Commission notice: Guidance document on the requirements for hydropower in relation to EU nature legislation

1

2018/C 213/02

Commission notice: Energy transmission infrastructure and EU nature legislation

62


EN

 


IV Notices

NOTICES FROM EUROPEAN UNION INSTITUTIONS, BODIES, OFFICES AND AGENCIES

European Commission

18.6.2018   

EN

Official Journal of the European Union

C 213/1


Commission notice: ‘Guidance document on the requirements for hydropower in relation to EU nature legislation’

(2018/C 213/01)

This document reflects the view of the European Commission and is not of a binding nature.

European Commission, May 2018

Catalogue ref …

Reproduction is authorised provided the source is acknowledged.

This document has been prepared with the assistance of N2K GROUP EEIG — Ecosystems Ltd, Brussels and Beleco, Czech Republic.

TABLE OF CONTENTS

Purpose of the document 3

1.

Overview of EU Policy and Legislative framework 4

1.1.

The Birds and Habitats Directives 4

1.2.

The Water Framework Directive (WFD) 6

1.3.

Coordination between the WFD and the Nature Directives 6

1.4.

The Floods Directive 8

1.5.

The SEA and EIA Directives 9

1.6.

The relationship between SEA, EIA and Article 6 10

2.

Freshwater ecosystems and hydropower in the EU 10

2.1.

The status of the EU's river and lake ecosystems 10

2.2.

Pressures and threats of Europe's freshwater ecosystems 12

2.3.

The effects of hydropower on freshwater ecosystems 14

2.4.

Cumulative effects 19

2.5.

Distinguishing between significant and insignificant effects 21

3.

Good practice examples in mitigating effects and applying ecological restoration measures to hydropower 23

3.1.

Aiming for the best practicable ecological condition of rivers in the context of hydropower 23

3.2.

Dealing with existing hydropower having a negative effect on a Natura 2000 site 24

3.3.

Introducing ecological measures and restoration measures 25

3.4.

Good practice examples of ecological restoration 29

4.

Good practices in applying an integrated planning approach to hydropower 36

4.1.

The benefits of integrated planning 36

4.2.

Integrated national and regional plans 40

4.3.

Wildlife sensitivity and zoning 41

4.4.

Early consultation 44

5.

The assessment procedure under the Habitats Directive 46

5.1.

Introduction 46

5.2.

When is the Article 6 procedure required 46

5.3.

A step by step procedure for carrying out appropriate assessments 47

5.4.

Exceptions under Article 6.4 57
Abbreviations 61

PURPOSE OF THE DOCUMENT

This document offers guidance and presents a series of practical case studies on how hydropower can be made to operate in accordance with the requirements of the Habitats and Birds Directives. It examines the types of effects that might occur from hydropower activities and illustrates, through a series of practical experiences, how the effects of hydropower can be avoided or at least minimised under a range of different conditions.

More generally, it aims to act as a conduit for fostering synergies between EU policies and practices on energy, nature and water in order to achieve EU targets in a more coordinated, and wherever possible, mutually supportive manner.

Chapter 1 provides an overview of the EU policy and legislative framework in which hydropower is expected to operate in Europe. The key provisions of the Habitats and Birds Directives are briefly summarised as is their relationship with the Water Framework Directive and the EIA and SEA Directives.

Chapter 2 outlines the generally poor state of the EU's river and lake ecosystems, as well as their main pressures and threats, before going on to examine the range of effects hydropower can have on freshwater ecosystems, stressing the importance of potential cumulative effects in particular.

A significant number of Europe's wild fauna and flora species, including some 400 freshwater species protected under the Birds and Habitats Directives, depend on river and lake ecosystems for their survival. However, today most of Europe's rivers are in a highly degraded state and under immense pressure from a wide range of socio-economic activities (including hydropower).

From the latest State of Environment reports (1) it is clear that much still needs to be done to meet the objectives of the Water Framework Directive and the two Nature Directives. This can only be achieved if priority is given not just to preventing a further deterioration of our rivers but also to actively restoring their ecological status and removing, or at least significantly reducing, the pressures and threats they face.

Chapter 3 explores the ways in which this can be achieved, illustrating this with good practice examples of ecological restoration from across the EU.

Particular attention is given in Chapter 4 to the need for strategic planning and to designing more integrated hydropower plans and projects that take account of the river's ecological requirements early on in the planning process and wherever possible also include measures to improve the ecological status of the river.

The document goes on to describe in detail (Chapter 5) the procedure to follow when carrying out an appropriate assessment for a hydropower plan or project under Article 6 of the Habitats Directive. Clarification is provided on certain key aspects of this approval process and of its relation with other EU environmental assessment procedures. Experience has shown, time and again, that problems with the Article 6 approval process are very often caused by poor quality and incomplete appropriate assessments.

The guidance is designed primarily for use by competent authorities, developers and consultants. It will also be of interest to non-governmental organisations and other stakeholders who are working in the hydropower sector. The document has been written in consultation with Member state authorities as well as a range of key stakeholder and interest groups all of whom have provided valuable feedback on the various drafts.

The document is intended to be bound by, and faithful to, the text of the Birds and Habitats Directives and to the wider principles underpinning EU policy on the environment and hydropower. The good practice procedures and proposed methodologies are not prescriptive in their intent; rather they aim to offer useful advice, ideas and suggestions based on discussions with industry representatives, national and international authorities, NGOs, scientific experts and other stakeholders.

The document reflects only the views of the Commission and is not of a legally binding nature. It rests with the European Court of Justice to provide definitive interpretation of EU directives. Wherever relevant, existing European case law has been included. The present guide is therefore best read in conjunction with the existing general guidance and relevant European Court of Justice rulings on the two directives (2).

1.   EU POLICY AND LEGISLATIVE FRAMEWORK

Hydropower plays a key role in the implementation of the Renewable Energy Directive (3) and in contributing to the EU energy targets for 2020-2030. As with all other water-based activities, hydropower must conform to the requirements of EU environmental law, which has been introduced to protect and restore Europe's rivers and lakes. These legal requirements are laid down in the Water Framework Directive, the Floods Directive, the Birds and Habitats Directives, and the Environmental Assessments Directives (Environmental Impact Assessment - EIA and Strategic Environmental Assessment - SEA Directives).

This chapter outlines some of the key provisions of these EU laws that are relevant for hydropower. The focus is on the two Nature Directives in particular, as this is the main topic of the present document.

1.1.   The Birds and Habitats Directives

Europe's rivers are a major source of biodiversity and an important part of our rich natural heritage. They have, however, undergone major changes over the decades. This has reduced their resilience and capacity to provide for nature and wildlife. Most rivers are now in a degraded state and in need of restoration.

Recognising the alarming loss of biodiversity in Europe, the EU Heads of State and Government set themselves the ambitious target of halting, and reversing, this loss by 2020. In May 2011, the Commission adopted an EU biodiversity strategy to 2020 (4) setting out a policy framework for achieving this. In April 2017, it launched a new action plan (5) to rapidly improve the practical implementation of the Habitats and Birds Directives and accelerate progress towards the EU 2020 goal of halting and reversing the loss of biodiversity and ecosystem services.

The Birds and Habitats Directives are the cornerstones of the EU's nature and biodiversity policy. They enable all EU Member States to work together, within a common legislative framework, to conserve Europe's most endangered, vulnerable and valuable species and habitats across their entire natural range within the EU, irrespective of political or administrative boundaries.

The overall objective of the two Directives is to ensure that the species and habitat types they protect are maintained and restored to a favourable conservation status (6) throughout their natural range within the EU.

This target is defined in positive terms, oriented towards a favourable situation which needs to be reached and maintained. It therefore goes beyond the basic requirement of avoiding deterioration.

Definition of favourable conservation status (FCS) under the Habitats Directive

Article 1

The conservation status of a natural habitat means the sum of the influences acting on a natural habitat and its typical species that may affect its long-term natural distribution, structure and functions as well as the long-term survival of its typical species within the territory of the EU.

The conservation status of a natural habitat will be taken as ‘favourable’ when:

Its natural range and the areas it covers within that range are stable or increasing, and

the specific structure and functions which are necessary for its long-term maintenance exist and are likely to continue to exist for the foreseeable future, and

the conservation status of its typical species is favourable.

The conservation status of a species means the sum of the influences acting on the species concerned that may affect the long-term distribution and abundance of its populations within the territory of the EU.

The conservation status will be taken as ‘favourable’ when:

population dynamics data on the species concerned indicate that it is maintaining itself on a long-term basis as a viable component of its natural habitats, and

the natural range of the species is neither being reduced nor is likely to be reduced for the foreseeable future, and

there is, and will probably continue to be, a sufficiently large habitat to maintain its populations on a long-term basis.

To achieve this objective, the EU Nature Directives require Member States to implement two main types of measures in particular:

The designation and conservation of core sites for the protection of species and habitat types listed in Annex I and II of the Habitats Directive and Annex I of the Birds Directive, and for the protection of all regularly occurring migratory birds. These sites make up the EU-wide Natura 2000 Network which currently contains over 27 500 sites. Lake and river ecosystems cover around 4 % of the total surface area of Natura 2000 (European Environment Agency, 2010, for EU 27).

The establishment of a species protection regime for all wild European bird species and other species listed in Annex IV of the Habitats Directive. These measures apply across the species' entire natural range within the EU, i.e. both within and outside protected sites such as Natura 2000.

Natura 2000 site protection provisions

The protection and management of Natura 2000 sites is governed by the provisions of Article 6 of the Habitats Directive, which also determines the relationship between the site's conservation and other land-uses, such as hydropower, in and around the area (7).

Article 6 is divided into two types of measures:

The first concerns the conservation management of all Natura 2000 sites and the setting of conservation objectives for these sites. It requires Member States to:

(a)

elaborate and implement positive conservation measures which correspond to the ecological requirements of the habitat types in Annex I and the species in Annex II present on the sites (Article 6.1); and

(b)

take appropriate measures to avoid any deterioration of habitat types and habitats of species or any significant disturbance of the species present (Article 6.2).

The Habitats Directive recommends the development of Natura 2000 management plans as a means of identifying the necessary conservation measures for Natura 2000 sites in an open and transparent manner. They are useful tools for setting conservation objectives and helping to build a consensus view on the management solutions for the site amongst all stakeholders and interest groups. They also provide a mechanism for integrating conservation measures for Natura 2000 into the wider Water Framework Directive's programme of measures.

The second type of measure (governed by Article 6.3) concerns the assessment procedure for any plan or project that could affect one or more Natura 2000 site (see Chapter 5 for full details). In essence, the assessment procedure requires that any plan or project that is likely to have a significant effect on a Natura 2000 site undergoes an appropriate assessment (AA) to study these effects in detail, in view of the site's conservation objectives.

The competent authority can only agree to the plan or project if, based on the findings of the AA, it has ascertained that it will not have an adverse effect on the integrity of the site concerned. It is important to note that the onus is on demonstrating the absence (rather than the presence) of significant negative effects.

In exceptional circumstances, a derogation (Article 6.4) may be invoked to approve a plan or project having an adverse effect on the integrity of a Natura 2000 site if it can be demonstrated that there is an absence of less damaging alternatives and the plan or project is considered to be necessary for imperative reasons of overriding public interest. In such cases, adequate compensation measures will need to be secured to ensure that the overall coherence of the Natura 2000 network is protected.

It is important to note that the assessment procedure under the Habitats Directive is not the same as that foreseen under the EIA or SEA Directives (8) and Article 4.7 of the WFD even if they should ideally be integrated with one another or at least coordinated.

Species protection provisions

The second set of provisions of the Nature Directives concerns the protection of certain species across their entire natural range within the EU, i.e. regardless of whether they are inside or outside Natura 2000 sites. The species protection measures apply to species listed in Annex IV of the Habitats Directive and all wild bird species in the EU. The exact terms are laid down in Article 5 of the Birds Directive and Articles 12 (for animals) and 13 (for plants) of the Habitats Directive.

In essence Member States are required to prohibit, for these species:

their deliberate disturbance during breeding, rearing, hibernation and migration;

the deterioration or destruction of breeding sites or resting places;

the deliberate destruction of nests or eggs, or the uprooting or destruction of protected plants.

Derogations to the species protection provisions are only allowed in restricted cases — such as to prevent serious damage to crops or livestock or in the interests of public health and safety — provided that there is no other satisfactory solution and the consequences of these derogations are not incompatible with the overall aims of the Directives. The conditions for applying derogations are set out in Article 9 of the Birds Directive and Article 16 of the Habitats Directive (9).

The species protection provisions are highly relevant to hydropower facilities operating also outside Natura 2000 sites. They aim to ensure that any new developments do not destroy the breeding and resting sites of any wild bird or any species listed under Annex IV of the Habitats Directive unless they have sought from the competent authorities a derogation in accordance with the terms of the Directives. This provision can be especially important for hydropower situated on a river harbouring migratory species, such as migratory birds or fish (e.g. European sea sturgeon Acipenser sturio or the apron Zingel asper both listed in Annex IV of the Habitats Directive).

1.2.   The Water Framework Directive

The Water Framework Directive (WFD) establishes a framework for the protection and sustainable management of inland surface waters (rivers and lakes), transitional waters (estuaries), coastal waters and groundwater. It aims to ensure that all water bodies meet ‘good status’ as a rule by 2015 (except for heavily modified and artificial water bodies where the objective is to achieve a good ecological potential). Like the Nature Directives, the WFD goes beyond the basic requirement of preventing the further deterioration of water bodies and the terrestrial ecosystems and wetlands directly depending on the aquatic ecosystem.

To help achieve this objective, the WFD requires Member States to establish a river basin management plan for each river basin district. The Directive envisages a cyclical process where river basin management plans are prepared, implemented and reviewed every 6 years.

