COMMISSION STAFF WORKING DOCUMENT IMPACT ASSESSMENT Accompanying the document Proposal for a Regulation of the European Parliament and of the Council on streamlining measures for advancing the realisation of the trans-European transport network

SWD/2018/178 final - 2018/0138 (COD)

Brussels, 17.5.2018

SWD(2018) 178 final

COMMISSION STAFF WORKING DOCUMENT

IMPACT ASSESSMENT

Accompanying the document

Proposal for a Regulation of the European Parliament and of the Council

on streamlining measures for advancing the realisation of the trans-European transport network

{COM(2018) 277 final}
{SEC(2018) 228 final}
{SWD(2018) 179 final}


Glossary

Term or acronym

Meaning or definition

AA

Appropriate Assessment

ACER

Agency for the Cooperation of Energy Regulators

CBA

Cost Benefit Analysis

CBS Report

Former European Commission Vice-President H. Christophersen, Professor K. Bodewig, European Coordinator, Professor C. Secchi, European Coordinator in the "Action Plan – Making the best use of new financial schemes for European transport infrastructure projects", June 2015,

CEF

Connecting Europe Facility

CNC

Core Network Corridor

ECJ

European Court of Justice

EFSI

European Fund for Strategic Investments

EIA

Environmental Impact Assessment

EIAH

European Investment Advisory Hub

ESIF

European Structural Investment Funds

EU

European Union

GDP

Gross Domestic Product

JASPERS

Joint Assistance to Support Projects In European Regions

MS

Member State

NGO

Non-governmental organisation

NPV

Net Present Value

OPC

Open Public Consultation

OSS

One-Stop-Shop

PO

Policy Option

PPP

Public-Private Partnership

SEA

Strategic Environmental Assessment

SME

Small and medium sized enterprises

TEN-E

Trans-European Network for Energy

TEN-T

Trans-European Network for Transport

TEN-T Regulation

Regulation (EU) No 1315/2013 of the European Parliament and of the Council of 11 December 2013 on Union guidelines for the development of the trans-European transport network and repealing Decision No 661/2010/EU OJ L 348, 20.12.2013, p. 1–128



1INTRODUCTION: POLITICAL AND LEGAL CONTEXT

1.1Political context

The European Commission holds stimulating economic growth and boosting investment in the real economy at the heart of its priorities. The Investment Plan for Europe, which translates this overarching goal into operational terms, has three objectives: to make smarter use of financial resources, to provide visibility and technical assistance to investment projects, and to remove obstacles to investment, the so-called third pillar of the Plan. The present initiative aims at contributing to this third pillar by helping removing obstacles to investments in the infrastructure projects in the transport sector. Currently, some of the most complex projects require up to 10 years 1 to clear all necessary administrative procedures to start works, and for the more routine ones up to five years. It is therefore not possible to fully reap the expected benefits of infrastructure projects in terms of growth and jobs but also wider socio-economic benefits. The time between the political decision and the delivery of the infrastructure asset is in fact too long to bear fruit in the short term 2 . Therefore, it is necessary to unlock the potential of key transport infrastructure investments with high EU added value, namely the Trans-European Transport Network (TEN-T).

The EU TEN-T policy 3 recognises the importance of a strategic approach to developing a Europe-wide smart, efficient and sustainable network of transport infrastructure. The TEN-T has a dual layer structure – the comprehensive network shall ensure connectivity of all regions of the EU whereas the core network consists of those elements of the network which are of the highest strategic importance for the EU and are shown on the maps contained in Annex I of the TEN-T regulation  4 . The TEN-T Regulation defines binding targets for implementation, as the core network needs to be implemented by 2030 and the comprehensive network by 2050. The TEN-T policy 5 also establishes Core Network Corridors which are operational tools to facilitate the coordinated and timely implementation of the core network.

The recent Commission Communication on boosting the potential of cross-border regions in the EU 6 highlights that transport is a key enabler of exchanges between regions across national borders. This also underlines the crucial role TEN-T is playing for the integration of the Single Market. Infrastructure projects on cross-border connections are nevertheless the most difficult to be developed. Especially public transport services not only help integration processes but also enhance the sustainability of cross-border connectivity. Yet, insufficient or low-quality public transport services are still a reality for many citizens in border regions.

Supporting the Investment Plan for Europe

The analysis carried out by the Commission on the Core Network Corridors allows for the identification of bottlenecks and missing links as well as other relevant infrastructure projects to ensure compliance with EU standards and the efficiency of the EU transport 7 . It is estimated that the investments needed from 2021 until 2030 to complete the TEN-T core network amount to about €500 billion for the EU, based on inputs from Member States. The total needs, including TEN-T comprehensive network, as well as investments in decarbonisation, digitalisation, urban transport and maintenance are estimated to amount to about € 1,500bn between 2021 and 2030. The achievement of the TEN-T core network and its corridors is expected to generate additional € 4,500bn or 1.8% of GDP and 13 million additional job-years by 2030 8 .

The effective and timely delivery of the TEN-T is essential for the efficient functioning of the Single Market and also an enabler for the decarbonisation and digitalisation of transport and the transition to low carbon mobility 9 .The recent Commission communications emphasise the need to mobilise private investments in sectors critical to Europe’s future 10 and where market failures remain 11 as well as reiterate that cross-border and sustainable transport and TEN-T infrastructure is critical for the EU to shift to a low-carbon and resource-efficient economy 12 .

Political impetus to streamlining permitting for TEN-T

The Council of Ministers adopted conclusions 13 on 3 December 2014 where they considered “that permitting procedures are an essential part of the planning of (transport) projects, that an early consultation and coordination of parties is crucial to streamline these procedures, accelerate projects and avoid additional costs, thereby increasing investors’ confidence”. The Council then invited the Commission to take stock of good practices and identify ways to simplify procedures for projects of the core network.

The simplification of permitting rules and administrative arrangements as a means of accelerating the implementation of the TEN-T has been identified as one of the recommendations in the so-called CBS Report Action Plan 14 , presented by European Coordinators Bodewig and Secchi as well as former Vice President H. Christophersen. In January 2018, a progress report of the implementation of their recommendations reiterated the call to consider setting up of special (single) procurement rules for cross-border projects and setting time limits for the permitting procedure 15 .

The complex permitting processes delaying the implementation of transport infrastructure projects are not a typically European problem. The complexity of regulation affecting the efficient permitting procedure has been debated in the G7 format and in the Declaration of the Ministers adopted at the G7 Transport Ministers Meeting in Cagliari in June 2017, where the Ministers stressed the importance of building public acceptance of infrastructure projects, of efficient administrative procedures and of streamlining the regulatory environment 16 . Efforts to streamline the procedures are also made at national level, for example in Germany with the Strategy for speeding up the planning process which has similar objectives to this initiative 17 .

Long term investments need long term strategy

The TEN-T policy was completely revamped in 2013 with the adoption of a new regulation defining a holistic strategy based on the establishment of the core network by 2030 and the comprehensive network by 2050.

The TEN-T policy has nevertheless existed for 25 years and at the time of the preparation of the current TEN-T framework, evidence already existed on the existence and impacts of delays in permitting and other regulatory procedures. Initially it was planned to integrate the simplification measures also for TEN-T framework, but it was in the end considered premature due to several factors. Namely, the reshaped TEN-T framework included already an ambitious set of innovations, in particular in connection with the new funding instrument. Moreover, the respective horizontal pieces of legislation such as directives on public procurement and on environmental assessments were planned to be reviewed and adapted also to the needs of the transport infrastructure developments. For these reasons, the current TEN-T Regulation does not provide for specific solutions as regards the permit granting procedures, unlike the TEN-E Regulation. As a result, the present initiative could also not be developed as part of the REFIT programme.

Finally, it should be highlighted that no evaluation of the TEN-T Regulation is planned in the near future. The TEN-T regulation was conceived as long term plan for at least two multi-annual financial frameworks to provide stability, as most of the projects need ca. 10 years to be implemented. The co-legislators have foreseen that the evaluation of the TEN-T Regulation would only take place in 2023 to feed into a possible revision of the regulation for the multi-annual framework post 2027.

1.2Legal context

The investments on the core network consist of the construction of new parts of the network as well as the rehabilitation and upgrading of existing infrastructure parts which already exist but, either are not of sufficient quality and capacity to meet the current needs, or do not meet the required TEN-T standards. In this context, all key EU pieces of legislation that relate to infrastructure investments apply to TEN-T projects: in particular environment 18 , public procurement 19 and State aid 20 .

National legislation transposing EU Directives directly govern the procedures at Member State level, but these must be in conformity with EU legislation. The main areas for which Member State authorities have sole competence are spatial planning 21 and land use and linked sectoral planning (e.g. transport plans); and other areas such as archaeological considerations, forestry etc. All this creates a quite complex set of rules which the project promoters have to comply with when designing and implementing the projects of EU importance.

The authorisation framework stems from different obligations, and sets forth the process that projects must go through to apply for and receive development consent and procure the works and services necessary for implementation. This occurs at two levels: the strategic level – planning the development of the transport network at national and/or regional level; and the project level – including the planning phase and the permitting procedure, as shown in Figure 1 below. Three inter-linked and often overlapping phases can be distinguished:

nStrategic planning: The ministry or authority responsible for transport devises a national transport plan which provides for the long-term development and modernisation of the transport network. It defines strategic priorities for different transport modes. A Strategic Environmental Assessment (SEA) 22 is generally carried out, along with Appropriate Assessment (AA) if required according to the relevant EU Directive 23 .

nProject planning: This phase assesses the timeliness and feasibility of a proposed project, including alternatives to achieving the objectives of the project. Feasibility studies set out the infrastructure needs and defined solutions and can include traffic analyses, cost-benefit analyses (CBA) and environmental assessments. These may or may not be regulated by national standards, or by the requirements of EU funding programmes such as the Connecting Europe Facility (CEF) or the European Structural Investment Funds (ESIF). Various alternative options are assessed on the basis of economic, social and environmental criteria. The preferred option is then integrated into the spatial plan(s). In certain countries, the approval of the project will automatically result in amendments of the spatial plans, while in others, a specific land-use permit will be required in addition to the construction permit. In some cases, a major modification to a spatial or other plan to take into account a new project may require revision to the SEA.

nPermitting procedure: The permitting procedure generally covers the activities required to prepare an application for development consent, and follows on closely from project planning. This phase includes the Environmental Impact Assessment procedure (EIA), the spatial planning decision(s), and all the other permits to be granted. This phase concludes with the acquisition and/or expropriation of the necessary land.

Public procurement procedures, State aid control, potentially other regulated procedures and the applications for funding also form part of the preparation of an infrastructure project as presented in the authorisation framework in Figure 1 : Generic authorisation framework

Figure 1: Generic authorisation framework

Building upon the existing possibilities

Various developments in the regulatory framework applicable to the implementation of the TEN-T projects took place in the recent years, notably a revised EIA Directive was adopted in 2014 24 , a new set of directives in the field of the public procurement 25 . In the field of State aid, the Notice on the Notion of Aid 26 , the revised General Block Exemption Regulation 27 and the infrastructure grids have been adopted, providing further clarifications on the rules applicable to transport infrastructure.

However, these measures have a horizontal scope. The analysis of their application so far allows the Commission services to assess the level of additional measures necessary for addressing the specific needs of TEN-T projects and to define the different level of intervention in different areas targeted on those needs – going from a broader perspective in the permitting procedures where the impact of the revised measures is the least visible so far, to public procurement where limited adjustments would only be needed in the cross-border context. As regards State aid control, the recent clarifications address the needs of project promoters to understand the rules applicable to transport infrastructure leaving only the issue of the procedure.

2PROBLEM DEFINITION

2.1What are the problems? 

The problems identified in the analytical work leading to this initiative are the delays and legal uncertainties which impact the effective delivery of the TEN-T core network projects.

Experience with the implementation of the TEN-T projects located on the core network corridors, as well as those in the previous legislative setting 28 , has shown that the completion of the projects is very often delayed due to the complex regulatory and administrative arrangements. If a given project is delayed, the positive economic and social effects meant to be generated by this project will happen later than planned. At the same time, the problems that the project is expected to address (e.g. congestion, bottlenecks or pollution) are going to persist over a longer period. Moreover, the overall implementation of the core network risks to be delayed and completion by 2030 as foreseen by the TEN-T Regulation is unlikely.

Given the transnational nature of the TEN-T, any delay impacting one project has an adverse effect on the whole stretch of a corridor. The TEN-T framework adopted in 2013 moves from a project driven approach (patchwork of individual projects) to a network approach based on a dual layer TEN-T to be realised. This requires a synchronised approach for the development of projects across the borders, both in terms of project preparation and permitting. This is even more relevant as regards cross-border public procurement. In the case of cross-border projects developed together by the neighbouring Member States, the joint tendering procedures are necessary to better grasp synergies and benefits of scale.

TEN-T infrastructure projects are not often attractive to private investors. There may be different reasons, which are also addressed in the context of the third pillar of the Investment Plan for Europe as well as in the Progress Report of January 2018 to the CBS Report. The complexity of some regulatory procedures in the area of project financing is one of them. This, next to the other inefficiencies of the permit granting process, concerns in particular perceived uncertainties with regard to State aid control but also the way permitting procedures may affect public-private partnerships.

The Netherlands – a dynamic market of PPP in transport

The Netherlands is a prominent example of the development of the PPP market. According to the EPEC Market Update 2017 29 it is currently the 4th largest PPP market in the EU, also beyond Germany which is the biggest economy overall. The clarity of rules topped up with constant development of expertise in this field bore fruit with materialisation of a high number of projects – also in the transport sector financed with an EFSI guarantee.

The TEN-T network as a whole cannot properly function and offer all of its benefits at EU level before all the elements are completed. The delayed implementation of the TEN-T network will put off the benefits the EU expects from a smart, efficient, sustainable and well-functioning transport network, especially in light of its objectives to foster low emission mobility in Europe. It is very well illustrated by a sequence of sections to be upgraded in one of the busiest transport corridors across the continent – the Rhine Alpine CNC:

Zevenaar – Emmerich – Oberhausen

This cross-border section located on the RhineAlpine CNC is in fact composed of two different projects – one implemented by the Dutch RIM (ProRail) and the second by the German RIM DB Netz. This section is crucial to provide capacity for growing traffic on one of the EU's busiest rail freight routes and fully use the potential of the newly built Betuwe Line in NL. The Dutch part has already been completed; however the works on the DE part are yet to start and currently are not foreseen to be finished before 2022, while originally planned for 2013, i.e. 9 years of delay.

This delay, even if the project from the procedural point of view is a purely German national project, affects the development of the Corridor and TEN-T network as a whole.

In addition, unnecessary costs can also arise when regulations or procedures are not clear enough and the time needed for their application cannot be foreseen with an acceptable level of certainty. The lack of predictability in the procedures leaves a high level of uncertainty for projects promoters and potential private investors leading ultimately to sub-optimal investment choices. Finally, such legal uncertainty can also deter private investment from participating in TEN-T infrastructure projects and results in increased costs in terms of access to capital.

Several Member States have already started to develop measures at national level to address the issue. The approach under the present initiative should not lead to unnecessary burden on Member States that face fewer difficulties because they already have established a one stop shop and meet the deadlines. However, a synchronised approach would trigger innovation and improvements for the Member States that are lagging behind.

It should be borne in mind that the annual administrative costs currently incurred by the authorities and project promoters are estimated at €21 million.

Figure 2: Problem tree

Several root causes leading to these problem drivers have been identified.

First, investment projects in transport infrastructure are highly complex and multidimensional ventures which combine different elements which can create potential problems – these are technical complexities related to engineering challenges, several impacts on different areas (environmental, economic, social, political) as well as complexities related to their size and capital required. Finding resources for their delivery can generate problems related to funding and financial procedures.

Another root of the problem is the fact that many of the transport infrastructure projects are linear, i.e. located in a long stretch of land having impacts along its way on all the neighbouring pieces of land and their occupiers resulting in a high number of stakeholders affected and multiple administrative proceeding (e.g. spatial planning in different regions and localities).

The projects are highly susceptible to generate conflicts, as the procedures and requirements to properly address their expected impacts may stem from different legislations and acts adopted at different levels (from local to the EU and international level). Some project promoters are confronted with multiple use of the infrastructure next to water supply, power generation, agriculture etc 30 .

On top of this comes the additional complexity of the cross-border projects where all the procedures are handled differently across the borders, also due to diverging national transposition of relevant EU directives.

These root causes are inherent to transport infrastructure projects. However, there are other problem drivers that impact delays and uncertainties in the TEN-T project implementation, which range from technical (project preparation capacity, feasibility, engineering complexity and other technical issues), to political and funding issues. They remain outside the scope of this impact assessment and the present initiative.

In particular, the problems related to the availability of funding (beyond the EU contribution), technical challenges as well as administrative capacity of either project promoters or supervising authorities, cannot be effectively address by the present initiative. Either it is beyond the mandate of the EU action or it is addressed already elsewhere, for example via dedicated instruments such as technical assistance in funding programmes (e.g. CEF programme support actions) or horizontal mechanisms (e.g. voluntary ex ante assessment in the public procurement area). However, the problems referred to above – delays due to procedures and high level of uncertainty due to procedures – can be effectively addressed by tackling the above problem drivers as presented in this impact assessment.

2.2Lessons learnt from the TEN-E experience

Since 2013, the TEN-E Regulation 31 contains provisions aiming at reducing the timeframes for authorising the projects of common interest in the TEN-E. It also introduced the concept of the single authorising authority for all the permit granting processes. The TEN-E experience has therefore been duly taken into account.

This was done in the context of the two supporting studies for the present impact assessment by also interviewing the relevant services in the Directorate General for Energy of the European Commission and reviewing any available useful analysis.

According to the Commission's recent assessment; it has proven successful with bringing the average duration of the permit granting process in energy transmission projects from 10 years to an expected 3.5 years and is a useful guidance for the solutions presented in this initiative 32 .

2.3Who is affected by the problem?

The problem mainly affects three categories of actors: project promoters, public administrations at local, regional or national level and civil society often represented by NGOs. A detailed analysis on the categories of actors which are affected by the problem is presented in Annex 3 to the present impact assessment report.

2.4Getting evidence to evaluate the current situation 

To best evaluate the situation, the Commission carried out an extensive analysis of the situation and possible solutions. It completed an exploratory study, which made recommendation to improve and better coordinate authorisations procedures for infrastructure projects 33 . This exploratory study conducted an extensive analysis of the problem and 17 pre-selected cases were screened. Further in-depth studies examined the regulatory and administrative frameworks for transport projects in ten selected Member States to identify the sources of delay, cost and uncertainty, as well as good practices. The selection of countries, in combination with the countries represented in the ten project case studies, has ensured that the research reflected the general picture across the EU 34 .

The study findings regarding the organisation of the permitting procedure were that delays in permitting often occur due to overly complex procedures, involving multiple steps and multiple authorities. A single permitting authority was proposed for TEN-T projects, together with overall time limits for the permitting procedures. It also found that projects face considerable delays when challenged by the public or stakeholders due to the quality of the procedures used to engage the public and due to timing, i.e. the point at which those procedures take place during the process of project preparation. It suggested measures such as requirement for public involvement before a permitting application is submitted, establishing principles for the conduct of public consultation procedures for TEN-T projects, carrying out public information campaigns and improvements to the process for appeals of decisions on development consent.

For delays due to environmental assessment, it proposed mandatory joint procedure for all environmental assessment procedures stemming from EU legislation, various technical clarifications and providing more dedicated external technical assistance services for the preparation of TEN-T projects, focused on environmental assessments. In public procurement, the delays would be partly addressed once the recent revisions of relevant EU directives are fully implemented in the coming years. A special procurement regime aiming at speeding up cross-border procurement and review procedures was proposed. As regards State aid notifications, the study identified two key issues at the Member State level driving delays and uncertainty, namely late notification by the Member State and the poor quality of notifications (including information gaps). In addition, the study suggested reducing State aid decision timeframes for selected TEN-T projects.

2.5What are the problem drivers?

Five underlying causes to the problems have been identified and are described below as problem drivers.

2.1.1Multiple stages and authorities involved in permitting procedures

Permitting procedures in the Member States differ greatly in the number of necessary permits and decisions to be obtained, as illustrated in Table 1 . The number of authorities and levels of governance that may be involved in permitting procedures, as well as their competence and power in the procedure also vary significantly across Member States. Among the ten Member States analysed in detail in the exploratory study 35 , four have a single-stage permitting procedure 36 , where all permitting decisions (environment, spatial planning etc.) are handled through a single development consent procedure. While only one permitting authority grants the final decision, consultation of other authorities generally remains a prerequisite, as the different assessments may relate to policy areas that are within the domain of other authorities. The other six countries have multi-stage permitting procedures 37 .

In addition to the statutory permits and decisions, binding opinions or decisions of a number of authorities can be necessary before the permitting authority can issue a permit. The large number of permitting authorities involved is in part due to the wide scope of impacts considered in environmental assessments. The internal organisation of Member States and the level of decentralisation are others relevant factors potentially increasing the number of authorities involved in the procedure.

Five of the Member States analysed in the exploratory study have integrated various steps – environmental permit, spatial planning and construction permit – into a single permitting procedure (Austria, Germany, Italy, the Netherlands, and the United Kingdom). In Austria, Italy, the Netherlands and the United Kingdom, environmental and spatial planning decisions are integrated into a single development consent procedure. In Germany, all decisions on environmental assessments and other permits are integrated in the plan approval procedure; however spatial planning remains separate (Regional planning procedure), and precedes the plan approval procedure. In the Netherlands, land use plans are automatically updated when the development consent is granted, avoiding the completion of a separate spatial planning decision 38 .

These efforts, even if in many cases effective, are not sufficient to form an EU-wide approach and provide for a synchronised implementation of the TEN-T. First, they are not systematically coupled with time limits (see specifically Section 00) and secondly these measures are not undertaken by the other Member States (even if some of their streamlined approaches are very successful – e.g. integrated permitting in Poland for national roads and railways). But since even the purely national projects affect the developments on the other parts of the Corridors and TEN-T network, as explained also in the Problem section, a harmonising effort across the EU is needed.

Furthermore, the 2018 CBS Progress Report highlights that delays in permitting are often due to multiple steps and authorities and recommends the introduction of a simplified process or at least a mandatory joint procedure for all environmental assessments at project level.

The situation of multiple stages and authorities involved in permitting procedures is described in further details in Annex 5, section 1. The results of the Open Public Consultation carried out for this initiative show that all the categories of stakeholders (98 respondents) with one exception fully or rather agree that permitting procedures are complex and lengthy when it comes to the TEN-T projects (Figure 2 in Annex 2). Moreover, permitting procedures in relation to the TEN-T projects are perceived as suboptimal by most respondents (59 out of 95) to the Open Public Consultation (Figure 5 in annex 3).

It is worth noting that all categories of respondents including governments disagree with the statement that permitting procedures are organised in an optimal way (Figure 3 in Annex 3).

Why does it drive the problem?

As evidenced in the exploratory study 39 , factors of delay, costs and uncertainty in permitting procedures are often rooted in procedural aspects. TEN-T projects have multiple impacts on land-use and the environment, often require conducting multiple environmental assessments, and, given their size, can fall under several jurisdictions if the procedure is handled at regional or local level. Consequently, in some Member States, permitting procedures are complex, involving many steps and permitting authorities, leading to duplication of permits and applications to be submitted by project promoters, duplication of or overlaps in assessment procedures, and significant administrative burden and costs for both the project promoters and permitting authorities. The higher the number of different authorities involved in the permitting procedure (either as permitting authority or consulted authority), the more complex it becomes to gather all of the intermediate decisions required to grant the final permit.

Cross-border projects are particularly vulnerable to the problems described above. The number of permits, the sequence of approvals, time limits, and requirements for public consultation can vary greatly between countries and can result in permitting procedures happening at different speeds on either side of the border 40 .

2.1.2Absent or unenforced time limits

In some Member States, time limits are set out in the legislation for the main permits (EIA, spatial planning) and public consultations, as illustrated in Table 1 . However, global time limits for the entire permitting procedure have not been fixed in any Member State, even where an integrated permitting procedure exits (e.g. Germany). Time limits for environmental assessments generally exist, at least for certain procedures, in particular for screening and scoping, and public consultation. The 2014 amendment to the EIA Directive introduced time limits for screening decisions. However, the competent authority has the possibility, in exceptional cases related to the nature, complexity, location or size of the project, to extend this deadline 41 .

Stakeholders often mentioned that missing documentation or documentation of poor quality was the reason why the permit cannot be issued within the time limit, as additional data had to be requested to the applicant, which often stops the procedure 42 .

In most of the Member States analysed in the exploratory study 43 , sanctions are not applied in case of missed deadlines. Only in Romania, authorities responsible for issuing different certificates or notifications can be fined if they do not respect the timelines for issuing documents, as required by the law.

Why does it drive the problem?

Case studies conducted for this impact assessment showed that large cross-border infrastructure projects generally exceed ten years from early planning to construction. In the ten Member States studied, the duration of the permitting procedure (from the submission of the application to the last permit granted) was, according to interviewed stakeholders, between two and five years 44 . Regardless of the source of the problem, one way of addressing lengthy procedures is to establish time limits, to incentivise permitting authorities to adopt measures and/or administrative practices accelerating the granting of permits. However, global time limits for the entire permitting procedure have not been fixed in any Member State, even where an integrated permitting procedure exits 45 .

Table 1: Permit granting procedures in selected Member States

Member State

Number of procedures required

Number of permitting authorities

Time Limits

Average duration according to stakeholders

Fast-track procedures

Austria

1-3

1-2 (+)

9-12 months for EIA

15 years

n/a

Czech Republic

4 (+ 10-15 opinions)

2

45-90 days per procedure

Final approval: no time limit

3-4 years

n/a

Germany

1

1

No legal time limits

2 years

n/a

Hungary

7-9

4-6

30-42 days per procedure

1-4 years

Possibility to conduct several procedures in parallel

Italy

1

2

150 days for EIA

Up to 10 years

Legge Obbietivo (2001), Development consent granted on preliminary project Tighter time limits for decision-taking

The Netherlands

1

1

2 years

6 years

Limitations of legal standing of municipalities, time limits for judgements in appeals

Poland

2-4

2-3

1-2 months (standard rules of the code of administrative procedures)

1.5-4 years

Number of permits needed reduced to 2 or 3, land covered by permit becomes automatically property of State Treasury

Romania

6-7

6-7

6-12 months EIA,

5-165 days per other procedures

2-5 years

Development consent granted with preliminary approvals regarding forest land and utilities

Automatic change of agricultural land into constructible land once the ownership title is transferred to the state Extension of validity of permits until the end of the construction works

Spain

3

2

24 months for SEA

9 months for EIA

Not available

n/a

United Kingdom

1

1

12 months (9 in Scotland)

Two years

n/a

Source: European Commission based on Milieu et al., 2016.

2.1.3Differing public procurement procedures for cross-border TEN-T projects

Challenges related to public procurement

Public procurement can bring major challenges to TEN-T projects. The research carried out for the exploratory study 46 showed that problems in the procurement phase can result in delays and increased costs for projects. Delays in the completion of the procurement phase appear to be the consequence of a complex legal framework, the absence of time limits for the award procedure and, in particular, the long review procedures to challenge the award decision. Increased costs are directly related to delays but also to the selection of poor quality projects, which appears to be mainly driven by the lack of capacity of contracting authorities to conduct procurement procedures. These challenges are even more prominent for cross-border projects and still remain to be addressed as explained below.

The legal framework for public procurement within the EU is set out in Directive 2014/23/EU, on the award of concession contracts; Directive 2014/24/EU, on public procurement; and Directive 2014/25/EU on procurement by entities operating in the water, energy, transport and postal services sectors. The ‘new’ EU Public Procurement Directives had to be transposed into the Member States’ national legal orders by 18 April 2016. The main objective of the new Directives is to simplify procedures and at the same time make these procedures more flexible 47 ; this is likely to contribute to tackling some of the problems identified above.

The problems linked to cross-border cooperation and differences in the ways in which Member States have transposed the legislation may not be fully tackled by the new legislation. This clearly comes out as a result of the targeted workshop organised specifically on public procurement 48 . Moreover, the full extent of potential problems linked to partial or incorrect transposition, gold-plating, and differences across Member States will only be known once a conformity-checking exercise of transposition of these new Directives has been completed 49 . It may therefore be the case that the new measures will improve the situation regarding complexities and delays related to public procurement procedures for TEN-T projects, and this needs to be taken into account when assessing policy options in this area.

One of the main purposes of EU public procurement is ‘to achieve smart, sustainable and inclusive growth while ensuring the most efficient use of public funds’ 50 . However, public procurement procedures can be a challenge for the smooth implementation of large infrastructure transport projects. This has been recognised in the 2015 CBS Report ‘Action Plan Making the best use of new financial schemes for European transport infrastructure projects’ which included a series of recommendations to ‘streamline and simplify procurement procedures’ 51 .

Remaining complexity of the legal framework

The exploratory study 52 found that, within the transport sector, and more specifically within the context of TEN-T projects, in six out of the ten Member States covered by the study the perception is the same – the complexity of the applicable rules (mainly resulting from the transposition and application of the old EU Public Procurement Directives) is considered an obstacle to a quicker public procurement procedure.

It appears therefore that the complexity of the legal framework and the application of differing public procurement rules to projects developed in a cross-border context can also lead to delays and increase legal uncertainty.

Recent developments in the area of public procurement

Since 2017, the Commission has taken some initiatives to accompany the implementation of public procurement legislation. In particular, a voluntary ex-ante mechanism has been set up 53 to enable the project promoters and other relevant actors to get targeted assistance and assessment from the Commission when developing the procurement strategies for their projects as well as the stage of launching the procurement procedures. This mechanism consists of three elements: a helpdesk 54 , a notification mechanism 55 and an information exchange mechanism.

