information shall be provided on the execution of the programme of scrutinies for the period ending on 30 June preceding the closing date for submission of the report, as referred to in Article 9(1) of Regulation (EEC) No 4045/89, including the following points, both in total and broken down by control body (where more than one carries out controls pursuant to that Regulation):
(a) the number of undertakings scrutinised during the scrutiny period, in accordance with the specimen form shown in sheet A of this Annex;
(b) the number of undertakings still in the course of being scrutinised, in accordance with specimen form shown in sheet A of this Annex;
(c) the number of undertakings that were not subject to scrutiny during the period in question as a result of the non-execution of some scrutinies, in accordance with the specimen form shown in sheet A of this Annex;
(d) the reasons why the scrutinies referred to in point (c) were not carried out;
(e) the breakdown, by amounts received by or paid to, and by measure, of the scrutinies referred to in points (a), (b) and (c), in accordance with the specimen form shown in sheet B of this Annex;
(f) the results of the scrutinies referred to in point (a), in accordance with the specimen form shown in sheet C of this Annex, including:
(i) the number of scrutinies for which irregularities were discovered, and the number of undertakings involved;
(ii) the nature of these irregularities;
(iii) the measure concerned where an irregularity was discovered;
(iv) the estimated financial consequence of each irregularity;
(g) an indication of the average duration of scrutinies in person/days, indicating, where practicable, the time spent on planning, preparation, execution of controls, and reporting.
5. Execution of the scrutiny programmes preceding the one covered by the present programme
The report shall contain the results of the scrutinies carried out in respect of previous scrutiny periods, for which the results were not available at the time of the submission of the reports for those scrutiny periods, including for each previous scrutiny period:
(a) the status of scrutinies communicated pursuant to point 4(b) and (c) in previous annual scrutiny reports, in accordance with the specimen form shown in sheet D of this Annex;
(b) the number of scrutinies through which irregularities were discovered, and the number of undertakings involved, in accordance with the specimen form shown in sheet C of this Annex;
(c) the nature of these irregularities, in accordance with the specimen form shown in sheet C of this Annex;
(d) the measure concerned where an irregularity was discovered, in accordance with the specimen form shown in sheet C of this Annex;
(e) the estimated financial consequence of each irregularity, in accordance with the specimen form shown in sheet C of this Annex.
The results of the scrutinies pursuant to the third subparagraph of Article 7(1) of Regulation (EEC) No 4045/89 shall be presented as such.
6. Mutual assistance
Mutual assistance requests made and received pursuant to Article 7 of Regulation (EEC) No 4045/89 shall be communicated, including the results of scrutinies carried out as a matter of priority pursuant to Article 7(2) and (4) of that Regulation, and a summary of the lists both sent and received pursuant to Article 7(2) and (3) of that Regulation.
7. Resources
Details on the resources available for the carrying out of the scrutinies under Regulation (EEC) No 4045/89 shall be transmitted, including:
(a) the number of staff, expressed in person/years, allocated to scrutinies pursuant to Regulation (EEC) No 4045/89, by control body and, where appropriate, region;
(b) training received by staff working on scrutinies pursuant to Regulation (EEC) No 4045/89, with an indication of the proportion of the staff referred to in point (a) who have received such training, and the nature of the training itself; and
(c) computer equipment and tools at the disposal of staff working on scrutinies pursuant to Regulation (EEC) No 4045/89.
8. Difficulties in applying Regulation (EEC) No 4045/89
Information shall be provided on any difficulties encountered in the application of the Regulation, and the measures taken to overcome them or proposals to this end.
9. Suggestions for improvement
Where appropriate, suggestions shall be made for the improvement, either of the application of Regulation (EEC) No 4045/89 or, of that Regulation itself.
PART II
SHEET A
SCRUTINY REPORT FOR THE PERIOD …
(Article 9 of Regulation (EEC) No 4045/89)
SHEET B
SCRUTINY REPORT FOR THE PERIOD …
(Article 9 of Regulation (EEC) No 4045/89)
Report of control in relation to EAGGF Guarantee Fund budget headings in respect of the EAGGF financial year …
Scrutiny programme …
B(1) EAGGF Budget Article or Item No |
B(2) Total value of expenditure relating to undertakings selected for scrutiny… (EUR) |
B(3) Controlled undertakings |
B(4) Undertakings in the course of control |
B(5) Undertakings not controlled |
|
(i) expenditure actually controlled (EUR) |
(ii) total expenditure relating to those undertakings (EUR) |
(i) total expenditure relating to those undertakings (EUR) |
(i) total expenditure relating to those undertakings (EUR) |
||
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Totals: |
|
|
|
|
|
SHEET C
SCRUTINY REPORT FOR THE PERIOD …
(Article 9 of Regulation (EEC) No 4045/89)
Potential irregularities discovered in relation to EAGGF Guarantee Fund budget headings in respect of the EAGGF financial year …
Scrutiny programme …
C(1) EAGGF Budget Article or Item No |
C(2) Number of potential irregularities discovered |
C(3) Number of payments concerned |
C(4) Number of undertakings concerned |
C(5) Estimated value of potential irregularities |
C(6) Description and nature of each potential irregularity discovered, the reference number(s) of the undertaking(s) concerned and the OLAF reference number(s) where communication in accordance with Article 3 of Regulation (EEC) No 595/91 has been sent |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Totals: |
|
|
|
|
|
SHEET D
SCRUTINY REPORT FOR THE PERIOD …
(Article 9 of Regulation (EEC) No 4045/89)
ANNEX III
SHEET A
SHEET B
PROPOSED SCRUTINY PROGRAMME FOR THE PERIOD …
(Article 10 of Regulation (EEC) No 4045/89)
Scheme of control in relations to EAGGF Guarantee Fund budget headings
EAGGF financial year …
B(1) EAGGF Budget Article or Item No |
B(2) Total expenditure by EAGGF budget heading … (EUR) |
B(3) Total expenditure by EAGGF budget heading relating to undertakings whose receipts or payments, or the sum thereof, were above EUR 40 000 … (EUR) |
B(4) Total expenditure by EAGGF budget heading relating to undertakings included in the scrutiny programme … (EUR) |
B(5) Number of undertakings by EAGGF budget heading included in the scrutiny programme |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Totals: |
|
|
|
|
SHEET C
PROPOSED SCRUTINY PROGRAMME FOR THE PERIOD …
(Article 10 of Regulation (EEC) No 4045/89)
Criteria adopted in drawing up the programme in the area of export refunds and other sectors where risk analysis selection techniques have been adopted where these differ from those included in the proposals for risk analysis sent to the Commission pursuant to Article 2(2) of Regulation (EEC) No 4045/89.