1.3.   Coordination between the WFD and the two Nature Directives

The Water Framework Directive and the two Nature Directives are closely interlinked as they both aim to protect and restore Europe's freshwater ecosystems. They should therefore be implemented in a coordinated way to ensure that they operate in an integrated manner. The following highlights some of the key points of interaction between the WFD and the two Nature Directives that are relevant for hydropower plants in particular, derived from the Commission's FAQ on links between the Water Framework Directive and the Nature Directives (10).

Distinct objectives of the WFD and Nature Directives

The WFD and the Nature Directives all operate, at least in part, on the same environment and have broadly similar ambitions of ensuring the non-deterioration of rivers and improving the status of aquatic ecosystems. However, while their overall objectives are similar, their specific aims are nevertheless distinct even if they are closely interlinked.

The WFD aims to protect and improve all surface waters and groundwater so that they reach good status or potential and to avoid deterioration. The Birds and Habitats Directives, on the other hand, aim to protect, maintain and restore particular species and habitat types in order to bring them up to a favourable conservation status across their natural range within the EU.

Achieving good ecological status under the WFD usually helps to achieve the conservation objectives of water-dependent habitats and species in Natura 2000, and vice versa. However, the requirement of ‘good ecological status’ refers to water bodies while favourable conservation status refers to specific habitat types and species.

Thus, reaching good ecological status is not necessarily sufficient for reaching favourable conservation status, even if all water bodies would reach good ecological status. There may therefore be a need to implement additional conservation measures in order to achieve the Natura 2000 site's conservation objectives for the species and habitat types for which it is designated.

This is explicitly recognised in the WFD. Article 4.2 of the WFD states that ‘where more than one of the objectives […] relates to a given body of water, the most stringent shall apply ’. For instance, if a Natura 2000 site is designated for otters or freshwater pearl mussels, it may also be necessary to regulate overfishing even if this is not necessary to achieve good ecological status under the WFD.

These additional requirements should ideally be included, or at least referred to, in the WFD river basin management plan via specific provisions regarding protected areas to ensure coherence (and avoid conflicts) between the WFD measures and the Natura 2000 measures (see Article 4.1.c).

Heavily modified water bodies or artificial water bodies and Natura 2000

According to Article 4.3 of the WFD, some water bodies that are significantly modified by human activities in their physical characteristics may be designated as heavily modified water bodies provided they fulfil all the provisions of Article 4.3 (11). Water bodies that have been created by human activity where there was no water body before (e.g. a man-made reservoir or an artificial navigation canal) can be designated as artificial water bodies.

For heavily modified water bodies and artificial water bodies the WFD objective of ‘good ecological potential’ applies (instead of good ecological status) if the requirements for less stringent objectives such as ‘moderate ecological potential’ are not applicable. In plain words this means the best practicable ecological condition that is compatible with the legitimate use which was the basis for its designation as a heavily modified water body or artificial water body (12).

A heavily modified water body or artificial water body may also be designated as a Natura 2000 site, if it harbours a species or habitat type listed in Annex I of the Birds Directive or in Annexes I or II of the Habitats Directive. In such cases, appropriate conservation measures will need to be implemented for that species or habitat as well, in accordance with the conservation objectives of the site. Again, these measures may be stricter than those required for achieving ‘good ecological potential’. They should also be integrated into the WFD river basin management plans by specific provisions on protected areas (see Article 4(1)c in conjunction with Article 4(2)).

Assessing new developments under the WFD

Like the Nature Directives, the WFD has specific provisions for assessing new developments on water bodies. According to Article 4.7 of the WFD, exemptions can be approved by the authorities for new modifications and sustainable human development activities that result in the deterioration of the status of the water body or that prevent the achievement of good ecological status or potential, or good groundwater status under certain conditions. This potentially includes new developments related to hydropower (13).

If the development potentially affects both a WFD objective and a Natura 2000 site then both the Article 4(7) procedure under the WFD and the Natura 2000 assessment procedure under Article 6.3 of the Habitats Directive must be undertaken (ideally in a coordinated or integrated manner). Each has a different legal focus: one will assess if the project is likely to compromise the primary objectives of the WFD, the other will assess whether it will adversely affect the integrity of a Natura 2000 site. However, this does not prevent certain aspects of the assessment being coordinated, e.g. through surveys and consultations.

The WFD makes it clear that a development cannot go ahead if it is not consistent with other EU environmental legislation. In other words, if the project does not compromise the objectives of the WFD but does adversely affect the integrity of a Natura 2000 site then it cannot be approved under the WFD unless an exemption under Article 6.4 of the Habitats Directive has also been accepted. Clarification on the application of WFD Article 4(7), on the exemptions to the environmental objectives, including the linkage to the Nature Directives, is provided in CIS Guidance Document No 36 on WFD Article 4.7 which was endorsed in 2017 (14).

Conserving the freshwater pearl mussel in Ireland's sub-river basins

The freshwater pearl mussel Margaritifera margaritifera is one of the longest-living invertebrates on earth. Owing to its complicated life history and its need for near natural, clean flowing waters, it is a key biological indicator species for the quality of river ecosystems. The species is protected under the EU Habitats Directive but is in an unfavourable conservation status throughout Ireland. Sedimentation or sedimentation with nutrient enrichment has been identified as the main causes of this.

In 2009, national legislation was developed to support the achievement of favourable conservation status for the freshwater pearl mussel. This legislation set obligatory environmental quality objectives for freshwater pearl mussel habitats within Natura 2000 sites. It also required that sub-basin management plans be prepared along with a programme of measures. The purpose of these plans was to address the catchment-wide issues that are contributing to the species decline. The format used mirrored that of the river basin management plans under the WFD so that the sub-basin management plans could operate under the umbrella of the river basin management plans later on.

In Ireland, the close linkages between the Habitats and Birds Directives, and the WFD were highlighted at an early stage. In 2009, the National Technical Coordination Group for the Water Framework Directive established a subcommittee — the National Conservation Working Group, — to work on the development of nature conservation aspects of the WFD. The Working Group's core objective was to ensure that this development of the nature conservation aspects of the Water Framework Directive were well coordinated and supported within Ireland and to facilitate effective communication between the relevant government agencies involved.

For the sub-basin plans for the freshwater pearl mussels, the Group played a key role in refining and further developing a national set (‘toolkit’) of standard catchment measures for freshwater pearl mussels that are practical, functional and cost effective. It also reviewed the plans to ensure their practicality and effectiveness, and identified policy and guidance gaps, which would hinder their implementation.

http://www.wfdireland.ie/docs/5_FreshwaterPearlMusselPlans/

http://kerrylife.ie

http://www.environ.ie/en/Environment/Water/WaterQuality/WaterFrameworkDirective/

1.4.   The Floods Directive

In November 2007, Directive 2007/60/EC was adopted. It establishes a framework for assessing and managing flood risks and requires Member States to draw up:

Flood hazard and flood risk maps, that map out the identified flood risk areas per river basin (or other agreed unit area of management). These maps should also show the potential adverse consequences associated with different flood scenarios, including information on potential sources of environmental pollution as a consequence of floods, as well as protected areas such as Natura 2000 sites in those areas (deadline December 2013).

Flood risk management plans for managing and reducing the potential adverse consequences of flooding. These plans should include a prioritised set of measures, addressing all aspects of flood risk management from prevention and protection to preparedness, taking into account the characteristics of the particular river basin or sub-basin (deadline December 2015).

Activities under the Floods Directive must be in line with the requirements of the Nature Directives. For instance, if a flood protection measure risks affecting one or more Natura 2000 sites, it too, must follow the procedure under Article 6 of the Habitats Directive, and an appropriate assessment should be carried out to assess the potential effects of the plan or project on the integrity of the Natura 2000 site(s).

1.5.   The SEA and EIA Directives

The SEA Directive

Directive 2001/42/EC on the assessment of the effects of certain plans and programmes on the environment (the ‘SEA Directive’) aims to provide for a high level of protection of the environment. It aims to do this by ensuring that the environmental consequences of certain plans and programmes are identified, assessed and taken into account during their preparation and before their adoption.

A strategic environmental assessment is mandatory for a variety of plans and programmes which set the framework for future consent of the development of projects listed in the EIA Directive. It is also mandatory for any plans or programmes, which, because of their likely significant effect on Natura 2000 sites, require an assessment pursuant to Article 6.3 of the Habitats Directive.

Under the SEA process, Member States are required to prepare an environmental report that assesses the likely significant environmental effects of the plans and programmes, and the effects of any reasonable alternatives. In addition, they must consult the authorities, which by reason of their specific environmental responsibilities, are likely to be concerned by the environmental effects of implementing plans and programmes (i.e. environmental authorities) and the public.

The consultation should be early and effective, allowing the environmental authorities and the public to express their opinion on the draft plan or programme, and on the accompanying environmental report before the plan or programme is adopted. The process of developing the SEA is intended to be coordinated with the plan's development leading to the inclusion of environmental considerations into the final version of this plan.

Ultimately, the SEA aims to encourage a more integrated and efficient approach to territorial planning where environment, including biodiversity considerations, are taken into account much earlier on in the planning process and at a much more strategic level. This should lead to fewer conflicts further down the line at the level of individual projects. It also allows for a more appropriate siting of future developments away from areas of potential conflict such as in Natura 2000 sites.

The EIA Directive

While the SEA process is for plans and programmes, EIA Directive 2011/92/EU, as amended by Directive 2014/52/EU (commonly referred to as the ‘EIA Directive’), is for individual public and private projects. Thus, the consent to develop a project (15) which is likely to have significant effects on the environment should be granted only after the project's likely environmental effects have been assessed.

The EIA Directive distinguishes between projects requiring a mandatory EIA (‘Annex I projects’ (16)) and those where Member State authorities must determine if projects are likely to have significant effects (‘Annex II projects’). This is done through a ‘screening’ procedure that takes into account criteria in Annex III of the Directive. Most installations for hydroelectric energy production are Annex II projects (17).

1.6.   The relationship between SEA, EIA and Article 6.3 of the Habitats Directive

According to the EIA Directive (as amended by Directive 2014/52/EU), a coordinated and/or joint procedure should be undertaken if an assessment of a project is required under both the EIA Directive and the Nature Directives. The Commission issued guidance on setting up any coordinated and/or joint procedures for projects (18) that simultaneously have to be assessed under the EIA, Habitats, Birds, Water Framework, and Industrial Emissions Directives.

Under the coordinated procedure, Member States must coordinate the various individual assessments of the environmental impact of a particular project, required by the relevant Union legislation, by designating an authority for this purpose. Under the joint procedure, Member States have to provide for a single assessment of the environmental impact of a particular project required by the relevant Union legislation.

The appropriate assessment under EU nature legislation should nevertheless remain a clearly distinguishable and identifiable part of the overall environmental report. This is because the Habitats Directive's appropriate assessment measures different aspects of the natural environment and has different criteria for determining ‘significance’ than the EIAs/SEAs. The EIA/SEAs consider all aspects of the environment, including biodiversity, whereas the Nature Directives' assessment focuses specifically on possible effects on the species and habitat types for which the Natura 2000 site has been designated.

There is also a distinction for the outcome of each assessment. The assessments under the SEA and EIA lay down procedural requirements but do not establish obligatory environmental standards. The outcome of assessment under the Habitats Directive, on the other hand, is immediately binding for the competent authority and conditions its final decision.

In other words, if the appropriate assessment cannot ascertain that the plan or project will not adversely affect the integrity of a Natura 2000 site, the authority cannot agree to the plan or project as it stands unless, in exceptional cases, they meet the conditions of the derogation procedure under Article 6.4.

If an assessment has to be made under the Habitats Directive, the Court of Justice of the European Union clarified that the SEA Directive would apply on its own merits for plans and programmes (19).

Guidance Document ‘Streamlining environmental assessment procedures for energy infrastructure “projects of common interest”’ (PCIs)

Like all other development projects, hydropower is subject to a number of environment assessment procedures. The Commission has issued guidance on how to streamline these various procedures, in particular for projects of community interest (PCIs) under the Ten-E Regulation, while ensuring the maximum level of environmental protection in accordance with EU environmental law.

The Commission guidance makes a series of recommendations, which, although designed with PCIs in mind, are also relevant for all energy plans or projects, including hydropower developments. The recommendations focus in particular on:

Early planning, ‘road mapping’ and scoping of assessments;

Early and effective integration of environmental assessments and of other environmental requirements;

Procedural coordination and time limits;

Data collection, data sharing and quality control;

Cross-border cooperation, and

Early and effective public participation.

http://ec.europa.eu/environment/eia/pdf/PCI_guidance.pdf

2.   FRESHWATER ECOSYSTEMS AND HYDROPOWER IN THE EU

2.1.   Status of the EU's river and lake ecosystems

The structural complexity and highly dynamic nature of rivers and lakes make them exceptionally rich ecosystems, bringing lifeblood, or in this case water, to large parts of the surrounding countryside. As well as being valuable habitats in their own right, they act as vital ecological corridors, encouraging the dispersal and migration of species over long distances. They are also responsible for the development of a rich mosaic of interconnected, water dependent wetlands such as floodplain forests, marshes, fens, wet meadows, all of which further enhance their overall biodiversity.

A significant number of Europe's wild fauna and flora species, including some 400 freshwater species protected under the Birds and Habitats Directives, depend on river and lake ecosystems for their survival. Altogether, lakes and rivers cover around 4 % of the land surface of Natura 2000 (some 31 560 km2 — an area larger than Belgium) having been designated for species such as the Atlantic salmon Salmo salar, otter Lutra lutra, kingfisher Alcedo atthis, white-clawed crayfish Austropotamobius pallipes, thick-shelled river mussel (Unio crassus) as well as habitat types such as water courses of plain to montane levels, alluvial forests, wet meadows, humid grasslands and fens.

In addition, rivers are also a vital multi-functional resource for Europe's economy and social well-being, servicing a large number of different sectors and delivering many important goods and services to society. However their intensive use has put immense pressure on this valuable resource over the last 150 years, with the result that few of the major rivers are now in an entirely natural state. In addition to being subjected to varying degrees of pollution and high nutrient loads, which has led to a significant degradation in water quality, many rivers have also undergone major changes to their hydro-morphology, natural flow dynamics and ecological connectivity.