Notwithstanding, the usefulness of all these elements for contracting authorities and project promoters, the mechanism is however not binding, only provides a compliance assessment and is not automatically open to all TEN-T projects. Certain thresholds apply – as a principle only project beyond 500 million EUR can ask for advice. TEN-T projects of common interest may use the mechanism but only if a decision on the admissibility which will be taken on a case by case basis. This may limit the attractiveness of the instrument to promoters of medium-sized projects.

Why do complexities specific to cross-border procurement drive the problem?

Cross-border projects face specific difficulties in conducting public procurement. This has been highlighted by the project promoters for a long time was confirmed in the public consultation carried out for the exploratory study. They include legal barriers, language barriers and lack of experience in doing business in other countries 56 .

Brenner Base Tunnel

This cross-border project is one of the emblematic TEN-T projects aiming at linking together different parts of the EU. Since the very beginning it was conceived as a long-term asset worth in total 8bn EUR.

In the case of project of this size, a delay of the EIA procedure of 1.5 years in 2006-2007 generated significant losses as a result of inflation and cost of financing.

Moreover, as a result of procurement issues, delays in the start of phase III/works (2011) of about 19 months caused a shift of the finalisation of the project from 2025 to 2026 and led to additional costs of about 20mn EUR (including additional time till finalisation).

Some of these deficiencies were addressed with the adoption of the new procurement directives in 2014. Nevertheless, there are other issues that are still not regulated at EU level, as noted in the 2015 CBS Action Plan, namely ‘the use of a single language in tender and contracting documents’. These problems were reiterated in the Progress Report presented in January 2018.

According to the new rules, the participating contracting entities can agree to apply the national procurement rules of the Member State where the joint entity has its registered office or the national provisions of the Member State where the joint entity is carrying out its activities. In addition, they can choose to apply this agreement for an undetermined period, when fixed in the constitutive act of the joint entity, or limit its application to a certain period of time, certain types of contracts or to one or more individual contract awards.

The new public procurement directives allow for a margin of discretion in the choice of the applicable law, the participating contracting entities struggle to decide on which law to apply and that the scope of application of the agreement ends up being significantly reduced (e.g. applying only during a certain period of time). In addition, these new rules do not seem fully satisfactory for infrastructure projects promoters who still mention the application of different national legal frameworks as the most difficult area for public procurement in the context of cross-border projects 57 .

2.1.4Coordination challenges for the delivery of cross-border projects

Cross-border projects face particular challenges that impact the timing and efficiency of delivery. The involvement of more than one Member State, and often of multiple regional and/or local authorities, can particularly impact the timely completion of permitting procedures. Any delay or obstacle on one side of a border will necessarily impact project delivery on the other side, as project promoters will not proceed with a project until the delivery on both sides of the border can be assured. Given the priority that TEN-T policy gives to cross-border projects 58 , TEN-T core network projects are likely to be particularly impacted by these challenges.

Fehmarn Belt Fixed Link

According to the latest information the German plan approval process for the Fehmarn Belt Fixed Link project could only be finalised by summer 2018. Initially, the plan approval process was expected to be completed by autumn 2015, which means so far more than 3 years of delay. Only after this approval, the construction of the tunnel and access routes on Danish and German side could start. However, it is expected that the plan approval will be brought to the federal administrative court which could result in additional two years of delay. This planning process concerns the German part of the Fixed Link itself, as well as the German access routes and is a prerequisite for the construction phase.

Why does it drive the problem?

Cross-border projects encounter specific problems arising out of inconsistencies between legal permitting frameworks and procedures across Member States. As demonstrated in previous section of this report, the number of permits, the sequence of approvals, time limits, requirements for public consultation can vary greatly between countries and can result in permitting procedures happening at different speeds on either side of the border. Increased coordination of procedures is key in cross-border projects to ensure that the project can develop at roughly the same pace. Different procedures and sequence of permitting procedures generally impact the whole approval process and create time gaps between authorisations in both countries. Detailed description on how the cross-border contexts (such as transboundary EIAs and strategic planning) affect the permitting of the TEN-T projects is contained in Annex 5.

2.1.5Perceived uncertainties related to State aid procedures

State aid control makes sure that State resources mobilised for investments do not lead to unjustified distortion of completion. Some transport authorities may however find State aid notifications challenging, given that in the past investments in transport infrastructure was considered to fall outside State aid rules  59 .

Given the objective to attract more investors to the sector (blending of private and public financing), there will be more and more situations where the State aid control clearance will be of importance in the implementation of the TEN-T projects. Some streamlining measures in this respect have already been applied in the context of the implementation of the European Fund for Strategic Investments which provided for the possibility of priority treatment of the projects benefitting from the support of the European Fund for Strategic Investments  60 .

Why does it drive the problem?

The exploratory study 61 determined that the two main problems at the Member State level driving delays and uncertainty in State aid notifications are late notification and the poor quality of notifications (including information gaps). Cases of late notification generally come from a lack of awareness from authorities or project promoters of the need to notify potential State aid cases to the Commission. In addition, the lack of experience with State notifications in some authorities may lead to notifications that are of a lower quality. This can result in the Commission having to request further information to clarify the facts, lengthening the time needed to have a complete notification necessary for adopting a decision. Some project promoters may also be uncertain about the applicability of State aid rules to their project may also need to seek expert opinions, contributing to additional project costs. There has been important progress in clarifying the State aid rules applicable to the transport infrastructure projects in recent years. In May 2016 the Commission adopted the Notice on the Notion of aid 62 where the Commission clarified in particular when public funding for infrastructure projects falls within the scope of EU State aid control. In 2014 new Aviation Guidelines 63 were adopted and in May 2017 the revised General Block Exemption Regulation as regards aid for port and airport infrastructure 64 was adopted in 2017. In addition, the Commission services published so-called "analytical grids" on the application of State aid rules to the public financing of infrastructure (e.g. for ports, airports, road and rail infrastructure) 65 .

However, the CBS Progress Report proposes to make further steps, also in light of the request of some stakeholders (for example in the light of what already exists as regards the priority treatment of certain cases on mobilising investments 66 ). As acknowledged by stakeholders during the workshop devoted to governance and State aid issues, ex-ante appraisal of State aid compliance is crucial for the financial sector to engage in a project. Therefore, the Progress Report recommends a swift appraisal procedure by the European Commission if a project is in conformity with State aid rules to be generalised in order to clear the project upfront and thus provide legal certainty and predictability about the overall investment.

The Commission carries out its assessment of State aid compliance only once the notification is complete. Therefore, it encourages Member States to make use of the pre-notification procedure which can help the Member States to submit complete notifications. In addition, the Commission gives the possibility to Member States for important and complex projects to establish a mutually agreed planning clearly setting out the timeline and milestones, and the information that needs to be delivered, ensuring a swift adoption of the decision once the notification takes place. This provides Member States with the possibility to agree with the Commission to a priority treatment of the case.

2.6How will the problem evolve?

Without EU intervention, the implementation of the current legislative framework will continue to result in delays and legal uncertainties which impact the effective delivery of the TEN-T projects. As explained in section 2.2, given the transnational nature of the TEN-T, any delay impacting one project has an adverse effect on the whole stretch of a corridor. Overall, the implementation of the core TEN-T network, as foreseen by the TEN-T Regulation, is unlikely to be achieved by 2030.

This situation is not expected to be significantly changed by the transposition of the amendments to the EIA Directive which is meant to be effective as of May 2017. While these amendments are expected to facilitate EIAs for cross-border projects, they do not foresee the complete integration and coordination of permitting procedures, do not introduce an overall time limits for all authorisations and provide for a possibility of optional schemes for conducting cross-border consultations through a joint body. The provisions in the revised EIA directive do not suffice for the needs of the TEN-T projects also as they only allow for integrating assessments required under the EIA, Habitats and Birds directives where appropriate and as the integration of assessments based on other pieces of EU legislation (e.g. water framework directive) remains optional.

In a similar way, this situation would not be significantly changed for the needs of TEN-T projects by the latest revisions of the EU Public Procurement Directives which were meant to be effective in national law since nearly two years. In case of the cross-border procurement, the Directives leave to the Member States to choose the applicable legal framework. The application of the rules to cross-border TEN-T projects would not improve the current situation as the decision will still be taken ad hoc, subject to changing political priorities, without providing the necessary stability to the project promoters.

Furthernore, the mentioned EU law on environmental assesment and public procurement has general nature and broader scope while for TEN-T infrastructure projects, more targeted measures appear necessary .

The risk of inadequate transposition or in diverging ways of this transporsition across the borders of these recent pieces of legislation cannot be excluded on the basis of the current experience. Further explanations are made in chapter 5.1 regarding the baseline scenario.

The administrative costs incurred by the authorities is estimated at €185 million for 2018-2030 (expressed as present value) in the baseline scenario and for project promoters at €937 million over the same time period. Overall, the administrative burden is projected at €1,122 million for 2018-2030, expressed as present value. 67

Finally, the suboptimal framework for the involvement of private investors remains on top of the other problem drivers and has a direct consequence: the investors' base will not expand and transport infrastructure projects will remain unattractive for private investors in many areas of the EU. This will limit the number of projects going ahead as the biggest financial burden will remain on the public expenditures.

3WHY SHOULD THE EU ACT?

3.1The EU's right to act

The EU’s competence to act in relation to transport networks is set out in Article 170 of the TFEU, which requires the EU to ‘contribute to the establishment and development of trans-European networks’ in the area of transport. In detailing what EU action in this area could include, Article 171(2) states that ‘Member States shall, in liaison with the Commission, coordinate among themselves the polices pursued at national level which may have a significant impact’ on the objective of the establishment of trans-European networks, and the ‘Commission may, in close cooperation with the Member States, take any useful initiative to promote such coordination’.

Hence, EU action to set out a framework to streamline the permitting and preparation of projects integral to the establishment of the TEN-T network is within the scope of the EU’s right to act. The EU shares competence in this area with the Member States.

3.2Subsidiarity: necessity of EU action

The transnational nature of the TEN-T network is clear. This is particularly evident in relation to cross-border projects; however, the corridor approach adopted in the TEN-T Regulation is inherently transnational – this approach is intended to ‘coordinate different projects on a transnational basis and synchronise the development of the corridor’ 68 . This coordinated, transnational approach is unlikely to be adequately addressed by Member State action alone.

Permitting procedures in Member States differ greatly in the number of necessary permits and decisions to be obtained. The number of authorities and levels of governance that may be involved in permitting procedures, as well as their competence and power in the procedure also vary significantly across Member States. The delays stemming from these procedures have however significant impact on the TEN-T core network completion.

In terms of public procurement, problems appear to be more related to the way applicable public procurement framework is organised at national level, in particular the long review procedures which appear to be main cause of delays. In case of cross border projects, the problems also stem from the differences in transposition of relevant EU law at national level. For cross-border projects, Member States face similar difficulties when it comes to coordination of public procurement and interpretation of the applicable EU rules, as well as coordination of transboundary environmental assessments.

While according to the results of the Open Public Consultation, national and regional authorities appear less confident that the EU should act, still the majority of stakeholders who participated in this consultation express themselves in favour of the EU taking action in this field (75 out of 99 respondents). The vast majority of individual respondents  believe in the effectiveness of the EU action in this field (16 out of 21 answers). In this sense, the results of the Open Public Consultation confirmed the conclusions of the three dedicated workshops carried out in 2017 and as well as of the interviews and consultations run in the Exploratory Study as shown in Figure 4 Annex 2.

3.3Subsidiarity: Added value of EU action

The completion of the TEN-T core network by 2030 aims at delivering an efficient, smart and sustainable transport network that underpins the single European transport area. This overall strategy is expected to promote low emission mobility, to enable the decarbonisation and digitalisation of transport, to benefit all users of the EU transport systems – businesses and citizens but also to generate investments, economic growth and jobs.

The implementation of the TEN-T requires significant coordination efforts of the various projects in order to fully exploit the overall network benefits at EU level. In this respect, the delivery of the TEN-T network relies on the efficient synchronisation not only of the investments but also of the implementation pace of individual projects to avoid time gaps and reap all benefits from a network approach. This is the approach that has been developed with the TEN-T regulation adopted in 2013. Several tools have been established to generate the European added value expected from the TEN-T network. These include the definition of harmonised standards for greater interoperability, sustainability and efficiency, the development of core network corridors to bridge missing links and remove main bottlenecks, the appointment of European coordinators to facilitate the coordination of relevant actors and the creation of the Connecting Europe Facility and other funding instruments to provide EU support for investments. However, no coordination tools or mechanisms are yet in place in the transport sector – and contrary to others such as energy – to address the needs for synchronisation, coherence and efficiency in the delicate phase of the planning and the implementation of infrastructure projects.

Indeed, infrastructure projects on the TEN-T core network face a number of challenges in regulatory and administrative processes that impact effective and efficient planning and implementation of TEN-T network. Such challenges in permitting procedures, environmental assessment procedures and public procurement practices contribute to increased delays, cost and uncertainty during the planning and preparation of core network projects. This is particularly the case of TEN-T cross-border projects which may be implemented across one or more Member States by a single entity (joint venture) like for Rail Baltica, Brenner Base Tunnel, Fehmarn Belt etc. Unnecessary complexity and duplication of efforts can be avoided by applying the same or coordinating the procedures across the border with a view to maximise synergies and reap the benefits of a European approach. Otherwise, these infrastructure projects are confronted with a multitude of national procedures, differing requirements and regulatory fragmentation.

The policy options presented aim to help the EU achieve the overall objectives of TEN-T policy. They specifically address some of the problems faced by TEN- T core network projects by seeking to streamline permitting, environmental assessment, procurement and State aid processes without prejudice of the content of the legislation underpinning these procedures. The objective of reducing delays and uncertainties can be more efficiently met by providing a stable and clear framework at the EU level

3.4 Why act now?

Several reasons plead for introducing now streamlining measures for the implementation of the TEN-T projects.

The TEN-T Regulation requires the completion of the core network by 2030. This means that there are less than 13 years left to complete all the necessary projects. Based on the fact that in extreme cases the process of project preparation in terms of obtaining permits and designing the technical and financial structure of project lasts around 10 years, no delays can be afforded to meet the deadline. Of course, not all projects are at that level of complexity and it may take less time to prepare them.. A conservative calculation as explained in Section 5.1 shows that in average projects are delayed by approximately 2 years.

The EU economy is still recovering from the economic and financial crisis which resulted in a clear drop in public and private investment in infrastructure. The European Commission has placed the relaunch of investment in the real economy at the very centre of its priorities for 2014-2019. This is the main raison d'être of the Investment Plan for Europe, which third pillar concentrates on the removal of administrative barriers hampering investments and the related benefits.

As a result, many of the TEN-T projects are planned only now to start being implemented in the coming years. These projects will benefit from the streamlined measures and be less prone to delays. This is particularly relevant to foster an effective implementation of TEN-T infrastructure projects in the current and next multi-annual financial frameworks.

The present initiative results from a long reflection process launched at the beginning of the current Commission to contribute to implementing its priorities. As already presented before, the CBS Progress Report clearly summarises the evolution of the reforms of the permitting processes and other authorisations procedures of which are subject TEN-T infrastructure projects are still not sufficient and more ambitious solutions are needed. After a long period of consultation and analysis – started already in 2014 with the Council conclusions under the Italian Presidency – the material and evidence gathered is solid enough to identify the main problems and propose solutions with initiating the legislative proposal. Recently, the TTE Council adopted in December 2017 conclusions on the progress of the Trans-European Transport Network (TEN-T) implementation and the Connecting Europe Facility (CEF) for transport which very much support the continuation of this infrastructure policy and encourage the Commission to give follow up to the reflections on the regulatory environment of the implementations of TEN-T projects 69 .

4OBJECTIVES: WHAT IS TO BE ACHIEVED?

4.1General objectives

The general objective of initiative on streamlining TEN-T implementation is addressing the delays and the high level of uncertainty which impact the effective delivery of the TEN-T core network projects. It will contribute to the objective set in Article 170 TFUE to establish and develop the trans-European transport network as well as to promote the interconnection and interoperability of national networks.

In particular, this initiative aims at accelerating the benefits of the implementation of a fully interoperable and interconnected transport network linking the main economic centres and all the Member States. It will help maximise the impact of the existing national networks requiring upgrades to meet the TEN-T interoperable parameters as well as bridge missing links in Europe. Since the development of the TEN-T focuses on the sustainable modes of transport, this initiative directly contributes to the transition to low emission mobility 70 .

4.2Specific objectives

To achieve this general objective the following specific objectives (SO) have been defined:

-SO1: minimising the risk of delays faced by individual TEN-T projects;

-SO2: increasing legal certainty for project promoters thus attracting more private investors to transport infrastructure

The specific objective 1 (SO1) aims at addressing the important delays encountered in the implementation of TEN-T infrastructure projects which are confronted to a series of difficulties as explained above.

SO1 will tackle the Problem Driver 2 (absent or unenforced time limits), Problem Driver 3 (differing public procurement procedures for cross border TEN-T core projects) and Problem Driver 4 (coordination of delivery of for cross border TEN-T core projects).

The specific objective 2 (SO2) aims at bringing greater clarity in the processes which project promoters need to follow in order to implement the projects, in particular through permitting and other administrative authorisations, public procurements and State aid control.

SO2 will tackle the Problem Driver 1 (multiple stages and authorities involved in permitting procedures), Problem Driver 2 absent or unenforced time limits), Problem Driver 3 (differing public procurement procedures for cross border TEN-T core projects) and Problem Driver 5 (reluctance of private investors to TEN-T core network infrastructure projects)

The initiative will in addition also provide more coherence in implementation of different EU policies. The perceived regulatory obstacles and legal uncertainties for TEN-T projects promoters are very often result of the diverging implementation of EU policies and diverging national implementation of EU rules and complementing them with additional requirements. The achievement of the specific objectives is planned without derogating to any objectives and standards required by the EU policies but by integrating them better together for the benefit of the TEN-T implementation. No trade-offs are expected between the various EU policies.

The objectives are also in line with the policy of attracting private capital to the areas traditionally reserved for public intervention as well as re-launching investment in the real economy. The increased investment in TEN-T infrastructure is necessary to at least partly address the backlog in the transport infrastructure investment being the result of the financial crisis 71 .

The initiative will contribute to closing the infrastructure gap, in particular time gaps in procedures, between different Member States and it will specifically address the cross-border projects which are the priority in the TEN-T core network corridors.

Finally, the initiative is planned to reduce the administrative cost due to over complex procedures and delays in permitting procedures borne by the project promoters. Since the material rules are not planned to be changed, the compliance cost of the initiative is not expected to be high.

5WHAT ARE THE AVAILABLE POLICY OPTIONS?

5.1What is the baseline from which options are assessed (baseline scenario)?

Building on previous priority project reports (2012) 72 , the impact assessment support study assumes that in the baseline scenario only 50% of investments would occur on schedule while 25% of the investments would be delayed due to permitting procedures by one year, 15% by two years, and 10% by three years under a conservative approach.

An analysis of the likely pattern of delays has been made, based on the findings from previous priority project reports (2012). A selection of 34 projects was made. Amongst these projects, 16 projects finished later than planned, delayed on average by 4.25 years. The cross-border projects were on average delayed more than the others. Amongst the 34 projects, delays were caused by a range of factors; technical, political, funding, and procedural. It was not possible to isolate empirically the level or probability of delay linked to specific permitting procedures. However, it is possible to conclude that delays are not occurring on all projects, and that the delays attributed to permitting procedures should be lower than the total length of the delays, as other delay factors are present. Therefore, a “conservative approach” has been chosen for the Baseline scenario that considers an average delay of 2 years due to the permitting procedures.

The baseline scenario builds on the updated EU Reference scenario 2016 but assumes the delays in the implementation of the core TEN-T network investments due to the permitting procedures. 73 The scheduled cumulative investment profile and the investment profile including delays are provided in Figure 3 .

Figure 3 : Cumulative investment profile – scheduled and with delays (baseline scenario)

In the baseline scenario, EU transport activity is expected to continue growing beyond 2015. Freight transport activity for inland modes is projected to increase by 28% between 2015 and 2030 (51% for 2015-2050). Passenger traffic growth would be lower than for freight at 17% by 2030 (36% for 2015-2050). Road transport would maintain its dominant role within the EU for both passenger and freight transport. Rail transport activity is projected to grow faster than for road: passenger rail activity would go up by 33% between 2015 and 2030 (70% for 2015-2050); rail freight activity by 39% by 2030 (75% for 2015-2050). Inland navigation (i.e. inland waterways and national maritime) activity is projected to go up by 23% by 2030 and 43% for 2015-2050. However, delays in investments due to permitting procedures would lead to lower activity than in the updated EU Reference scenario for both rail and inland navigation already over 2015-2020. A description of the baseline scenario assumptions and more detailed results are provided in Annex 4 on Analytical methods.

The administrative costs incurred by the authorities is estimated at €185 million for 2018-2030 (expressed as present value) in the baseline scenario and for project promoters at €937 million over the same time period. Overall, the administrative burden is projected at €1,122 million for 2018-2030, expressed as present value. 74  

Considering the uncertainty, an alternative baseline has been used for the assessment of the policy options where 60% of investments would occur on schedule while 20% of the investments would be delayed due to permitting procedures by one year, 10% by two years, and 10% by three years. The alternative baseline scenario shows higher investments taking place in the beginning of the period. A description of the alternative baseline scenario and more detailed results are provided in Annex 4 on Analytical methods.

The lack of predictability in the procedures is expected to continue, leaving high level of uncertainty for projects promoters and ultimately leading to sub-optimal investment choices. In addition, such uncertainty would not help attract more investments from private capital to transport infrastructure projects which is an objective of the Investment Plan for Europe. This would also limit the impact of financial schemes such as the European Fund for Strategic Investments as well as other innovative financial instruments in the infrastructure field.

5.2Description of the policy options

The stakeholder consultation, the expert meetings, independent research and their own analysis have allowed the Commission services to identify different policy measures, which served as a basis for the identification of the main policy options (in the form of policy option packages). The following process was applied for establishing the policy options:

·Step 1: Identify an extensive list of policy measures addressing the problems (considered policy measures);

·Step 2: Consider policy measures which are retained after a preliminary assessment;

·Step 3: Combine the considered policy measures into policy options and identify options which can be discarded.

The analysis led to a clear conclusions that not the same level of ambition is necessary in every area and a stepwise approach would be appropriate.

In the case of the permit granting procedures, the situation is diverging in many Member States and no harmonised approach has been taken at EU level yet. A higher level of intervention is necessary to cater for a synchronisation of the procedures across the border and allow for a concerted implementation of projects.

In the case of public procurement, a modernised framework started to apply in the last years. However, a gap remains in the area of cross-border procurement and commonly developed projects by two or more Member States. Here, the intervention may only target this specific situation.

In the case of State aid control, the newly adopted clarifications already removed a majority of the uncertainty which hampered the development of projects in the last years. In the case of complex project with sophisticated financial structures, it seems nevertheless necessary that the European Commission is contacted early in the process by the competent national authorities, making use of pre-notifications, which in turn allows complete notifications and facilitates the State aid assessment. The prioritisation of the case, following a mutually agreed timetable between the Member States and the Commission, may allow the swifter adoption of the decision.

Table 2: Available policy measures

Policy measures

Description

Preliminary assessment

Policy Measure 1: Changing the existing legal framework

This measure would envisage changing the legal framework which is applicable to the TEN-T projects. It would require in particular adaptation of the EU directives which are applicable for environmental assessments at project level, EU public procurement rules as well as specific rules on State aid. The foreseen changes would introduce simpler solutions and less stringent requirements for TEN-T projects. This special treatment would derive from the fact that the TEN-T core network projects are per se of specific EU importance and relevance.

The option is feasible from a legal point of view, as the acts to be changed are already in place and there is no doubt that the EU has the competence to act in this field. From a technical point of view the option is also feasible; however, additional analysis would be necessary to determine which minimum requirements would need to remain compulsory. The option would also likely foster project implementation with more flexible approach to certain requirements causing particular problems to project promoters.

However, the option does not seem to be possible or opportune from a political point of view. Firstly, the EU acts most likely to be changed have been very recently revised (for example, new or recently revised public procurement directives) or amended (the EIA directive). Reopening of this legislation would not be rational from the effectiveness and efficiency point of view as well as from the political point of view vis-à-vis the co-legislators. For these reasons, the measure has been discarded.

Policy Measure 2: Exempting TEN-T core network projects from the requirements of the EU legal framework

This measure would provide for a general exemption from the application of certain EU requirements for TEN-T core network projects – modelled e.g. on the similar rules applied for defence purposes. This would be justified by the EU importance of the TEN-T infrastructure overriding other policy objectives.

The option would be very effective from the point of view of transport stakeholders and project promoters. However, the option is not considered legally and politically feasible as there are no sufficient legal grounds for such an intervention into other policy objectives. Moreover, depriving other actors (notably citizens) of the rights acquired by virtue of other pieces of EU legislation for the benefit of project promoters does not seem legitimate and proportionate. The measure is therefore discarded from further analysis.

Policy measure 3: Optimisation of the permitting procedures at national level

This measure would leave the responsibility and authority for delivering the relevel permits at Member State level with the introduction of requirements about the organisation of the proceedings. The procedure would be handled by a single competent authority or ‘one-stop-shop’, designated by each Member State, along with integration of administrative procedures from the point of view of the project promoter.

The measure is considered feasible from the political and legal points of view as the competence related to the territory remains at national level and the EU has right to act based on the clauses in the Treaty on the trans-European networks. The measure is considered to be effective by addressing directly the key problem drivers. The measure has been already applied in the TEN-E setting. The measure will be further analysed.

Policy measure 4: Introduction of an EU authorisation procedure

This measure would define the EU framework for authorisation as well as a separate public procurement framework to be applicable for TEN-T cross-border projects by replacing the national rules. The responsibility and the authority for delivering authorisation for TEN-T core network projects would be shifted to the EU level. The procedure would be handled by an EU authority. A possible variant of this measure is to define the framework at EU level but to keep its application at national level.

The measure is considered feasible from the political and legal points of view, but as the competence is split between EU and Member States, a detailed analysis is required to examine all possible implications. From the technical point of view, the measure requires greater analysis, in particular to determine the key European standards to be applied. The proportionality of the measure is preliminarily considered to entail risks such as the misperception by civil society, NGOs or citizens that their rights to be heard in the context of authorisation procedures would be limited or compromised. The measure is nevertheless considered to be effective by addressing directly the key problem drivers. This policy measure will therefore be further analysed.

Policy measure 5: Introduction of time limits for permitting and other procedures

This measure would define the maximum duration for permitting procedures. This requirement would apply at national level.

The measure is considered feasible from the political and legal points of view with a precedent being in place in the TEN-E framework. The measure does not target the objectives of the EU policies in place but limits itself to the organisation and efforts made and engaged resources in case of certain limited number of projects. The measure is considered to be effective by addressing directly the key problem drivers and will be further analysed.

Policy measure 6: Limiting time for appeals in the procedures related to TEN-T

This measure would further develop policy measure 5 by adding time limits to appeal against the administrative authorisations. This may encompass also remedies in public procurement.

The measure is preliminarily considered feasible from the political point of view; however, it requires further analysis from legal point of view as the EU may not be competent to interfere in this part of the national administrative and judicial legal frameworks. This also true in case of remedies in the public procurement where remedies are treated by courts, due to the national procedural autonomy. However, some proceedings and requirements are derived from EU pieces of law, clarifying their application as regards e.g. the statute of repose may be also assessed by this option. The proportionality of the measure is considered appropriate as it limits the time for appeals while safeguarding the rights of the interested parties. It also addresses the problem drivers leading to the legal uncertainty. Hence, it will be further analysed.

Policy measure 7: Targeted technical assistance

This measure would introduce technical assistance for project promoters and authorities involved in authorisation of TEN-T projects.

The measure is considered feasible from the political and legal point of view as this kind of support is already widely used in different policies. From the financial point of view the measure would require analysis and defining the resources to be used to support the mechanism. The proportionality of the measure is considered appropriate since it contributes to addressing problem drivers. As a consequence, it will be further analysed.

Policy measure 8: Guidelines and clarification of the existing legislation, targeted use of existing mechanisms

This measure would consist of developing a set of soft law instruments meant to clarify and provide more certainty on the application of existing EU legislation. This would in particular concern the rules related to the environmental assessments at project level (including purely indicative time frames), as well as rules on public procurement. It would also build upon the existing support mechanisms – e.g. EIAH, voluntary ex ante mechanism in the public procurement, support/helpdesk on the environmental assessment, etc.

The measure is considered feasible from the political and legal point of view as developing the soft law as well as guiding principles is the competence of the Commission. The effectiveness of the option is not considered optimal as the implementation of the guidelines remains voluntary. The measure has the potential to address part of the problem drivers and should be further analysed.

Policy measure 9: Simplified rules on cross-border procurement

This measure would consist of introducing simplified rules for cross-border procurement, in particular as regards the definition of the applicable EU public procurement rules. It may consist of developing an EU framework for cross-border procurement of TEN-T projects or better targeting the rules of the existing legal acts at EU level.

The measure is considered feasible from the political and legal point of view as the rules on the public procurement are regulated at EU level. Difficulties may arise from the fact that level this solution would eliminate the current flexibility given to the different Member States through the public procurement directives. The specific problems faced by cross-border projects would be effectively and proportionally addressed by this measure. Further analysis is needed on the specific content of the measure as well as the appropriate instrument in relation to the previous policy measures. The measure will be further analysed.

Policy measure 10: Priority treatment of State aid notifications for TEN-T core network projects

The measure would foresee the prioritisation of the related cases, following a mutually agreed timetable between the Member State and the Commission, setting out clearly the milestones and information to be delivered by the Member State. It would build on existing best practices and allow a swifter adoption of the decision after notification.

The use of pre-notification would be encouraged.

The measure is considered feasible from the political and legal point of view as certain arrangements already exist. In addition, State aid control being the exclusive prerogative of the European Commission, the measure would not raise particular legal or institutional difficulties.