Sector where scrutiny is proposed (show EAGGF budget heading as set out in sheet B, column B(1) of this Annex) |
Comments on risk and selection criteria adopted (give brief details, e.g. detected irregularities or exceptional increase in expenditure) |
|
|
SHEET D
PROPOSED SCRUTINY PROGRAMME FOR THE PERIOD …
(Article 10 of Regulation (EEC) No 4045/89)
Proposed scrutinies, if any, of undertakings whose receipts or payments, or the sum thereof, were less than EUR 40 000 during the EAGGF financial year …
EAGGF budget heading (as set out in sheet B, column B(1)) |
Number of undertakings that it is proposed to scrutinise |
Specific reason for scrutiny |
|
|
|
SHEET E
ANNEX IV
ANNEX V
ANNEX VI
ANNEX VII
ANNEX VIII
QUARTERLY REPORT
(as provided for in the first subparagraph of Article 7(4) of Regulation (EEC) No 4045/89)
of … (Member State)
on requests for inspection and on the results of inspection for the first [ ], second [ ], third [ ], fourth [ ] quarter 20…
QUARTERLY OVERVIEW TABLE:
REQUESTS sent to:
Member State |
Total number per Member State |
REQUEST |
|
Date sent |
Reference No |
||
|
|
|
|
|
|
|
|
|
|
|
|
Total: |
|
|
|
REPLIES sent to:
Member State |
Total number per Member State |
REPLY |
|
Date sent |
Reference No |
||
|
|
|
|
|
|
|
|
|
|
|
|
Total: |
|
|
|
SHEET A
SHEET B
ANNEX IX
Information to be contained in the annual risk analysis referred to in Article 2(2) of Regulation (EEC) No 4045/89
1. Assessment of previous year’s risk analysis
Information shall be provided concerning the assessment of effectiveness of the previous year’s risk analysis, including the evaluation of its strengths and weaknesses. Any possibilities for improvement shall be clearly identified and implementation thereof shall be considered.
2. Library of information
Information shall be provided on all sources of information taken into account in order to prepare and conduct the risk analysis. Particular reference shall be made to Regulation (EEC) No 386/90.
3. Selection procedure
A description shall be provided of the procedure to be applied in order to select the undertakings to be scrutinised. A clear indication shall be made of the number/percentage of undertakings and sectors/measures to which risk analysis, random, automatic and/or manual selection shall be applied. Sectors/measures to be excluded shall be clearly identified and the reasons for exclusion shall be described.
4. Risk factors and risk values to be applied
Where risk analysis shall be applied, information shall be provided on all risk factors taken into consideration and the subsequent possible values assigned to those risk factors. This information shall be provided in accordance with the specimen tables provided below.
Risk factors and risk values applicable to all measures subject to risk analysis |
||
Risk factors |
Risk values |
|
Description |
Values |
|
|
|
|
|
|
|
|
|
|
Specific risk factors and risk values applicable to export refunds |
||
Risk factors |
Risk values |
|
Description |
Values |
|
|
|
|
|
|
|
Specific risk factors and risk values applicable to… (sector/measure) |
||
Risk factors |
Risk values |
|
Description |
Values |
|
|
|
|
|
|
|
5. Weighting of risk factors
Where appropriate, a description shall be provided of the procedure to be applied to weight the risk factors.
6. Results of risk analysis
Information shall be provided on how the results of risk analysis and the establishment of a ‘scoring list’ (for each specific sector/measure, where appropriate) will be reflected in the selection of undertakings into the final scrutiny plan.
Particular attention shall be given to the possibility of joint actions as provided pursuant to Article 7(1) of Regulation (EEC) No 4045/89.
7. Difficulties encountered and suggestions for improvement
Information shall be provided on any difficulties encountered and the measures taken to overcome them or proposals to this end. Where appropriate, suggestions shall be made for improvement.
( 1 ) OJ L 388, 30.12.1989, p. 18.
( 2 ) OJ L 328, 5.12.2002, p. 4.
( 3 ) OJ L 170, 3.7.1990, p. 23.
( 4 ) OJ L 308, 29.11.1996, p. 30.
( 5 ) OJ L 295, 16.11.1999, p.1.