In 2015, the European Environment Agency's report on the State of Europe's environment (20) concluded that more than half of the rivers and lakes in Europe had not reached a good ecological status or potential. In 2009, only 43 % of surface water bodies were in a good or high ecological status. The situation was not expected to improve much by 2015 with only 53 % of water bodies expected to reach a good ecological status. This is far removed from the targets set by the WFD.

In terms of EU protected freshwater species and habitats, the situation is even more severe. According to the Commission's latest State of Nature report on the conservation status of habitats and species protected under the two Nature Directives for 2007-2012 (21), almost three quarters of freshwater species (74 %) and freshwater habitat types (73 %) had an unfavourable-inadequate or unfavourable-bad status. By contrast, only 17 % and 16 % respectively had a favourable status.

Image

Conservation status

Conservation status

(a) Species (5615 assessments)

(b) Habitats (94 assessments)

Favourable

Unknown

Unfavourable-inadequate

Unfavourable-bad

Conservation status and trends of species (a) and habitats (b) (Habitats Directive) associated with rivers and lakes ecosystem. Source EEA, 2015b, Article 17 reports and assessments.

The overall poor status of Europe's rivers is a significant cause for concern. It is clear that many of Europe's rivers are in a highly degraded state and that much still needs to be done to meet the objectives of the WFD and the two Nature Directives. This can only be achieved if the priority is not just to prevent their further deterioration but also to actively improve their ecological condition.

2.2.   Pressures and threats of Europe's freshwater ecosystems

Water bodies are under pressure from a wide variety of activities. Hydro-morphological pressures in particular have had a major effect and affect more than 40 % of river and transitional water bodies. Based on the first characterisation of river basins in relation to the WFD (22), most EU Member States indicated that pressures from urban development, flood defence, power generation including hydropower, inland water navigation, straightening and land drainage for agriculture are the strongest and affect the hydro-morphological status of water bodies to the highest degree.

Image

Rivers pressures

Rivers impacts

No pressures (22)

No impacts (19)

Point sources (22)

Organic enrichment (16)

Diffuse sources (22)

Nutrient enrichment (19)

Contamination (18)

Water abstraction (19)

Acidification (10)

Hydromorphology (22)

Altered habitats (16)

Other pressures (19)

Other impacts (14)

Percentage of water bodies

Percentage of water bodies

Significant pressures (left) and impacts (right) for rivers; the number of Member States included is indicated in parentheses (European waters — assessment of status and pressures 2012)

As regards the threats and pressures on Natura 2000 freshwater bodies, the State of Nature report identifies ‘changes in water bodies conditions’ as the most frequent by far, as compared to other threats and pressures.

Image

Figure 4.37 Top 10 (% of frequency) reported high-ranked pressures and threats for species (Habitats Directive) associated with rivers and lakes ecosystem

J02 Changes in water bodies conditions

J03 Other changes to ecosystems

H01 Pollution to surface waters

I01 Invasive alien species

A02 Modification of cultivation practices

K03 Interspecific faunal relations

F02 Fishing and harvesting aquatic resources

A07 Use of 'pesticides' in agriculture

D01 Roads, railroads and paths

K02 Vegetation succession/Biocenotic evolution

Pressures

Threats

State of Nature report, EEA 2015

Hydropower in the EU

Around 23 000 hydropower installations were recorded in the EU in 2011. The vast majority (91 %) are small (less than 10 MWH) and generate around 13 % of the total electricity production from hydropower. Large hydropower plants, on the other hand, represent only 9 % of all hydropower facilities but generate about 87 % of the total electricity production from hydropower (23).

Hydropower facilities are often concentrated in mountainous areas for technical reasons but have major far reaching effects on both large and small rivers and lakes across all kinds of different regions. In smaller rivers, even a small flow depletion or disruption to natural ecological conditions can have major negative implications for the river.

The following hydropower facilities are most frequently used:

 

Run-of-river hydropower plants . In the run-of-river hydropower systems, electricity production is driven by the existing flow and drop in elevation of a river. This type of installation uses the natural flow of a watercourse in order to generate electricity. There is no intention to store water and to use it later on. This type is most common for small hydropower stations but can also be found with large stations.

 

Storage run-of-the-river hydropower schemes : A storage reservoir offers the opportunity to store water during periods of low demand and release it during peak periods. The generating capacity is therefore less dependent on availability of the water flow. Such reservoirs can comprise daily, seasonal or yearly storage, thus allowing it to meet peak electricity demands and facilitating the integration of variable renewable energy productions e.g. from wind energy into the energy system.

 

Reservoir hydropower plants . The conventional reservoir plant has a reservoir of a big enough size to permit the storage of water during both wet and dry seasons. Water is stored behind the dam and is available to the plant as and when required. Such a plant can be used efficiently throughout the year, either as a base load plant or as a peak load plant as required.

 

Pumped-storage hydropower plants . These are based on reservoirs at different elevations, which make it possible to generate supplementary electricity during high peak demands. The water is pumped to the higher reservoir at the time of a lower demand and released down through turbines when the demand is high. Pumped-storage hydroelectric power stations are not excluded from the Renewable Energy Directive but they are not taken into consideration for renewable energies statistics.

2.3.   The effects of hydropower on freshwater ecosystems

The range of effects a hydropower facility can have on species and habitat types protected under the two EU Nature Directives will vary considerably from one site to another. It will depend on the individual characteristics of the river, its physical and ecological state — whether already degraded or still pristine, large or small, mountainous or lowland etc. — as well as on the type and scale of hydropower facilities and the species and habitats for which the site has been designated. There is therefore a need to look at each facility on a case-by-case basis.

The effects can occur at any stage of the life cycle of a hydropower installation, from its initial construction to its renovation, decommissioning or their day-to-day operation and management. They can result in the loss, degradation and fragmentation of natural habitats and populations of species that depend on these habitats for their existence. The significance of loss depends on the scale of the effects as well as on the rarity and vulnerability of the habitats and species affected.

The remainder of this chapter outlines the range of effects that hydropower can have on habitats and species under the EU Nature Directives in particular. Operators who are aware of the types of effects and who have an understanding of the complexities of the riverine ecosystems will be better placed to ensure that their activities are compatible with the requirements of the WFD and Nature Directives. They will also be better placed to identify potential win-win situations to help restore already degraded rivers wherever possible.

Changes in river morphology and riverine habitats

Any physical modification to water bodies will affect the normal hydrological processes and disrupt the ecological continuity (24) of freshwater systems both longitudinally and laterally, e.g. by disconnecting rivers from their surrounding floodplains and wetlands, or by creating a ponding effect around power plants.

The most obvious form of habitat loss is the direct physical destruction of the habitats themselves upstream or downstream or in the surrounding area (e.g. land take, inundation, removal of riparian vegetation or physical structures in the river). But even without physical land take, the disruption of natural hydromorphological processes can also disrupt or alter the biotic and abiotic conditions that are vital for the habitat's structure and functioning. Additionally, it can lead to the colonisation of degraded habitats by invasive species that could end up displacing the natural fauna.

Barriers to migration and dispersal of protected species

Rivers, lakes and riparian zones play an important role in the dispersal and migration of freshwater species and in more localised movements between different feeding, breeding, resting and nesting areas. They act as vital ecological corridors or stepping stones across the landscape. Any barriers or impediments to their free movement up or down stream, however small, can have important consequences for the survival of these species.

Image

Image

Image

Range of impacts caused by different hydropower facilities

Source: Veronika Koller-Kreimel

Hydropower installations can either directly or indirectly disrupt or prevent species dispersal and migration. The most obvious are dams and impounded areas which present physical barriers to fish migration, preventing the fish from travelling up and down the river. This has major effects on the survival of a wide range of freshwater species, resulting in the fragmentation, isolation and ultimate disappearance of some freshwater fish populations in particular.

The barrier effect is especially severe when there is more than one obstacle on a river stretch. Even with very small structures or physical barriers, rivers can rapidly become un-passable. Artificial canals can also act as barriers to species movement because they cut through and consequently fragment terrestrial habitats. They may also create artificial connections between catchments which can enhance the spread of non-native species, to the detriment of native species.

Although up- and downstream migration is important for all fish species, continuity is essential for diadromous species in particular. Upstream migration is most important for populations of anadromous fish and lamprey species like Salmo salar, sea lampreys Petromyzon marinus and Lampetra fluviatilis or some sturgeons as Acipenser sturio because of their need for periodical (optimally annual) long-distance migrations. Downstream migrations are essential for their juveniles and for adults of catadromous fish such as the eel Anguilla anguilla, which is protected under the Eel Regulation (25).

Disruption of sediment dynamics

Sediments are a natural part of aquatic ecosystems and are essential for the hydrological, geomorphological and ecological functioning of these systems. Sediment forms a variety of habitats which directly and indirectly support a broad range of species. Under natural conditions, there is a permanent downstream transport of sediments (mainly gravel) which maintains the ecological structure and function of the rivers. Transverse structures such as weirs or dams tend to disrupt the natural sediment dynamics.

Large reservoirs can trap over 90 % of incoming sediment which can lead to increased erosion of the river bed and banks downstream as well as the local destruction of important hydromorphological structures such as gravel bars. Maintenance works on weirs and dams involving the periodic flushing of sediments (especially in summer when there is water scarcity) can also be detrimental for habitats and species if not managed properly.

Upstream of a dam, in a reservoir or in impounded sections, the reduction of the sediment transport capacity causes sediment to accumulate which can have a negative effect on both species and habitats, e.g. by promoting the growth of algae and other aquatic weeds that crowd out the protected species. The accumulation of gravel or other silty sediments on the riverbed or in the water column may be especially detrimental to lithophile species, such as grayling Thymallus thymallus, which use these areas as spawning grounds for the freshwater pearl mussel Margaritifera margaritifera and the thick shelled river mussel Unio crassus. It is also detrimental for bird species, such as the plover or sandpiper that use dry gravel beds as nesting places.

Removing barriers on the Danube River Basin District

Hydropower generation accounts for around 45 % of river and habitat continuity interruptions in the Danube River Basin District. A total of 1 688 barriers are located in the District's rivers with catchment areas of more than 4 000 km. 600 of these barriers are dams/weirs, 729 are ramps/sills and 359 are classified as other types of interruptions. 756 are currently indicated to be equipped with functional fish migration aids. 932 continuity interruptions (55 %) have been a hindrance to fish migration since 2009 and are currently classified as significant pressures. According to the latest Danube Basin River Management Plan, the Danube countries plan to significantly reduce the continuity interruption by dams by 2021.

Image

Danube River Basin District: River and habitat continuity interruption – (above) current situation 2015; (1st map) expected improvements by 2021 (2nd map).

Source: DRBMP.

https://www.icpdr.org/main/management-plans-danube-river-basin-published

Changes of the ecological flow regime

Ecological flows are a vital mechanism for maintaining essential processes of healthy river ecosystems upon which EU protected species and habitats depend and to ensure a good ecological status of the water bodies (26). A change in ecological flow can reduce or degrade the extent of the aquatic habitat as well as its connectivity with riparian habitats.

Too little water flow for instance can have a wide range of negative effects including the drying out of spawning sites for fish and lamprey species or preventing the development of fish eggs and juveniles. Fish migration upstream can also be hampered in the depleted reach, either because of blockages from the low flows or because of insufficient stimuli encouraging fish to migrate.

Inadequate flow rates in the original riverbed can also cause the water to overheat and contain insufficient oxygenation (as described above). This creates unsuitable living conditions for a whole range of species such as fish, crayfish and lamprey species, bivalve molluscs, or dragonflies dependent on flowing water habitats.

Changes of the flow regime by peaking hydropower plants

Strong oscillations in water flow can cause major damage to both species and their habitats, especially in small rivers. Hydropeaking stresses organisms living in affected parts of the watercourse, especially those unable to handle sudden changes in water levels, like juvenile fish, or other slow moving or static organisms (especially plant species). The hydropeaking regime influences also the behaviour of the prey of protected species and consequently affects their fitness levels.

Image

The effect of hydropeaking is especially acute during sensitive periods (e.g. periods of drought or frost) and is increasingly relevant in view of climate change. Another adverse consequence of peaking hydropower plants is often a significantly different (much lower) temperature of water discharged during the peaking period. Species that are adapted to regular water temperatures cannot survive sudden changes lasting for several hours a day.

Changes in seasonal flood cycles

Measures are sometimes used to modify streambeds in order to be able to control better the flow of water. Interventions in flow control can result in the disruption of the seasonal flood cycles, causing sometimes the complete disappearance of the target habitat types and species connected to these cycles. Examples of affected habitats include alluvial forests, temporary ponds and oxbow lakes and rivers as well as their associated species.

RIPEAK — EU RESEARCH PROJECT: Responses of RiParian forests to hydroPeaking: towards a sustainable hydropower management

Hydropeaking refers to short-term changes in river flow occurring within the span of a day caused either by turning on or off hydro-turbines to generate electricity according to variations in the market demand. As a result, downstream and upstream river hydrology, hydraulic parameters, water quality, river morphology, and ultimately the fluvial ecosystem, are modified. Scientific studies on the effects of hydropeaking are scarce and most of them have focused on fish fauna. Moreover, there are no studies on riparian vegetation.

Hydropeaking might result in a failure of riparian species recruitment and hence affects the maintenance of riparian populations. Thus, by analysing seed germination and seedling performance, it might be possible to define hydropeaking — vegetation responses relationships that make it possible to quantify, correlate and predict biological responses to hydropeaking. Such relationships are crucial to objectively define thresholds which help to minimise ecological effects of hydropower generation without causing significant production losses.