The measure would imply that the Commission commits to make its best endeavours efforts to handle State aid cases related to TEN-T core network projects in a speedy way while respecting all requirements of State aid control. The Commission would foresee the priority treatment of TEN-T core network projects, notably as regards mutually agreed planning. This could be addressed in the context of the current identification of best practices for the conduct of State aid control procedures.

The measure addresses problem drivers rooted in the EU role in the context of projects' implementation. The measure will be further analysed.

Policy measure 11: Promotional Campaign on the importance of TEN-T networks at EU level

This measure would aim at mitigating the inherent resistance that some stakeholders may have to the idea of ‘European’ projects. It would consist of conducting public information and awareness raising activities dedicated to the aim of explaining the relevance of EU transport networks. The campaign would target both civil society and authorities involved in the permitting procedures.

The measure is considered feasible from the political and legal points of view. Sources of funding would need to be defined. However, the measure does not seem to be effective and would not adequately address the problem drivers. The measure will not be further analysed.

Policy measure 12: Increased use of strengthened coordination mechanisms foreseen in TEN-T policy

This measure would reinforce the mandate of the European Coordinators appointed by the Commission to facilitate the implementation of the TEN-T core network corridors. The reinforced mandate would enable the European Coordinator to facilitate or ensure adequate coordination of the work of the national authorities involved in the permit granting or (if PM 3 is applied) the national one-stop-shops.

This option is considered feasible from the legal and political point of view as the role of the European Coordinators is positively assessed by the Member States and stakeholders. The option would require reinforcing the Coordinators' secretariats placed in the European Commission. As the measure targets seem to be addressing effectively the problem driver related to the cross-border nature of certain projects, it will be further analysed.

Table 3: Retained policy measures

Driver 1 Multiple stages and authorities involved in the permitting procedures

Measures

Description

3

Optimisation of the permitting procedures at national level

Establishment of a one-stop-shop (OSS) at national level. The OSS would continue to apply national permitting rules (transposed from EU directives).

Integration of various administrative procedures at national level (notably all environmental assessments EIA, Habitat, Water, Seveso, Waste, Birds etc.. currently optional) – legal requirement needed / similar to TEN-E

4

Introduction of an EU authorisation procedure

Definition of a specific framework for the authorisation of TEN-T core network projects to be applied at EU level. This would include integrated procedures, time limits, cases for overriding public interest and make requirement under existing Directives directly applicable legal requirement needed

8

Guidelines and clarification of the existing legislation, targeted use of existing mechanisms

Guidelines for TEN-T project promoters and better orientation of existing instruments (such as the voluntary ex-ante assessment mechanism in the public procurement)

7

Targeted technical assistance

Targeted technical assistance measures for TEN-T core network projects(including high quality and efficient packaging of routine projects). The technical assistance may be modelled on the current JASPERS or EIAH initiatives or use these initiatives if decision is made on their extending to the new MFF.

Driver 2 - Absent or unenforced time limits

Measures

Description

8

Guidelines and clarification of the existing legislation, targeted use of existing mechanisms

Guidelines for TEN-T project promoters with purely indicative time frames

5

Introduction of time limits for permitting and other procedures

Introduction of time limits for overall permitting procedures by the way of recommendation or by legal requirement / similar to TEN-E

6

Limiting time for appeals in the procedures related to TEN-T

Introduction of time limits for legal appeals while preserving access to justice

Driver 3: Differing public procurement procedures for cross-border TEN-T projects

 

Measures

Description

9

Simplified rules for cross-border procurement

Requirement to opt for a single legal framework for public procurement of cross-border TEN-T core network projects (currently optional) – legal requirement needed

6

Limiting time for appeals in the procedures related to TEN-T

Introduction of binding time limits for remedies while preserving access to justice for unsuccessful tenderers

8

Guidelines and clarification of the existing legislation, targeted use of existing mechanisms

Guidelines for TEN-T project promoters and better orientation of existing instruments in the public procurement area (such as the voluntary ex-ante assessment mechanism)

Driver 4 Coordination challenges for the delivery of cross-border projects

Measures

Description

12

Increased use of strengthened coordination mechanisms foreseen in TEN-T policy

Reinforced mandate of the TEN-T European Coordinators to facilitate the cooperation of national permit granting bodied

Driver 5: Perceived uncertainties related to State aid control procedures

Measures

Description

7

Targeted technical assistance

Technical assistance measures for TEN-T core network projects (including high quality and efficient packaging of routine projects) – targeted for project promoters, national authorities and contracting authorities

10

Priority treatment of State aid notifications for TEN-T core network projects

Priority treatment of TEN-T core network projects, following a mutually agreed timetable between the Member State and the Commission, setting out clearly the milestones and information to be delivered by the Member State.

5.3Combining the policy measures into policy options 

Table 4 below provides a description of the three policy options which are envisaged. They have been defined so as to reflect an increasing level of regulatory intervention, in particular the intervention into the national and regional legal systems and the possible adverse effects on the other affected stakeholders than the project promoters, in particular citizens.

The policy options address all the problem drives however they entail an increasing level of expected impacts.

The policy packages are cumulative, in the sense that some measures in policy option 1 are also part of policy option 2, which itself includes further measures. This is valid also for policy option 3 that adds the definition of the rules to be applied in authorisations and public procurement. The only exception is for policy option 3b where the authorisations at EU level would not require the OSS and national level.

It is also worth noting that some policy measures, notably those in policy option 1, involve both non-regulatory instruments (non-binding measures) and/or regulatory instruments.

Detailed description of the policy options by the affected policy areas

Policy option 1 (PO1) – Minimal change to the existing instruments and development of soft law as well as accompanying measures.

This option would consist in particular of developing a series of guidelines for TEN-T project promoters and better orientation of existing instruments (such as planned public procurement helpdesk, JASPERS or EIAH support) as well as of developing targeted technical assistance measures for TEN-T projects of common interest. It would recommend indicative time frames for overall permitting procedures.

·Authorisations and permits:

-Guidelines for the permit granting procedures and application of the EU acquis in this field, including indicative time frames.

-Systematic encouragement in soft law instruments (e.g. guidelines) to apply joint and/or coordinated procedures under Article 2(3) of the revised EIA Directive 75 .

·Public procurement

-Guidelines for TEN-T project promoters and better orientation of existing instruments (such as planned public procurement helpdesk, JASPERS or EIAH support)

·State aid: No change

·Other

-Targeted technical assistance measures for TEN-T core network projects (including high quality and efficient packaging of routine projects).

-Effective technical assistance (e.g. modelled on the JASPERS or the European Investment Advisory Hub, or directly using these initiatives if decision is made on their extending to the next MFF) to support project preparation and horizontal issues affecting the implementation of TEN-T projects, both at the Member State and EU level (systematically involving cooperation Member States – JASPERS (or other initiatives of this type) –European Commission to develop tailor-made solutions for individual Member States);

-Reinforced mandate of the TEN-T European Coordinators to facilitate the coordination of national permit granting bodies

Policy option 2 (PO2) – Limited binding action to be decentralised and implemented at national level.

This option would foresee the legal requirement for Member States to introduce one-stop-shop for TEN-T core network projects and ensure that the most rapid treatment legally possible.is given to them. The key elements of this option would consist of a set of the following measures:

·Authorisations and permits:

-Establishment of a mandatory one-stop-shop (OSS) at national level. The OSS would continue to apply national permitting rules (transposed from EU directives)

-Mandatory integration of various administrative procedures at national level (notably all environmental assessments EIA, Habitat, Water, Seveso, Waste, Birds etc.. currently optional)

-Introduction of time limits for overall permitting procedures

-Introduction of time limits for legal appeals while preserving access to justice.

·Public procurement

-Requirement to mandatory opt for a single legal framework for public procurement of cross-border projects (currently optional)

-Guidelines for TEN-T project promoters and better orientation of existing instruments (such as planned public procurement helpdesk, initiatives modelled on the JASPERS or EIAH support, or directly using these initiatives if decision is made on their extending to the next MFF)

·State aid

-No modification of legislative nature

-Priority treatment of State aid notifications for TEN-T core network projects, following a mutually agreed timetable between the Member State and the Commission

·Other

-Targeted technical assistance measures for projects of common interest (including high quality and efficient packaging of routine projects)

-Reinforced mandate of the TEN-T European Coordinators to facilitate the coordination of national permit granting bodies

Policy option 3 (PO3) –An EU framework for authorisation of the TEN-T core network projects.

This option includes elements of the Policy option 2 however instead of the mandatory one-stop-shop and integration of administrative procedures at the national level it introduces a specific EU framework for the authorisation of TEN-T core network projects (including integrated procedures, time limits, cases for overriding public interest and directly applicable requirements)and the definition of a specific (supranational) set of rules to be applied in public procurement of cross-border projects. Policy option 3 contains two sub-options which differ in the level of application and therefore include further measure:

-PO3a: the measures regarding EU authorisation procedure with time limits are defined at EU level but remain applied at national level, with national institutions implementing them in practice and following the national administrative procedural rules with possibility for appeal and access to justice based on the national administrative procedural law;

-PO3b: the measures regarding EU authorisation procedure with time limits are applied at EU level by the Commission (or its agencies). Usual EU rules on procedures and possibility for appeal apply with EU judicial remedies to the Court of Justice of the European Union.

Scope of the measures:

The analysis of policy options is made on a three different categories of projects which are the following:

-All TEN-T core network projects, as identified through the TEN-T framework;

-Projects identified on the Core network corridors – with a particular role for the European Coordinators to identify these projects;

-Projects which are pre-identified as those eligible to benefit from Union financial support through CEF (as well as from other sources such as EFSI etc.) and which would be reflected in Annex I to the CEF regulation.

Table 4: Definition of policy options

Policy option 1 - Minimal change to the existing instruments and development of soft law as well as accompanying measures

·Measures aimed at providing guidelines and clarification of the existing legislation (including indicative time frames), targeted use of existing mechanisms in all of the fields identified as problem drivers (environmental assessments, public procurement, State aid and development of alternative financing for the TEN-T core network projects);

·Measures aimed at introduction of time limits for permitting and other procedures

·Measures aimed at targeted technical assistance;

·Measures aimed at increased use of strengthened coordination mechanisms foreseen in TEN-T policy.

Policy option 2 - Limited binding action to be decentralised and implemented at national level t national level.

·Measures aimed at optimisation of the permitting procedures at national level (one stop shop, most rapid treatment legally possible);

·Measures aimed at targeted technical assistance;

·Measures aimed at introduction of time limits for permitting and other procedures;

·Measures aimed at limiting time for appeals in the procedures related to TEN-T core network;

·Measures aimed at requiring the national authorities to opt for a single legal framework for public procurement of cross-border projects (law of the seat of the contracting authority);

·Measures aimed at increased use of strengthened coordination mechanisms foreseen in TEN-T policy;

·Measures aimed at giving priority treatment of State aid notifications for TEN-T core network projects.

Policy option 3a An EU framework for authorisation of the projects of common interest to be applied at national level

In addition to the measures in policy option 2, this policy option intends to establish a common set of EU rules for authorising TEN-T core network projects at national level and includes the following policy measures:

·Measures aimed at introduction of an EU authorisation procedure with time limits to be applied at national level;

·Measures aimed at targeted technical assistance;

·Measures aimed at limiting time for appeals in the procedures related to TEN-T core network;

·Measures aimed at simplifying rules for cross-border procurement;

·Measures aimed at increased use of strengthened coordination mechanisms foreseen in TEN-T policy;

·Measures aimed at giving priority treatment of State aid notifications for TEN-T core network projects.

Policy package 3b An EU framework for authorisation of the projects of common interest to be applied at EU level

In addition to the measures in policy option 2, this policy option intends to establish a common set of EU rules for authorising TEN-T core network projects and apply them at EU level. It includes the following policy measures::

·Measures aimed at introduction of an EU authorisation procedure with time limits to be applied at EU level;

·Measures aimed at targeted technical assistance;

·Measures aimed at limiting time for appeals in the procedures related to TEN-T core network;

·Measures aimed at simplifying rules for cross-border procurement;

·Measures aimed at increased use of strengthened coordination mechanisms foreseen in TEN-T policy;

·Measures aimed at giving priority treatment of State aid notifications for TEN-T core network projects.

Table 5 below links the individual policy measures with the problem drivers identified in the problem definition and the respective policy options.

Table 5: Presentation of policy options related to mapping of measures and drivers (V: voluntary; M: mandatory)

Policy measure

P1

P2

P3a

P3b

Driver 1: Multiple stages and authorities involved in permitting procedures

1.Optimisation of the permitting procedures at national level

x

✓ M

x

x

2.Introduction of an EU authorisation procedure applied at national level

x

x

✓ M

x

3.Introduction of an EU authorisation procedure applied at EU level

x

x

x

✓ M

4.Guidelines and clarification of the existing legislation, targeted use of existing mechanisms

✓ M 

✓ V

✓ V

✓ V

5.Targeted technical assistance

✓ M  

✓ V

✓ M  

✓ M  

Driver 2: Absent or unenforced time limits

6.Introduction of time limits for permitting and other procedures

✓V

✓ M

✓ M

✓ M

7.Limiting time for appeals in the procedures related to TEN-T

V

✓ M

✓ M

✓ M

Driver 3: Differing public procurement procedures for cross-border TEN-T projects

8.Simplified rules for cross-border procurement

x

✓ M 

✓ M 

✓ M 

9.Limiting time for appeals in the procedures related to TEN-T

x

✓ M 

✓ M 

✓ M 

10.Guidelines and clarification of the existing legislation, targeted use of existing mechanisms

✓ M

✓ V

✓ V

✓ V

Driver 4: Coordination challenges for the delivery of cross-border projects

11.Increased use of strengthened coordination mechanisms foreseen in TEN-T policy

✓ M

✓ M

✓ M

✓ M

Driver 5 Perceived uncertainties related to State aid control procedures

12.Targeted technical assistance

✓ M

✓ V

✓ M

✓ M

13.Priority treatment of State aid notifications for TEN-T core network projects

x

✓ M

✓ M

✓ M

6WHAT ARE THE IMPACTS OF THE POLICY OPTIONS?

This section presents the economic, social and environmental impacts for the different policy options. Impacts are assessed for infrastructure projects in the road, rail, maritime and inland waterways projects and then compared to the baseline scenario. Each policy option has a different level of effectiveness in terms of reducing the delays in the implementation of investment projects (i.e. soft measures in PO1 versus limited binding action in PO2 and EU framework for authorisation of TEN-T core network projects in PO3); this has been taken into account in evaluating the impacts. The options have been tested for three different scopes of application (TEN-T core network, core network corridors and CEF Annex 1 projects). More details on the methodology used are presented in Annex 4 on analytical methods. 76

The assessment of economic as well as social and environmental impacts can be considered as a conservative one: it takes into account only the currently planned TEN-T core network projects and not the future projects, in particular after 2030, which are not in the TEN-T plans yet. The benefits would be larger when also considering the TEN-T comprehensive network projects beyond 2030.

6.1 Economic impact

All three policy options generate benefits in terms of reduced delays in project implementation relative to the baseline. They have direct impacts on investments profile over time, users' transport costs and macro-economic impacts in terms of generated growth. The impacts on the administrative costs for the project promoters and the permitting authorities are also discussed in this section, followed by the impacts on the transport as a business and a qualitative analysis of impacts on SMEs.

6.1.1 Impacts on investments

The reduced delays in project implementation have a direct impact on the cumulative investment profile in each policy option (see Table 6 ). PO1 results in higher investments already in 2020 (39% of total investments over the lifetime of the projects) as it implies minimal change to the existing instruments and development of soft law that take less time to implement. However, PO1 is less effective by 2025 compared to PO2 and PO3. PO2, reflecting limited binding action to be decentralised and implemented, results in 84.2% of total investments taking place by 2025, compared to 81.4% in the Baseline. PO3 that reflects an EU framework for authorisation of core TEN-T projects to be applied at national level results in higher impact, with 85.1% of total investments taking place by 2025. The ranking of the options in terms of impacts is similar for rail and waterborne transport (see Table 6 ).

Table 6: Share of total core TEN-T investments in the policy options for 2020-2025 over the lifetime of the projects

Cumulative investments (share of total core TEN-T network investments over the lifetime of the projects)

2020

2021

2022

2023

2024

2025

Total investments

Baseline

38.7%

50.1%

60.0%

68.5%

75.5%

81.4%

Option 1

39.0%

50.6%

60.7%

69.3%

76.4%

82.1%

Option 2

38.7%

50.1%

61.6%

71.2%

78.9%

84.2%

Option 3

38.7%

50.1%

60.0%

73.9%

80.0%

85.1%

Rail transport

Baseline

36.1%

46.9%

56.1%

64.3%

71.2%

77.2%

Option 1

36.4%

47.4%

56.8%

65.1%

72.0%

77.9%

Option 2

36.1%

46.9%

57.6%

66.9%

74.5%

80.1%

Option 3

36.1%

46.9%

56.1%

69.5%

75.6%

81.0%

Waterborne transport

Baseline

40.6%

53.8%

65.8%

75.2%

82.9%

89.0%

Option 1

41.0%

54.5%

66.7%

76.1%

83.8%

89.7%

Option 2

40.6%

53.8%

67.7%

78.2%

86.5%

91.8%

Option 3

40.6%

53.8%

65.8%

81.1%

87.7%

92.7%

Source: Impact Assessment support study; waterborne transport covers inland waterways and maritime.

6.1.2Impacts on tranport users' costs

All policy options for all scopes of applications show benefits in terms of reduced user costs compared to the baseline scenario. They bring benefits to the users in terms of time savings, increased reliability of transport and lower transport costs, and thus contribute to the increased productivity of the sector. The TEN-T core network scope of application shows the highest benefits, as the scope is also the largest. PO1 would generate €1.8 bn of benefits (0.1% decrease in total user costs compared to the baseline over 2018-2030, expressed as present value), while PO2 would result in €5.1 bn reduced user costs (0.2% decrease relative to the baseline). PO3 shows the largest benefit (€6.6 bn) due to the higher effectiveness of a specific EU framework for the authorisation of TEN-T core network projects in reducing the delays.

The application of the three options to the core network corridors and CEF Annex 1 projects would bring smaller benefits as the scope of the projects is narrower than the TEN-T core network (i.e. the core network corridors cover about 75% of the core network investments). Even when considering the narrower scope of application (CEF Annex 1 projects), the policy options would still result in more than €1 bn reduction of user costs relative to the baseline (expressed as present value over 2018-2030). The ranking of policy options in terms of reduced user costs would be similar for all scopes of application.

Table 7: Impacts on user costs relative to the baseline over the lifetime of the projects (2018-2030)

 

Baseline*

PO1

PO2

PO3a/PO3b

Total user costs (present value in million € and % change to the baseline)

Core TEN-T network, of which:

2,460,763

-1,838

-5,069

-6,648

-0.1%

-0.2%

-0.3%

Core network corridors

-1,379

-3,802

-4,986

-0.1%

-0.2%

-0.2%

CEF Annex 1 projects

-1,020

-2,813

-3,690

0.0%

-0.1%

-0.1%

Source: Panteia, Impact Assessment support study (2018); Notes: * The baseline figures relate to the traffic on the core TEN-T network

6.1.3Impact on economic growth

All policy options are expected to have a positive impact in terms of economic growth. Compared to the baseline, PO3 shows the highest economic benefits generated at EU level, in the range of €1.2 bn to €2.1 bn (1.2-2.1%) over 2018-2030, followed by PO2 (€0.9 bn to €1.6 bn benefits, 0.9-1.6% increase relative to the baseline) and PO1 (€0.3 bn to €0.6 bn benefits). The impacts are assessed through multiplier effects; they account for wider effects than only the construction of projects, namely the indirect effects on other economic sectors and the effects induced by increased productivity, improved conditions for international trade and technological spill-overs. More explanations regarding the quantification of these impacts are provided in Annex 4.

Table 8: Annual average economic benefits relative to the baseline for 2018-2030

 

Baseline

PO1

PO2

PO3a/PO3b

Economic benefits (in billion € and % change to the baseline)

Core TEN-T network projects, of which:

95

0.6

1.6

2.1

0.6%

1.6%

2.2%

Core network corridors projects

0.4

1.2

1.6

0.4%

1.2%

1.6%

CEF Annex 1 projects

0.3

0.9

1.2

0.3%

0.9%

1.2%

Source: M-FIVE and Panteia, Impact Assessment support study (2018)

6.1.4Impact on administrative burden

The initiative is expected to have a direct impact on the administrative costs for the permitting authorities and for the project promoters. The administrative burden for authorities considers both costs for the EU institutions and the Member States authorities. The inputs used for calculating the impacts on administrative burden are provided in Annex 4. They draw on results of the stakeholders' consultation, literature review, TEN-E impact assessment 77 , etc. 78

In PO1, the introduction of guidelines for permit granting and effective technical assistance for project promoters is estimated to lead to savings in administrative burden for the TEN-T project promoters in the order of €27 million over 2018-2030 relative to the baseline (expressed as present value). However the authorities’ administrative burden is expected to slightly increase (€9 million, 5% increase relative to the baseline) because guidelines would need to be defined and implemented (albeit on a voluntary basis).

In PO2, the establishment of a one-stop-shop at national level 79 is estimated to lead to slightly higher costs for the permitting authorities (€13 million over 2018-2030 horizon) but also for larger benefits in terms of reduced costs for project promoters (€166 million) over 2018-2030 horizon relative to the baseline. PO2 is in fact the option which achieves the highest reduction in the total administrative burden (€153 million).

PO3, which includes elements of PO2 like the mandatory one-stop-shop and the integration of administrative procedures at the national level but also a specific EU framework for the authorisation of TEN-T core network projects, results in higher additional costs for permitting authorities than PO1 and PO2 (€20 million over 2018-2030 horizon) but also lower benefits for project promoters than PO2 (€120 million over 2018-2030 horizon relative to the baseline).

Table 9: Impacts on administrative burden relative to the baseline scenario, over the period 2018 – 2030, expressed as present value

 

Baseline (€ million)

Policy options

Difference in costs relative to the baseline (€ million)

% change in costs relative to the baseline

Promoter

937

PO1

-27

-3%

PO2

-166

-18%

PO3

-120

-13%

Authority

185

PO1

9

5%

PO2

13

7%

PO3

20

11%

Total

1,122

PO1

-18

-2%

PO2

-153

-14%

PO3

-100

-9%

Source: Panteia, Impact Assessment support study (2018)

These calculations have also been confirmed by the results of the opinion of the stakeholders on the planned measures. Regarding the integration of procedures under a national single entity (OSS), the measure was supported in particular by project promoters, individuals and industrial interest groups, i.e. those who would largely benefit from the planned measures. However, more reserved opinions were expressed by national but mainly regional governments, i.e. those stakeholders where administrative costs would be generated, at least in the induction period.

Figure 4: Should a single permitting authority (a ‘one-stop-shop’) be entrusted to apply standardised procedures to TEN-T projects?

Source: results of the Open Public Consultation.

6.1.5Impacts on transport as a business

The overall aim of TEN-T policy is the promotion of sustainable modes of transport and modal shift to railways, inland waterways and short sea shipping. For passenger rail, the reduction in delays in the implementation of the core TEN-T investment projects is estimated to lead to 551 to 2,940 additional million passenger-kilometres (1.3% to 6.7%) in 2025 and 320 to 1,704 million passenger-kilometres (0.6% to 3.4%) in 2030 relative to the baseline. Similarly, rail freight activity would go up by 273 to 1,458 tonne-kilometres (0.3% to 1.4%) in 2025 and 160 to 856 tonne-kilometres (0.1% to 0.7%) in 2030 relative to the baseline. Waterborne transport activity would also increase, by 359 to 1,916 tonne-kilometres in 2025 and 68 to 360 tonne-kilometres in 2030 relative to the baseline. PO3 shows the highest impacts in terms of traffic shifted from road towards rail and waterborne transport.

Table 10: Traffic shifted to rail and waterborne transport in 2030 relative to the baseline (in million pkm/tkm)

Traffic shifted to rail and waterborne transport in 2025 and 2030 (in millions pkm/tkm and % change to the baseline)

Baseline*

PO1

PO2

PO3a/P3b

Core TEN-T network projects - results for 2025

Passenger transport

259,998

-14

0.0%

-56

0.0%

-75

0.0%

Road

216,310

-565

-0.3%

-2,261

-1.0%

-3,015

-1.4%

Rail

43,688

551

1.3%

2,205

5.0%

2,940

6.7%

Freight transport

626,552

-15

0.0%

-62

0.0%

-83

0.0%

Road freight

171,596

-648

-0.4%

-2,593

-1.5%

-3,457

-2.0%

Rail

105,579

273

0.3%

1,093

1.0%

1,458

1.4%

Waterborne transport**

349,377

359

0.1%

1,437

0.4%

1,916

0.5%

Core TEN-T network projects - results for 2030

Passenger transport

273,775

204

0.1%

815

0.3%

1,087

0.4%

Road

224,195

-116

-0.1%

-463

-0.2%

-617

-0.3%

Rail

49,580

320

0.6%

1,278

2.6%

1,704

3.4%

Freight transport

680,578

92

0.0%

366

0.1%

489

0.1%

Road freight

182,889

-136

-0.1%

-545

-0.3%

-727

-0.4%

Rail

118,483

160

0.1%

642

0.5%

856

0.7%

Waterborne transport**

379,206

68

0.0%

270

0.1%

360

0.1%

Source: Panteia, Impact Assessment support study (2018); Notes: * The baseline figures relate to the traffic on the core TEN-T network; ** Waterborne transport covers inland waterways and national maritime.

6.1.6Impact on small and medium size entreprises

The TEN-T core network projects are usually implemented by large civil contractors, specialised in delivering pieces of large infrastructure and associated engineering structures. This requires specific experience and competence and not many SMEs have the necessary capacity. Cross-border procurement based on merged tendering procedures across the border may also strengthen the position of larger companies which have more experience in working in different Member States. The participation of SMEs is in any case very often limited by contracting authorities, given the requirement of substantial experience and capacity. Therefore, no direct impacts on the SME sector are expected.

However, at large construction sites SMEs are usually sub-contractors implementing simpler works and parts of the infrastructure which do not require specific equipment or experience. The overall impact on the civil engineering market is expected to have positive spill-over effects on SMEs in the construction market. This impact is believed to be captured in the analysis of the wider economic impacts on jobs and growth.

6.2Environmental impacts

Environmental impacts are assessed in terms of impacts on CO2 emissions and air quality as well as impacts on noise emissions.

6.1.7CO2 emissions and air quality

The faster shift of traffic from road to more sustainable transport modes in the policy options relative to the baseline is projected to result in lower emissions of CO2. The reductions are presented in cumulative terms over the lifetime of the projects (2018-2030).

Table 11: Impacts on CO2 emissions and costs relative to the baseline over the lifetime of the projects (2018-2030)

 

Baseline*

PO1

PO2

PO3a/PO3b

CO2 emissions (thousand tonnes CO2 difference and % change relative to the baseline)

Core TEN-T network, of which:

1,602,292

-917

-2,686

-3,543

-0.1%

-0.2%

-0.2%

Core network corridors

-688

-2,015

-2,657

0.0%

-0.1%

-0.2%

CEF Annex 1 projects

-509

-1,491

-1,966

0.0%

-0.1%

-0.1%

Costs (present value in million € and % change relative to the baseline)

Core TEN-T network, of which:

85,939

-68

-193

-253

-0.1%

-0.2%

-0.3%

Core network corridors

-51

-144

-189

-0.1%

-0.2%

-0.2%

CEF Annex 1 projects

-38

-107

-140

0.0%

-0.1%

-0.2%

Source: Panteia, Impact Assessment support study (2018); Note: * The baseline figures relate to the traffic on the core TEN-T network.

The most effective option from this perspective is PO3, where the CO2 emissions reductions for the largest scope of application (core TEN-T network) amount to 3.5 million tonnes relative to the baseline scenario, representing around €253 million external costs savings over 2018-2030 relative to the baseline (expressed as present value). PO2 shows somewhat lower impacts, with 2.7 million tonnes of CO2 saved relative to the baseline (equivalent to €193 million external costs savings), followed by PO1 with significantly lower impacts (0.9 million tonnes of CO2 saved, equivalent to €68 million external costs savings).

The environmental impacts of the initiative are also foreseen to result in the reduction of emissions of air pollutants from road transport such as NOx and particulate matter (PM2.5). The overall impacts of the policy options on the air pollution, despite being positive, are however limited in size (€2.9 to 7.6 million external costs savings for the core TEN-T network scope of application).

Table 12: Impacts on external costs of air pollution relative to the baseline over the lifetime of the projects (2018-2030)

 

Baseline*

PO1

PO2

PO3a/P3b

External costs of air pollution (present value in million € and % change relative to the baseline)

Core TEN-T network, of which:

49,344

-2.9

-5.6

-7.6

0.0%

0.0%

0.0%

Core network corridors

-2.2

-4.2

-5.7

0.0%

0.0%

0.0%

CEF Annex 1 projects

-1.6

-3.1

-4.2

0.0%

0.0%

0.0%

Source: Panteia, Impact Assessment support study (2018); Note: * The baseline figures relate to the traffic on the core TEN-T network.

6.1.8Impact on noise emissions

All policy options are projected to lead to benefits in terms of savings in external costs of noise relative to the baseline linked to the reduction in road traffic. PO1, in its largest scope (core TEN-T network), would result in about €10 million external costs savings over 2018-2030, expressed as present value. PO2 and PO3 show somewhat higher impacts (€27 to 35 million) relative to the baseline, equivalent to around 0.1-0.2% decrease. This outcome is linked to the higher amount of traffic shifted away from road in PO2 and PO3 relative to PO1.

Table 13: Impacts on external costs of noise relative to the baseline over the lifetime of the projects (2018-2030)

 

Baseline*

PO1

PO2

PO3a/PO3b

External costs of noise (present value in million € and % change relative to the baseline)

Core TEN-T network, of which:

19,319

-10.2

-26.9

-35.1

-0.1%

-0.1%

-0.2%

Core network corridors

-7.6

-20.1

-26.3

0.0%

-0.1%

-0.1%

CEF Annex 1 projects

-5.6

-14.9

-19.5

0.0%

-0.1%

-0.1%

Source: Panteia, Impact Assessment support study (2018); Note: * The baseline figures relate to the traffic on the core TEN-T network.

6.3Social impacts

Apart from the economic and environmental impacts, the initiative is expected to generate a number of social impacts and to affect civil society players such as local communities and their authorities, conservation NGOs and the individual citizens’ rights vis-à-vis the processes of TEN-T infrastructure planning, which are usually managed at national level.

This section presents the impacts on public participation in strategic planning, on public participation in the planning and approval of individual projects and on public acceptance but also on employment, health and EU cohesion, local benefits, life quality and social inclusion.

6.1.9Impacts on public participation in strategic planning

The long term planning of transport infrastructure is usually done at highest national (or federal) level and usually also linked to the allocation of public funds to individual projects.

This process is usually subject to public consultation based on national rules related to the long-term strategies. Transport infrastructure development strategies are "plans and programmes” in the sense of the Strategic Environmental Assessment Directive (SEA Directive) 80 . The SEA Directive requires the consultation of the public with sufficient time foreseen to allow the expression of opinions. None of the policy options would derogate the rules set by SEA Directive.

PO1 has no impact on the involvement of the civil society. If a set of guidelines are prepared to address the inefficiencies of the implementation and preparation of the projects, these will be targeting the procedures at project level, not affecting the involvement of civil society at strategic level.

PO2 would also have no impact on the implication of civil society in strategic planning as this policy option integrates permitting procedures at the level of a single project (and not at the level of plans and programmes).

The application of PO3 would result in granting certain permits or authorisation according to EU rules or even at EU level in the case of sub-option PO3b with reference to the TEN-T core network. In such circumstances, the TEN-T framework would become the main strategic infrastructure "plan or programme" in the sense of the SEA directive. A strategic environmental assessment would then need to be conducted at EU level with the appropriate consultation at EU level. This may lead to a greater distance with EU citizens and could entail a negative impact on civil society and public participation. It can be assumed that consultations run at EU level may be less accessible and less comprehensible for local communities, despite all the efforts made by the European Commission to publicise them. Thus the civil society could have less impact on strategic planning of transport infrastructure that is directly affecting their everyday life.

Different approaches to communication on strategic decisions lead to blockages at project stage – case of the Lyon – Torino link

A key challenge in many TEN-T projects is that the main project benefits are often realised at EU level, rather than at national, regional or local levels. This needs to be communicated early in the process of preparing a project. In case of the Lyon – Torino Railway, on the French side public participation took place early in the project planning phase, leading to greater transparency and acceptance of the project by the local municipalities. On the contrary, Italian efforts to involve the local citizens in the planning process came only in 2006, after significant opposition from the local population in the Italian Susa Valley organised in the "‘No Tav" movement. Participation is an ongoing process, which should start before the project decision is made for instance in the context of a SEA and continue after the formal approval (permitting phase) of the project.

6.1.10Impacts on public participation in the planning and approval of individual projects and on public acceptance

The development of infrastructure projects requires detailed project designs to identify notably the actual alignment and technical solutions. This process is usually subject to public consultation based on national rules transposing the requirements of the Environmental Impact Assessment Directive. On top of these requirements come consultations based on various national rules (spatial planning, other administrative and material rules on affected parties e.g. owners of the neighbouring pieces of land). These consultations are most important for civil society to be heard in the process leading to the development of transport infrastructure. All the considered policy options would have implications on these rights of the civil society.

EU directives requiring public consultations have been transposed in a differing manner across Member States. As explained above in section 2, national rules go sometimes beyond what is required by EU law. Clarifying those rules as foreseen under PO1 would be neutral on civil society's participation, as Member States can continue to apply existing rules. A positive effect may even be seen in the cross-border context resulting from a greater alignment of consultation procedures which ultimately increase the involvement of civil society from across the border.

An undersea tunnel blocked at one of the ends

The Fehmarn Belt Fixed Link aims to create a direct fixed 18km long undersea link between Denmark and Germany. In Denmark, the approval process was reasonably smooth. The EIA of the Fehmarn Belt link, after extensive and effective consultation, was approved by the Danish parliament in the form of a Construction Act in April 2015. Approval on the German side has been delayed. Under German law, only a German authority can apply for project approval for motorways on German territory. Moreover, compared to Denmark, the procedure in Germany is longer, with numerous public consultations and hearings. Public participation is equally important in Denmark and Germany and, while both comply with the EIA Directive and the Aarhus Convention, their processes differ. As a result, the project, ready at the Danish side, is blocked at German shore and cannot go forward until all the procedures are completed.

PO2 is not meant to change the rules governing public involvement in the planning of individual projects. However, the integration of procedures as well as the coordination of the overall authorisation procedures would have an impact on public consultations. The existing complex process of project approval involving several bodies at different stages of the procedure would be replaced by one procedure with a single authority leading the process (one stop shop authority). While there is a risk that this could affect their rights due to changed procedures and potentially reduced time for public consultations, civil society as well as local communities could also benefit from a clearer framework allowing their comments to be well channelled and better addressed to the decision maker. As a trade-off for the potentially reduced possibilities of various consultations where they can express their views, the greater synchronisation of process and introduction of time limits could also be an opportunity for local communities and conservation NGOs to have their voice heard due to innovations in the procedures. For instance, the use of new technologies or the digitalisation of public consultation can simplify and increase the outreach to the population concerned and increase civil society impact 81 . As in the PO1, positive effects are expected also in the cross-border context with better comprehension of the consultation systems in the neighbouring Member State.

Under PO3, any attempts to simplify existing requirements notably by reducing certain steps or possibilities of public consultation could be well accepted by national authorities and project promoters while they would be negatively perceived by civil society, in particular by NGOs active in the environmental area. The positive effects of a clarification of the procedures as foreseen under PO2 would be offset by the suspicion of lowering environmental or other standards. The risk of negative social impacts appears even greater if authorisations are brought up to the EU level (PO3b). The decision making authority in the latter case would be much more distant from the affected communities. Even if the fundamental rights would be safeguarded by the careful definition of the rules, their effective enforcement would be difficult due to technical and organisational issues.

In the public consultation it was particularly highlighted by local and regional authorities as well as NGOs and civil society that currently the general public is not sufficiently involved in the project planning. According to this group of stakeholders, the general public is insufficiently involved in the whole project planning; it may be due to the scattered procedures which are not perfectly timed or coordinated.

Figure 5: According to your knowledge and experience, what may be the reason for a lack of public acceptance of certain transport infrastructure projects?

Source: results of the Open Public Consultation.

6.1.11Impact on employment

All policy options are expected to have positive impacts on employment. PO3 in its largest scope of application (core TEN-T network projects) would result in around 7,500 additional jobs per year or 2.2% increase relative to the baseline. PO2 also shows significant impacts in terms of additional job creation relative to the baseline (5,600 additional jobs per year or 1.6% increase relative to the baseline). PO1 and the reduced scope of application (core corridor networks and CEF Annex 1 projects only) generate lower but still positive impacts relative to the baseline. The impacts are assessed through multiplier effects. More explanations regarding the quantification of these impacts are provided in Annex 4.

Table 14: Annual average impacts on employment relative to the baseline for 2018-2030

 

Baseline

PO1

PO2

PO3a/PO3b

Employment impacts (in thousand job-years and % change to the baseline)

Core TEN-T network projects, of which:

344

1.7

5.6

7.5

0.5%

1.6%

2.2%

Core network corridors projects

1.3

4.2

5.6

0.4%

1.2%

1.6%

CEF Annex 1 projects

1.0

3.1

4.2

0.3%

0.9%

1.2%

Source: M-FIVE and Panteia, Impact Assessment support study (2018)

6.1.12Impact on public health – reduction of accidents

The initiative does not specifically target public health. However, it is expected to result in a decrease of road traffic relative to the baseline and modal shift to safer modes (in particular rail). The improvement of safety of the transport operations is also linked to the provision of better quality infrastructure and filling the gaps in the missing infrastructure. Hence, it would result in a reduction of the number of fatalities, serious and slight injuries relative to the baseline. If infrastructure projects are implemented as planned without delays, those benefits will be generated earlier.

The highest savings in terms of external costs of accidents are achieved in PO3 (€389 million relative to the baseline or 0.4% decrease) when applied to the largest scope of projects, i.e. to all the TEN-T core network projects. However, PO2 also achieves significant savings in the external costs of accidents, in the order of €297 million relative to the baseline over 2018-2030 (expressed as present value). All options and all scopes of application show positive impacts relative to the baseline.

Table 15: Impacts on external costs of accidents relative to the baseline over the lifetime of the projects (2018-2030)

 

Baseline*

PO1

PO2

PO3a/PO3b

External costs of accidents (present value in million € and % change to the baseline)

Core TEN-T network, of which:

91,581

-105.3

-297.0

-389.0

-0.1%

-0.3%

-0.4%

Core network corridors

-79.0

-222.8

-291.8

-0.1%

-0.2%

-0.3%

CEF Annex 1 projects

-58.4

-164.9

-215.9

-0.1%

-0.2%

-0.2%

Source: Panteia, Impact Assessment support study (2018); Note: * The baseline figures relate to the traffic on the core TEN-T network.

6.1.13Impact on EU cohesion, local benefits, life quality and social inclusion

The implementation of the TEN-T network aims at strengthening EU cohesion, in particular by enhancing accessibility and connectivity of all regions and by reducing infrastructure quality gaps between Member States. These objectives enshrined in the TEN-T Regulation are not questioned by stakeholders and were recently confirmed in Council conclusions 82 . As explained in the baseline scenario, the timely completion of the TEN-T network is at risk given the significant delays currently encountered by individual TEN-T projects, in particular because of lengthy permitting procedures.

In addition, the changing patterns of mobility – mobility as a service, transport as public service – need to be taken into consideration to assess social impacts. The effective involvement of the local communities influences this aspect of the implementation of the TEN-T network which is not only about long-distance flows. The network is also vital to ensure access of the local communities to economic centres and to shape mobility in urban areas.

Finally, transport infrastructure is an increasingly key factor of life quality for EU citizens and for social inclusion. The timely completion of the TEN-T core network is expected to enhance the transition to low emission mobility to reduce negative externalities of transport (as explained in section 6.2 on environmental impacts). Good transport infrastructure is fundamental to ensure good connections, to reduce congestion and enhance new solutions such as digital ones to improve mobility. Mobility has a great impact on access to public goods like health, employment, culture or social inclusion.

The social impact on EU cohesion of PO1 is rather modest in light of its limited efficiency. No substantial changes to the currently applicable rules are expected, but best practices and positive experiences in terms of local benefits, life quality and social inclusion could be promoted with expected benefits in the long run.

On the other hand, the impact on EU cohesion under PO2 is assessed positively, as the measures would contribute to improving the implementation rate of the TEN-T core network. The impact on local benefits depends on the detailed designs of individual projects and is specifically linked of the quality of consultation procedures. A clear ownership of the authorisation by a single entity at national level is considered a better approach to integrate the interests of various stakeholders.

Local influence to a EUR 10billion project

In Italy, the Brenner Base Tunnel project was subject to two parallel and coordinated authorisation procedures: a central procedure coordinated with the local one, due to the fact that Bolzano is an Autonomous Province with its own EIA Committee. This allowed for a careful insertion of the project in the region, both from the point of view of the required authorisations and the necessary agreements, e.g. an in-depth preventive analysis, especially as concerns logistics, sharing of the project with the local population, consideration of local requests and agreement on the location of construction and disposal sites 83

PO2 is also likely to provide greater synchronisation of procedures and cross-fertilisation of measures at the scale of the entire infrastructure project. In the case of cross-border projects, social benefits could be brought more coherently across the border through green or social procurement. If a project is developed separately at every step of the permitting procedure or separately on two sides of the border, the social aspects have less opportunity to be taken into account in a coherent manner.

Social inclusion in a project of pan-European importance

Based on the new public procurement directives, the project promoter of the inland waterway canal linking the Seine with the Scheldt is using social clauses in every contract for works. These clauses require a certain number of local citizens to be employed during the execution of contracts. Procurement is an opportunity for territorial economic development as well as to increase the public acceptance of a project. However, based on the experience of the project promoter, it necessitates strong project management structure and strong partnership with local stakeholders 84

PO3 is also expected to generate positive impact on EU cohesion by fostering TEN-T implementation. However, the impact on local benefits appears more negative than PO2 as the one-size-fits-all approach inherent to the definition of a single and uniformed set of rules could be detrimental to the delivery of local benefits.

Finally, the respondents in the open public consultation in particular emphasised the fact that focus on local benefits is one of the factors contributing to the raising public acceptance for individual projects. This element was second only to the greater involvement of the general public in the project preparation 85 .

6.4Legal implications 

The initiative and the possible solutions are expected to have important legal implications. One of the elements contributing to this is the fact that the initiative relates to various existing legal provisions stemming from different legal frameworks (local/regional, national and EU).

The three policy options will have different legal implications at different levels and in some cases would require the introduction of new procedural rules in the national administrative law. Therefore, careful analysis of the effectiveness, the implications for stakeholders and civil society as well as the cost of enforcement has been carried out as part of the present impact assessment. The reduction of legal uncertainty and the increase in private investment is taken into account in the assumptions on reduction in delays.

6.1.14Legal feasability and effectiveness of the options

The legal implications of PO1 would be limited as it would be voluntarily applicable to the Member States and would not require changing the existing rules. However it is important to distinguish soft law’s lack of legally binding effect from its potential impact in practice. Soft law may affect policy development and practice precisely because it exercises an informal ‘soft’ influence, and can therefore sometimes be presented as a more flexible instrument in achieving policy objectives. A possible choice of soft law measure under this option could be recommendations, which while have no binding force might have certain legal effects and would allow the Commission to have a coordinating role.

The requirement to establish a one-stop-shop at national level for the purpose of coordinating and issuing development consent for TEN-T projects, foreseen under PO2, would need to be set forth in an EU legislative instrument. This option would apply to all projects on the TEN-T core network. This option also includes the adoption of certain limited provisions of public procurement legislation as well as targeted technical assistance and streamlined procedures at the EU level when applicable. A similar solution is already in force within the TEN-E Regulation for energy infrastructure projects. As PO2 would to a large extent follow the TEN-E precedent with the application of additional measures in the public procurement field, it is considered feasible from the legal point of view.

From a legal perspective, the effectiveness of such a system would depend on degree of integration of the one-stop shop (OSS) designated by a Member State. The integrative approach to the OSS is perceived to be more effective than the coordinated approach 86 . This policy option does not entail any changes to the EU legal acts that are currently in force.

As regards time limits, the PO2 would also to a large extent replicate the TEN-E precedent. Their introduction by means of an EU regulation would not require adapting national legislation, but the right of the Member States to set more ambitious deadlines than the ones foreseen by the EU legislative act will be safeguarded.

The European framework envisaged under PO3 would be created for the authorisation of TEN-T core network projects, along with the development of a framework of single rules to be applied in public procurement of cross-border projects and for environmental assessments. For these projects, the new framework would replace all national rules and regulations including those deriving from EU legislation. This would entail making the requirements currently stemming from EU directives directly applicable. This would require an EU legislative instrument adopted to streamline regulatory and administrative procedures for TEN-T core network projects but would also raise the issue of the appropriate legal basis if it affects the requirements under other EU legislation.

In the case of PO 3a, the national rules on administrative proceedings would remain in place and would not be affected. However, under PO 3b the EU would be directly in charge of issuing permits. In such a case, this would imply the usual decision-making procedures of the Commission to adopt individual -decisions or more likely to establish an ad hoc decision-making system for implementing this possibly complex scheme.

In addition, it would require supplementing this piece of EU legislation with implementing measures to govern the permitting procedures which are currently not regulated in a sufficiently detailed manner by directives, e.g. technical standards for buildings and structures, technical standards for environmental assessments at project level, administrative rules on the neighbouring pieces of land, rules on compensations related to compulsory purchase of land, rules on communication of interested parties.

Finally, PO3 raises significant concerns in particular as regards the competence of the EU to act in the fields of spatial planning and land use which are the sole competence of the Member States.

As a result, from the legal perspective, PO3 in general is likely to raise serious subsidiarity questions and, in the case of PO3b more particularly, setting up an implementing system and an administrative capacity at EU level with the associated administrative burden would have important implications.

6.1.15Impact on judicial review

As it does not entail immediate legal effects, PO1 would not have any impact on the judicial review.

PO2 would not have important effects on the judicial review either. The current national rules would continue to apply as far as the definition of the competent court and procedural rules are concerned. Member States would only able to introduce time limits for challenging administrative decisions such as a statute of repose, in accordance with their own procedural rules. Any intrusive rules cannot be proposed due to the lack of competence of the EU to regulate the judiciary systems of Member States.

In the case of PO3a, the same considerations as for PO2 apply. However, as for the PO3b there are several options to ensure access to justice. Transport projects involve very large numbers of stakeholders, and decisions issued by competent authorities granting development consent for projects face legal challenges by stakeholders. Such legal appeals are likely to cause delays in the preparation and implementation of some TEN-T projects. Under the current system, these legal challenges are most likely to be heard at national level. As a new EU framework regulation would fall under EU law, the competent court would be the EU general court.

7HOW DO THE OPTIONS COMPARE?

7.1Overall assessment of direct impacts 

The combined measures under the three policy options have economic, social and environmental impacts related to users' costs and external costs. The net benefits stemming from the user costs savings and external costs savings for all three options are positive, with the highest net benefits presented by PO3, amounting to €7.7 bn for the core TEN-T network projects (see Table 16 ). Again, the application of the three options to the narrower scope, such as core network corridors and CEF Annex 1 projects only is expected to bring smaller benefits, €5.8 bn in case of corridors projects for PO3 and €4.3 bn in case of CEF Annex 1 projects for PO3.

Table 16: Costs and benefits of the policy options relative to the baseline over the lifetime of the projects (2018-2030)

Net benefits (in million €, constant prices 2015)

PO1

PO2

PO3a/PO3b

Core TEN-T network projects

 

 

 

Social benefits

 

 

 

User costs savings

1,838

5,069

6,648

External costs savings

273

724

947

Air pollution

3

6

8

Noise

10

27

35

Congestion

86

202

263

Accidents

105

297

389

Climate change

68

193

253

Total social benefits

2,111

5,793

7,595

Administrative costs reduction

18

153

100

Net benefits (present value)

2,129

5,946

7,696

Core network corridors projects

 

 

 

Social benefits

 

 

 

User costs savings

1,379

3,802

4,986

External costs savings

205

543

710

Air pollution

2

4

6

Noise

8

20

26

Congestion

65

151

197

Accidents

79

223

292

Climate change

51

144

189

Total social benefits

1,583

4,345

5,696

Administrative costs reduction

14

115

75

Net benefits (present value)

1,597

4,460

5,771

CEF projects

 

 

 

Social benefits

 

 

 

User costs savings

1,020

2,813

3,690

External costs savings

151

402

526

Air pollution

2

3

4

Noise

6

15

19

Congestion

48

112

146

Accidents

58

165

216

Climate change

38

107

140

Total social benefits

1,171

3,215

4,215

Administrative costs reduction

10

86

56

Net benefits (present value)

1,182

3,301

4,271

Source: Impact Assessment support study

In quantitative terms and considering the direct impacts and wider economic impacts (as shown in previous chapter in Table 7 and Table 8 ), PO3 clearly generates the highest positive results.

In addition to quantitative analysis of the impacts it is particularly important for this initiative also to assess the impacts of the proposed measures which go beyond the quantified social benefits and include social impacts on civil society, fundamental rights of citizens affected by the options as well as on the legal certainty. Therefore, the assessment also requires a thorough examination of the distributive effects on various categories of affected stakeholders and the qualitative review of the different impacts. This analysis needs to take into account the advantages and negative effects of the policy options in light of the criteria of their efficiency, effectiveness and coherence. This is also important as the overall aggregated positive figures may include also negative effects on citizens and local communities directly affected by the investments.

Eastern motorway bypass of Łódź

This greenfield construction of a new motorway along the Baltic-Adriatic Core Network Corridor links the existing A1 heading north towards Gdańsk on the Baltic Sea and A1 leading to the industrial region of Upper Silesia. The construction of the new road did not use EU funding. It replaced the existing national road crossing the TEN-T urban node of Łódź and directly affecting hundreds of thousands of inhabitants of the agglomeration with increased noise, pollution, low road safety and congestion. It affected also the seamless flows on this strategic N-S connections going through the centre of Poland. The new road negatively affected the quality of lives of the residents of the relatively sparsely populated suburbs; however the overall impact on the whole region is positive. Moreover, a lot of effort was invested into mitigation measures such as protection from increased noise, new trees plantations as well as engineering structures in order to reduce the impacts on the local transport.

7.2Effectiveness 

The effectiveness of the policy options must consider the extent to which these objectives are achieved. Table 17 presents the objectives and the indicators that have been developed to monitor the level of achievement of the objectives. The effectiveness of each policy option in achieving the objectives is presented in Table 18, using the indicators described above.

Table 17: Linking of objectives to key indicators

General objectives

Specific objectives

Indicators

establishment and development of trans-European networks in the area of transport as well as promoting the interconnection and interoperability of national networks

minimising the risk of delays faced by individual TEN-T projects

·Value of user benefits linked to quicker implementation of TEN-T

·Value of non-user benefits linked to quicker implementation of TEN-T

increasing legal certainty for project promoters thus attracting more private investors to transport infrastructure

·Legal effectiveness for TEN-T projects promoters (qualitative assessment)

All options show positive results in terms of users' costs savings and external costs savings linked to the quicker delivery of the TEN-T core network projects and its narrower scopes (core network corridors, CEF Annex 1 projects). PO1 has a more limited impact relative to PO2 and PO3. PO2 strongly contributes to the achievement of objectives, however not to a lesser extent in comparison with sub-options of the PO3. PO3 reduces the risks for project promoters to the minimum and results in the highest direct benefits, these benefits are however not very much higher than the ones brought by the PO2. In all cases, the benefits are the highest also when the scope of application is the broadest – i.e. when all projects located at TEN-T core network would benefit from the new rules.



Table 18: Effectiveness of policy options    

Key: Impacts expected

✗✗

O

✓✓

Strongly negative

Weakly negative

No or negligible impact

Weakly positive

Strongly positive

Unclear

PO1

PO2

PO3

PO3a

PO3b

Specific objective 1: Minimising the risk of delays faced by individual TEN-T projects

User benefits linked to quicker implementation of TEN-T core network (present value)

€1,838 million

€ 5,069 million

✓✓

€ 6,648 million

✓✓

External costs savings linked to quicker implementation of TEN-T (present value)

€273 million

€724 million

✓✓

€ 947 million

✓✓

Specific objective 2: increasing legal certainty for project promoters thus attracting more private investors to transport infrastructure

Legal effectiveness for TEN-T core network projects promoters (qualitative assessment)

The legal certainty will increase, however due to the nature of the soft law, its effectiveness will be limited.

0

The positive impact on legal certainty would be high as the procedures would be integrated with clear ownership in the OSS and the rules applied at national (well-known) level

✓✓

The positive impact on legal certainty would be high as the procedures would be integrated and the rules applied by the OSS at national level. However, the contents of the requirements established directly at EU level would be new to project promoters.

The positive impact on legal certainty would be high as the procedures would be integrated. However, the contents of the requirements established directly at EU level would be new to project promoters and the administrative procedures as well as judicial proceedings handled at EU level would create new level of uncertainty.

In terms of effectiveness to ensure legal certainty for TEN-T project promoters, the PO2 and PO3a seem to be most effective as they contribute to the streamlining of procedures at national level while keeping the common administrative procedures at national level which are well-known for project promoters. PO3a will result in project promoters having to learn and adjust to the new framework which could differ from what they are used to. PO1 seems to have negligible effect as the guidelines to existing procedures would not have decisive effect and bear the risk to be differently interpreted at different levels. Finally, PO3b may have weakly negative effects for the certainty of the project promoters. Indeed, the rules will be streamlined and made simpler for TEN-T projects. However the shift of responsibilities for handling the procedures to the EU level will create a certain level of uncertainty in terms of procedures as well as potential appeals which would need to be lodged to the EU courts.

Finally, experience from the application of the TEN-E rules proves that the scheme proposed under PO2 has proven successful in the other area of TEN.

TEN-E experience

The Agency for the Cooperation of Energy Regulators (ACER) confirms in the report of 2016 its previous year’s finding that those TEN-E Projects of Common Interest which applied for permit granting after 16 November 2013 (i.e. according to the new rules of TEN-E Regulation requiring establishment of a OSS at national level) are in general more optimistic about the expected duration of the permit granting than those which applied before. The average duration of the permit granting is 3.5 years and 5.5 years respectively.

Source: Consolidated Report on the progress of electricity and gas projects of Common Interest for the year 2016, ACER 2017 87

7.3Efficiency

The efficiency of the options is assessed on the basis of the resources or at least cost involved in light of the objectives of reducing the risk of delays and the increased certainty for project promoters. All options are expected to have positive impact in terms of administrative costs on the project promoters with PO2 having the biggest impact. Even if PO3 in both of its configurations will have also high positive impact on promoter's administrative it is expected to be lower than for PO2 as in the case of PO3, additional training and learning is required. PO1 is expected to have modest positive impact.

For permitting authorities, in all options the impact will be negative due to the need of additional training and learning. It is expected that the impact will be the highest in case of PO3 where a significant amount of training will be needed. The lowest negative impact is expected in case of PO1 and rather medium in case of PO2.

In all cases, the overall net impact is positive for all options, which is the highest in case of PO2.

The objective of the implementation of the TEN-T is the transition towards low emission mobility. The efficiency of the options was also assessed in terms of acceleration of the benefits brought by individual projects. Regarding the external costs savings also here the PO3 is the most efficient option, while PO1 is the least. Expected results for PO2 are relatively high; however somewhat lower then PO3 and considerably higher than PO1.

Increasing the rights of the TEN-T projects promoters cannot be assessed only against their interests and the overall highly aggregated benefits. Social impacts and impacts on civil society have to be duly taken into accounts. Moreover, civil society shows greater interest to have their say and participate in the decision making process on projects that can affect the everyday life and the quality of life. Their participation may be hampered by lack of clarity of rules and procedures. Recent cases show that the effective and early involvement of the civil society as well as greater focus on local benefits is helpful and prevents conflicts and appeals at later stage of the project implementation 88 .

The clarified rules and increased technical assistance leading to more efficient public consultation (PO1) will have weakly positive result. PO2 is expected to contribute in general positively to the involvement of civil society in the permitting processes by clarifying the rules and better structuring the paths. However, the integration of consultation may potentially have adverse effect on the length of consultations which so far may be sequenced and concentrate subsequently on different topics. This could particularly be the case if the present initiative would derogate to the consultation requirements stemming from the applicable directive by replacing them with a simplified consultation. On the other hand, the introduction of a certain parallelism or greater synchronisation of the consultations will not have such negative effect. It will safeguard all the existing assessments and consultations while cutting the overall needed time and ensuring greater transparency for the benefit of the citizens and NGOs that can better understand when to have their say in the project planning.

Finally, both sub-options of the PO3 are expected to have negative results. In the case of PO3a bringing unfamiliar new requirements will not be offset by the clearer structure and the overall impact will be weakly negative. Whereas in the case of PO3b, the overall impact is expected to be strongly negative due to new unfamiliar rules and the shift of handling of the procedures to the EU level.

Finally, the legal stability is necessary for long-term TEN-T projects. Significant changes to the way the procedures are handled and frequent changes to their contents are believed to be counterproductive. On the other hand, the problem is clearly driven by the organisation of the procedures and the stability in this respect will not offset the results of the suboptimal situation. Evolutionary changes in the PO2 are believed to be best balanced in this area, bringing greater coordination of existing processes which become clearer and more understandable for both project promoters and the civil society.

Table 19: Efficiency of policy options    

Key: Impacts expected

✗✗

O

✓✓

Strongly negative

Weakly negative

No or negligible impact

Weakly positive

Strongly positive

Unclear

PO1

PO2

PO3

PO3a

PO3b

Impact on cost borne by project promoters (savings)

€ 27 million

€166 million

✓✓

€120 million

✓✓

Impact on cost borne by permitting authorities

€9 million

€13 million

€20 million

✗✗

Impact on CO2 emissions for the TEN-T core network (cumulative over 2018-2030)

-917 thousand tonnes CO2 compared to the baseline

-2,686 thousand tonnes CO2 compared to the baseline

✓✓

-3,543 thousand tonnes CO2 compared to the baseline

✓✓

Impact on civil society

Clarification of rules will increase the efficiency of public consultation but is subject to the efficiency of voluntary application of soft law measures.

Structuring and integration of permitting procedures are believed to have positive effects on the civil society to have their voices heard in the public consultations thus leading to cross-fertilisation and greater focus on local benefits.

✓✓

Unfamiliar rules and requirements are not be fully offset by the positive effects of structuring and integration of permitting procedures. The perception by the civil society risks being negative.

Unfamiliar rules and distant handling of procedures risk having strongly negative impact on the civil society involvement and will reduce the concentration on local benefits in TEN-T project planning. Perception by the civil society will be crealy negative.

✗✗

Impact on legal framework stability

Stability is ensured, however the main problem drivers remain not efficiently addresses.

Evolutionary changes without significant modifications to the rules and their contents provide balance between the necessity for stability and optimisation of applicable frameworks.

✓✓

Changes in the contents will result in necessary adaptation of project promoters and may be suboptimal for long-term planning of TEN-T projects.

Drastic change in comparison with current situation, discutable competence of the EU to handle procedures having impacts on local communities

✗✗

7.4Coherence

The objectives of this initiative are in line with the relevant EU policies in the field of transport policy, the Single Market and priorities in other EU policies. All the options contribute to the stimulating investment and creating jobs with the streamlining of investment in the real economy.