This project aims to shed some light on the sustainable management of rivers subjected to hydropower production. For this goal, an in-depth literature review, analysis of sub-daily flow series, field experiments and computer modelling are planned. The final contributions from the project expected are: (1) new hydrological and ecological (i.e. riparian vegetation) metrics of hydropeaking impact, (2) new hydrology-ecology models to quantify such effects and (3) new effective measures for a sustainable operation of hydropower dams.

http://www.emg.umu.se/english/research/research-projects/responses-of-riparian-forests-to-hydropeaking/

Water chemical and temperature changes

Dams can fundamentally change the chemical quality, mineral composition and the pH of the river both up and downstream, for instance by accumulating contaminants in sediments. All these changes influence the composition of plant and animal communities present. Organisms are also influenced by changes of water temperature and connected alterations of oxygen concentration. Reservoirs can lead to an important increase of temperature but also to a reduction in temperature if the water is taken from the bottom.

Injuries and killing of individual animals

Fish and other species passing through a hydropower plant can be injured or killed. A hydropower plant can cause (27):

injuries through physical contact with guide vanes, turbine runner or turbine casing

damage from pressure fluctuations during the turbine passage

wedging onto intake screens or injuries caused by cleaning machines

injuries caused by intense flow and constructions of overflow in spillways

susceptibility to predation due to the disorientation.

The degree of mortality can vary from 0 to 100 % at a single hydro power plant (28). Much depends on the type of fish present and on the type of hydropower construction and the mitigation measures used. The mortality rate of turbines increases with the velocity and number of rotor blades and with decreasing distance between the blades (Kaplan). Mortality can reach 100 % when fish pass through turbines that are mainly in high-pressure plants (e.g. with a Pelton turbine).

Displacement and disturbance

River engineering works may cause disturbance to certain species and disrupt their life cycles both inside and outside Natura 2000 sites, especially in the case of benthic fauna and flora which rely on a good water quality. This may affect the species ability to breed, feed, rest or disperse and migrate.

If the disturbance reaches significant levels it can lead to the exclusion of the species from that area and hence the loss of habitat use or it can result in poorer survival and/or breeding success. In the case of rare and endangered species even small or temporary disturbances can have serious repercussions for their long-term survival in the region. Such situations would be incompatible with the species protection provisions of the two Nature Directives.

Effects on terrestrial species and habitats

Hydropower may have effects not just on freshwater species and habitats but also on terrestrial species and habitats. Again this can occur at any time e.g. during the construction, decommissioning or renovation of hydropower. It can also be caused by associated infrastructures such as access roads, pipe routes, or powerlines designed to connect the hydropower facility to the electricity grid.

In addition to the loss, degradation or fragmentation of the habitats involved, these structures could cause the death or significant disturbance of terrestrial species. Birds for instance might collide with and be electrocuted by overhead electricity wires or their breeding sites could be severely disturbed by regular traffic on the access roads. Such effects may be especially significant when the hydropower plant and associated infrastructures are located along migration routes or along narrow valleys with cliffs used by raptors, or next to important bird wetlands.

2.4.   Cumulative effects

As the EEA's State of the Environment report illustrated, most European rivers are now in a degraded state and the majority have reached a saturation point where they can no longer host any new developments or activities without causing a further significant deterioration of the river's status. Special consideration must therefore be given to assessing the potential cumulative effects of any new activities, including those for hydropower plants, on rivers in general and on Natura 2000 site(s) in particular.

The assessment of cumulative effects is especially important on near natural rivers, particularly small rivers, that are vulnerable to any changes in their hydromorphology. Even one or two small installations may bring about unacceptably high effects that are in conflict with the legal requirements of the WFD and the two Nature Directives.

The assessment of cumulative effects should consider all of the hydropower plants and other developments in the catchment area, irrespective of whether they are situated in or outside the Natura 2000 sites. It may be that one hydropower project, taken on its own, will not have a significant effect, but if its effect is added to those of other already existing activities or approved projects their combined effects can become significant.

Cumulative effects will often only occur over time. It is therefore important to consider all plans or projects during the assessment. This includes any plans and projects which have been approved in the past but which have not yet been implemented or completed, as well as any existing pressures and threats. In this context, information available in the WFD river basin management plans and Natura 2000 management plans may be useful for this.

Also, it is important to note that an already approved plan or project does not create a presumption in favour of any other plans or projects that may be proposed in the future. For example, if a hydropower development does not give rise to a significant effect and is therefore approved, the approval does not create a presumption in favour of further hydropower developments in the future. On the contrary, the approval of this project may mean that the river will have reached its carrying capacity and will not be able to tolerate any further developments, however small.

In addition, the assessment of cumulative and in combination effects is not restricted to the assessment of similar types of plans or projects in the same sector. Any other types of plans or projects that could, in combination with the plan or project under investigation, have a significant effect, should be taken into account during the assessment. Potential cumulative effects should be assessed using sound baseline data and not rely on qualitative criteria only. They should be assessed as an integral part of the overall assessment and not be treated as an ‘afterthought’ at the end of the assessment process.

Lastly, a cumulative assessment must also consider already existing installations on the river (the so called ‘pre-load’) (29). For instance, if a new project is planned with a new turbine, its effect must be assessed in light of the existing hydropower plant even if this was built decades ago. If the cumulative effects are significant, the new project will be refused.

Recommendations on small hydropower plants, Federal Environment Agency, Germany

In Germany, around 80 % of the usable hydropower potential has already been exploited. The technological potential was also largely exhausted. This was reflected in the relatively low rates of support available for hydropower use in support programmes. The remaining exploitable potential therefore mainly concerns small, previously undeveloped, virtually undisturbed waters. Yet the possible harmful ecological effects on the few remaining small undisturbed watercourses in Germany are likely to be considerable.

Macro-economic cost-benefit analysis has also shown that the economic costs can be considerable, compared with the benefit. The smaller the installation's capacity and the more natural the watercourse, the less favourable the cost-benefit analysis is. Economic evaluations show that, especially with small hydroelectric power plants with a capacity of up to 100 kW, in all three cases of new construction, modernisation and reactivation, the cost of producing energy is higher than the rates of payment under the Renewable Energy Act. Therefore in many cases, even in favourable circumstances, electricity can hardly be produced economically.

Economic considerations show that a subsidy that covers the operating costs of small hydroelectric power plants — in particular plants with a capacity of under 100 kW — leads to high macro-economic costs for the avoidance of CO2 emissions. Against the background of negative ecological effects, further exploitation of the potential of small hydroelectric power plants is not a priority for climate protection.

Considering prevailing legal provisions and the requirements of the EC Water Framework Directive, the following recommendations have been put forward:

On account of their higher efficiency, large hydroelectric power plants are generally to be given preference to small and micro-installations for secondary use on waters already developed and impounded. When developing hydropower capacity attention should be focused on their optimisation.

With virtually undisturbed waters, or those where re-naturalisation is planned, the use of hydropower should be renounced.

The construction and reactivation of small hydroelectric power plants is unproblematic at existing weirs that cannot be demolished, in particular when, at the same time, ecological improvements — for instance, restoring free passage — can be achieved.

With the reactivation of installations currently not in operation, and the renewal of water rights, concerns of water protection should be more strongly considered and conditions laid down (for example, functional fish ladders, structurally-guaranteed dynamic minimum water flow, exclusion of flash floods downstream dams).

In the case of new installations, impounding of a water body for diversion is to be avoided. Constructional methods should be chosen, which divert the water used in such a way that the free passage and character of the watercourse is maintained (e.g. lateral water intake with a diversion structure in the water body). Requirements are to be issued on minimum flow and on measures for the avoidance of damage to fish from turbines. Flash floods downstream of dams are to be prohibited.

Abstract from: Hydroelectric Power Plants as a Source of Renewable Energy - legal and ecological aspects – Umweltbundesamt, November 2003 http://www.umweltbundesamt.de/sites/default/files/medien/publikation/long/2544.pdf

2.5.   Distinguishing between significant and insignificant effects

Identifying the range of effects on the species and habitats that are likely to be affected by a hydropower development plan or project is the first step of any impact assessment. After that, it is necessary to determine whether the effect is significant or not in view of the Natura 2000 site's conservation objectives. Clearly, the assessment of significance needs to be done on a case-by-case basis, in function of the site-relevant species and habitats and of the precise characteristics of the project itself and on the basis of sound scientific expertise (see Chapter 5).

The loss of a few individuals may be insignificant for some species but may have serious consequences for others. Population size, distribution, range, reproductive strategy and life-span will all influence the significance of the effects, and this will vary from one Natura 2000 site to another, even if they are designated for the same species. The interconnectivity of effects should also be taken into account. For instance, land take on its own may not be significant for a particular species, but when combined with major disruptions to natural river flows, the impact may become significant.

The assessment of significance should be considered over an appropriate geographical scale. For migratory species that move over very long distances (such as Atlantic salmon Salmo salar), the effect at a specific site may have consequences for the species over a larger geographical area (river basin). Likewise, for resident species with large territories or changing habitat uses, it may be necessary to consider potential effects on a regional, rather than a local scale.

The conservation objectives of the Natura 2000 sites are also essential for helping to determine if there is a likely significant effect. This is confirmed by the European Court of Justice Waddenzee ruling (30) paragraph 49, ‘… where a plan or project not directly connected with or necessary to the management of a site is likely to undermine the site's conservation objectives, it must be considered likely to have a significant effect on that site. The assessment of that risk must be made in the light inter alia of the characteristics and specific environmental conditions of the site concerned by such a plan or project.’

The appropriate assessment must be based on the best available data. This may require dedicated field surveys or monitoring programmes some time in advance of the project. The investors have to be able to anticipate this in their planning and ensure the relevant data from biological and hydrological surveillance includes information on all important aspects (life cycle and seasonal variability). Such studies can sometimes take several years before they are able to capture sufficiently the life cycle of the species and habitat types concerned (see Chapter 5 for details).

Guidance on setting thresholds of significance in Germany

In Germany, as elsewhere, because of a high level of subjectivity, it was difficult to assess the significance of effects on Natura 2000 target features, which is the core of the appropriate assessment. As a result, the competent authorities often did not have the reasonable scientific certainty they needed to back their decisions on whether or not to authorise a plan or project. It also left them open to legal challenges. To address this problem and ensure a more uniform and consistent approach when assessing the impact significance in practice, the German Federal Agency for Nature Protection (BfN) commissioned a research project to provide scientifically tested rules and conventions for all habitat types and species listed in the Birds and Habitats Directives that occur in Germany (31). The resulting guidance document was published in 2007.

The starting premise for the guide is that any permanent loss of habitat types and habitats for species in a Natura 2000 site should be considered a significant impact. However, a certain level of loss could nevertheless be treated as insignificant for some habitat types and species under certain conditions. The guide provides scientifically agreed thresholds and criteria for determining significance, which are based on qualitative as well as functional aspects — not just quantitative criteria.

Thus, for an impact to be considered insignificant all the following conditions must be met:

Specific features of the given habitat/ habitat for species or key habitats of the typical species must remain unaltered,

Orientation values of ‘quantitative — absolute area loss’ are not exceeded,

Supplementary values of ‘quantitative — relative area loss’ of 1 % are not exceeded,

Cumulative effects with other projects do not exceed the above threshold values, and

Cumulative effects with other factors do not occur.

For the 2nd indent, 7 size classes for habitats and 8 for species were developed, providing ranges in which the threshold values for every habitat type/species lie; 3 threshold degrees for each class were set. In practice this means that for 21 of the 91 habitat types occurring in Germany, no loss is acceptable, while for the remaining habitats some loss may be considered insignificant if it is scaled according to size classes and degrees. As for the 53 species from Annex II, no tentative threshold values exist for 16 of them, nor for 20 of the 98 Birds Directive species. In other words, no impact is likely to be acceptable. All these conclusions/ figures/ thresholds are intended to act as guidance only. This means that a case-by-case approach within each AA is still required.

Since its publication, the guidance document has been successfully tested in the German courts and is now applied across the country.

http://www.bfn.de/0306_ffhvp.html

Scales used by experts licensed for AA in the Czech Republic

A practical issue is the scale used for evaluation of the significance of effects during the AA. There is no prescription, but based on long practical experience, the following scale has been recommended to be used by AA experts licensed by law in the Czech Republic (32): Impact significance is to be assessed against each target feature of the given site. If the impact on even a single target feature is marked with ‘-2’ it automatically means the site integrity is adversely affected and such a project must not be granted a permit within the Article 6.3 procedure.

Value

Term

Description

Examples

-2

Significant adverse impact

Significant adverse impact.

Excludes plan/project implementation

Significant disturbance or destructive impact on habitat or species population or its substantial part; significant disturbance of ecological demands of the habitat or species; significant impact on the habitat or natural development of a species. Under certain conditions, the impact can be lowered by mitigation measures.

Disruption of migration routes to spawning places of anadromous species

Destruction of habitat by inundation because of new dam.

Hydrological changes because of derivation significantly influencing population.

-1

Moderately adverse impact

Limited/moderate/non-significant adverse impact. Plan/project implementation is not excluded.

Moderate troublesome impact to habitat or species population; moderate disruption of ecological demands of habitat or species; marginal impact on habitat or natural development of a species.

Its elimination through mitigation measures is possible but application of mitigation measures cannot be enforced, unless national legislation requires differently.

Modernisation — using technology less damaging to fish, building fish passes on existing barriers.

Impact on margin parts of population.

Influence on habitat common in surrounding area.

0

Zero impact

The plan/project has no demonstrable impact.

Outside area of occurrence.

+1

Moderately positive impact

Moderate favourable impact on habitat or species population; moderate improvement of ecological demands of the habitat or a species; moderate favourable impact on the habitat or on the natural development of a species.

Reconstruction of peaking hydropower to run-of-river hydropower without weir or dam.

+2

Significantly positive impact

Significant favourable impact on habitat or species population; significant improvement of ecological demands of habitat or a species, significant favourable impact on the habitat or natural development of a species.

Demolition of hydropower plant.

3.   GOOD PRACTICE EXAMPLES IN MITIGATING EFFECTS AND APPLYING ECOLOGICAL RESTORATION MEASURES TO HYDROPOWER

3.1.   Aiming for the best practicable ecological condition of rivers in the context of hydropower

As stated in the previous chapter, few of Europe's large rivers remain in a relatively natural state, having been physically altered over the years for a wide variety of reasons, including for hydropower generation. The modernisation of existing hydropower plants should therefore be prioritised over the construction of new ones, to improve their ecological footprint.

A range of measures can be taken to mitigate hydropower plants' negative effects on river ecosystems and surrounding habitats and species, and to help improve their conservation status. This is a major part of achieving the objectives of the WFD and the two Nature Directives.

Opportunities should also be sought to decommission inefficient or obsolete installations and remove them entirely from the river system. It should be noted that the default action to be taken under the WFD if a body of water has been degraded by an existing installation is to restore the river to good ecological status. Significant physical modifications can only be made if they also serve a legitimate purpose that cannot be achieved by other better environmental options (see WFD Article 4.3 for more details on the requirements for HMWB/AWB designation and respective guidance).

The possibilities for technically upgrading hydropower installations and introducing ecological restoration measures must be evaluated on a case-by-case basis taking account of their cumulative effects. The type of ecological measures that can be implemented will depend very much on local circumstances, such as the condition of the river, other ongoing pressures along the river and the facilities already in place, as well as the type of species and habitats present.

3.2   Dealing with existing hydropower plants having a negative effect on a Natura 2000 site

Existing hydropower facilities located in or near, or having negative effects on, Natura 2000 sites must at all times conform to the provisions of Article 6.2 of the Habitats Directive. More specifically, Article 6.2 imposes an obligation to ensure that the site does not deteriorate as compared to the state it was in when it was first designated under Natura 2000. This means that Member States should take all appropriate action that they may be reasonably expected to take to ensure that there is no deterioration of habitats and/or significant disturbance of species.

This means that Member States are legally obliged to:

investigate the threats and pressures brought about by the presence of hydropower facilities on the species and habitat types for which the site was designated, and

take the necessary remedial measures if these existing pressures are causing a decline or degradation of the targeted species and habitats present.

The European Court of Justice confirmed this requirement in the Owenduff Case (C-117/00) (33), where it ruled that Article 6.2 was infringed because measures had not been adopted to prevent the deterioration of habitats of the species for which an SPA was designated. Several CJEU Cases (34) have further clarified the type of legal protection regime that needs to be put in place for the purposes of Articles 4.1 and 4.2 of the Birds Directive and Article 6.2 of the Habitats Directive. They stress in particular the need for the legal regime to be specific, coherent and complete, capable of ensuring the sustainable management and the effective protection of the sites concerned (C-293/07).

The Court also identified infringements in cases where the regime in place was ‘too general and did not concern specifically the SPA or the species that live in it’ (C-166/04), measures taken were ‘too partial, isolated measures, only some of which promote conservation of the bird populations concerned, and so did not constitute a coherent whole’ (C-418/04), or SPAs were submitted to ‘heterogeneous legal regimes which did not confer on the SPAs a sufficient protection’ (C-293/07). It also considered that purely administrative or voluntary measures were not sufficient for the purposes of Article 6.2 (C-96/98).

It should be noted that, for Natura 2000 sites, Article 6.1 of the Habitats Directive also requires Member States to put in place conservation measures that correspond to the ecological requirements of the habitat types in Annex I and the species in Annex II present on the sites. This means that hydropower installations must also comply with any more ambitious conservation objectives going beyond non-deterioration set under Article 6.2. They should also be integrated into the programme of measures within the RBMP.

Although not obligatory, the Habitats Directive encourages nature authorities to develop Natura 2000 management plans in close cooperation with local stakeholders and land owners concerned to identify the threats and pressures on each Natura 2000 site and to jointly determine the necessary conservation measures that need to be implemented.

Hydropower operators' good communication with authorities and/or bodies in charge of management planning is essential and can lead to the inclusion of measures which can benefit both the conservation objectives and the hydropower operation.

3.3.   Introducing ecological mitigation and restoration measures

A wide range of measures can be introduced for both existing and new hydropower plants to reduce their ecological effects (35). These can either mitigate potential effects before they happen or restore damage that has already been done. Such measures can for instance involve:

the restoration of river continuity and fish migration, for example by removing old or obsolete structures or building fish passes;

reducing fish mortality for example by installing screens at inlets and specially adapted turbines;

the restoration of an adequate variable ecological flow (including mitigation of low flows, dynamic flows, fish flows and rapidly changing flows) and sediment dynamics that improves the structure and functioning of freshwater habitats.

A wide range of measures can also be introduced to actively restore, reconnect or recreate valuable natural riverine habitats and habitats for rare and endangered species in order to make a net positive contribution to improving a river's ecological condition in line with the objectives of the WFD and the Nature Directives. The type of measure chosen will very much depend on the ecological condition of the body of water in question, the type of hydropower facility present, other pressures and threats, and the overall cost and potential for improving the hydropower facility's efficiency and generating capacity.

Once the measures have been implemented, monitoring systems should be put in place to ensure that they have the desired effect and, where this is not the case, remedial measures should be taken to address any failings.

Distinguishing between mitigation, compensation and ecological restoration

Mitigation measures are directly linked to the likely effects and form part of the project, or are introduced by the authority as a condition for authorising a plan or project. Based on the precautionary principle, they are designed to remove likely negative effects, pre-empt them or reduce them to a level where they will no longer adversely affect the integrity of the site. At the date of the decision authorising the project's implementation, the mitigation measures under the project must ensure that there is no reasonable scientific doubt as to the absence of adverse effects on the integrity of the site in question (36).

Compensatory measures are intended to compensate for any damage that may be caused by the project. They can only be considered under Article 6.4 if the plan or project has been accepted as being necessary for imperative reasons of overriding public interest and where no alternatives exist (see Section 5).

Ecological restoration measures are not necessarily linked to an environmental impact assessment and are designed to make a net positive contribution to improving the ecological condition of an already degraded river in line with the objectives of the WFD and the Nature Directives.

Table

Overview of the most widespread measures to mitigate water storage

Hydromorphological alterations

Main ecological impact

Mitigation of …

Mitigation measure options

River continuity for upstream fish migration reduced or interrupted

Fish: populations of migratory and other riverine fish absent or abundance reduced

Upstream continuity for fish

Ramp

Fish pass

By-pass channel

River continuity for downstream fish migration reduced or interrupted

Fish: Populations of migratory and other riverine fish absent or abundance reduced

Downstream continuity for fish

Less damaging turbines for fish

Fish screens

By-pass channel

Fish pass

Artificially extreme low flows or extended low flows

Reduced abundance of plant & animal species.

Alterations to composition of plant & animal species

Low flow

Provide additional flow

River morphology changes

Loss of or reduction in flows so that they are not sufficient to trigger and sustain fish migrations

Migratory fish absent or abundance reduced

Fish flow

Provide fish flow

Loss, reduction or absence of variable flows sufficient for flushing

Alteration/reduced abundance of fish and invertebrate species

Variable flow

Passive flow variability

Active flow variability

Rapidly changing flows (including hydro peaking)

Reduction in abundance of animal and plant species due to stranding and wash out

Rapidly changing flows

Balancing reservoir(s) (internal)

Relocate tailrace

Reduce rate

Modify river morphology

Balancing reservoirs (external)

Alteration of general physico-chemical conditions both up- and downstream (e.g. temperature, super saturation etc.)

Altered composition or growth of macro invertebrate communities and fish or fish mortality

Physico-chemical alteration

Flexible intake

Multiple intakes

Management of reservoir level

River continuity for sediment disrupted or reduced leading to changes in substrate composition

Reduction in fish and invertebrate abundance and alterations in species composition

Sediment alterations

Mechanical break-up of bed armouring

Removal of sediment

Re-introduce sediment (intake structures)

Re-introduce sediment (reservoirs)

Restore lateral erosion processes

Introduce mobilising flows

Artificially extreme changes in lake level, reductions in quality and extent of shallow water and shore zone habitat

Reduction in abundance of plant and animal species.

Alterations to species composition.

Lake level alteration

Reduce abstraction

Increase inflows

Create embayment(s)

Manage shore/shallow habitats

Connectivity to tributaries

Artificial floating islands

Dewatered shore line and reduced river flow — ponded river

Alterations to plant and animal species composition (e.g. favouring disturbance-intolerant species/still water species)

Ponded rivers (impoundments)

Bypass channel

Reduce storage level

In-channel habitat improvements

Lateral reconnection

Source: Adapted from Table 3 in ECOSTAT working group report on a common understanding of using mitigation measures for reaching good ecological potential for heavily modified water bodies, part 2: Impacted by water storage (37)

In hydropower facilities, particular attention is often paid to the potential range of techniques that can be used to restore or facilitate the upstream and downstream movement of fish and other aquatic fauna within river systems. This is an evolving science in which a wide variety of techniques and innovative solutions are regularly trialled out and re-evaluated. It is not however a cure-all.

There are too many examples of fish migration aides that have been put in place as a supposed mitigation measure but which have turned out to be either ineffectual or even detrimental to the fish populations they are supposed to help. This may be because the devices were ill conceived and not fit for purpose, or that they did not take account of the cumulative effects of other already existing obstacles along the river stretch. It may also be because the conditions for device maintenance or management were not respected or that there was no monitoring system to check whether or not the device was actually doing the job it was designed to do.

This is why it is important to ensure not only that the fish pass or adapted turbine is built according to state-of-the-art developments in this sector and current best practices, but also that a sound monitoring system is in place to provide feedback on its effectiveness. In general, monitoring should show that the device makes it possible for all riverine species to enter the pass and that the vast majority (e.g. 85 %) can also exit alive.

In the case of a fish pass, where possible, nature-like passes should be preferred, because the general rule is that the more nature-like a pass is, the better it works. The choice of the most suitable type of fish pass (e.g. vertical slot, bypass, rock-ramp, lift) strongly depends on local conditions (height of barrier, character of the stream, usability of neighbouring sites, etc.) and requires careful study on a case-by-case basis.

Likewise, the impact of turbines on fish is usually significant but can sometimes be reduced by making certain adaptations to the turbine geometry and their mode of operation. However, such adapted turbines have so far not proven to be a guarantee that no fish will be killed or that the turbine is not still a barrier for migration. Once again, effectiveness must be assessed and monitored on a case-by-case basis.

The planning of fish passes or adapted turbines should also be dependent on evaluation of the cumulative effect of the barriers in the wider river system. Building one fish pass along a river riddled with barriers may prove to be both expensive and inefficient. It is therefore important to look more strategically at all the barriers on the river stretch in question in order to decide on the best course of remedial action.

Finally, it is essential to have a regular maintenance plan for all new constructions. Many fish passes or turbines will no longer be effective over the medium- to long-term if they are not maintained regularly enough.

When is a fish ladder deemed an adequate mitigation measure?

Findings of the ECJ Ruling 142/16 on the Moorburg coal-fired powerplant

The Moorburg coal-fired power plant is situated within the port of Hamburg, on the south bank of the southern section of the Elbe river. This is a migratory route for certain fish species listed in Annex II to the Habitats Directive and as such plays an important role in a number of Natura 2000 areas situated upstream of the Geesthacht weir (Germany) whose conservation objectives cover these species. These areas are situated up to a distance of approximately 600 km from the plant. The Geesthacht weir is situated on the Elbe corridor, in between the Moorburg power plant and the Natura 2000 areas.

Before authorisation for construction of the Moorburg plant was granted on 30 September 2008, an environmental impact assessment was conducted under German water legislation. This assessment concluded that the authorisation was compatible with the conservation objectives of the Natura 2000 areas because the operator had agreed to install a second fish ladder approximately 30 km from the plant, by the Geesthacht weir. There was therefore an intention to compensate for fish killed during the operation of the cooling mechanism, which draws large quantities of water from the river in order to cool the Moorburg plant (‘the fish ladder’). In addition, the impact assessment prescribed multi-phase monitoring in order to verify the effectiveness of the fish pass. The Commission considered that the authority concerned had wrongly classified the fish ladder as a mitigating measure.

Findings of the Court:

In order to ensure that the construction of the Moorburg plant would not adversely affect the integrity of the Natura 2000 areas concerned, it was the responsibility of the German authorities to take account of the protective measures included in that construction project. In that regard, it is settled case-law that the application of the precautionary principle in the context of the implementation of Article 6(3) of the Habitats Directive requires the competent national authority to take into account, inter alia, the protective measures forming part of that project aimed at avoiding or reducing any direct adverse effects on the site, in order to ensure that it does not adversely affect the integrity of the protected site (… C-521/12,..C-387/15 and C-388/15 …).

In the present case, it is clear from the file submitted to the Court that … the fish ladder was intended to increase migratory fish stocks by allowing those species to reach their breeding areas, along the middle and upper reaches of the Elbe, more quickly. Increasing stocks in this manner was expected to compensate for the fish deaths near the Moorburg plant so that the conservation objectives of the Natura 2000 areas upstream of the plant would not be significantly affected.

However, it is clear that the impact assessment itself did not contain definitive data regarding the effectiveness of the fish ladder, and merely stated that its effectiveness could only be confirmed following several years of monitoring .

It must therefore be held that, at the time the authorisation was granted, the fish ladder, even though it was intended to reduce direct significant effects on the Natura 2000 areas situated upstream of the Moorburg plant, could not guarantee beyond all reasonable doubt , together with the other measures referred to in paragraph 35 of the present judgment, that that plant would not adversely affect the integrity of the site, within the meaning of Article 6(3) of the Habitats Directive.

As regards the estimates on which the impact assessment was based, it should be pointed out that the data relating to the years 2011 to 2014 was collected by the Federal Republic of Germany after the granting of the authorisation of 30 September 2008.

In that regard, it should be noted that it is at the date of adoption of the decision authorising implementation of the project that there must be no reasonable scientific doubt remaining as to the absence of adverse effects on the integrity of the site in question (judgment of 26 October 2006, Commission v Portugal, C-239/04, EU:C:2006:665, paragraph 24 and the case-law cited).’