A deeper and fairer internal market will be achieved by the enhanced implementation of the TEN-T network whose aim is to physically connect the markets of the Member States with the clear EU added value with a focus on cross-border connection. All the Policy Options contribute to these objectives.

In terms of coherence with the other EU policies, PO1 and PO2 align best as they follow the existing requirements and try to best organise the implementation of the priorities of various policies, in particular the environmental protection and the functioning of the internal market with smart public procurement rules, with the goals of the TEN-T. Through better alignment of these policies' objectives with the TEN-T implementation, synergies are expected to be achieved.

In terms of coherence with the other policies, the sub-options of the PO3 are not perfectly coherent with the objectives of public participation and access to justice stemming from the application of the EU acquis in the field of environment, public procurement etc. This policy option would entail the risk of creating derogatory rules which would then provoke a suspicion to be more lenient on certain requirements or contribute to fragmenting the legal framework. This could put at stake the coherence of these policy fields. In addition, the PO3b by bringing the permitting procedures, affecting to the large extent local communities and individual citizens, would not be fully in line with the objective of Enhancing cooperation between different EU justice systems and preserving the rule of law

7.5Proportionality and subsidiarity

None of the options go beyond what is necessary to achieve the objectives. However, one needs to note that PO3 in its both sub-options could cause proportionality and subsidiarity concerns as it replaces the national permitting systems and, in case of PO3b, shifts the responsibility of handling the permitting procedures entirely to the EU level.

PO2 leaves Member States the responsibility to determine their administrative set-ups while safeguarding the necessity of the priority, timelines and efficient treatment of the projects of EU importance, i.e. those implementing the transport networks whose impacts go beyond the national context (similarly to networks managed at local, regional and national levels where decisions are made at different levels). Here, while preserving the national competence and the principle of territorial sovereignty, the EU importance of the projects is incorporated to the permitting systems by given the most rapid treatment legally possible under the national permitting systems to TEN-T projects.

7.6Opinion of the stakeholders on the key policy measures discussed

Regarding the integration of procedures under a national single entity, a “one-stop-shop” (OSS), this solution is supported in particular by project promoters, individuals and industrial interest groups, while more reserved opinions are expressed by national and in particular regional authorities.

In response to the possibility of introducing time limits to the permit granting process, project promoters, individuals, industrial interest groups and one responding NGO agree that this process should not last longer than 2 years, and that the establishment of such time limit can help reduce excessive delays. Local and regional authorities as well as some national governments are however more reserved. They are also of a critical view on time limits for the total duration of approval procedures for TEN-T projects, stating that since procedures for large-scale and complex projects are usually very time-consuming, such limits may have the risk of creating relative delays for small uncomplicated projects.

In terms of public procurement issues, a common set of rules at EU level applied to cross-border projects is considered in particular by project promoters and industrial groups, as the most effective solution to improve public procurement issues. National authorities argue that such a set of rules would be more effective when applied to cross-border projects benefiting from EU funding. As identified above, cross-border procurement based on a single legal framework may also strengthen the position of larger companies which have more experience in working in different Member States. The potentially decreased participation of SMEs in such large procedures is believed to be offset by greater possibilities of working as subcontractors in the increased overall construction market. This measure is not expected to have any negative impacts on citizens directly.

As regards definition and handling of procedures at EU level, there is reluctance expressed by some national governments, who in big numbers take strong positions against this approach. They argue that it would not speed up the permitting process and might result in the duplication of efforts, since only national authorities are able to verify the individual approval requirements of each country, and therefore, some procedure would be duplicated. However, the workshops devoted to public procurement and permit granting procedures showed some support from project promoters to rules and procedures that would be developed at EU level specifically for TEN-T infrastructure projects. On the other hand, the representatives of civil society expressed concerns that such rules and procedures would result in reducing their possibility to be consulted on the projects. 89

7.7Sensitivity analysis

A sensitivity analysis has been performed for the baseline scenario and for the effectiveness rates used in quantifying the policy options.

An alternative baseline scenario has been considered where 60% of investments would occur on schedule while 20% of the investments would be delayed due to permitting procedures by one year, 10% by two years, and 10% by three years. Consequently, the impacts of the policy options have been assessed drawing on the alternative baseline scenario while at the same time keeping the effectiveness rates unchanged.

In addition, a sensitivity analysis has been performed on the effectiveness rates. More conservative levels for the effectiveness of the policy options have been assumed: 10% for PO1, 50% for PO2 and 70% for PO3. In this case, the policy options have been quantified drawing on the central baseline scenario.

The results of the sensitivity analysis with respect to the baseline and the effectiveness rates are presented in terms of net benefits Figure 6 . The detailed results are presented in Annex 4 on Analytical methods.

Figure 6: Net benefits (in million €, constant prices 2015)

Source: Impact Assessment support study

Overall, the sensitivity analysis shows that the alternative baseline scenario and lower effectiveness rates result in somewhat lower net benefits. However, the ranking of the options in terms of net benefits does not change.

7.8Preferred Policy Option

Based on the assessment above PO3 is the most effective in terms of wider economic impacts and also direct user and non-user benefits. However, PO3 shows clearly negative impacts in terms of legal stability and social impacts in terms of the involvement of civil society in the infrastructure planning. Moreover, this options does not seem to be fully coherent with the objectives of the other policy areas, overall objectives and general principles of the Union as well as it does not seem proportional for the objectives it is meant to achieve.

The impacts of PO1 are much more balanced and it is proportional to the objectives it is meant to achieve. However the overall the effectiveness and efficiency of this option is not high.

Taking into consideration the experience of the projects in the field of the TEN-E, the evolutionary model of PO2 which is respecting the national permitting processes but at the same time a requires to better coordinating them, seems to be effective and the most efficient option 90 .

PO2 therefore qualifies as the preferred option, it performs much better in terms of effectiveness and efficiency in comparison with PO1 and is does not have the drawbacks present in the case of application of PO3, in particular of the sub-option PO3b. It is also proportional to the objectives it is to achieve and coherent with the other policies of the EU and its fundamental principles. PO2 seems to achieve a balanced and efficient framework based on an increased effectiveness of administrative procedures to foster the implementation of TEN-T projects and, at the same time, on clearer and more inclusive processes to strengthen public acceptance of infrastructure projects.

8HOW WOULD ACTUAL IMPACTS BE MONITORED AND EVALUATED?

Monitoring and evaluating the legal act which will streamline the implementation of the TEN-T should build on existing measures to monitor the implementation of the TEN-T as such. It should therefore use to the largest possible extent the existing framework and in a simple and transparent way to make it easily accessible for interested stakeholders. It is not the intention to create a complex system of new performance indicators.

The monitoring of specific policy objective 1 will be measured by the general advancement of the implementation of the TEN-T and number of TEN-T core network projects which do not experience delays. This monitoring will be done using the existing method of monitoring the implementation of the TEN-T provided for in article 49 (3) of the TEN-T Regulation.

Projects receiving CEF support are subject to a more detailed and regular reporting carried out by the executive agency INEA.

In addition, the European Coordinators will be able to highlight any achievements or difficulties occurring for infrastructure projects in their core network corridor work plans provided for in article 47 of the TEN-T regulation and which are regularly updated.

The monitoring of specific policy objective 2 will be measured by the number of TEN-T projects using innovative EU financial instruments as well as private capital.

Given that there are several drivers of the problems and that all cannot necessarily be addressed by the present initiative (as explained in section 2.1 – e.g. political and funding issues), any positive results will not be easily attributable to the exclusive implementation of the measures adopted. Therefore, the overall evaluation should take into consideration the general pace of the implementation of TEN-T.

8.1Indicators 

For the main specific policy objectives, the following monitoring indicators have been identified:

·Minimising the risk of delays faced by individual TEN-T projects:

-The advancement of the TEN-T implementation in terms of compliance with the standards and requirements.

-Progress in investment supported by EU in the TEN-T transport infrastructure measured by the number of CEF projects (or the projects supported by its successor) implemented on time and/or not delayed due to permitting/procurement issues.

·Increasing legal certainty for project promoters thus attracting more private investors to transport infrastructure

-The increase of number of the TEN-T infrastructure projects financed with the use of the EU-supported financial instruments (e.g. EFSI and its successors).

8.2Operational objectives 

Based on the preferred options, the following operational objectives have been identified.

Table 20: Operational objectives

Operational objectives

Indicators

Accelerate the pace of the implementation of the TEN-T

% of the TEN-T compliant infrastructure in railways and inland navigation

Increase the effectiveness of EU funding for the delivery of the TEN-T core network

Number of EU-funded projects encountering delays related to permitting or procurement procedures.

Increased use of private and alternative financing in the TEN-T infrastructure projects

Number of TEN-T infrastructure projects using EFSI and its successor or related schemes

(1)

Milieu Ltd., Study on permitting and facilitating the preparation of TEN-T core network projects, study for DG MOVE 2017, (Henceforth: Milieu et al.), section 3.1.2, p. 36

(2)

Report on Public Finances in EMU, 2016, DG ECFIN, ISSN 2443-8014 (online), https://ec.europa.eu/info/sites/info/files/ip045_en_0.pdf

(3)

Regulation (EU) No 1315/2013 of the European Parliament and of the Council of 11 December 2013 on Union guidelines for the development of the trans-European transport network and repealing Decision No 661/2010/EU, (Henceforth the TEN-T Regulation)

(4)

Art. 38(1) of the TEN-T Regulation.

(5)

TEN-T Regulation

(6)

Communication from the Commission to the Council and the European Parliament Boosting growth and cohesion in EU border regions, 20.9.2017, COM(2017) 534 final

(7)

The CNC work plans along with their supporting studies are available at:

  https://ec.europa.eu/transport/themes/infrastructure/downloads_en

(8)

 Delivering TEN-T, Facts & Figures, https://ec.europa.eu/transport/sites/transport/files/delivering_ten_t.pdf , September 2017.

(9)

In the conclusions adopted on 5 December 2017, the Council reiterated its strong commitment to the implementation of the TEN-T and the necessity to continue this policy to boost investment in transport and contribute to global objectives in particular in terms of climate action. 15425/17 TRANS 541, available at: http://data.consilium.europa.eu/doc/document/ST-15425-2017-INIT/en/pdf

(10)

European Commission (2016), Europe Investing Again: Taking stock of the Investment Plan for Europe and next steps, COM(2016) 359

(11)

"Rail infrastructure funding from governments budgets is the prevailing source of funds which hardly can be extended because of increasing budget constraints. New instruments to foster private-type funding such as LGTT or Project Bonds have not been successful for railway projects as they require sufficient cash flows stemming from the projects. Recently a better blending of instruments has been suggested by the use of concession-like funding which allows for constructing availability-based PPPs with modest revenue streams or mixed funds combining different financial sources including road user or externality charges." - The Results and Efficiency of Railway Infrastructure Financing within the European Union, Study for the European Parliament, October 2015

http://www.europarl.europa.eu/RegData/etudes/STUD/2015/552308/IPOL_STU%282015%29552308_EN.pdf  

(12)

European Commission (2016|), A European Strategy for Low-Emission Mobility, COM(2016)501

(13)

Informal meeting of EU Transport Ministers, Building Infrastructure to Strengthen Europe’s Economy, September 2014.

http://www.consilium.europa.eu/uedocs/cms_data/docs/pressdata/en/trans/146017.pdf

(14)

Former European Commission Vice-President H. Christophersen, Professor K. Bodewig, European Coordinator, Professor C. Secchi, European Coordinator in the "Action Plan – Making the best use of new financial schemes for European transport infrastructure projects", June 2015, available at http://ec.europa.eu/transport/themes/infrastructure/ten-t-guidelines/doc/2015_06_03_cbs_action_plan_final.pdf , (Henceforth: CBS Report)

(15)

Progress Report of the Action Plan Making the best use of new financial schemes for European transport infrastructure projects, January 2018, https://ec.europa.eu/transport/sites/transport/files/cbs2_report_final.pdf , (Henceforth: CBS Progress Report)

(16)

  http://www.g7italy.it/sites/default/files/documents/Final%20Declaration_0.pdf . This is also in line with the efforts in the past years and still on-going in the United States: https://www.whitehouse.gov/wp-content/uploads/2018/02/INFRASTRUCTURE-211.pdf  

(17)

https://www.bmvi.de/SharedDocs/DE/Publikationen/G/innovationsforum-planungsbeschleunigung-abschlussbericht.pdf?_ _blob=publicationFile  

(18)

In particular: Strategic Environmental Assessment Directive 2001/42/EC, Water Framework Directive 2000/60/EC, Environmental Impact Assessment Directive 2011/92/EU amended by 2014/52/EU, Habitats Directive 92/43/EEC, Birds Directive 2009/147/EC, Seveso Directive 2012/18/EU

(19)

Concessions Directive 2014/23/EU Public Procurement Directive 2014/24/EU, Services Procurement Directive 2014/25/EU, Remedies Directive for the utilities sector 92/12/EEC amended by 2007/66/EC, Remedies Directive for the public sector 89/665/EEC amended by 2007/66/EC

(20)

Council Regulation (EU) 2015/1589 of 13 July 2015 laying down detailed rules for the application of Article 108 of the Treaty on the Functioning of the European Union, OJ L 248, p.9-29

(21)

Although the EU enacted the Maritime Spatial Planning Directive 2014/89/EU

(22)

Directive 2001/42/EC of the European Parliament and of the Council of 27 June 2001 on the assessment of the effects of certain plans and programmes on the environment

(23)

Council Directive 92/43/EEC of 21 May 1992 on the conservation of natural habitats and of wild fauna and flora

(24)

Directive 2014/52/EU of the European Parliament and of the Council of 16 April 2014 amending Directive 2011/92/EU on the assessment of the effects of certain public and private projects on the environment, OJ L124, p. 1-18

(25)

Directive 2014/24/EU of the European Parliament and of the Council of 26 February 2014 on public procurement and repealing Directive 2004/18/EC OJ L 94, pp. 65-242 and Directive 2014/25/EU of the European Parliament and of the Council of 26 February 2014 on procurement by entities operating in the water, energy, transport and postal services sectors and repealing Directive 2004/17/EC, OJ L94, p. 243-347.

(26)

Commission Notice on the notion of State aid as referred to in Article 107(1) of the Treaty on the Functioning of the European Union, OJ C262 p. 1-50

(27)

Commission Regulation (EU) 2017/1084 of 14 June 2017 amending Regulation (EU) No 651/2014 as regards aid for port and airport infrastructure, notification thresholds for aid for culture and heritage conservation and for aid for sport and multifunctional recreational infrastructures, and regional operating aid schemes for outermost regions and amending Regulation (EU) No 702/2014 as regards the calculation of eligible costs, OJ L 156, p. 1–18

(28)

Under the former legislative framework, the TEN-T policy identified 30 Priority Projects. Several of them have been completed but some are still on-going, the experience with Priority Projects also shows that there issues related to permitting procedures impacted the delivery of several projects (e.g. PP17, PP18/30, PP24), Implementation of the Priority Projects, November 2012; DG MOVE based on data from Member States, https://ec.europa.eu/transport/sites/transport/files/themes/infrastructure/ten-t-policy/priority-projects/doc/pp_report_nov2012.pdf  

(29)

Market Update Review of the European PPP Market in 2017, EIB, March 2018

(30)

This is particularly the case with waterborne projects where the transport function of the infrastructure is only one of its objectives.

(31)

Regulation (EU) No 347/2013 of the European Parliament and of the Council of 17 April 2013 on guidelines for trans-European energy infrastructure and repealing Decision No 1364/2006/EC and amending Regulations (EC) No 713/2009, (EC) No 714/2009 and (EC) No 715/2009, p.39

(32)

According to the analysis of ACER, the average duration of permitting expected by PCI promoters in the pool of 96 electricity PCIs is 3.5 years. For gas, the average permit granting duration for the pool of assessed 54 PCIs was 3.2 years. Commission Staff Working Document Accompanying the document Commission Delegated Regulation amending Regulation (EU) No 347/2013 of the European Parliament and of the Council as regards the Union list of projects of common interest, Annex II, SWD (2017) 425 final

(33)

Milieu et al

(34)

The TEN project case studies concern the following Member States: Czech Republic, Germany, Hungary, Italy, the Netherlands, Poland, Romania, United Kingdom, Austria and Spain.

(35)

Annex 3 to the Milieu et al., Country executive summaries.

(36)

Germany, Italy, the Netherlands and the United Kingdom

(37)

Austria, Czech Republic, Hungary, Poland, Romania, and Spain. For details see Table 2 in the Annex 1 to Milieu et al.

(38)

Milieu et al. Annex 6 Guide of good practices, p. 11

(39)

Milieu et al., section 3.1.1, p. 31

(40)

A prime example is the Fehmarn Belt Fixed Link project, where the approval process went quite smoothly in Denmark, while the approval in Germany is still dependent on the completion of several rounds of public hearings.

(41)

In that event the competent authority shall inform the developer in writing of the reasons justifying the extension and of the date when its determination is expected (Article 4(6)).

(42)

For details see consultations done in the context of the exploratory study – Annex 5 to the Milieu et al.

(43)

Annex 1 to Milieu et al., Problem Definition, Section 1.1.3

(44)

Only countries were stakeholders provided information on the duration of the permitting procedure (excluding preparation of the application) were considered in this average.

(45)

In most of the Member States selected for analysis in the exploratory study, time limits have been set out in the legislation for the main permits (EIA, spatial planning) and public consultations (Milieu et al. Annex 3, Country Executive Summaries).

(46)

Milieu et al., Section 3.4, p. 56

(47)

The simplification of procurement procedures is envisaged to take place through the establishment of shorter procedural deadlines or the resort to e-procurement and other measures to reduce paperwork. Flexibility is improved through the possibility of using innovation partnerships, broader possibilities for negotiation with tenderers (competitive procedure with negotiation) and the use of best quality-price award criteria (including the total lifecycle cost). See for instance DG MARKT leaflet “New Rules on Public Contracts and Concessions – Simpler and More Flexible”, available at http://ec.europa.eu/internal_market/publications/docs/public-procurement-and-concessions_en.pdf .

(48)

Conclusions of the Stakeholders Workshop Smart and effective public procurement for TEN-T cross-border projects, Brussels, 15 June 2017,

(49)

A conformity checking of the three Directives will be conducted by DG GROW in 2017. The contract notice for consultancy services for completeness and compliance checks of national transposition measures and other legal assessment services in the field of EU public procurement law, no. 2016/S 125-222903, was published on 21 June 2016. The notice is available on TED.

(50)

See e.g. Recital 4 of Directive 2014/25/EU

(51)

CBS Report

(52)

Annex 1 to Milieu et al., Problem Definition, Section 2.1.2

(53)

Communication from the Commission to the Institutions: Helping investment through a voluntary ex-ante assessment of the procurement aspects for large infrastructure projects, COM(2017) 573

(54)

National authorities can contact the helpdesk on specific issues they face when developing the procurement plan for a project. These questions could, for example, concern the applicable EU legal framework governing the project (procurement or utilities directives; concessions directive, etc.), conditions for exclusions from the directives, procurement procedures to be used, selection and award criteria, etc.

(55)

The notification mechanism is designed to enable the project promoters to receive the Commission's views on the compliance with EU procurement legislation.

(56)

 For example, the case studies also showed that differences in national legislation can lead to significant delay. The complex legal framework for procurement applied in France and Italy in the Lyon-Turin case gave rise to prolonged discussions between both countries on the implementation of the applicable EU rules. The implementation of specific measures to prevent criminal infiltrations in public procurement was one of the specific points of discussion, since French and Italian law did not implement European law in a similar way at national level.

(57)

Results of the open public consultation being part of the IA process. The Complex procurement in the Rail Baltica cross-border project is illustrated in the Progress Report of the Action Plan Making the best use of new financial schemes for European transport infrastructure projects. It highlights the difficulties regarding public procurement for the Joint Venture RB RAIL AS which has the sole responsibility for defining the procurement contracts. However, contracts are governed by the law of the state where the works are performed.

(58)

See, for example, recital 13 of the TEN-T Regulation.

(59)

Case T-128/98, Aéroports de Paris v Commission of the European Communities, European Court of Justice, 2000; Joined Cases T-443/08 and T-455/08 Freistaat Sachsen, Flughafen Leipzig/Halle et al v Commission of the European Communities, European Court of Justice, 2011, ECR II-1311

(60)

European Commission, MEMO/15/5419

(61)

Milieu et al., Section 3.5, p. 66

(62)

Commission Notice on the notion of State aid pursuant to Article 107(1) TFEU, OJ C 262 of 19.7.2016, p.1-50

(63)

Guidelines on State aid to airports and airlines, OJ C 99, 4.4.2014, p. 3.

(64)

Commission Regulation (EU) 2017/1084 of 14 June 2017 amending Regulation (EU) No 651/2014 as regards aid for port and airport infrastructure, notification thresholds for aid for culture and heritage conservation and for aid for sport and multifunctional recreational infrastructures, and regional operating aid schemes for outermost regions and amending Regulation (EU) No 702/2014 as regards the calculation of eligible costs, OJ of 20.06.2017, L 156, p.1-18

(65)

  http://ec.europa.eu/competition/state_aid/modernisation/notice_aid_en.html

(66)

Under the Investment Plan for Europe, projects benefiting from the EFSI may combine in their financial schemes also sources of financing which are considered as State aid, also e.g. ESI Funds. In order to simplify and accelerate their implementation, the Commission has committed to assess the compliance of ESI Funds with State aid rules as a matter of priority and to give it fast-track treatment. The Commission aims to complete its assessment within six weeks of receiving the complete notification from the Member State. European Commission, MEMO/16/313

(67)

Source: Panteia, PwC, M-FIVE Impact Assessment support study (2018) (henceforth: Panteia et al). More details on the assumptions used for the administrative burden are provided in Annex 4.

(68)

Recital 43, TEN-T Regulation

(69)

15053/17 TRANS 525, http://data.consilium.europa.eu/doc/document/ST-15053-2017-INIT/en/pdf  

(70)

The initiative is listed in the action plan attached to Communication A European Strategy for Low-Emission Mobility, COM(2016) 501 final

(71)

"In 2008, annual investment in transport infrastructure in the EU28 was approximately € 130 billion, which was broadly consistent with historical levels of about 1% of GDP. However, investment fell during the financial crisis and the following period. It is therefore estimated that investment now needs to rise to €160 billion a year until 2020, as a minimum, to address the backlog and restore investment to pre-crisis levels. " Commission non-paper with a view to the Ministerial lunch debate taking place at the Transport Council on 1 December 2016

http://data.consilium.europa.eu/doc/document/ST-14826-2016-INIT/en/pdf

(72)

Implementation of the Priority Projects, November 2012; DG MOVE based on data from Member States, https://ec.europa.eu/transport/sites/transport/files/themes/infrastructure/ten-t-policy/priority-projects/doc/pp_report_nov2012.pdf

(73)

The updated EU Reference scenario 2016 assumes the completion of the core TEN-T network by 2030 and of the comprehensive TEN-T network by 2050. A full description of the updated EU Reference scenario 2016 is provided in the Impact Assessment accompanying the revision of the Eurovignette Directive: http://eur-lex.europa.eu/legal-content/EN/TXT/?uri=CELEX:52017SC0180 .

(74)

Source: Panteia, PwC, M-FIVE Impact Assessment support study (2018) (henceforth: Panteia et al). More details on the assumptions used for the administrative burden are provided in Annex 4.

(75)

 Commission guidance document on streamlining environmental assessments conducted under Article 2(3) of the Environmental Impact Assessment Directive (Directive 2011/92/EU of the European Parliament and of the Council, as amended by Directive 2014/52/EU), (2016/C 273/01)

(76)

A discount rate of 4% has been used for presenting the costs/benefits as present values.

(77)

SEC (2011) 1233

(78)

Panteia et al.

(79)

This option was previously considered for the TEN-E impact assessment (SEC (2011) 1233). During that study, a large majority of stakeholders (over 75%) stated that the one-stop-shop could bring substantial decreases in administrative burden. The one-stop-shop solution proposed in the TEN-E was expected to generate a 25% reduction of cost for the project promoters.

(80)

Directive 2001/42/EC of the European Parliament and of the Council of 27 June 2001 on the assessment of the effects of certain plans and programmes on the environment

(81)

 See in this context the Strategy for speeding up the planning process of the German Federal Ministry of Transport and Digital Infrastructure – https://www.bmvi.de/SharedDocs/DE/Publikationen/G/innovationsforum-planungsbeschleunigung-abschlussbericht.pdf?__blob=publicationFile .

(82)

In the conclusions adopted on 5 December 2017, the Council reiterated its strong commitment to the implementation of the TEN-T and the necessity to continue this policy to boost investment in transport and contribute to global objectives in particular in terms of climate action. 15425/17 TRANS 541, available at: http://data.consilium.europa.eu/doc/document/ST-15425-2017-INIT/en/pdf

(83)

Conclusions of the Workshop: Efficient permitting for TEN-T projects – Brussels, 17 October 2017.

(84)

Conclusions of the Workshop: Smart and effective public procurement for TEN-T cross-border projects, Brussels 15 June 2017

(85)

According to the views of stakeholders in the open public consultation, tout of 91 respondents 66 mentioned involvement of general public at different level of project planning as a best practice. Focus on local benefits was chosen by 61 out of 91. Extensive use of ICT was named by 43 respondents while promotion of local employment and SME's by 35.

(86)

According to the views of stakeholders in the open public consultation, the OSS should have extended decision making power (44 in favour of this approach instead of coordination powers only what was selected by 22 respondents, 12 opted for another solution and 11 did not express their opinion). This view was shared in particular be project promoters, industrial groups, regional authorities and individuals. Groups which were most sceptical to this solution were national governments and regional/local authorities.

(87)

  http://www.acer.europa.eu/official_documents/acts_of_the_agency/publication/consolidated%20report%20on%20the%20p rogress%20of%20electricity%20and%20gas%20projects%20of%20common%20interest%20for%20the%20year%202016.pdf  

(88)

The Brenner Corridor Platform (BCP) gathering infrastructure ministries of Austria, Germany and Italy, the five regions Bavaria, Tirol, Alto Adige, Trento, Verona, railway and highway companies and the European Commission is an example of involvement of regions and focus on local benefits in infrastructure projects.

(89)

More details on the outcomes of the open public consultations can be found in the Annex 2 as well as in to the Panteia et al. 2018 (Report on the results of the public consultation).

(90)

 There is evidence that the promoters of PCIs expect acceleration of the procedures in their individual cases. According to the analysis of ACER, the average duration of permitting expected by PCI promoters in the pool of 96 electricity PCIs is 3.5 years. For gas, the average permit granting duration for the pool of assessed 54 PCIs was 3.2 years. Commission Staff Working Document Accompanying the document Commission Delegated Regulation amending Regulation (EU) No 347/2013 of the European Parliament and of the Council as regards the Union list of projects of common interest, SWD(2017) 425 final https://ec.europa.eu/energy/sites/ener/files/documents/swd_accompanying_pci_list_final_2017_en.pdf

Top

Brussels, 17.5.2018

SWD(2018) 178 final

COMMISSION STAFF WORKING DOCUMENT

IMPACT ASSESSMENT

Accompanying the document

Proposal for a Regulation of the European Parliament and of the Council

on streamlining measures for advancing the realisation of the trans-European transport network

{COM(2018) 277 final}
{SEC(2018) 228 final}
{SWD(2018) 179 final}


ANNEXES

ANNEX 1: Procedural information concerning the process to prepare the impact assessment report and the related initiative

Lead DG

The lead DG for this initiative is DG MOVE. This impact assessment report concerns the initiative with Agenda planning reference PLAN/2016/210-MOVE – "Streamlining the implementation of the Trans-European Network for Transport (TEN-T)".

Foreseen adoption date: 02 May 2018

Organisation and timing

The initiative received political validation in January 2017 and the impact assessment work started immediately afterwards. It lasted until February 2018.

The Inter-service Steering Group (ISSG) was set-up with invitations sent to DG CLIMA, DG CNECT, DG COMP, DG ECFIN, DG ENER, DG ENV, DG FISMA, DG GROW, DG MARE, DG REGIO and SJ.

The ISSG was chaired by the DG MOVE with the close involvement of the Secretariat General. The following DGs actively participated in the ISSG: DG COMP, DG ENER, DG ENV, DG GROW, DG MARE, DG REGIO, DG RTD, DG MARE and SJ.

Eight ISSG meetings were held on 31 May, 28 June, 14 September, 17 November and 13 December 2017 as well as 18 January 2018, 30 January and 7 February 2018.

Consultation of the Regulatory Scrutiny Board

The Regulatory Scrutiny Board ("RSB") was consulted on 7 March 2018.

The impact assessment was submitted to the Commission’s Regulatory Scrutiny Board on 14 February 2018. Following the meeting on 7 March 2018, the Board issued a positive opinion with reservations. The Board made recommendations. Those were addressed in the revised IA report as follows:

Main considerations

Modification of the IA report

(1)    The report does not give sufficient evidence on how public procurement and permit procedures affect delays in construction. It does not explain how it varies across sectors and Member States. The report lacks a description of the lessons learnt from TEN-E, EFSI, and action taken in Member States to streamline processes.

Examples were presented more prominently to illustrate the impacts of delays in permitting granting processes and procurement on individual projects and how it affects the completion of the TEN-T and the network effects.

More reference was made to the results of the implementation of the TEN-E and EFSI State aid scheme.

Specific paragraphs were added to describe the experience of Member States and the actions taken to streamline their processes.

All these elements strengthened the granularity of the analysis.

(2)    The report misses the stakeholder views of the options, especially those of Member States and citizens.

The results of the open public consultations and other stakeholders' consultation were presented in the respective sections to a much greater extent.

A specific section was developed in the chapter 7 on the comparison of policy options.

(3)    The assessment of impacts lacks a sensitivity analysis and an explanation of the assumptions of the calculation, in particular regarding the degree of delays that the measures can realistically avoid.

A sensitivity analysis was developed and presented in section 7.7 of the report. More detailed results are included in Annex 4. More explanations have been added on the assumptions used in Annex 4.