The Commission also stated that the city of Hamburg granted the authorisation without taking into account, in the impact assessment for the Moorburg plant, the potential cumulative effects with those stemming from the Geesthacht pumped-storage power plant, which dates back to 1958 and does not have any specific fish protection mechanisms. According to the Commission, it is irrelevant that the Geesthacht pumped-storage power plant was constructed before the transposition period of the Habitats Directive expired, for the provisions of Article 6(3) of that directive are not limited to plans and projects approved or completed after this deadline.

Findings of the Court

Under Article 6(3) of the Habitats Directive, when assessing cumulative effects national authorities are required to take into account all projects which, in combination with the project for which an authorisation is sought, are likely to have a significant effect on a protected site in the light of the objectives pursued by that directive, even where those projects precede the date of transposition of that directive.

Projects which, like the Geesthacht pumped-storage power plant, are likely to cause, as a result of their combination with the project to which the impact assessment relates, deterioration or disturbance likely to affect the migratory fish present in the river and consequently result in the deterioration of the site concerned in the light of the objectives pursued by the Habitats Directive, are not to be excluded from the impact assessment required under Article 6(3) of the Habitats Directive.

http://curia.europa.eu/juris/liste.jsf?num=C-142/16

ICPDR technical paper: Measures for ensuring fish migration at transversal structures

This document aims to inform the Danubian countries about existing technical solutions for restoring river continuity for fish migration. All guidelines currently available in the upper Danube catchment were considered. Their comparison showed that their overall structure and content is basically consistent and that deviations are only marginal in most cases. Since most guiding documents are only available in the German language, this document aims to provide the most important facts in English.

https://www.icpdr.org/main/practical-advice-building-fish-migration-aids

3.4.   Good practice examples of mitigation and/or ecological restoration

The following good practice examples illustrate how various types of mitigation and/or ecological restoration measures have been introduced to hydropower installations under a range of different circumstances.

The management of freshwater Natura 2000 sites in England, with particular reference to hydropower and river Special Areas of Conservation (SAC)

Natural England is the statutory agency responsible for providing advice on protected sites in England, including Natura 2000 sites. Natural England's approach to decision-making on protected freshwater sites is habitat-led but species-aware. Objectives are based on natural ecosystem function, with freshwater species conserved as characteristic components of the naturally functioning ecosystem wherever possible.

A holistic view of protected freshwater habitat features is taken - river habitat (for instance, Habitats Directive Annex II feature H3260: watercourses with Ranunculion and Callitricho-Batrachion vegetation) comprises the whole river corridor, encompassing all of the small-scale biotopes within it. The key components of natural habitat function (flow regime, natural morphology and sediment regime, water chemistry and an absence of direct biological stresses such as non-native species) are an intrinsic part of the objectives agreed for the habitat feature. Target levels of naturalness for these components are set out in the UK guidance for protected sites. Effects on these components of natural function are addressed through a range of protection and restoration measures.

The approach has much in common with the principles of ecological status objectives in the Water Framework Directive, but differs in terms of the level of precaution applied to decision making, the level of ambition for protecting natural function and addressing historical damage, and the level of consideration of effects on natural ecosystem functioning. The approach is also in tune with climate change adaptation principles for freshwater ecosystems, which require a focus on the restoration of natural function.

The English surface water network (including freshwater SACs) contains many thousands of in-channel structures, considerably affecting natural river and lake ecosystem function. Some are large structures with major ecological effects, whilst others are small and numerous, creating considerable cumulative effects. Many are associated with existing abstraction licences, which may or may not be used. Some were built for hydropower whilst many could be retrofitted.

Restoration plans have been drawn up to remove physical modifications to river SACs wherever possible, in order to restore natural habitat function. This is an ambitious and long-term programme, initiated ten years ago (Wheeldon et al. 2015). There are also programmes to alleviate abstraction stress and pollution, and tackle non-native species.

A joint regulators' statement on hydropower has been drawn up with the water regulator in England (the Environment Agency) to set out decision-making processes relating to protected sites. This recognises the need for environmental precaution, proper consideration of cumulative effects, and decisions to be taken in the light of the specific conservation objectives of the site and associated restoration plans.

Where a Natura 2000 river restoration plan considers an in-channel structure to be immovable, or where it will take a long time period to remove it, then there may be scope for hydropower generation (permanent or temporary). However, the structure should be modified to minimise its impact on natural habitat function, and target values for the natural flow regime should be met (including limits on the cumulative extent of depleted reaches caused by abstraction). Given the objectives of protected freshwater sites in England, and the precaution and ambition associated with restoring natural habitat function, the freshwater Natura 2000 network is not a natural focus for hydropower development. Whilst there may be local circumstances where hydropower would be compatible with Natura 2000 objectives, greater opportunities exist outside of the protected site series in the wider surface water network.

If hydropower developments are particularly important on the Natura 2000 network but conflict with conservation objectives, then a case for overriding public interest can be made. However, alternative solutions involving other forms of renewable energy with less nature conservation impact are likely to be more cost-effective.

http://publications.naturalengland.org.uk/publication/5478339747774464?category=5605910663659520

Release of controlled floods from hydropower plants in the Ebro River (Spain)

In Spain, controlled floods were legally established in 2008. Since that time, a number of flooding events have been carried out in Mediterranean rivers. For example, controlled flood rates have been calculated and released in the Lower Ebro River (Northeast Spain) since 2002, from the dam complex that regulates the river (Mequinenza-Ribarroja-Flix Dams).

The main goal of these floods has been to control macrophyte populations and improve sedimentary activity in the channel (Tena et al., 2013). The dam complex was constructed between 1948 and 1969 and has a total storage capacity of ca. 1 700 hm3. The reservoir system was created with several goals in mind: hydropower generation, water supply (including supply to a downstream nuclear power plant), and flood control.

Flood releases from the dams were managed by the hydroelectric operator (Endesa Generación S.A.) and controlled by the Ebro Basin authority. In 2002, an understanding was reached between the hydropower operator, the water authorities, and the scientific community to promote the release of floods. Since then controlled floods have been performed on a regular basis, twice a year (in autumn and spring). The discharged floods have normally required the delivery of about 36 hm3 over 16 hours, with peak flows of 900 to 1 300 m3/s (each).

The design and downstream effects of these floods have been monitored and discussed in several studies (Batalla et al., 2006; Batalla & Vericat, 2009; Tena et al., 2013). The cost of the release has also been calculated and analysed, showing that the provision of artificial floods had a cost equivalent to a small fraction of the energy delivered to the market and overall annual revenue (0.17 % for the two annual controlled floods) (Gómez et al., 2014).

References

Gómez, C.M., Pérez-Blanco, C.D., & Batalla, R.J. 2014. Tradeoffs in river restoration: Flushing flows vs hydropower generation in the Lower Ebro River, Spain. Journal of Hydrology 518: 130-139.

The national framework strategy for migratory fish in France

France's rivers host eleven species of diadromous fish that migrate long distances between the sea and freshwater to complete their complex lifecycles. Many, such as European sturgeon, the Atlantic salmon, the Allis shad and the river lamprey, are protected under the EU Habitats Directive. However, despite the efforts undertaken to conserve these species, they all remain in an unfavourable condition in France and elsewhere in the EU.

Recognising the scale of the problems facing these species in France, the Ministry for Ecology and Sustainable Development launched a national strategy for the conservation of migratory fish species in 2010. Designed as an evolving framework strategy, it sets a number of overall targets and objectives that can be adjusted over time in function of the species' ability to recover.

Because of the many different administrations and stakeholders involved in or potentially affected by the conservation, use and restoration of these migratory fish, a major effort was made right from the start to involve everyone concerned in the strategy's development so that they endorsed the overall approach taken and were ready to contribute to its implementation. The Ministry of Sustainable Development formally adopted the strategy in 2010; it was endorsed by all those involved.

Several river basin management plans in France (known as Schémas directeurs d'amenagement et de gestion des eaux, SDAGE) propose a significant number of measures to improve the situation of migratory species present, as defined in the national strategy.

A national plan for the restoration of river continuity, adopted in 2010, also plays an important role in implementing the national strategy for migratory species. It is built around five pillars:

Create a national inventory of the 60 000 obstacles that have significant repercussions for the functioning of the aquatic ecosystem.

Define priority areas for intervention at the level of each of the river basins (in line with the Plan Grenelle for green and blue infrastructure).

Revise the programmes of Water Agencies to make the necessary funding available for restoration works in priority areas.

Mobilise the services of the water police within the framework of a multiannual programme of controls on those obstacles that are most disruptive for fish migration.

Evaluate the environmental benefits of the restoration measures and ensure close monitoring of their effects.

Referenciel des obstables a L'ecoulement: une cartographe nationale des obstacles sur les cours d'eau: http://www.eaufrance.fr/referentiel-des-obstacles-a-l

Restoring river connectivity in Austria

Austria's river basin management plan states that the lack of longitudinal and lateral continuity is one of the principal pressures on the country's rivers. It recognises that a good ecological status under the WFD is only achievable if the migration of aquatic species and the transportation of sediment is made possible both from the river's head to the mouth and from the river to its wetlands. River connectivity is also vital for the recovery of species and habitats protected under the two Nature Directives.

The restoration of the longitudinal continuum is therefore seen as one of the primary goals of the management plan. The priority areas for the removal of migratory barriers were identified in 2009, and a number of river restoration projects have since been implemented. Several have been co-financed under the EU LIFE programme. This has ensured that the restoration measures introduced are improving not only the river's connectivity for the benefits of the WFD and migratory fish, but also the overall conservation condition of the various Natura 2000 sites along the river.

In 2011, these efforts were taken to a new level with the launch of a major LIFE+ project designed to implement an extensive network of measures on the Austrian part of the Danube. Called ‘LIFE+ Network Danube’, it is the largest project of its kind in Austria so far, with a total budget of € 25 million. The project is run by VERBUND, Austria's leading electricity company, with the support of the Federal Ministry of Environment and the Fishing Associations. It aims to build on the work done under previous LIFE projects along the Danube, which together have already succeeded in making 20 km of the rivers Melk, Pielach and Ybbs passable for migrating fish species.

The project will implement a wide range of different actions along the upper part of the Danube in order to improve its overall ecological status and the conservation status of some 17 fish species listed in the Habitats Directive. Ecological stepping stones will also be created between four major Natura 2000 sites along the river, which should also improve their overall conservation status.

More specifically, ‘Network Danube’ will restore uninterrupted, natural fish migration paths (at least 22 km) at five of the largest run-of-river power plants along the Austrian Danube using a multitude of ecological measures. It will also recreate important gravel habitats (gravel banks, gravel islands) in the reservoirs of these five power plants and restore 500 m of river branches along the Danube. Flood protection will also be included in this process.

The individual projects are currently being discussed regionally and will be submitted to the responsible authorities for approval before being rolled out. One of them, the Ottensheim-Wilhering bypass channel, will be Austria's longest fish ladder to date. The 14.2-km bypass route is being created through the Innbach-Aschach cost around 8 million euros.

VERBUND's ultimate goal is to make the part of the Danube that flows through Austria (some 352 km) completely passable for fish by 2027.

http://www.life-netzwerk-donau.at/de/

Hydromorphological restoration priorities in Austria

Hydromorphological pressures, such as water abstraction, impoundments and discharges, are affecting significant parts of Austria's water bodies. This is largely the reason for why two-thirds of rivers do not have a good ecological status under the WFD (BMLFUW 2014). Austria's latest draft river basin management plan, published in 2015, prioritises the improvement of the hydromorphology of its rivers. It emphasises the need for largescale environmental revitalisation programmes to improve river structure and aid the recovery of endangered rheophilic fish species. Restoring dynamic floodplains and their drift zones will not only help improve the rivers' ecological status under the WFD but should also improve the conservation condition of the Natura 2000 sites, species and habitats present.

Image

Considered a priority area, the upper Mur river has been the focus of several major restoration projects, often co-financed under EU LIFE (38). Thanks to these projects, new river structures were created and meanders were re-connected to the Mur. Artificial bank reinforcement structures were also partially removed over a total length of 4.7 km. This opened up over 90 km of the river for the free passage of fish.

Work on a further seven new sections of the river is continuing under a second LIFE project. However, there is still the challenge of how to reconcile the needs of the WFD, Natura 2000 and the Floods Directive on the one hand, and the requirement to produce renewable energy on the other, over the entire length (330 km) of the river in Austria. To address this, the authorities, in consultation with stakeholders, have developed a new plan that includes a carefully drawn-up zoning scheme with ecological priority zones, trade-off zones and zones with no particular restrictions or interest (mainly in the middle- to lower stretches of the river). This plan, which is valid until 2022, sets the foundations for complying with the mandatory energy targets, while maintaining/improving the river's ecological status in accordance with EU environmental laws.

The Kembs project: environmental integration of a large existing hydropower scheme, France

The Kembs dam diverts water to the Grand Canal d'Alsace, which is equipped with four hydropower plants. The Old Rhine river, downstream of the dam, is 50 km long and has been strongly affected by dykes since the 19th century. As the Kembs scheme concerns three countries with varying views on how to deal with the environment, Electricity de France decided to take an integrated approach to achieving environmental improvements instead of striving for a strict ‘impact/mitigation’ balance.

This has resulted in:

A significant increase in ecological flow: under a variable regime, the released flow varies daily depending on the natural flow entering the reservoir. A new plant (8.5 MW, 28 GWh) was built to limit the energetic losses and to ensure the daily modulation of flow in the Old Rhine.

Strong geomorphological movements in the Old Rhine, with the supply of gravel from the new plant and the implementation of the original concept of controlled erosion.

Actions to ensure fish migration (longitudinal and lateral) and the recovery of wetlands.

Examples of environmental measures include:

Connection between the Grand Canal d'Alsace and the wetland of the ‘Petite Camargue Alsacienne’. This protected area includes a network of ponds and small waterways that are reconnected to the Grand Canal d'Alsace as well as two new fish passes.