Further considerations and adjustment requirements

(1) The report does not explain the timing of this initiative sufficiently well, especially why it has to precede the finalisation of the TEN-E and TEN-T evaluations. Its connection to the multi-annual financial framework cycle should be clearer. The report should give the reasons for not addressing the issues of permitting and public procurement earlier when the TEN-T regulation was adopted or later against the backdrop of first results.

A new paragraph was added in the introduction to present the evaluation strategy concerning TEN-T policy, the articulation of the various elements of this policy in the long-term. In particular, the IA report informs about the planned evaluation of the TEN-T Regulation and its possible revision in 2023.

(2) The description of the context needs to reference any recently adopted relevant legislation and its expected impacts on the problem. The context sections need to clarify the scope of the initiative, explaining why some known TEN-T problems are out of scope and others are not.

Reference was added to the recent developments in the area of EIA, public procurement and State aid. It was better explained why these measures are not sufficient to meet the needs of the TEN-T projects.

(3) The report needs to give more indications on how public procurement and permit procedures affect delays in the construction of infrastructure. It should show which provisions are the most problematic. It needs to be clear how the problem varies across Member States, across sectors and between cross-border and non-cross-border projects. Furthermore, the report needs to argue for each dimension of the problem, i.e., permitting, public procurement and state aid, why the efforts done by Member States to streamline processes are not sufficient. Finally, the problem description needs to fully cover the problems with state aid and its relevance for TEN-T as well.

See Main Consideration above (1)

A table presenting the situation in different Member States and their streamlining measures was inserted in the report. More details were added in order to demonstrate the existence of the problems and the need for actions undertaken at EU level with different levels of intervention.

As regards State aid, it was better explained why State aid clearance is important for the implementation of TEN-T projects, the recent developments in this field to improve legal certainty and the need to build upon existing best practices to shorten the time for State aid clearance at EU level.

(4) The report should include the lessons learnt from efforts to streamline complex procedures in TEN-E and in the Member States as well as best practices developed elsewhere, e.g., under EFSI. It needs to explain how this experience has affected the development of options for this initiative.

More developments were made to better reflect the initiatives taken by Member States as well as the lessons learnt from TEN-E experience in the IA report. A reference was made to the existing arrangements as regards State aid control for EFSI projects.

(6) From the report, it is not immediately clear how the level of ambition differs regarding permitting, public procurement and state aid. The development of options for each needs to be more closely tied to the problem description, the legislative context, and lessons learnt and best practices from efforts elsewhere.

A chapeau was developed to introduce the chapter on possible measures. The different levels of ambition per issues or areas was better presented.

It was also made clearer that policy options are built upon the description of the problem drivers.

(7) The discussion of the options needs to include the views of the stakeholders. When stakeholders are sceptical in some cases, the report should address their concerns and explain the mitigation measures it proposes. It is important that the description of stakeholder views is neutral and balanced across all stakeholder groups.

A new subsection was added in the Chapter on comparison of options to present the opinion of the various groups of stakeholders on each proposed solution.

(8) Regarding the intervention logic, it seems that the low investors' base is not a problem driver, but rather a consequence of the problems. The objectives should correspond to the revised problem drivers. The operational objectives should lend themselves to operationalisation to allow for measuring progress in terms of concepts like complexity.

The structure was largely modified to reflect this reservation. The lack of interest of private investors in infrastructure project was presented rather as a consequence than a problem driver as such. Problems stemming from complex permit granting procedures, public procurement, delays etc are affecting the attractiveness of those projects to private investors. Remaining uncertainties as regards State aid control, in particular the duration of the State aid clearance, was highlighted as a problem driver, in that sense.

(9) Given that the reductions in delays associated with the different options derive from stakeholders' views, the report should indicate the type of evidence collected from stakeholders and the robustness of their contribution to avoid the impression that assumptions predetermined the selection of outcomes. It is, in particular, important to explain how the views allow differentiating between the three options. A sensitivity analysis needs to be performed to verify how changes in expected time savings change the ranking of options.

The IA report and its annexes were improved to describe the type of evidence gathered from the stakeholders.

The views of stakeholders were also further reflected on the various measures envisaged under the policy options.

In addition, a sensitivity analysis was performed to examine the effect of changes in the baseline and in the effectiveness rates used in the assessment of the policy options. The results are included in section 7.7 of the report and in Annex 4.

(10) Streamlining complex cross-border processes might lead to some risks. Especially citizens and smaller economic operators might have difficulties to participate in the consultation or procurement processes, when these are using procedures from another Member State, which they are not familiar with. The report needs to discuss how and to what extent these risks can be mitigated.

The analysis was even further reinforced on unintended consequences. The absence of impacts on the length of individual consultation was further clarified. More explanations were added on the possible mitigation measures in the chapter on social impacts.

The analysis of the impacts on SME was also supplemented by considerations on the possible implications of cross-border public procurements on smaller businesses.

Data used in impact assessment and external expertise

The initiative follows up a long reflection process and responds to the political invitation to act. In 2014, the Council of Ministers already invited the Commission to take stock of good practices and identify ways to streamline permitting procedures for projects of common interest of the core network 1 . The CBS Report presented by European Coordinators Bodewig and Secchi as well as former Vice President H. Christophersen recommended the simplification of administrative authorisation, permitting rules and/or regulatory procedures in order to facilitate the implementation of the TEN-T.

In the Rotterdam Declaration 2 , the EU transport ministers called for the development and implementation of improved coordinated procedures in particular in the procurement and State aid areas, they also called on the European Commission to assess various ways to simplify procedures for projects of common interest on the TEN-T core network.

Finally, in January 2018, a progress report of the implementation of their recommendations reiterated the call to consider setting up of special (single) procurement rules for cross-border projects and setting time limits for the permitting procedure. 3

The Commission sought external expertise in the economic field through a contract for a support study with Panteia et al. The findings of the support study fed into the final impact assessment report. 4

The expertise gathered by the Exploratory Study 5 carried out in 2015/2016 was also used to prepare certain elements of the impact assessment report, notably in terms of problem definition.

In the course of both studies, a wide range of stakeholders were consulted to confirm the scope and the magnitude of the problems and to provide their views on the potential solutions to these problems. In parallel to the external studies, the Commission services sought further expertise and input from stakeholders by means of dedicated meetings throughout the impact assessment, an open public consultation 6 .

Other sources of data used included:

· Action Plan - Making the best use of new financial schemes for European transport infrastructure projects Christophersen, Bodewig and Secchi Report – 2015, and its Progress Report published in January 2018.

·Individual studies for the nine Core Network Corridors, DG MOVE 2014 with the second generation finalised in 2017 7

·Work Plans of the 11 TEN-T European Coordinators (9 Core Network Corridors + ERTMS and Motorways of the Sea programme) 8  Cost of non-completion of the TEN-T, Fraunhofer Institute, 2015,

·Communication on 'Building the transport core network: core network corridors and Connecting Europe Facility 9  

· Progress report on implementation of the TEN-T network in 2014-2015 , February 2017

· Delivering TEN-T, Facts & Figures , September 2017. 

ANNEX 2: Stakeholder consultation synopsis report

I. Introduction

This report provides a summary of the outcomes of the stakeholder consultation activities which were carried out as part of the study to support the impact assessment.

It provides a basic analysis of the range of stakeholder groups that were engaged in those activities and a summary of the main issues which they raised.

The objectives of the consultation activities were to:

Provide to the wide public and stakeholders an opportunity to express their views on the importance and relevance of the problems and issues related to the current legal framework, in order to help formulate and refine the problem definition;

Gather specialised input (data and factual information, expert views) on specific aspects of the legislation from the enforcement community and from the industry; and

Gather input (data and/or estimates, expert views) on the expected impact and level of support of a set of measures intended to address issues and problems identified in the current legal framework.

The consultation activities included:

·Two open public consultations organised by the Commission services;

·A series of workshops in the context of the impact assessment;

·Stakeholder interviews in the context of the impact assessment;

·Consultation activities in the previous exploratory study along with an open public consultation and dedicated working sessions.

·Feedback mechanism 10 to the Inception Impact Assessment that was published in June 2017 at the Commission's website.

·The initiative related to the streamlining of implementation of the TEN-T was also discussed at ministerial level on two occasions. It was discussed at the Regional Transport Investment Conference on 23 and 23 March 2017 in Sofia. It was also discussed at the Informal Transport Minister Council on 21 September 2017 in Tallinn along with other issues related to the development and financing of the TEN-T.

II. Methodology

(1)Feedback mechanism to the Inception Impact Assessment

Three pieces of feedback were received – from an individual, a national agency and an association of transport infrastructure managers. All three pieces welcomed the initiative to streamline the implementation and based on the preliminary presentation of the considered options, supported a limited binding action to be implemented at national level as one being effective and in line with the principle of subsidiarity.

(2)Open public consultation (OPC)

The consultation aimed gathering the opinions of the general public and stakeholders as regards the main problems and proposed solutions for facilitating the implementation of the TEN-T projects.

This consultation was developed with the objective of gathering opinions from the general public and stakeholders with regard to the main issues and proposed solutions for facilitating the implementation of the TEN-T projects.

A total of 99 responses were received, representing 23 different EU Member States equivalent to 94% of all contributions ( Table 1 ). Only three replies came from countries outside the EU, namely Norway and FY Republic of Macedonia, whilst three more were provided by representatives of European, multinational or global organisations. Three questionnaires with severely incomplete responses had to be discarded. Additional pieces of feedback were also provided to the Commission services and were also taken into consideration in the overall analysis. Moreover, 20 respondents identified themselves as individuals, and 79 as organisations. As can be seen in Table 1 , regional, local or municipal authorities (20%), project promoters (19%) and industrial, business or sectorial associations (20%) were the organisation categories with higher representation, closely followed by National governments (16%).

Table 1: Breakdown of responses by Member States.

Country

Individuals

Organisations

Number of Respondents

EU-Members States

Germany

1

10

11

Hungary

2

7

9

Belgium

1

8

9

Austria

2

5

7

Italy

3

4

7

Spain

1

5

6

Sweden

-

5

5

Finland

-

4

4

Romania

2

2

4

France

1

3

4

Czech Republic

-

4

4

Denmark

1

3

4

Netherlands

2

2

4

Slovak Republic

1

1

2

Poland

-

2

2

Bulgaria

1

1

2

Portugal

-

2

2

Latvia

-

2

2

Lithuania

-

1

1

Malta

-

1

1

Luxembourg

1

-

1

Cyprus

-

1

1

Ireland

-

1

1

Non-EU countries

Norway

-

2

2

FY Republic of Macedonia

1

-

1

Other

EU, global or multi-national

-

3

3

Total

20

79

99

Table 2: Breakdown of responses by type of organisation.

Type of organizations represented

Number of respondents

%

A company (other than project promoter)

10

13%

A national government

13

16%

A project promoter (public or private)

16

20%

A regional/ local/municipal authority

16

20%

An industrial interest group, business association, sectorial association

15

19%

NGO, civil society, environmental group or charity

3

4%

Other:

Institution governed by public law

2

3%

Cross-border cooperation

2

3%

Reflection group on freight transport

1

1%

Public organisation for regional collaboration

1

1%

Total

79

100%

When asked about which mode of transport their activities mainly focused on, 24 of respondents said to concentrate on rail, 22 on multimodal, and 15 on road transport. A significant 20 of respondents do not focus on any particular mode, as they represent individuals.

Table 3: Breakdown of responses by mode of transport

Mode of transport focus

Total

Rail

24

Multimodal (combined) transport

22

No Answer

20

Road

15

Maritime transport and ports

9

Inland waterways and ports

8

Air transport

1

Total

99

3.Series of workshops with stakeholders and different Commission Services

As part of the consultations strategy a series of dedicated workshops was organised to discuss as widely as possible with all interested stakeholders the problems and possible solutions to which are part of the present initiative. In order to cover horizontal aspects of the EU legislation, these meeting were organised jointly with the respective Commission's services, i.e. DG GROW, DG COMP and DG ENV. The workshops were addressed to the TEN-T stakeholders, i.e. the members of the Core Network Corridors forums as well as representatives of the Member States grouped in the TEN-T Committee, the topics discussed were the public procurement, governance and financing of cross-border projects as well as environmental permitting at project level and public consultations.

(3)Workshop: Smart and effective public procurement of TEN-T cross-border projects, Brussels, 15th June 2017

The workshop was very well attended with almost 100 participants representing different sectors and types of organisations, including project promoters and national and regional authorities. The workshop was organised along with the services of DG GROW who presented their recent initiatives and the new ways to simplify the public procurement for infrastructure projects and informed their usual stakeholders on the opportunity to take part in the workshop.

i)Cross Border projects, governance and financing, Tallinn, 21 September 2017

This workshop, organised jointly with DG COMP, was held as a dedicated session being part of the Connecting Europe Conference and was widely promoted along with the main event. The workshop and the conference were very well attended with more than 1300 participants.

ii)Workshop: Efficient permitting for TEN-T projects, Brussels, 17th October 2017

This workshop was very well attended with almost 120 participants representing different sectors and types of organisations, including project promoters and national and regional authorities. The workshop was organised along with the services of DG ENV who presented their recent initiatives and the new ways to simplify the environmental permitting in the transport infrastructure sector as well as invited stakeholders from the environmental sector.

4.Stakeholder interviews

Additional interviews were conducted in selected Member States, with either face to face or telephone interviews to complement some aspects related to the study. Those interviewed consisted of relevant staff in national administrations in France, Germany, The Netherlands, Poland, and Italy as well as in the Directorate General for Energy in the European Commission.

The interviews were performed between the 6 December 2017 and the 17 January 2018.

5.Consultation activities in the previous exploratory study along with and open public consultation and dedicated working sessions.

i)Open public consultation

As part of the exploratory study, a fully-fledged open public consultation was conducted. The consultation was launched on 17 June 2016 and remained opened for a period of twelve weeks, until 5 September 2016. The consultation asked for opinions on possible options to streamline and facilitate the permitting, procurement and state aid procedures for TEN-T core network projects, and invited respondents to comment on the impact of proposed options and suggest any further possible options.

In total, 88 responses to the questionnaire were received, including 84 from 21 Member States and four responses from non-EU Member States (Norway, Serbia and Switzerland). Of these, 21 were received from individuals, and 67 from organisations, consisting mainly of public authorities (14 national governments, 20 regional, local or municipal authorities). In addition, three organisations (one national government and two industry associations) sent written contributions.    

Table 4: Breakdown of responses by type of organisation

Type of organisation

Number of respondents

A regional/local/municipal authority

20

A national government

14

A company (other than project developer)

10

A project developer (public or private)

8

An industrial interest group, business association, sectoral association

6

Other:

9

·Port authority / Port Governance Agency

2

·Executive agency

1

·Intergovernmental organisation

1

·Public sector undertaking

1

·Allocation Body

1

·Bi-national society

1

·Regulatory Body for Mobility and Transports

1

Responses were received from most EU Member States. The largest samples of answers are coming from countries with large TEN-T projects (Italy, Poland, Germany and France).

Table 5: Breakdown of responses by Member States

Member States

Number of respondents

Italy

12

Poland

9

Germany

9

France

7

Belgium

6

Portugal

5

Greece

4

Sweden

4

Netherlands

3

Slovenia

3

Spain

3

Bulgaria

3

Austria

3

Denmark

2

Czech Republic

2

Romania

2

Latvia

2

Lithuania

2

Luxembourg

1

Slovak Republic

1

Hungary

1

Non-EU countries

3

Norway

1

Serbia

2

Switzerland

1

ii)Discussions and meetings with stakeholders

On 27-29 January 2016, during the TEN-T European Coordinators Seminar at the EIB in Luxembourg, a discussion was held on the problem definition. Participants included TEN-T European Coordinators, EIB and project promoters.

On 3 March 2016, a workshop was organised with European Coordinators for TEN-T corridors and Brussels based transport associations to discuss the challenges in the planning and implementation of TEN-T core network projects. The stakeholders were also invited to present good practised in this field that could feed into the analysis.

The problems with specific focus on waterborne projects were discussed at the Motorways of the Sea Forum on 17 May 2016. Participants included national competent authorities (TEN-T Committee members), Commission services, and wider transport stakeholders. The purpose was to present and discuss policy options.

iii) Final Workshop

The final workshop was a half-day meeting dedicated entirely to the presentation and discussion of the policy options contained in this report. It was held on 7 December 2016 in Brussels during a week of TEN-T Corridor forum meetings and participants included national competent authorities, wider transport stakeholders and Commission services. The agenda included presentations from a project promoter, a private investor on the regulatory and administrative challenges that TEN-T projects face. The approach to project permitting for cross-border network projects in the energy sector was presented by DG Energy. The options in this report were presented by the consultant for feedback and discussion.

iv) Interviews in the framework of the Exploratory Study

In the framework of the Exploratory study, in-depth studies were carried out by national experts to examine the regulatory and administrative frameworks for transport projects in ten selected Member States to identify the sources of delay, cost and uncertainty, as well as good practices. The country studies were completed on the basis of desk research (particularly legal analysis) and interviews with competent authorities and project promoters in the Member States. The country studies helped to better understand the current situation in the individual Member States and how the effects of possible solutions would be distributed. Moreover, the case studies of individual projects also included direct interviews (particularly competent authorities and project promoters).

1.Conclusions of all consultation activities

The objectives of the consultation activities have been largely achieved. All relevant stakeholders’ groups representing all EU Member States have been consulted and most provided their views, together with some quantitative information, where available, related to existing issues and the policy measures under consideration. However, even if the consultation strategy targeted other stakeholders than the TEN-T project promoters or authorities involved in the implementation of transport infrastructure projects (e.g. by involving other DGs and their networks of contacts), the majority of the stakeholders participating in the workshops represented the transport area.

The information collected corresponded in general to the objectives and expectations of the consultation activities defined for each stakeholder group, although in a number of cases stakeholders.

The number of responses to some of the consultation activities was above the average of the usual experience of DG MOVE. However, given the fact that the present initiative is going beyond the traditional transport related topics, a greater number of respondents would better reflect the general trends in the area.

1.1.Summary of input from the workshops

Conclusions on public procurement:

There is room for facilitation the public procurement procedures for cross-border TEN-T projects (special purpose vehicles for implementation, single procedures, assistance, language, etc.);

If there is a legislative proposal, it will apply as of next MFF only, taking into consideration the cycle of the co-legislators.

Conclusions on the governance and financing:

A stronger involvement of the European Commission is requested by the participants, both diplomatic and participation in the structures of the joints ventures;

A common framework for the entire duration of the project's implementation is seen as a facilitating element – e.g. choice of the law of one country and apply to the entire project;

All procedures and permits should be done in parallel, a one-stop-shop is an interesting concept;

Stability and certainty of financing solutions is crucial for the smooth implementation of the large cross-border infrastructure projects.

Conclusions on environmental assessments:

There is room for facilitation in the permitting procedures in a form of 'smart evolution' to address the needs of key TEN-T projects, in particular in simplifying the rules for cross-border TEN-T projects (aligning the procedures, assistance, language rules, joint body, etc.) or integrating certain procedures to avoid duplications;

Good quality information is a necessary pre-requisite for a smooth permitting procedure;

Guidelines in terms of applicability of certain procedures or promotion best practices in terms of public consultation are welcome;

Lack of available data and expertise should be addressed. This can be done via a specific targeted technical assistance for project promoters as some projects are very complex and not typical;

Public consultations can positively feed into the project preparation process if they are well-timed and address the right stakeholders and communities.



1.2. Summary of input from the open public consultation

1.2.1.Overall scoping and confirmation of the problems

The consultation has provided evidence that the main issues identified in the permitting procedures of TEN-T projects, relate to the steps on the strategic level of a project’s preparation, including the attainment of spatial planning permits, planning permissions and environmental assessments at project level.

For project promoters in particular, public procurement for works and obtaining final development consent or construction permits, and environmental assessments at project level, constitute key obstacles.

All stakeholder categories (9 companies, 12 national governments, 13 project promoters, 16 regional/local/municipal, all 20 industry groups and 13 individuals) generally agree that TEN-T projects are subject to lengthy and complicated procedures, recognising the existence of the identified problem. Only 5 respondents do not agree that there is a problem of this nature (2 industry groups, a company, a project promoter and a NGO). 17 respondents (mainly 5 regional/local/municipal authorities, 5 industrial interest groups, and 3 project promoters) recognised that cross-border projects are particularly impacted by regulatory and administrative obstacles. However, 29 of participants from all stakeholder type stated that all transport infrastructure projects are subject to such problems.

Figure 1: TEN-T project are subject to complex and lengthy permitting procedures and other processes

Source: Open Public Consultation (2017)

In general, 59 respondents from all category types (32 project promoters, national and regional governments more pronouncedly, while individuals less so), mostly agreed that permitting procedures are not organised in an optimal way and therefore, identified there is room for improvement.



Figure 2: Permitting procedures are not organised in an optimal way

Source: Open Public Consultation (2017)

Figure 3 Permitting procedures are organised in an optimal way, by category of stakeholders

Source: Open Public Consultation (2017)

When asked to identify the biggest challenges for the procurement of cross-border projects, 60 respondents of all categories, selected the application of different national legislations and the difficulties on agreeing on the applicable one, as the foremost obstacles. Industrial and business associations, as well as other companies, highlighted the lack of experience of the contracting authorities and the insufficient promotion of best practices, as key challenges as well.

A high number of respondents also agreed on the existence of difficulties and need for improvement in the fields of State aid (45 respondents) and public consultation processes (80 respondents from all stakeholder type), pointing out the lack of general understanding of the common socio-economic benefits from transport projects and the insufficient involvement of the population, as main causes for the latter. Individuals, industrial associations and other companies, also included the ineffective communication of information by project promoters as an important factor.



1.2.2. Evaluation of possible solutions

The consultation found that respondents, both individuals and organisations, agree that the EU should take action to address inefficiencies in the permitting procedure of TEN-T projects.

Figure 4: Should the EU take action to address inefficiencies in the permitting procedures in case of TEN-T projects?

Source: Open Public Consultation (2017)

integration of procedures under a “one-stop-shop” (OSS)

Support for the integration of procedures under a national single entity, a “one-stop-shop” (OSS) was expressed in particular, by project promoters, individuals and industrial interest groups. More reserved opinions were expressed by national and regional governments. This was also confirmed by the bilateral interviews.

A significant portion of national and regional governments altogether are reluctant towards this solution. However, the individual qualitative analysis of their comments shows that this apparent disagreement stems, in some cases, from the fact that some countries have already implemented integrated procedures with a single entity (including fast track procedures). The existence of a single entity that manages the permitting process of such projects can be seen as a best practice example of “one-stop-shop” implementation.

In general, national governments believe that the integration of various administrative procedures for permit granting at national level – combined with time limits (see below) - are the most effective measures to reduce delays, speed up the process and give legal certainty. In their view, it creates a more attractive environment for private investors in the long-term.

Some national governments have expressed reservations with regard to the set-up of national “one-stop-shops”. They consider that, although this entity would be beneficial if implemented properly and would effectively speed up the process, it might also lead to additional administrative burden and organisational problems. The authority that would be appointed to act as OSS might not have all the competences and it might take several years before it becomes effective. They have pointed out the importance of defining a clear and specific role for such an entity and to avoid conflicts when a one stop shop is already in place.

According to project promoters and individuals the OSS should have extended decision-making capacity that would manage all environmental assessments at project level, spatial planning permissions and construction permits. On the other hand, the opinions of national and regional governments varied as to the extent of the integration of procedures and level of authority. A significant number of national representatives stated that such entities should have coordinating powers only.

·Introduction of time limits

Respondents – primarily project promoters, individuals and industrial interest groups - agreed that the permitting process should not last longer than 2 years, and that the establishment of such time limit could help reduce excessive delays. Local and regional authorities as well as some national government were more reserved. They have provided critical views on time limits for the total duration of approval procedures for TEN-T projects, stating that since procedures for large-scale and complex projects are usually very time-consuming, such limits would have the risk of creating relative delays for small uncomplicated projects. In the context of bilateral interviews, some national governments also highlighted that the delays are often caused by investors themselves, for which time limits would have less effect.

·Public acceptance and technical assistance

High levels of involvement of the general public throughout the whole project duration and effective communication of the common benefits it brings to society, were the preferred measures to overcome issues related to low public acceptance.

All respondents from all stakeholders’ type in general (see figure 33 from the online public consultation report in annex), and organisations more so than individuals, identified a need for technical assistance primarily in the fields of environmental assessments, financing structure development, including the designing of Public-Private Partnerships, and public procurement procedures.

·Common set of rules at EU level

A common set of rules at EU level applied to cross-border projects was identified, in particular by project promoters and industrial groups, as the most effective solution to improve public procurement issues. National authorities stated that such a set of rules would be more effective when applied to cross-border projects benefiting from EU funding.

At EU level, respondents agreed that environmental assessments (24 respondents, from which 5 project promoters. 5 industry groups, 4 national governments, 4 individuals and others), funding decisions (21 respondents,) and state aid clearance (20 respondents, from which 4 national governments, 2 project promoters, 2 companies, 3 regional governments and 4 industrial groups, 3 individuals) should be handled under a single procedure. They also affirm that such a simplified framework would have the highest positive impact for projects from the TEN-T Core Network.

However, there is reluctance amongst some national governments, regional and local authorities, who have taken strong positions against the definition and handling of the procedures at European level. They have argued that it would not speed up the permitting process and could result in the duplication of efforts, since only national authorities could verify the individual approval requirements of each country, and therefore, some procedure would be duplicated.

·Possible legal instrument

Amongst the available instruments for adopting measures to facilitate the permitting and preparation of TEN-T projects, the consultation showed a preference from respondents in general for the implementation of an EU Regulation on the permitting procedures and other elements of preparation of priority status TEN-T projects, which would be directly applicable in Member States.

Nevertheless, some national governments have provided different opinions in relation to the considered instruments. They showed hesitation towards the implementation of an EU Directive or a Regulation, and recommended caution, mentioning that these actions could endanger the stability of European legislation in the respective areas. These views were expressed in the course of the bilateral interviews with some national administrations. Some national administrations consider that it would impact directly the approval procedure of TEN-T projects, arguing that such measure would conflict with ongoing procedures at national level, and may even generate further delays. They warned against any new processes that would be established in addition to the existing ones, in particular when a one stop shop already exists in the country.

A variety of stakeholders, and in particular from national and local authorities support the value and significance of knowledge transfer, the guidance that such instructions can provide, and the importance of promotion and dissemination of best practices. It is nevertheless important to note that the development of non-binding EU guidelines for permitting procedures was evaluated as less effective than binding rules. When deepening the analysis through bilateral interviews, some national governments considered that soft law instruments would leave them greater room to implement the measures in the most effective way according to their specific needs. Other national governments on the other hand doubt their effectiveness.

1.3.Additional results from direct interviews with Member States' authorities

Opinions vary regarding soft law: some agree that soft law instruments will leave the necessary room for MS to implement the measures in the most effective way, according to the specific needs of each State, only others doubt their effectiveness.

In any case, they all support the development for best practice dissemination and knowledge exchange amongst MS, which can improve their national frameworks by learning from successful cases. They defended the value of developing guidelines and establishing standard procurement procedures.

Member States believe that the integration of various administrative procedures at national level and introduction of time limits for the permitting procedures are the most effective measures to reduce delays, speed up the process and give legal certainty, and thereby, generate attractiveness of private actors in the long-term. A couple of MS showed hesitancy towards the establishment of time limits for permitting procedures, since delays are often caused by the investors.

With regards to the proposal to set up a “one-stop shop” and to integrate authorisation procedures, some MS already have this integration and fast track for some projects. The existence of a single entity that manages the permitting process of such projects can be seen as a best practice example of “one-stop-shop” implementation.

They have expressed doubts with regards to the set-up of national “one-stop-shops”. They reflect that, although this entity would be beneficial if implemented in an ideal manner and would effectively speed up the process, it might also result in the creation of additional bureaucracy and lead to organisational problems. The authority that would be appointed to act as OSS might not have all the competences and it might take several years before it becomes effective. They have pointed out the importance of defining a clear and specific role for such an entity.



Some Member States expressed their reluctance towards the establishment of new European Directives or Regulations that would directly determine the content of the approval procedure of TEN-T projects, arguing that such measure would conflict with ongoing procedures at national level, and therefore, generate further delays.

In general, Member States agree with measures to improve, clarify and simplify procedures as they believe it is above all essential to stabilise the legal framework.

ANNEX 3: Who is affected by the initiative and how

Stakeholders affected by the current situation

The following stakeholders have been identified as the main groups of stakeholders affected by the existing problems, as described in Chapter 2 of the main report (problem definition). All main groups of stakeholders recognise that permitting procedures for TEN-T projects are not organised in an optimal way.

Figure 5: Permitting procedures are organised in an optimal way, by category of stakeholders

Source: Open Public Consultation (2017)

·Promoters of transport infrastructure projects

All project promoters of TEN-T projects are confronted to permitting procedures and other procedures such as public procurement and State aid clearance in order to implement and realise their transport infrastructure project.

In particular, this concerns the infrastructure managers of the TEN-T networks (rail, road, ports, inland waterways). This group of affected stakeholders also includes entities which are set up only for the purpose of implementation of a project, such as special project companies and joint ventures in case of cross-border projects.

Project promoters are mostly affected by the complexity of the procedures resulting in delays and legal uncertainties creating additional costs for them. They tend to agree that many of the stages described in the above authorisation framework pose problems in terms of project preparation. The project promoters who participated in the open public consultation (16 contributions) were asked to identify the steps that most lengthen procedures and create administrative burden for them. They mentioned, in the following order, public procurement works, environmental assessments at project level and construction permits as the most cumbersome stages in their response 11

Figure 6: Steps affecting the most the length and create administrative burden from the point of view of project promoters

Source: Open Public Consultation (2017)

·Public administrations at local, regional or national level

Another group of affected stakeholders is composed of local, regional and national authorities which often are responsible both for the promotion of projects – since most of the TEN-T infrastructure is owned by the State or subnational public entities – and for the issuance of specific permits and carrying out the procedures required by law.