Controlled erosion: This innovative concept uses floods' natural erosion capacity to resupply the Old Rhine river with aggregates, after the dykes are dismantled. The recovery of a non-fixed gravel bed will (in conjunction with the variable flow rate) enable fish spawning and the growth of pioneer vegetation. A small-scale model was used to determine the minimum excavations needed to activate the erosion.

Retrieval of an ancient Rhine river arm and its connected environment: This large restoration project started in 2013. It involves the conversion of a 100ha cornfield and the renaturalisation of an 8 km old river arm. This re-natured area is now included in the Petite Camargue Alsacienne protected area, which is a partner in the project.

This integrated project has improved the environmental quality of the hydropower complex despite the energetic losses due to the increased ecological flow (partially recovered by the new plant).

http://alsace.edf.com/wp-content/uploads/2015/06/20150610-Renaturation-Kembs-EDF-PCA.pdf

Reactivation of sediment transport across a series of 11 hydropower stations along the transboundary High Rhine

In total, 73 km of the Rhine River from Lake Constance to Basel is impounded, and only three free-flowing stretches provide conditions that are more natural. The sediment transport and balance are disrupted and highly disturbed not only by the dams and weirs in the main river, but also by the highly reduced sediment input from major tributaries and from bank erosion due to extensive rip-rap constructions.

Since 1990, during the long process of issuing new concessions for individual hydropower plants, the problem of bed load sediment transport across the weirs was debated only within the concession perimeter. However, river sediment transport is clearly a large-scale, basin-wide issue, and if there is a series of hydropower stations then it must be tackled in a cooperative way.

In 2006, on an initiative of the Swiss environmental NGO Rheinaubund, the 11 hydropower plants, loosely organised in a hydropower association (VAR, Verband der Aare-Rhein-Kraftwerke), decided to form a common platform (PGG, Projekt-Gruppe Geschiebe) and, together with the responsible governmental authorities (Bundesamt für Energie, BFE, Switzerland and Regierungspräsidium Freiburg, RPF, Germany), to launch and finance a master plan for the reactivation of sediment transport and ecological revitalisation in the High Rhine. The PGG has only an advisory function, but national and regional authorities see the master plan as an expert study.

The master plan goes through the following process: (1) the PGG-Core Group of experts prepares the tender and contract, and the scientific/technical review of the master plan; (2) the PGG-Forum made up of delegates of various key stakeholders reviews the process of the Core Group and drafts the master plan; (3) the PGG-Plenum, composed of all interested stakeholders, is informed about the planned project in a first workshop, then about the progress of work by short reports, and about the final version of the master plan in a final workshop.

The master plan aims to:

provide a scientific review of the natural and present status of sediment transport (i.e. with and without hydropower plants),

provide basic scientific background knowledge about sediment transport mechanisms and modelling, and

describe all possible and technically feasible measures and scenarios to improve sediment transport and fish habitats along the whole impacted river section.

The first phase (which set out the organisation of the PGG and preparation of the master plan) lasted from 2007 to 2013. In a second phase, led by the Swiss and German authorities, the Plenum are discussing the political feasibility of recommended individual or combined measures, and finding solutions for implementing certain follow-up measures. These were organised according to priority, restoration potential, cost-benefit analysis and risk assessment.

For further information please visit: www.energiedienst.de

EU CH2OICE PROJECT Certification for HydrO: Improving clean energy

This project, which ran from September 2008 to February 2011, developed a technically and economically feasible certification procedure for hydropower generation facilities of a high environmental standard. The procedure had to be coherent with the requirements of the WFD, used for ‘green labelled’ electricity products, and be integrated, as much as possible, with existing EU tools, such as Ecolabel, EMAS, environmental impact assessment and sustainable energy action.

The project included the development and testing of an operational methodology to be used in marketable products and a set of guidelines to be used by developers and decision makers during planning and authorisation procedures. The partner countries were: Italy, Slovenia, France, Spain and Slovakia. In the long term, the project is expected to have a positive impact on hydropower generation in Europe, as it aim to focuses on directing new plants towards more sustainable solutions and facilitating the authorisation procedure.

Detailed project outputs

1

A general methodological approach for WFD (Water Framework Directive) — coherent certification was agreed by project partners where all the main problematic issues arising from past experiences and from the positions of main stakeholders involved were tackled, and ‘strategic’ decisions were taken (e.g.: whether to apply a quantitative, objective-oriented approach or one based on best practices).

2

Italy and Slovenia each defined and tested a national operational method for certification, based on consultation of national experts and stakeholders. By the end of the project, the certification method was ready to be implemented in a marketable product.

3

Guidelines for decision makers and hydropower generation companies were agreed for placing, constructing and managing new ‘green hydro’ plants. They help decision makers to quickly identify ‘no impact’ installations — e.g. plants on artificial ‘not significant’ water bodies — and guide them and hydropower plant designers to produce the right information for plant evaluation and authorisation.

4

An analysis document for Spain was produced, including a roadmap for the development of volunteer certification of hydropower generation facilities of a high environmental standard.

5

Proposals on the integration of the label scheme in existing procedures were presented and a feasibility analysis was carried out (and included a collection of points of view and agreements from relevant actors, where possible), with a focus on Italy and France.

https://ec.europa.eu/energy/intelligent/projects/en/projects/ch2oice

Sturgeon 2020: A strategic programme for the Sturgeon in the Danube

Sturgeon constitute an important part of the natural heritage of the Danube river basin and the Black Sea. They serve as excellent indicators of good water and habitat quality. Today, four out of the six species are critically endangered, one is considered vulnerable and one is extinct. All are now protected under the EU Habitats Directive.

In June 2011, the EU Strategy for the Danube region set as one of its targets (PA6 target) to ‘secure viable populations of Danube sturgeon species and other indigenous fish species by 2020’. A Danube sturgeon task force was created a year later in January 2012 to determine how to work together towards achieving this target. It brought together sturgeon experts, NGO delegates, and representatives of the International Commission for the Protection of the Danube River, the Danube strategy and national governments.

One of the task force's first actions was to draw up a Sturgeon 2020 programme, to act as a framework for concerted action. The Sturgeon 2020 programme is a living document and its success depends on the long-term commitment and implementation power of the countries concerned, since it requires complex cooperation between governments, decision makers, local communities, stakeholders, scientists and NGOs.

One obvious vehicle for taking forward the measures proposed under the Sturgeon 2020 programme is the Danube river basin management plan (DRBMP) and its joint programme of measures. The 2nd draft DRBMP, updated in 2015, sets as one of its visions and management objectives ‘that anthropogenic barriers and habitat deficits do not hinder fish migration and spawning anymore — sturgeon species and specified other migratory species are able to access the Danube River and relevant tributaries. Sturgeon species and specified other migratory species are represented with self-sustaining populations in the DRBD according to their historical distribution’.

The following are amongst the identified measures to be implemented in order to reach this management objective:

Specification of number and location of fish migration aids and other measures to achieve/improve river continuity, which will be implemented by 2021 by each country.

Specification of location and extent of measures for the improvement of river morphology through restoration, conservation and improvements, which will be implemented by 2021 by each country.

Avoidance of new barriers for fish migration imposed by new infrastructure projects; unavoidable new barriers must incorporate the necessary mitigation measures like fish migration aids or other suitable measures already in the project design

Closing the knowledge gaps related to the possibility for sturgeon and other specified migratory species to migrate upstream and downstream through the Iron Gate I & II dams, including habitat surveys,

If the results of these investigations are positive, the appropriate measures should be implemented and a feasibility study should be performed for the Gabčíkovo Dam and the upper Danube.

According to the DRBMP, by 2021 140 fish migration aids will be constructed in the river basin (120 have already been constructed since the first DRBMP.) These should ensure the migration of all fish species, including sturgeon, and age classes using the best available techniques. Around a further 330 measures to restore river continuity interruptions are planned to be implemented after 2021 (WFD Article 4.4).

http://www.dstf.eu

Fishpass Gars on the Inn River, Germany

In 2015, VERBUND constructed four fish ladders at the Inn power plants of Feldkirchen, Neuötting, Teufelsbruck and Gars, with a total investment of €9.7 million. Different construction methods were used to meet site-specific requirements and involved a range of mitigating measures such as additional spawning grounds, habitats for juveniles and sediment variation. The fish ladders offer native fish, such as Danube salmon, grayling, barbel and common nase, as well as other aquatic organisms, the possibility to circumnavigate the power plants.

The fish ladder concept was agreed in advance with the nature conservation authority, the Rosenheim water management board, the local fishing association and fishing industry experts. A number of artificial oxbows, spawning grounds, rebuilt river training structures, etc. have been put in place upstream and downstream. The planning and implementation phase was fully supported by local authorities and NGOs.

A scientific fish monitoring exercise over the next 10 years is expected to confirm a positive effect on the fish population of the Inn river. Preliminary observations confirm that the Danube salmon is once again spawning in the nature-like fish pass around Gars. This is a major success for such a rare and threatened species.

https://danubis.icpdr.org/system/files/shared/17_FRIK_VERBUND_Hydro%20Power%20GmbH_Ecological%20restoration%20measures%20at%20HP%20in%20AT.pdf

4.   GOOD PRACTICES IN APPLYING AN INTEGRATED PLANNING APPROACH TO HYDROPOWER

4.1.   The benefits of integrated planning

The requirement to ensure the production and use of energy from renewable sources and reduce greenhouse gases in line with the objectives of the EU Renewable Energy Directive represents a significant driver for the development and use of hydropower and other sources of renewable energy. At the same time, Member States must meet the objectives of the Water Framework Directive and the EU Nature Directives which aim to ensure that Europe's water bodies are not only prevented from deteriorating further but also reach a good status (or potential), and that EU protected species and habitats achieve a favourable conservation status across the EU.

These challenging tasks are best achieved through a strategic and integrated planning approach implemented through the national renewable action plans, river basin management plans and the conservation objectives of Natura 2000 sites (39).

A strategic planning approach:

is an excellent opportunity to integrate water, nature and energy policy objectives, as well as the objectives of other key policy areas;

makes it possible to link strategic planning for the aquatic environment and nature conservation with national energy planning on renewable electricity;

allows for the involvement of all interested parties, which can reduce subsequent potential conflicts and secure the projects;

uses the planning process to help set priorities (e.g. with respect to balancing energy, nature and water management priorities);

helps streamline the authorisation process on proposed new hydropower developments and improve transparency and predictability for hydropower developers;

allows the best environmental options and the overriding public interest of the project to be properly assessed;

provides upfront information to developers about where (geographically) gaining authorisation is likely to be possible as it identifies the most suitable and less suitable areas;

uses the policies and criteria established to help to manage the risks of cumulative effects from hydropower plants;

provides an opportunity through river basin management planning to integrate a strategic planning approach for hydropower development with water environment objectives, taking also into account the conservation objectives of the Natura 2000 sites involved.

This chapter looks at the various ways in which an integrated planning approach can be used to take account of potential negative effects on habitats and species during the early stages of the planning process. Chapter 5 looks at the requirements under the Nature Directives for a legal assessment of a proposed plan or project which is generally required to be made much later on, and then only in response to a ‘significant (negative) effect’.

However, if a strategic plan for the development of hydropower contains any substantive spatial element such as the identification of potential areas for development, this should itself also be subject to assessment as a ‘plan’ under Article 6(3) of the Habitats Directive. This provides an opportunity, in accordance with Article 6(3), to mitigate the potential effects of hydropower development on the Natura 2000 network by steering development away from sites which are likely to cause conflict between development interests and the protection of a Natura 2000 site.

The EU Blueprint to Safeguard Europe's Water Resources, adopted in 2012, also stresses the importance of strategic integrated planning: ‘… in the context of Article 4(7), … hydropower deserves specific attention … refurbishing and expanding existing installations should be given priority over new developments which should be underpinned by a strategic assessment at the river basin scale, selecting optimal locations in terms of energy production and lower environmental impact .’

It is clear that such an integrated planning process requires a more substantial initial investment for the public authorities concerned. However, all the evidence shows that, in the long run, integrated planning can deliver substantial benefits for all concerned — be it for the energy sector, the Water Framework Directive (WFD) objectives, the Natura 2000 objectives or other interests. These benefits often far exceed the initial extra investment required.

Strategic integrated planning should be carried out on several different levels and at several stages of the planning process, by both authorities and/or developers as appropriate. It should be used in particular when:

Selecting the type of renewable energy source that aims to achieve the objectives of the Renewable Energy Directive while offering the best option for the environment. This search for alternative solutions is required both in the exemptions procedure under Article 4(7) of the WFD and in the appropriate assessment procedure under Article 6 of the Habitats Directive. However, it is equally important during the strategic planning phase or when drafting national/regional renewable energy plans.

Identifying the most suitable locations for hydropower generation that are potentially appropriate from both an energy and an environmental perspective. At the same time, strategic integrated planning helps to identify areas where there is a high risk of significant effects and where, as a consequence, there is little chance of obtaining a permit under the Article 4(7) WFD exemptions procedure or the Article 6 appropriate assessment procedure under the Habitats Directive. Developing such risk assessments or biodiversity sensitivity maps early on in the planning process can help avoid or reduce the number of potential site-specific conflicts at a later stage in the development process, when financial resources have been committed and there is less room for manoeuvre. It also provides developers with a more transparent and stable regulatory environment which offers them greater certainty over the likely success of their planning application.

EU water directors' statement on hydropower development under the WFD, 2010

In 2010 the EU's water directors endorsed a statement on ‘Hydropower development under the WFD’ (40) summarising the key principles and recommendations agreed during the common implementation strategy process (CIS). This statement was mainly based on elements of the CIS policy paper on WFD and hydro-morphological pressures (41), the CIS guidance document No 20 on exemptions to the environmental objectives (42) and the conclusions of the first CIS workshop on WFD and hydropower (43).

Pre-planning mechanisms allocating ‘no-go’ areas for new hydropower projects should be developed. This designation should be based on a dialogue between the different competent authorities, stakeholders and NGOs.