Thus, the impact on the public administrations is twofold and results in varying views on the problem and on possible solutions. This was evidenced at the occasion of the targeted workshop 12 dedicated to efficient permitting for TEN-T projects which gathered representatives of national authorities dealing with permitting processes, but also national authorities directly involved in the development of infrastructure projects, notably cross-border projects.

·Civil society

The initiative affects also citizens in various ways. Permitting procedures are designed to preserve certain citizens' rights, for instance the property right, the quality of their environment or the protection against several nuisances. For this reason, one important element of the authorisation procedures concerns the stakeholders' consultation and the possibility for citizens – often represented by local groups or NGOs – to make their voice heard.

In recent years, the mobilisation of citizens in the context of the development of infrastructure projects has significantly increased. Local communities may sometimes oppose the construction of projects with largely positive impacts – economic or environmental – that have an effect elsewhere (larger city, port etc.). This opposition by local residents is linked to the fact that these new constructions or upgrades are close to their homes or imply nuisances or other negative effects to their immediate living environment. Projects often do not take into consideration the local context and impacts, as the regions, NGOs or communes are not effectively involved in the project planning and the administrative proceedings are too complex and difficult to understand. In addition, the mobilisation of local residents opposing infrastructure projects can be compounded by groups of activists which may employ more radical means to block the implementation of projects.

On the other hand, citizens cannot take advantage from the effective and on-time delivery of infrastructure projects and of the related benefits when the projects are delayed. They are likely to also support cost overruns one way or the other – be it as user of the infrastructure or as taxpayers when the projects are publicly developed. The over-complexity of procedures or the lack of coordination and predictability is likely to discourage the most concerned citizens (landowners, local inhabitants, local NGOs) from taking part in the consultations. The permitting procedures may also prove inefficient if the input from civil society is not taken into account at the right time, which calls for carefully designed and understandable procedures.

In order not to limit the fundamental rights of these stakeholders, the measures will have to be carefully design in order not to create an imbalance between various group of stakeholders, and in particular, not to be to the detriment of citizens and civil society.

Stakeholders affected in case of adoption of the preferred option

The preferred policy option is policy option 2, which includes legal requirement for Member States to introduce one-stop shop and integration of procedures for TEN-T core network projects and ensure that the most rapid treatment legally possible is given to them. Auxiliary measures concern application shorter deadlines for State aid clearance as well as dedicated technical assistance.

National authorities, including permitting bodies, project promoters and civil society are the most affected stakeholders.

National authorities

The national authorities would be affected by the need of designating or establishing a body whose objective would be to integrate or coordinate the permitting processes related to the TEN-T core network projects. It would lead to more efforts for integrating and coordinating existing procedures following a stock-taking exercise to identify the fast ones and the most relevant actors. Depending on the administrative organisation of the Member States this would require administrative measures to entrust the relevant bodies with a clear allocation of tasks and responsibility for making the necessary decisions. This will also provide additional support and impetus to initiatives developed at national level with the same objective. It will require a screening of the current procedures related to the permitting processes and the most rapid procedures available. Some lessons may also be drawn by national authorities from their own experience with the TEN-E permit granting schemes and certain scheme may even be simply extended to transport. While the preferred option would necessarily entail some administrative costs (even though more limited than for the permitting authorities), the additional workload and cost borne at national authorities are expected to decrease overtime.

As part of the national authorities, the permitting bodies are expected to be directly impacted policy option 2. The workload in terms of the necessary reorganisation of the working patterns and introduction of coordination or procedures currently running completely independently is expected not to be negligible in a ramp-up phase. The introduction of time limits for overall permitting procedures will result in an increased intensity of work. The administrative cost for this type of stakeholders in terms of NPV is expected to grow by 5%. However, the impact assessment shows that it will decrease overtime.



Project promoters

Project promoters are expected to be positively impacted by the preferred policy option. The measures covered by the initiative would lead to a significant simplification of the permit granting process. It would lead to a reduction in time and avoid long delays encountered in certain cases. The time limit will provide them with a clear indication of the overall duration of the permit granting process, increasing clarity and predictability of the implementation. Ultimately, this simplification and greater clarity will also facilitate their relations with investors, in particular private ones which would be more keen to support transport infrastructure projects. More specifically, promoters of cross border projects would also enjoy a facilitated framework for public procurement, as national authorities would necessarily need to opt for single rules. On the other hand, it should not be omitted that project promoters would also need to adapt to the new streamlined measures. However, this adaptation time is expected to be relatively short. Overall, the net present value of the change in the administrative cost borne by project promoters is expected to decrease by 13% compared to the baseline, which is far from being insignificant for TEN-T projects. It means important savings in external spend (law firms, engineering companies, financial experts etc.)

The impact of the changes in legal framework, which stability is very important for long-term projects, is not expected to be negative. The changes introduced by the PO2 focus on the organisation of procedures and not on the requirements and contents of the documentation necessary for obtaining authorisations, thereby reducing the risk of significant compliance costs

Civil society

The integration of procedures as well as the coordination of the overall authorisation procedures foreseen under policy option 2 is expected to have a positive impact on public consultations and thus on the involvement of civil society. The existing complex process of project approval involving several bodies at different stages of the procedure - which is largely considered unsatisfactory by civil society organisations - will be improved to ensure that one procedure is applied with a single authority leading the process (one stop shop authority).

Any misperceptions that the measures would affect citizens' rights to be beard and involved in the process due to changed procedures will be avoided, notably by designing a clearer and more inclusive process. The initiative will not reduce the time for public consultations as it would not affect the requirements set in each procedure but it will require greater coordination between them. Civil society and in particular local communities will also benefit from a clearer framework allowing their comments to be well channelled and better addressed to the decision maker. The greater synchronisation of process and introduction of time limits will also be an opportunity for local communities and conservation NGOs to have their voice heard due to innovations in the procedures.



Figure 7: Reasons for a lack of public acceptance of certain transport infrastructure projects



Summary of costs and benefits of the preferred option

I. Overview of Benefits (total for all provisions) – Policy Option 2 – 2018-2030

Description

Amount

Comments

Direct benefits

User cost reductions for the TEN-T core network

- €5.1bn (-0.2% compared to baseline)

Benefits include time savings, increased reliability of transport and lower transport costs for infrastructure users.

Traffic shifted to

rail transport in 2030

+ 2.6% for passenger transport and + 0.5% for freight transport compared to baseline

Traffic shifted to waterborne transport in 2030

+ 0.1% compared to baseline

Environmental benefits of the TEN-T core network projects:

Since the initiative aims at reducing delays, the positive impacts of the implementation of the TEN-T projects on environment and climate will be generated earlier.

CO2 emissions: - 2.7 million tonnes (- 0.2%) compared to baseline

External costs of air pollution: - €5.6 million compared to baseline

External costs of noise: - €26.9 million compared to baseline

Social benefits:

·Participation

·Cohesion

·Safety/public health

External costs of accidents: - €297 million (-0.2%) compared to baseline for TEN-T core network

The integration of procedures as well as the coordination of the overall authorisation procedures would simplify public consultations. Civil society as well as local communities could also benefit from a clearer framework allowing their comments to be well channelled and better addressed to the decision maker.

The initiative is expected to result in modal shift to safer and cleaner modes (in particular rail) and to decrease road traffic, hence it is expected to be positive in terms of public health.

An improved implementation of TEN-T projects would positively contribute to cohesion.

Indirect benefits

Positive impact on GDP of the implementation of the TEN-T core network projects

+1.6% compared to the baseline

This captures the indirect effects on economic sectors other than transport and the effects induced by increased productivity, improved conditions for international trade and technological spill-overs.

Employment impacts of implementing the TEN-T core network projects

5 600 job-years (+1.6% compared to the baseline)

II. Overview of costs – Policy Option 2

Promoters

Administrations

Combined impact

Baseline

Policy Option 2

Baseline

Policy Option 2

Policy Option 2

Total administrative costs in € million (2018-2030)

937

-166 (-18%)

185

+13 (+7%)

-153 (-14%)



ANNEX 4: Analytical methods

1.4.Description of analytical models used

A model suite has been used for the analytical work: PRIMES-TREMOVE transport model, the NEAC transport network model and an Excel-based tool developed by Panteia/NEA in the context of the Impact Assessment support study 13   14 While PRIMES-TREMOVE is a transport model covering the entire transport system, used for the development of the EU Reference scenario 2016, the NEAC model and the Excel-based tool developed in the context of the Impact Assessment support study focus specifically on the implementation of the TEN-T investment plans. A brief description of each model is provided below, followed by an explanation of each model’s role in the context of this impact assessment.

Section 4.2 presents the assumptions and results of the baseline scenario. Section 4.3 provides other assumptions used for evaluating the impacts of policy options while section 4.4 presents the assumptions used for calculating the administrative burden.

1.4.1.PRIMES-TREMOVE transport model

The PRIMES-TREMOVE transport model projects the evolution of demand for passengers and freight transport by transport mode and transport mean. It is essentially a dynamic system of multi-agent choices under several constraints, which are not necessarily binding simultaneously. The model consists of two main modules, the transport demand allocation module and the technology choice and equipment operation module. The two modules interact with each other and are solved simultaneously.

The projections include details for a large number of transport means, technologies and fuels, including conventional and alternative types, and their penetration in various transport market segments for each EU Member State. They also include details about greenhouse gas and air pollution emissions (e.g. NOx, PM, SOx, CO), as well as impacts on external costs of congestion, noise and accidents.

In the transport field, PRIMES-TREMOVE is suitable for modelling soft measures (e.g. eco-driving, deployment of Intelligent Transport Systems, labelling), economic measures (e.g. subsidies and taxes on fuels, vehicles, emissions; ETS for transport when linked with PRIMES; pricing of congestion and other externalities such as air pollution, accidents and noise; measures supporting R&D), regulatory measures (e.g. CO2 emission performance standards for new passenger cars and new light commercial vehicles; EURO standards on road transport vehicles; technology standards for non-road transport technologies), infrastructure policies for alternative fuels (e.g. deployment of refuelling/recharging infrastructure for electricity, hydrogen, LNG, CNG). Used as a module which contributes to a broader PRIMES scenario, it can show how policies and trends in the field of transport contribute to economy wide trends in energy use and emissions. Using data disaggregated per Member State, it can show differentiated trends across Member States.

PRIMES-TREMOVE has been used for the 2011 White Paper on Transport, Low Carbon Economy and Energy 2050 Roadmaps, the 2030 policy framework for climate and energy and more recently for the Effort Sharing Regulation, the review of the Energy Efficiency Directive, the recast of the Renewables Energy Directive, the European strategy on low-emission mobility, the revision of the Eurovignette Directive and the recast of the Regulations on CO2 standards for light duty vehicles.

The PRIMES-TREMOVE is a private model that has been developed and is maintained by E3MLab/ICCS of National Technical University of Athens 15 based on, but extending features of the open source TREMOVE model developed by the TREMOVE 16 modelling community. Part of the model (e.g. the utility nested tree) was built following the TREMOVE model 17 . Other parts, like the component on fuel consumption and emissions, follow the COPERT model.

As module of the PRIMES energy system model, PRIMES-TREMOVE 18 has been successfully peer reviewed 19 , most recently in 2011 20 .

1.4.2.NEAC model

NEAC is a network-based transport model, where the supply side of the transport sector is represented as a set of network structures connecting the trading regions in the model. The system covers all of Europe and neighbouring countries and provides the link between traffic and economic development across European regions.

The basic units within the system are NUTS3 regions. The model covers the road, rail and waterborne transport. Goods are traded between regions depending on their socio-economic needs and routed from origin to destination via the transport network. The volumes being traded, and the route/mode choices used determine the system’s cost, measured as user (internal) and non-user (external) cost. Through a combination of exogenous and endogenous effects, the system can be modelled over time to produce projections. Levels of economic development are linked to their levels of trade. Ports have a special role within the system as the primary gateways for intercontinental traffic. Sea transport is included within the multimodal network structures in NEAC.

NEAC model is particularly suitable for modelling transport infrastructure policies, port competition and containerisation.

NEAC is a private model, developed and maintained by Panteia/NEA 21 . It has been used for the 2014 TEN-T Corridor studies and more recently in the context of the 2017 TEN-T Corridor work plans 22 .

1.4.3.Panteia/NEA model

An Excel-based tool was additionally developed by Panteia/NEA to assess the impacts of delays in the implementation of core TEN-T network investments (i.e. the baseline scenario) and of measures related to the streamlining of TEN-T implementation. The tool covers EU28 and draws on input from: the updated EU Reference scenario 2016, the NEAC model, the TEN-T core network investment projects and the results of stakeholders’ consultation on the effectiveness of options to reduce delays in the implementation of core TEN-T network investments.

The approach to quantify impacts on social benefits includes several calculation steps:

Estimation of the effects of measures on the investments profile by transport mode;

Estimation of the effect of the investments profile on transport activity by transport mode;

Estimation of the impacts on total transport user costs;

Estimation of the impacts on CO2 emissions and air pollution emissions, and calculation of the external costs of air pollution, noise, congestion, accidents and climate change.

The impacts of measures related to the streamlining of TEN-T implementation on the investments profile draws on the results of stakeholders consultation. The inputs used are provided in section 4.2 and further explained in the Impact Assessment support study.

In a second step, the impacts of investment profiles on transport activity by mode are derived drawing on the NEAC model. The total user costs are calculated by applying the average unit costs to the transport activity by mode. CO2 emissions and air pollution emissions by transport mode are calculated by applying the emission factors per passenger-kilometre and tonne-kilometre from the updated EU Reference scenario 2016 to the transport activity by mode. External costs are derived in a similar way, drawing on the input from the updated EU Reference scenario 2016 and the 2014 Handbook on the external costs of transport 23 . A discount rate of 4% is used for deriving the present value of social benefits accruing over time.

In addition, GDP and employment effects have been estimated based on multipliers applied to the investment profiles by policy option. To capture the total scope of economic effects of the interventions it is necessary to measure the wider economic impacts, which is only possible by a fully-fledged macro-economic model. Such a macro-economic approach has been followed with the application of the ASTRA model in the study on Cost of non-completion of the TEN-T 24 , which has estimated the full growth and jobs impacts of not implementing the TEN-T by 2030 (i.e. the study modelled the whole sequence of direct effects, indirect effect, second round effects). This study delivered multipliers as a side product, which refer to impacts generated over the whole period up to 2030. They include the impacts during construction in the first phase of the planning horizon and the impacts stemming from the use of infrastructure after opening of the projects in later phases. The GDP and employment multipliers applied for the analysis are provided in the table below. For example, the time profile reveals that with increasing project lifetime the number of additional jobs increases such that the multipliers grow with the number of time periods of project life.

Table 4-1: GDP and employment multipliers applied for the analysis 25

Investment projects

2016 to 2030

1 to 5 years

1 to 10 years

1 to 15 years

GDP Multipliers in bn€ / bn€ of investments in €2015

4.24*

1.95

3.43

5.49

Employment multipliers in job-years / bn€ of investments in €2015

16,566*

11.624

15.124

19.024

Source: M-Five calculations, Impact Assessment support study; * All TEN-T projects

1.4.4.PRIMES-TREMOVE, NEAC and Panteia/NEA models role in the impact assessment

The PRIMES-TREMOVE transport model is a building block of the modelling framework used for developing the EU Reference scenario 2016, and has a successful record of use in the Commission's transport, climate and energy policy analytical work – it is the same model as used for the 2011 White Paper on Transport and the 2016 European strategy on low-emission mobility.

The NEAC model is a transport network model used to assess the impacts of infrastructure investments on transport activity by mode and has been extensively used for the 2014 TEN-T Corridor studies and the evaluation of the 2017 TEN-T Corridor work plans. NEAC model represents implementetion of the core TEN-T network invetment plans.

In this impact assessment, the NEAC model has been initially calibrated on an update of the EU Reference scenario 2016 (including few policy measures that have been adopted after its cut-off date i.e. end of 2014). The EU Reference scenario 2016 assumes the completion of the core TEN-T network by 2030 and of the comprehensive TEN-T network by 2050 and this represented the starting point for the development of the Baseline scenario. Subsequently, the NEAC model has been used to reflect the impacts of delays in the implementation of core TEN-T network investments on the transport activity. The Panteia/NEA tool together with NEAC model have been used for assessing the social benefits of the policy options, drawing on input from the updated EU Reference scenario 2016.

1.5.Baseline scenario 

1.5.1.Scenario design, consultation process and quality assurance

The Baseline scenario used in this impact assessment builds on the EU Reference scenario 2016 but additionally includes few policy measures adopted after its cut-off date (end of 2014). Building an the EU Reference scenario is a regular exercise by the Commission. It is coordinated by DGs ENER, CLIMA and MOVE in association with the JRC, and the involvement of other services via a specific inter-service group.

For the EU Reference scenario 2016, Member States were consulted throughout the development process through a specific Reference scenario expert group which met three times during its development. Member States provided information about adopted national policies via a specific questionnaire, key assumptions have been discussed and in each modelling step, draft Member State specific results were sent for consultation. Comments of Member States were addressed to the extent possible, keeping in mind the need for overall comparability and consistency of the results.

Quality of modelling results was assured by using state of the art modelling tools, detailed checks of assumptions and results by the coordinating Commission services as well as by the country specific comments by Member States.

The EU Reference scenario 2016 projects EU and Member States energy, transport and GHG emission-related developments up to 2050, given current global and EU market trends and adopted EU and Member States' energy, transport, climate and related relevant policies. "Adopted policies" refer to those that have been cast in legislation in the EU or in MS (with a cut-off date end of 2014 26 ). Therefore, the binding 2020 targets are assumed to be reached in the projection. This concerns greenhouse gas emission reduction targets as well as renewables targets, including renewables energy in transport. The EU Reference scenario 2016 provides projections, not forecasts. Unlike forecasts, projections do not make predictions about what the future will be. They rather indicate what would happen if the assumptions which underpin the projection actually occur. Still, the scenario allows for a consistent approach in the assessment of energy and climate trends across the EU and its Member States.

The report "EU Reference Scenario 2016: Energy, transport and GHG emissions - Trends to 2050" 27 describes the inputs and results in detail. In addition, its main messages are summarised in the impact assessments accompanying the Effort Sharing Regulation 28 and the revision of the Energy Efficiency Directive 29 , and the analytical work accompanying the European strategy on low-emission mobility 30 .

1.5.2.Main assumptions of the Baseline scenario

The projections are based on a set of assumptions, including on population growth, macroeconomic and oil price developments, technology improvements, and policies.

Macroeconomic assumptions

The Baseline scenario uses the same macroeconomic assumptions as the EU Reference scenario 2016. The population projections draw on the European Population Projections (EUROPOP 2013) by Eurostat. The key drivers for demographic change are: higher life expectancy, convergence in the fertility rates across Member States in the long term, and inward migration. The EU28 population is expected to grow by 0.2% per year during 2010-2030 (0.1% for 2010-2050), to 516 million in 2030 (522 million by 2050). Elderly people, aged 65 or more, would account for 24% of the total population by 2030 (28% by 2050) as opposed to 18% today.

GDP projections mirror the joint work of DG ECFIN and the Economic Policy Committee, presented in the 2015 Ageing Report 31 . The average EU GDP growth rate is projected to remain relatively low at 1.2% per year for 2010-2020, down from 1.9% per year during 1995-2010. In the medium to long term, higher expected growth rates (1.4% per year for 2020-2030 and 1.5% per year for 2030-2050) are taking account of the catching up potential of countries with relatively low GDP per capita, assuming convergence to a total factor productivity growth rate of 1% in the long run.

Fossil fuel price assumptions

Oil prices used in the Baseline scenario are the same with those of the EU Reference scenario 2016. Following a gradual adjustment process with reduced investments in upstream productive capacities by non-OPEC 32 countries, the quota discipline is assumed to gradually improve among OPEC members and thus the oil price is projected to reach 87 $/barrel in 2020 (in year 2013-prices). Beyond 2020, as a result of persistent demand growth in non-OECD countries driven by economic growth and the increasing number of passenger cars, oil price would rise to 113 $/barrel by 2030 and 130 $/barrel by 2050.

Techno-economic assumptions

For most transport means, the Baseline scenario uses the same technology costs assumptions as the EU Reference scenario 2016. For light duty vehicles, the data for technology costs and emissions savings has been updated based on a recent study commissioned by DG CLIMA 33 . Battery costs for electric vehicles are assumed to go down to 205 euro/kWh by 2030 and 160 euro/kWh by 2050; further reductions in the cost of both spark ignition gasoline and compression ignition diesel are assumed to take place. Technology cost assumptions are based on extensive literature review, modelling and simulation, consultation with relevant stakeholders, and further assessment by the Joint Research Centre (JRC) of the European Commission.

Specific policy assumptions

The key policies included in the Baseline scenario, similarly to the EU Reference scenario 2016, are 34 :

CO2 standards for cars and vans regulations ( Regulation (EC) No 443/2009 , amended by Regulation (EU) No 333/2014 and Regulation (EU) No 510/2011, amended by Regulation (EU) No 253/2014); CO2 standards for cars are assumed to be 95gCO2/km as of 2021 and for vans 147gCO2/km as of 2020, based on the NEDC test cycle, in line with current legislation. No policy action to strengthen the stringency of the target is assumed after 2020/2021.

The Renewable Energy Directive (Directive 2009/28/EC) and Fuel Quality Directive (Directive 2009/30/EC) including ILUC amendment (Directive 2015/1513/EU): achievement of the legally binding RES target for 2020 (10% RES in transport target) for each Member State, taking into account the use of flexibility mechanisms when relevant as well as of the cap on the amount of food or feed based biofuels (7%). Member States' specific renewable energy policies for the heating and cooling sector are also reflected where relevant.

Directive on the deployment of alternative fuels infrastructure ( Directive 2014/94/EU ).

Directive on the charging of heavy goods vehicles for the use of certain infrastructures (Directive 2011/76/EU amending Directive 1999/62/EC).

Relevant national policies, for instance on the promotion of renewable energy, on fuel and vehicle taxation, are taken into account.

In addition, a few policy measures adopted after the cut-off date of the EU Reference scenario 2016 at both EU and Member State level, have been included in the Baseline scenario:

Directive on weights & dimensions (Directive 2015/719/EU);

Directive as regards the opening of the market for domestic passenger transport services by rail and the governance of the railway infrastructure (Directive 2016/2370/EU);

Directive on technical requirements for inland waterway vessels (Directive 2016/1629/EU), part of the Naiades II package;

Regulation establishing a framework on market access to port services and financial transparency of ports 35 ;

·The replacement of the New European Driving Cycle (NEDC) test cycle by the new Worldwide harmonized Light-vehicles Test Procedure (WLTP) has been implemented in the Baseline scenario, drawing on work by JRC. Estimates by JRC show a WLTP to NEDC CO2 emissions ratio of approximately 1.21 when comparing the sales-weighted fleet-wide average CO2 emissions. WLTP to NEDC conversion factors are considered by individual vehicle segments, representing different vehicle and technology categories 36 .

Changes in road charges in Germany, Austria, Belgium and Latvia.

Reflecting the plateauing in the number of fatalities and injuries in the recent years, in the Baseline scenario it has been assumed that post-2016 vehicle technologies would be the main source of reduction in fatalities, serious and slight injuries while measures addressing infrastructure safety (such as the existing RISM and Tunnel Directives), and driver behaviour (such as legislation improving enforcement across borders, namely Directive 2015/413/EU facilitating cross-border exchange of information on road safety related traffic offences) would compensate for the increase in traffic over time.

Delays in the implementation of core TEN-T network investments. Building on previous priority project reports (2012) 37 , the Impact Assessment support study shows that in the baseline scenario only 50% of investments would occur on schedule while 25% of the investments would be delayed due to permitting procedures by one year, 15% by two years, and 10% by three years. The figure below shows the cumulative core TEN-T investments profiles: scheduled and with the delays assumed in the baseline scenario for all transport modes.

Figure 4-1: Cumulative investment profile – scheduled and with delays (baseline scenario)

1.5.3.Summary of main results of the Baseline scenario

EU transport activity is expected to continue growing under current trends and adopted policies beyond 2015, albeit at a slower pace than in the past. Freight transport activity for inland modes is projected to increase by 28% between 2015 and 2030 (1.7% per year) and 51% for 2015-2050 (1.2% per year). Passenger traffic growth would be lower than for freight at 17% by 2030 (1.1% per year) and 36% by 2050 (0.9% per year for 2015-2050). The annual growth rates by mode, for passenger and freight transport, are provided in the figure below 38 .

Road transport would maintain its dominant role within the EU. The share of road transport in inland freight is expected to slightly decrease at 70% by 2030 and 69% by 2050. Road freight activity expressed in tonnes kilometres is projected to grow by 27% between 2015 and 2030 (47% for 2015-2050) in the Baseline scenario. For passenger transport, road modal share is projected to decrease by 3 percentage points by 2030 and by additional 3 percentage points by 2050. Passenger cars and vans would still contribute 70% of passenger traffic by 2030 and about two thirds by 2050, despite growing at lower pace (14% for 2015-2030 and 27% during 2015-2050) relative to other modes, due to slowdown in car ownership increase which is close to saturation levels in many EU15 Member States and shifts towards rail.

Figure 4-2: EU passenger and freight transport projections (average growth rate per year)

 

Source: Baseline scenario, Impact Assessment support study

Note: For aviation, domestic and international intra-EU activity is reported, to maintain the comparability with reported statistics.

Rail transport activity is projected to grow significantly faster than for road, driven in particular by the opening of the market for domestic passenger rail transport services and the implementation of the TEN-T guidelines, supported by the CEF funding. Passenger rail activity goes up by 33% between 2015 and 2030 (70% for 2015-2050), increasing its modal share by 1 percentage point by 2030 and an additional percentage point by 2050. Rail freight activity grows by 39% by 2030 and 75% during 2015-2050, resulting in 1 percentage point increase in modal share by 2030 and an additional percentage point by 2050.

Transport activity of freight inland navigation 39 also benefits from the TEN-T core and comprehensive network investments, the promotion of inland waterway transport and the recovery in the economic activity and would grow by 23% by 2030 (1.4% per year) and by 43% during 2015-2050 (1% per year). However, as illustrated in Figure 4-3, delays in investments due to permitting procedures would lead to lower activity than in the updated EU Reference scenario over 2015-2020 for both rail and inland navigation.

Figure 4-3: Projected transport activity growth rates for rail and inland navigation in the Baseline and the EU Reference scenario 2016 for 2015-2020

Source: Baseline scenario and the updated EU Reference scenario 2016 (REF2016), Impact Assessment support study; Note: inland navigation covers inland waterways and national maritime.

Domestic and international intra-EU air transport would grow significantly (by 41% by 2030 and 93% by 2050) and increase its share in overall transport demand (by 2 percentage points by 2030 and by additional 2 percentage points by 2050). International maritime transport activity is projected to continue growing strongly with rising demand for oil, coal, steel and other primary resources – which would be more distantly sourced – increasing by 21% by 2030 and by 51% during 2015-2050.

The declining trend in transport emissions is expected to continue, leading to 13% lower emissions by 2030 compared to 2005, and 15% by 2050. 40 However, relative to 1990 levels, emissions would still be 13% higher by 2030 and 10% by 2050, owing to the fast rise in the transport emissions during the 1990s. Aviation would contribute an increasing share of transport emissions over time, increasing from 14% today to about 18% in 2030 and 21% in 2050. Maritime bunker fuel emissions are also projected to grow strongly, increasing by 10% during 2015-2030 (24% for 2015-2050).

NOx emissions would drop by about 42% by 2030 (52% by 2050) with respect to 2015 levels. The decline in particulate matter (PM2.5) would be less pronounced by 2030 at 40% (56% by 2050). Overall, external costs related to air pollutants would decrease by about 43% by 2030 (55% by 2050). 41  

High congestion levels are expected to seriously affect road transport in several Member States by 2030 in the absence of effective countervailing measures such as road pricing. While urban congestion will mainly depend on car ownership levels, urban sprawl and the availability of public transport alternatives, congestion on the inter-urban network would be the result of growing freight transport activity along specific corridors, in particular where these corridors cross urban areas with heavy local traffic. The largest part of congestion will be concentrated near densely populated zones with high economic activity such as Belgium and the Netherlands – to a certain extent as a result of port and transhipment operations – and in large parts of Germany, the United Kingdom and northern Italy. Estimating the costs of congestion is not straightforward, because it occurs mostly during certain times of the day, often caused by specific bottlenecks in the network. In the Baseline scenario, total congestion costs for urban and inter-urban network are projected to increase by about 17% by 2030 and 35% by 2050, relative to 2015.

Noise related external costs of transport would continue to increase, by about 12% during 2015-2030 (18% for 2015-2050), driven by the rise in traffic. External costs of accidents are projected to slightly go down by about 7% by 2030 (11% for 2015-2050).

1.6.Assumptions used for modelling the policy options

The effectiveness of policy options in reducing delays is provided in Table 4-2, drawing on stakeholders consultation. In the Panteia/NEA tool, these options influence the extent to which the baseline delays can be reduced.

PO1 and PO2 are assumed to have earlier start dates compared to PO3, but PO3 is assumed to be more effective in eliminating delays, and faster to reach full effectiveness. These assumptions are based on the different types of legal instruments involved. PO1 involves voluntary actions, and no binding time limits, but it can be implemented quickly. PO2 involves the establishment of national one-stop-shops following the approach adopted in the energy sector, where it was found that it took longer than expected to transpose the legislation and establish the one-stop-shops. PO3 involves the most complexity to initiate since it would require a new EU framework, but once established it would potentially eliminate a greater proportion of the delays, including those related to duplication of permitting procedures each side of a national border.

Table 4-2: Assumptions regarding effectiveness of options to reduce delays

PO1

PO2

PO3

Year of launch

2020

2022

2023

Effectiveness

15%

60%

80%

Build Up period

5

3

0

Source: Impact Assessment support study

The level of effectiveness is derived from the consultation report which found that:

75% of 93 respondents fully or rather agreed that a ‘one-stop-shop’ would facilitate and accelerate the permitting of TEN-T projects (Q31);

73% of the 96 respondents fully or rather agreed that such overall time-limit would be useful in accelerating permitting procedures (Q34);

68% of 88 respondents expected that an EU Regulation on permitting procedures, directly applicable in all Member States would be either effective of very effective (Q47);

26% of 86 respondents expected that EU Guidelines (not legally binding) would be either effective or very effective (Q47).

Thus, PO2 and PO3 which include mandatory provisions for a one-stop-shop and time limits were assumed to have higher effectiveness rates in reducing delays in procedures than PO1 which contains measures which are not legally binding. PO3, which includes an overall EU framework directly applicable in all Member States was assumed to have higher effectiveness than PO2.

The impacts on the cumulative investment profile in each policy option is provided in Table 4-3. In the modelling framework, lower delays compared to the baseline lead to positive modal shifts in the transport network, meaning in turn that user benefits (lower transport costs) and external costs savings are generated at different points in the timescale. These benefits are expressed as present value using a discount rate of 4%.

Table 4-3: Share of total investments in the policy options for 2020-2025 over the lifetime of the projects

Cumulative investments (share of total investments over the lifetime of the projects)

2020

2021

2022

2023

2024

2025

Total investments

 

 

 

 

 

 

Baseline

38.7%

50.1%

60.0%

68.5%

75.5%

81.4%

Option 1

39.0%

50.6%

60.7%

69.3%

76.4%

82.1%

Option 2

38.7%

50.1%

61.6%

71.2%

78.9%

84.2%

Option 3

38.7%

50.1%

60.0%

73.9%

80.0%

85.1%

Rail transport

 

 

 

 

 

 

Baseline

36.1%

46.9%

56.1%

64.3%

71.2%

77.2%

Option 1

36.4%

47.4%

56.8%

65.1%

72.0%

77.9%

Option 2

36.1%

46.9%

57.6%

66.9%

74.5%

80.1%

Option 3

36.1%

46.9%

56.1%

69.5%

75.6%

81.0%

Waterborne transport

 

 

 

 

 

 

Baseline

40.6%

53.8%

65.8%

75.2%

82.9%

89.0%

Option 1

41.0%

54.5%

66.7%

76.1%

83.8%

89.7%

Option 2

40.6%

53.8%

67.7%

78.2%

86.5%

91.8%

Option 3

40.6%

53.8%

65.8%

81.1%

87.7%

92.7%

Source: Impact Assessment support study; waterborne transport covers inland waterways and maritime.

1.7.Assumptions used for calculating the impacts on administrative burden

The methodology undertaken to assess the baseline and the impacts of the policy options on the administrative burden draws on literature review and the outcome of the interviews performed in the context of the Impact Assessment support study. The administrative costs cover:

·administrative personnel from public administration processing applications;

·administrative personnel from public administration providing feedback on the outcome of the applications;

·administrative personnel from the project managers, infrastructures managers, or any other stakeholder required to produce documentation related to an assessment;

·project managers and staff requiring time to follow the assessment procedures, i.e. to obtain, renew and modify the application process.

The baseline assumptions and results for the evolution of administrative burden are provided in Table 4-4. It considers the time spent (in person-hours) by the Promoters and the Authority 42 , the labour cost per hour 43 , the number of new projects launched per year and the total administrative cost in million €.

Table 4-4: Yearly administrative burden in the baseline scenario

Target group

Time spent per project (hours)

Labour costs (€ per hour)

Number of projects starting per annum

Total administrative costs in million €

Promoter

29,788

25.40 44

190

143.8

Authority

5,872

25.40

190

28.3

Source: Impact Assessment support study

Table 4-5 shows the impact of each measure identified under the three policy options, considering four main areas of intervention: authorisation and permits, public procurement, state aid and other. The percentages represent the potential maximum administrative cost/saving that each measure might achieve against the administrative cost currently incurred in any given year. However, these impacts do not occur in the same years and often they are not recurrent, as they include a combination of implementation and recurrent costs/benefits. Several measures included in the different policy options require similar actions. When the administrative costs of two measures were overlapping, their two figures have been combined.

Table 4-5: Administrative cost per measure: maximum potential cost or saving against the baseline scenario

Option / Description

Measures

Details

Promoter Admin. Cost

Authorities Admin. Cost

Option 1: Minimal change to existing instruments and development of soft law as well as accompanying measures

Authorisation and permits

Guidelines for the permit granting procedures and application of the EU acquis in this field.

-4.0%

1.0%

Systematic encouragement in soft law instruments (e.g. guidelines) to apply joint and/or coordinated procedures under Article 2(3) of the revised EIA Directive

Public procurement

Guidelines for TEN-T project promoters and better orientation of existing instruments (such as measures encompassed in COM(2017) 573 “Helping investment through a voluntary ex-ante assessment of the procurement aspects for large infrastructure projects”, JASPERS or EIAH support

-4.0%

1.0%

State aid

No modification

0.0%

0.0%

Other

Targeted technical assistance measures for carefully selected projects of common interest (including high quality and efficient packaging of routine projects).

-4.0%

2.5%

Effective technical assistance (e.g. Jaspers or the European Investment Advisory Hub) to support project preparation and horizontal issues affecting the implementation of TEN-T projects, both at the Member State and EU level (modelled on the JASPERS initiative and/or systematically involving cooperating Member States-JASPERS-Commission to develop tailor-made solutions for individual Member States).

-7.5%

2.5%

Facilitation support provided by the European Coordinators, where appropriate, in line with the mandate defined in the TEN-T regulation.

-4.0%

1.0%

Option 2: Limited binding action to be implemented at national level

Authorisation and permits

Establishment of a one-stop-shop (OSS) at national level. The OSS would continue to apply national permitting rules (transposed from EU directives) – legal requirement needed/similar to TEN-E

-10.0%

2.0%

Integration of various administrative procedures at national level (notably all environmental assessments EIA, Habitat, Water, Seveso, Waste, Birds etc. currently optional) – legal requirement needed/similar to TEN-E.

-7.5%

2.0%

Introduction of time limits for permitting procedures (possibly also for legal appeals while preserving access to justice) – legal requirement needed/similar to TEN-E

-7.5%

4.0%

Public procurement

Requirement to opt for a single legal framework for public procurement of cross-border projects (currently optional) – legal requirement needed

-2.5%

2.5%

Guidelines for TEN-T project promoters and better orientation of existing instruments (such as, measures encompassed in COM(2017) 573 “Helping investment through a voluntary ex-ante assessment of the procurement aspects for large infrastructure projects”, JASPERS or EIAH support).

-4.0%

1.0%

State aid

No modification

0.0%

0.0%

Shorter deadlines for State aid clearance – similar to EFSI projects.

-5.0%

2.0%

Other

Targeted technical assistance measures for carefully selected projects of common interest (including high quality and efficient packaging of routine projects).

-4.0%

2.5%

Option 3: An EU framework for authorisation of the project of common interest

Authorisation and permits

Definition of a specific framework for the authorisation of carefully selected projects of common interest. This would include integrated procedures, time limits, cases for overriding public interest and make requirement under existing Directives directly applicable – legal requirement needed.

-7.5%

7.0%

Public procurement

Definition of a specific framework for single rules to be applied in public procurement of cross-border projects – legal requirement needed.

-5.0%

5.0%

State aid

No modification

0.0%

0.0%

Shorter deadlines for State aid clearance – similar to EFSI projects.

-5.0%

2.0%

Other

Targeted technical assistance measures for carefully selected projects of common interest (including high quality and efficient packaging of routine projects).

-4.0%

2.5%

Source: Impact Assessment support study

To assess the cost savings, the number of projects being affected by each policy option has been multiplied to the potential cost saving per project as provided in Table 4-5. The present value over 2018-2030 has been further derived for each policy option and compared to the baseline. A discount rate of 4% has been used for calculating the present value.

1.8.Sensitivity analysis

A sensitivity analysis has been performed for the baseline scenario and for the effectiveness rates used in quantifying the policy options.

An alternative baseline scenario has been considered where 60% of investments would occur on schedule while 20% of the investments would be delayed due to permitting procedures by one year, 10% by two years, and 10% by three years. This can be regarded as a more conservative scenario relative to the central baseline estimate.

Consequently, the impacts of the policy options have been assessed drawing on the alternative baseline scenario while at the same time keeping the effectiveness rates unchanged (see Table 4-2). Using a more conservative baseline scenario results in higher investments taking place in the beginning of the period under all policy options and all transport modes, relative to the assessment based on the central baseline (see Table 4-6).

Table 4-6: Share of total investments in the alternative baseline scenario and policy options for 2020-2025 over the lifetime of the projects

Cumulative investments (share of total investments over the lifetime of the projects)

2020

2021

2022

2023

2024

2025

Total investments

 

 

 

 

 

 

Alternative baseline

40.6%

51.7%

61.3%

69.6%

76.5%

82.2%

Option 1

40.8%

52.1%

61.9%

70.3%

77.2%

82.8%

Option 2

40.6%

51.7%

62.6%

71.9%

79.3%

84.5%

Option 3

40.6%

51.7%

61.3%

74.2%

80.2%

85.3%

Rail transport

 

 

 

 

 

 

Alternative baseline

37.8%

48.4%

57.4%

65.4%

72.1%

78.0%

Option 1

38.1%

48.8%

58.0%

66.1%

72.8%

78.6%

Option 2

37.8%

48.4%

58.7%

67.6%

74.8%

80.4%

Option 3

37.8%

48.4%

57.4%

69.7%

75.8%

81.2%

Waterborne transport

 

 

 

 

 

 

Alternative baseline

43.0%

55.8%

67.4%

76.5%

83.9%

89.8%

Option 1

43.3%

56.3%

68.2%

77.2%

84.7%

90.4%

Option 2

43.0%

55.8%

69.0%

78.9%

86.9%

92.1%

Option 3

43.0%

55.8%

67.4%

81.3%

87.9%

92.9%

Source: Impact Assessment support study

Overall, the policy options result in lower net benefits relative to the assessment based on the central baseline. However, the ranking of the policy options in terms of net benefits does not change (see Table 4-7). PO1 results in net benefits of €1.8 bn for the core TEN-T network projects (€2.1 bn for the central estimate), while PO2 shows net benefits of €5 bn (€5.9 bn for the central estimate) and PO3 €6.4 bn (€7.7 bn for the central estimate).

Table 4-7: Costs and benefits of the policy options relative to the baseline over the lifetime of the projects (2018-2030)

Net benefits (in million €, constant prices 2015)

PO1

PO2

PO3a/PO3b

Core TEN-T network projects

 

 

 

Social benefits

 

 

 

User costs savings

1,534

4,238

5,558

External costs savings

228

606

793

Air pollution

2

5

6

Noise

8

22

29

Congestion

72

170

222

Accidents

88

248

324

Climate change

57

161

211

Total social benefits

1,761

4,843

6,350

Administrative costs reduction

12

113

72

Net benefits (present value)

1,773

4,956

6,423

Core network corridors projects

 

 

 

Social benefits

 

 

 

User costs savings

1,150

3,178

4,168

External costs savings

171

454

594

Air pollution

2

3

5

Noise

6

17

22

Congestion

54

128

166

Accidents

66

186

243

Climate change

43

120

158

Total social benefits

1,321

3,632

4,763

Administrative costs reduction

9

85

54

Net benefits (present value)

1,330

3,717

4,817

CEF projects

 

 

 

Social benefits

 

 

 

User costs savings

851

2,352

3,084

External costs savings

126

336

440

Air pollution

1

3

4

Noise

5

12

16

Congestion

40

94

123

Accidents

49

138

180

Climate change

32

89

117

Total social benefits

977

2,688

3,524

Administrative costs reduction

7

63

41

Net benefits (present value)

984

2,751

3,565

Source: Impact Assessment support study

In addition, a sensitivity analysis has been performed on the effectiveness rates. More conservative levels for the effectiveness of the policy options have been assumed: 10% for PO1, 50% for PO2 and 70% for PO3. In this case, the policy options have been quantified drawing on the central baseline scenario. Using more conservative effectiveness rates results in somewhat lower investments taking place in the beginning of the period under all policy options (in particular in PO1), relative to the central estimates and the baseline (see Table 4-8).

Table 4-8: Share of total investments in the baseline scenario and policy options for 2020-2025 over the lifetime of the projects, under alternative assumptions for effectiveness rates

Cumulative investments (share of total investments over the lifetime of the projects)

2020

2021

2022

2023

2024

2025

Total investments

 

 

 

 

 

 

Baseline

38.7%

50.1%

60.0%

68.5%

75.5%

81.4%

Option 1

38.9%

50.4%

60.4%

69.0%

76.1%

81.9%

Option 2

38.7%

50.1%

61.3%

70.8%

78.3%

83.7%

Option 3

38.7%

50.1%

60.0%

73.2%

79.5%

84.7%

Rail transport

 

 

 

 

 

 

Baseline

36.1%

46.9%

56.1%

64.3%

71.2%

77.2%

Option 1

36.3%

47.2%

56.6%

64.8%

71.7%

77.6%

Option 2

36.1%

46.9%

57.4%

66.5%

73.9%

79.6%

Option 3

36.1%

46.9%

56.1%

68.9%

75.0%

80.6%

Waterborne transport

 

 

 

 

 

 

Baseline

40.6%

53.8%

65.8%

75.2%

82.9%

89.0%

Option 1

40.9%

54.3%

66.4%

75.8%

83.5%

89.4%

Option 2

40.6%

53.8%

67.4%

77.7%

85.9%

91.3%

Option 3

40.6%

53.8%

65.8%

80.3%

87.1%

92.3%

Source: Impact Assessment support study

Similar to the use of a more conservative baseline, lower effectiveness rates would lead to somewhat lower net benefits relative to the central estimates (in particular for PO1). However, the ranking of the policy options in terms of net benefits does not change. PO1 results in net benefits of €1.4 bn for the core TEN-T network projects (€2.1 bn for the central estimate), while PO2 shows net benefits of €5 bn (€5.9 bn for the central estimate) and PO3 €6.7 bn (€7.7 bn for the central estimate).

Table 4-9: Costs and benefits of the policy options relative to the baseline over the lifetime of the projects (2018-2030)

Net benefits (in million €, constant prices 2015)

PO1

PO2

PO3a/PO3b

Core TEN-T network projects

 

 

 

Social benefits

 

 

 

User costs savings

1,225

4,224

5,817

External costs savings

182

603

829

Air pollution

2

5

7

Noise

7

22

31

Congestion

57

168

230

Accidents

70

248

340

Climate change

46

160

221

Total social benefits

1,407

4,827

6,646

Administrative costs reduction

9

137

85

Net benefits (present value)

1,416

4,964

6,731

Core network corridors projects

 

 

 

Social benefits

 

 

 

User costs savings

919

3,168

4,363

External costs savings

136

452

622

Air pollution

1

3

5

Noise

5

17

23

Congestion

43

126

172

Accidents

53

186

255

Climate change

34

120

166

Total social benefits

1,055

3,620

4,984

Administrative costs reduction

7

103

64

Net benefits (present value)

1,062

3,723

5,048

CEF projects

 

 

 

Social benefits

 

 

 

User costs savings

680

2,344

3,228

External costs savings

101

335

460

Air pollution

1

3

4

Noise

4

12

17

Congestion

32

93

128

Accidents

39

137

189

Climate change

25

89

123

Total social benefits

781

2,679

3,688

Administrative costs reduction

5

77

48

Net benefits (present value)

786

2,756

3,736

Source: Impact Assessment support study

ANNEX 5: Auxiliary elements for the analysis of the problem and the definition of policy options

The present annex further develops certain elements taken into consideration in the definition of the problems and the elaboration of the policy options. In particular, it further develops certain problem drivers in section 2.4 of the impact assessment and describes in more details the policy options identified in section 5.2 of the impact assessment.

Detailed description of certain problem drivers

The following contextual elements further explain and illustrate the underlying causes to the problems identified in the impact assessment.

1.    Multiple stages and authorities involved in permitting procedures

In addition to the statutory permits and decisions, binding opinions or decisions of a number of authorities can be necessary before the permitting authority can issue a permit. For example, in the Czech Republic, the three main permits can only be granted once around 15 binding decisions of national, regional or local authorities have been issued. In Poland, the decision on the implementation of state roads investment and the decision on location of railways must be accompanied by the opinions of a least eight categories of authorities (Provincial and municipal governments; the Minister dealing with health issues; the voivodship responsible for restoration of monuments; the relevant maritime administration; the relevant regional directorate of State Forests; and the relevant manager of rail/road infrastructure).

The large number of permitting authorities involved is in part due to the wide scope of impacts considered in environmental assessments, which leads to the involvement of several sectoral authorities, either for granting permits or delivering an opinion or a decision. Competent Ministries or authorities for environment, water, nature protection, cultural heritage, agriculture and forest are typically requested for an opinion or a decision in the permitting procedure. The level of decentralisation of the procedure is another factor explaining the number of authorities involved in the procedure. As analysed in the exploratory study 45 , most permits or decisions are delivered by national/federal authorities, in some Member States, certain permits, mainly related to land-use, are delivered by regional authorities or governments (Austria, Germany, Hungary, Poland, Romania), sub-regional authorities (Hungary) and municipalities (Czech Republic, Romania). In a number of cases, this leads to repeating the permitting procedure, and where relevant, the public consultation involved, in all regional or local jurisdiction crossed by the project 46 .

A more decentralised procedure can also lead to additional administrative burden for project promoters, especially when the regional or local authorities handle procedural aspects differently. Interviewed stakeholders mentioned that where regional or local administrations have a permitting role, the interpretation of what documentation needs to be provided by the project promoter as part of an application can differ greatly from one authority to another, even if the information to be provided is spelled out in the EIA directive.

In the Progress Report of January 2018 to the CBS Report 47 , it was highlighted once again that delays in permitting often occur due to the involvement of multiple steps and multiple authorities and a simplified process of permitting procedures was recommended. According to this report, at least a mandatory joint procedure for all environmental assessment procedures at project level stemming from EU legislation should be introduced, by grouping and aligning several permitting steps time-wise without undermining the qualitative standards of the assessment of the individual criteria. Indeed, this is a particularly complex domain which is not helped by uncertainties related to certain provisions in some pieces of legislation (in particular the Water Framework Directive and the Birds and Habitats Directives).

In addition, the large number of authorities involved in some countries makes the process highly vulnerable to the administrative capacity of authorities to issue decisions within reasonable timeframes. The lack of administrative capacity has been identified in particular in sectoral authorities (for example, water, cultural heritage), and in regional/local authorities, in which permitting is generally dealt with along with their regular workload, without dedicated extra staff 48 .

2.    Specific implications of cross-border context for the permitting of TEN-T projects

a)Limited cooperation in transboundary EIA 

The EIA Directive sets out obligations regarding cross-border EIAs. The EIA Directive establishes that, when a Member States is aware that a project is likely to have significant effects on the environment in another Member State, or where a Member State likely to be significantly affected requests it, the Member States planning the project must provide affected Member States a description of the project, together with any available information on its possible transboundary impact and information on the nature of the decision which may be taken (Article 7(1)). The affected Member State(s) can then decide to participate in the EIA, and if so, make available the documentation to the authorities and the public likely to be concerned by the project. CJEU rulings have also stressed that EIAs must take into account cross-border impacts when part of the project is located in another Member State in view of not compromising the effectiveness of the EIA Directive (case C-205/08) 49 . Taking into consideration of cross-border impacts – which inevitably is the objective of the EIA Directive – adds on challenges for TEN-T projects which are confronted with different ways of administrative proceedings across the border.

During the permitting procedure of the Fehmarn Belt Fixed Linked project outlined above, the EIA procedure and the public consultation have not been coordinated between Denmark and Germany, with the result that delays in Germany are severely impacting the timeframe of the project, already approved in Denmark. Although Member States will often decide to carry out separate EIAs in line with their own EIA procedures, aligning timeframes for the EIA procedure, the public consultation and the decision-making process would facilitate the process leading to approval.

There are also a number of examples of inadequate assessment of transboundary impacts in the case studies. The failure to consider such impacts can fuel public opposition and provide project opponents with justified grounds for appeals against projects.

In the Romanian-Bulgarian common section of the Danube 50 , the EIA in the initial feasibility study was not properly addressed in a cross-border project context. The lack of attention to good coordination between the two countries in the preparation and execution of the EIA was one of the failures of that study.

The Commission has produced guidance on transboundary EIAs 51 ; However, the implementation of Article 7 of the EIA Directive and in particular requirements concerning public consultation has proved challenging in cross-border projects, first because it creates additional obligations such as translating and adapting consultation documents, and because Member States have to define responsibilities on both sides for the organisation of the public consultation. Amendments to Article 7 of the EIA Directive, adopted in 2014 and which had to be transposed by Member States by May 2017, are expected to facilitate EIAs for cross-border projects. Under these changes, Member States involved in projects likely to have transboundary effects are expected to consult with each other on these effects and measures to reduce or eliminate these effects, and agree on a reasonable timeframe for consultations. The amendment provides the Member States with the option of conducting cross-border consultations through a joint body.

Finally, the Progress Report of January 2018 to the CBS Report 52 reiterated that the existing conventions (such as the Espoo Convention) for cross-border projects are not used to the full extent. The 'Espoo Convention on EIA in a Transboundary Context' 53 allows for a coordinated, cross-border comprehensive EIA, streamlining different national procedures with a joint agreement and providing a single environmental report, it has been successfully used in the context of certain energy infrastructure projects.

b)Poor strategic planning and diverging objectives

Cross-border infrastructure projects require an early and strong strategic planning based on clear objectives and providing a sound basis for later decisions. The absence of this planning can weaken project planning documents and assessments as well as create obstacles and delays in implementation.

There is a particular need for early and transparent public participation, assessment of alternatives and a clear project definition prior to the project decision. The importance of the SEA and the opportunities offered by this instrument for early involvement are not always properly explored. Early assessment of transport plans and programmes may help avoiding problems at project level, later on in the project implementation.

Cross-border projects are often faced with different possibilities and diverging priority objectives, especially when multiple countries are involved, like in the case of Rail Baltica project 54 .

(1) http://www.consilium.europa.eu/uedocs/cms_data/docs/pressdata/en/trans/146017.pdf    Council of the European Union, Council conclusions on Transport infrastructure and the Trans European Network, Council Conclusions, Brussels, 3 December 2014
(2)    Ministerial Declaration, Implementing the Trans-European Network (TEN-T) TEN-T Days 2016, Rotterdam, June 2016 https://english.eu2016.nl/binaries/eu2016-en/documents/publications/2016/06/20/ministerial-declaration-on-implementing-ten-t/ministerial-declaration-ten-t-20-06-2016-rotterdam.pdf
(3)    Progress Report of the Action Plan Making the best use of new financial schemes for European transport infrastructure projects, January 2018, https://ec.europa.eu/transport/sites/transport/files/cbs2_report_final.pdf
(4)    [Insert link once published].
(5)    Study on permitting and facilitating the preparation of TEN-T core network projects, Milieu, December 2016, https://ec.europa.eu/transport/sites/transport/files/permitting_ten-t_final_report.pdf
(6)     https://ec.europa.eu/transport/themes/infrastructure/consultations/2017-ten-t-implementation_en  
(7)    Available at their respective subpages at: https://ec.europa.eu/transport/themes/infrastructure/downloads_en  
(8)    Available at their respective subpages at: https://ec.europa.eu/transport/themes/infrastructure/downloads_en
(9)    COM(2013) 940 final of 7 January 2014. Among others, this Communication aims at providing information on the potential budget and instruments available under the new policy framework and at explaining how the Commission intends to support the creation and the functioning of the core network corridor
(10)    Source: https://ec.europa.eu/info/law/better-regulation/initiatives/ares-2017-3272163_en  
(11)    See also Figure 1 in Annex 3
(12)    See Annex 2 Stakeholders consultations
(13)    Link to the IA support study once published.
(14)    Source: http://www.e3mlab.ntua.gr/e3mlab
(15)    Source: http://www.tmleuven.be/methode/tremove/home.htm  
(16)    Several model enhancements were made compared to the standard TREMOVE model, as for example: for the number of vintages (allowing representation of the choice of second-hand cars); for the technology categories which include vehicle types using electricity from the grid and fuel cells. The model also incorporates additional fuel types, such as biofuels (when they differ from standard fossil fuel technologies), LPG and LNG. In addition, representation of infrastructure for refuelling and recharging are among the model refinements, influencing fuel choices. A major model enhancement concerns the inclusion of heterogeneity in the distance of stylised trips; the model considers that the trip distances follow a distribution function with different distances and frequencies. The inclusion of heterogeneity was found to be of significant influence in the choice of vehicle-fuels especially for vehicles-fuels with range limitations.
(17)    The model can be run either as a stand-alone tool (e.g. for the 2011 White Paper on Transport and for the 2016 Strategy on low-emission mobility) or fully integrated in the rest of the PRIMES energy systems model (e.g. for the Low Carbon Economy and Energy 2050 Roadmaps, for the 2030 policy framework for climate and energy, for the Effort Sharing Regulation, for the review of the Energy Efficiency Directive and for the recast of the Renewables Energy Directive). When coupled with PRIMES, interaction with the energy sector is taken into account in an iterative way.
(18)    Source: http://ec.europa.eu/clima/policies/strategies/analysis/models/docs/primes_model_2013-2014_en.pdf .
(19)    Source: https://ec.europa.eu/energy/sites/ener/files/documents/sec_2011_1569_2.pdf  
(20)    Source: https://www.panteia.com/themes/transport-mobility/transport-models/
(21)    Source: https://ec.europa.eu/transport/themes/infrastructure/downloads_en
(22)    Source : https://ec.europa.eu/transport/themes/sustainable/internalisation_en
(23)    Source : https://ec.europa.eu/transport/sites/transport/files/2015-06-fraunhofer-cost-of-non-completion-of-the-ten-t.pdf
(24)    Source: https://ec.europa.eu/transport/sites/transport/files/2015-06-fraunhofer-cost-of-non-completion-of-the-ten-t.pdf  
(25)    In addition, amendments to two Directives only adopted in the beginning of 2015 were also considered. This concerns notably the ILUC amendment to the Renewables Directive and the Market Stability Reserve Decision amending the ETS Directive.
(26)    ICCS-E3MLab et al. (2016), EU Reference Scenario 2016: Energy, transport and GHG emissions - Trends to 2050
(27)    SWD(2016) 247
(28)    SWD(2016) 405
(29)    SWD(2016) 244
(30)    European Commission/DG ECFIN (2014), The 2015 Ageing Report: Underlying Assumptions and Projection Methodologies, European Economy 8/2014.
(31)    OPEC stands for Organization of Petroleum Exporting Countries.
(32)    Source: https://ec.europa.eu/clima/sites/clima/files/transport/vehicles/docs/technology_results_web.xlsx  
(33)    For a comprehensive discussion see the Reference scenario report: “EU Reference Scenario 2016: Energy, transport and GHG emissions - Trends to 2050” 
(34)    Awaiting signature of act (Source : http://www.europarl.europa.eu/oeil/popups/ficheprocedure.do?reference=2013/0157(COD)&l=en)  
(35)    Simulation at individual vehicle level is combined with fleet composition data, retrieved from the official European CO2 emissions monitoring database, and publicly available data regarding individual vehicle characteristics, in order to calculate vehicle CO2 emissions and fuel consumption over different conditions. Vehicle CO2 emissions are initially simulated over the present test protocol (NEDC) for the 2015 passenger car fleet; the accuracy of the method is validated against officially monitored CO2 values and experimental data.
(36)    Implementation of the Priority Projects, November 2012; DG MOVE based on data from Member States, https://ec.europa.eu/transport/sites/transport/files/themes/infrastructure/ten-t-policy/priority-projects/doc/pp_report_nov2012.pdf
(37)    Projections for international maritime and international extra-EU aviation are not included in the total passenger and freight transport activity to preserve comparability with statistics for the historical period.
(38)    Inland navigation covers inland waterways and national maritime.
(39)    Including international aviation but excluding international maritime and other transportation.
(40)    External costs are expressed in 2013 prices. They cover NOx, PM2.5 and SOx emissions.
(41)    Source: Regulation of the European Parliament and of the Council on guidelines for trans-European energy infrastructure and repealing Decision No 1364/2006/EC
(42)    Source: Eurostat, http://ec.europa.eu/eurostat/statistics-explained/index.php/Hourly_labour_costs
(43)    Source: Eurostat http://ec.europa.eu/eurostat/statistics-explained/index.php/Hourly_labour_costs
(44)    See specifically Table 3 in the Annex 1 of the Exploratory Study, Milieu (2016) Study on permitting and facilitating the preparation of TEN-T core network projects
(45)    For example, in Austria, procedures at State level for federal roads and rail projects will be repeated in all States affected by the project. In Czech Republic, Hungary and Romania, land-use decisions must be obtained in all counties or municipalities affected by the project.
(46)    Former European Commission Vice-President H. Christophersen, Professor K. Bodewig, European Coordinator, Professor C. Secchi, European Coordinator in the "Action Plan – Making the best use of new financial schemes for European transport infrastructure projects", June 2015
(47)    Milieu, Study on permitting and facilitating the preparation of TEN-T core network projects, December 2016
(48)    European Commission, Guidance on the Application of the Environmental Impact Assessment Procedure for Large-scale Transboundary Projects, 2013, p. 10.
(49)    Milieu (2016) Study on permitting and facilitating the preparation of TEN-T core network projects.
(50)    European Commission, Guidance on the Application of the Environmental Impact Assessment Procedure for Large-scale Transboundary Projects, 2013, http://ec.europa.eu/environment/eia/pdf/Transboundry%20EIA%20Guide.pdf  
(51)    Op. cit.
(52)     https://www.unece.org/fileadmin/DAM/env/eia/documents/legaltexts/Espoo_Convention_authentic_ENG.pdf
(53)    Milieu (2016) Study on permitting and facilitating the preparation of TEN-T core network projects