In order to minimise the need for new sites, the development of hydropower capacities could be supported by modernising and upgrading existing infrastructures.

The development of hydropower should be accompanied by improved water ecology, clear ecological standards for new facilities or modernised existing facilities, and improved operating conditions. New hydropower plants should, for example, all have fish passages and should respect a minimum ecological flow.

An analysis of costs and benefits of the project is necessary to enable a judgment on whether the benefits to the environment and to society preventing deterioration of status or restoring a water body to good status are outweighed by the benefits of the new modifications. This does not mean that it will be necessary to monetise or even quantify all costs and benefits to make such judgment.

The size of the project is not the relevant criteria to trigger Article 4(7). The relevant approach is to assess whether a given project will result in deterioration of the status of a water body. Thus, projects of any size may fall under Article 4(7).

Choosing whether to renovate existing hydropower schemes or develop new hydropower facilities. As stated before, many factors have to be taken into consideration, such as the state of the water body under the WFD and the Habitats and Birds Directives, and the objectives in terms of reaching the target of good ecological status or favourable conservation status. The river assessments and Natura 2000 conservation objectives also help reveal the extent to which the river can absorb further developments without any deterioration of the water body or adverse effects on the integrity of one or more Natura 2000 sites.

Selecting the most appropriate project design that takes account of the potential effects already from the outset and builds into the initial design plan a series of mitigation measures that eliminates, or at least reduces, the final impact of the project on the aquatic environment and on Natura 2000 in particular. The traditional approach to developing a plan or project, be it for hydropower or for any other interests, is to first design the plan or project for its purpose and then later to consider wider environmental and other use issues. However, this often results in potential conflicts being taken into consideration at a relatively late stage in the planning process, at a time when there is less room for manoeuvre. In practice, it also means that project or plan developers have little interaction with experts from the environmental sector before the project is submitted for an appropriate assessment.

When the design concept is already so far advanced, the environmental impact assessment often becomes an exercise in damage limitation. This means that, even if all the rules governing such assessments, including those under the Habitats Directive, were followed thoroughly, there is no guarantee of success. This traditional approach to project or plan design can also lead to long discussions with planning authorities, other interest groups and NGOs during the public consultation phase which can, in turn, cause significant delays to the planning process and incur additional costs.

Recognising these difficulties, more and more infrastructure planners are now adopting an integrated approach to project planning and design. The integrated approach considers both the infrastructure and the ecological needs of the site at the outset and factors these into the initial project design, together with other land uses of the river. This also promotes a more interactive and transparent planning process and encourages the active assistance and input from ecologists and other stakeholders from the beginning.

The hydropower sustainability assessment protocol

The Hydro4LIFE project, run by the International Hydropower Association, aims to help support the implementation of a hydropower sustainability assessment protocol within the EU. The protocol proposes a methodology to measure the performance of a hydropower project across 20 environmental, social, technical and economic topics. It provides a common language to allow governments, civil society, financial institutions and the hydropower sector to talk about and evaluate sustainability issues. The protocol is the result of intensive work by the Hydropower Sustainability Assessment Forum, a global multi-stakeholder body with representatives from social and environmental NGOs, governments, banks and the hydropower sector.

Assessments cover all stages of the project: early stage, preparation, implementation and operation. Each project is given a score from 1 to 5 (5 being proven best practice) for each of the 20 topics. One of the topics concerns biodiversity and invasive species. During the project preparation phase particular attention is paid to

ecosystem values;

habitats;

specific issues such as threatened species and fish passage in the catchment, reservoir and downstream areas; and

potential effects arising from invasive species associated with the planned project.

http://www.hydrosustainability.org/Protocol/The-Protocol-Documents.aspx

Developing sustainable hydropower in the Danube basin: guiding principles developed by the International Commission for the Protection of the Danube River (ICPDR)

In 2010, the Ministers of the Danube countries asked for guiding principles to be developed on integrating environmental aspects in the use of hydropower in order to ensure balanced and integrated development, and that potential conflicts of interest are dealt with from the outset. The guiding principles were drafted as part of a broad participative process involving representatives from energy and environment administrations, the hydropower sector, NGOs and the scientific community. They were adopted by the ICPDR in 2013 and make the following key recommendations:

General principles for developing sustainable hydropower

1.

Hydropower development needs to respect the principles of sustainability, taking into account environmental, social and economic factors in an equally balanced way.

2.

Renewable energy generation like hydropower should be part of a holistic approach to energy policies (national energy plan, including renewable energy action plans). Untapped renewable energy potential, energy savings and increasing energy efficiency are important points that should be considered in this approach.

3.

In order to ensure sustainable hydropower development and to balance the different public interests, national/regional hydropower strategies should be drafted based on these basin-wide guiding principles. These strategies should consider the multifunctional use of hydropower infrastructure (flood control, water supply, etc.) and effects (including cumulative ones) on the environment.

4.

Weighing the public interests at national/regional level has to be done in a transparent, structured and reproducible way based on criteria and relevant information, involving public participation at an early stage of the decision-making process.

5.

Renewable energy production as such is not generally regarded as an overriding public interest. A hydropower project is not automatically of overriding public interest just because it will generate renewable energy. Each case has to be assessed on its own merits according to national legislation.

6.

Involving citizens and citizens' groups, interested parties and NGOs whose interests are affected by a hydropower project is crucial in optimising the planning processes and developing a common understanding and acceptance in the practical implementation of new hydropower projects.

7.

Hydropower development has to take into account the effects of climate change on the aquatic ecosystems and water resources (resilience of river habitats, quantity of flow, and seasonal changes of flow).

Technical upgrade of existing hydropower plants and ecological restoration

8.

Technical upgrading of existing hydropower plants should be promoted to increase their energy production. These types of improvements are the most environmentally friendly way to achieve environmental objectives (e.g. WFD).

9.

The technical upgrading of existing hydropower plants should be linked to ecological criteria for protecting and improving water status. National energy strategies and instruments should use incentives or eco-labels to promote and financially support technical upgrading.

10.

The combination of technical upgrading with ecological restoration of existing hydropower installations implies a win-win situation both for energy production and for improving environmental conditions.

Strategic planning approach for new hydropower development

11.

A strategic planning approach (linked to the renewable energy action plan and the river basin management plan) is recommended for the development of new hydropower stations. This approach should be based on a two-level assessment (including lists of recommended criteria), the national/regional assessment followed by the project specific assessment. This approach is in line with the prevention and precautionary principle as well as the polluter pays principle.

12.

A first step identifies river stretches where hydropower development is forbidden by national or regional legislation/agreements (exclusion zones). In a second step, all other stretches will be assessed using the assessment matrix and classification scheme (Figures 14 and 15).

13.

The national/regional assessment is an instrument to help administrations direct new hydropower stations to those areas where minimum effects on the environment are expected. This can be achieved by integrating hydropower production and ecosystem demands and by supporting decision making through clear and transparent criteria, including aspects of energy management as well as the environment and landscape. Danube-basin-wide or trans-border aspects need to be taken into account where appropriate.

14.

The national/regional assessment benefits both the environment and water sector but also the hydropower sector since it increases the predictability of the decision-making process and makes transparent where licences for new projects are likely to be issued.

15.

While the assessment at national/regional level is more of general nature, the project-specific assessment classifying the appropriateness of river stretches for potential hydropower use provides a more detailed and in-depth assessment of the benefits and effects of a concrete project. This helps in assessing whether a project is appropriately tailored to a specific location. The project-specific assessment is carried out in response to an application for issuing the licence for a new hydropower plant and therefore depends on the specific project design.

16.

Current and new policy developments, in particular the implementation of EU legislation and the EU Danube strategy, should be reflected accordingly.

17.

In order to support hydropower in the most sustainable way, incentive schemes for new hydropower projects should take into account the results of the strategic planning approach and adequate mitigation measures.

Mitigation of negative effects of hydropower

18.

Mitigation measures have to be set to minimise the negative effects of hydropower installations on aquatic ecosystems. If national legislation provides for this, losses of hydropower generation from existing hydropower plants due to the implementation of mitigation measures may be compensated.

19.

Ensuring fish migration and ecological flows are priority measures for maintaining and improving the ecological status of waters.

20.

Other mitigation measures such as improving sediment management, minimising the negative effects of artificial water level fluctuations (hydropeaking), maintaining groundwater conditions or restoring type specific habitats and riparian zones are important for riverine ecology and wetlands directly depending on aquatic ecosystems. These measures should therefore be considered in the project design, taking into account cost-effectiveness and security of electricity supply.

https://www.icpdr.org/main/activities-projects/hydropower

4.2.   Integrated national or regional hydropower plans

Enacted at national, regional or local levels depending on the laws in place in each country, spatial plans allow different demands on the land to be examined across a broad geographical area. This enables an integrated sustainable development strategy to be drawn up that searches for synergies, and minimises conflicts, wherever possible.

Spatial plans also provide for a more balanced development framework because they enable wider societal and environmental concerns to be taken into account early on in the planning process. This tends to lead to a more predictable and stable planning framework for all concerned which should help reduce the risk of difficulties and delays at later stages, for instance at the level of individual projects. They also encourage different economic sectors, interest groups and the general public to become engaged through public consultation, thereby ensuring greater transparency in the decision-making process.

Spatial planning, and indeed sectoral planning, is therefore an important tool for the industry. In the case of hydropower energy generation, a number of countries have developed specific hydropower plans at national or regional level to decide on future developments in function of demand and opportunities. In addition, all Member States are required to draft national renewable energy plans under the Renewable Energy Directive in order to decide the most appropriate mix of renewable energy measures for a particular country or region in terms of meeting targets for use of renewables. Both types of plan not only enable an analysis of projected needs for different types of renewable energies, including hydropower generation, but also provide an opportunity to take into account wider socioeconomic considerations (river basin management plans or Natura 2000) at an early and strategic stage in the planning process.

Appropriate assessment of plans

Article 6 of the Habitats Directive also requires appropriate assessments for plans and programmes (e.g. national or regional hydropower plans or renewable energy action plans). This is confirmed by the European Court of Justice (44). An appropriate assessment of a spatial plan or programme will of course be at a more strategic level, but the procedure is essentially the same as for projects. Thus, the appropriate assessment should consider the effect of the plan or programme on the integrity of the Natura 2000 sites, alone and in combination with other plans or projects.

The assessment work undertaken should be proportionate to the geographical scope of the plan and the nature and extent of any potential effects. Sufficient information on the proposed plan must also be obtained to allow the appropriate assessment to be carried out correctly. The underlying aim at all times is to avoid or remove any foreseeable adverse effect on the integrity of Natura 2000 sites, or to remove any reasonable grounds for concern that such an adverse effect may occur.

A key benefit of carrying out appropriate assessments for a particular plan is that it can pre-empt any potential later conflicts with Natura 2000 sites when assessing the effects of individual projects by, for instance, zoning activities away from Natura 2000 sites. It also requires those involved to consider less damaging solutions to meet the plan's objectives at a very early stage in the planning process and encourages them to develop a more integrated and holistic approach to hydropower development.

4.3.   Wildlife sensitivity maps and zoning

Land use or sectoral plans usually cover a broad geographical area. This scale, combined with the spatial nature of the plans, enables strategic decisions to be made about the capacity and location of hydropower developments over a broad area, while taking into account the multifunctional role of the rivers and the potential environmental impact of the decisions.

In this context, one effective way of avoiding or minimising potential conflicts with Natura 2000 sites is to identify locations along a river that are considered suitable or unsuitable for hydropower. This can then be overlaid on a map showing the nature conservation interests of the river in order to identify potential areas of conflict – for instance protected sites such as Natura 2000 sites, or migratory routes for EU protected species.

Wildlife sensitivity maps are useful in helping to locate hydropower developments in areas that are away from areas such as Natura 2000 sites where there is a high risk of significant effects and where the various environmental permit procedures, be they under the WFD, Habitats Directive or EIA Directive, will necessarily be more onerous and likely to be refused. Sensitivity maps can also be developed for selected categories of species (e.g. fish species of European importance) or particular types of habitats or protected areas over a pre-determined area. However, it is important that the maps be based on the best available data and information and that the criteria for selection be transparent and clear for all concerned (and eventually subject to public consultation). The maps should also be at a sufficiently fine resolution to provide a reliable characterisation of the areas.

The other major advantage of wildlife sensitivity maps is that they help pre-empt any potential conflicts with Articles 5 of the Birds Directive and 12 and 13 of the Habitats Directive. As explained in Chapter 1, these provisions aim to ensure the protection of species of European importance across their entire natural range in the EU, irrespective of whether they are in a Natura 2000 site or not. Hydropower developers or planners must therefore ensure that they operate in accordance with these strict species protection rules.

However, sensitivity maps based on existing species distributions can be misleading since existing distributions can themselves be a product of existing effects that need to be addressed. Any use of such maps needs to take account of plans to restore species distributions. Once hydropower maps and wildlife sensitivity maps have been developed they can be overlaid and different stretches of the river can be allocated to one or more of the following broad categories:

—    Favourable areas — those areas that show good hydropower potential (also in terms of upgrading existing facilities) and where there is a low risk of conflict with nature conservation interests — e.g. on a heavily modified water body of low ecological interest and or where there are no Natura 2000 sites or EU protected migratory species.

—    Less favourable areas — where there is some risk of conflict with one or more Natura 2000 sites or EU protected species along the river.

—    Unfavourable areas — where there is a high risk of conflict with one or more Natura 2000 sites or EU protected species along the river. These areas are best avoided because it will be very difficult or impossible to meet all the conditions of the Article 6 assessment procedure under the Habitats Directive and the exemptions procedure under Article 4(7) of the WFD.

Note that sensitivity maps can only provide a broad outline of areas of potentially high risk (where new developments are best avoided altogether), medium risk (where mitigation measures may be possible), and low risk (where the impact is expected to be limited or low). As such, they are not a substitute for an environmental impact assessment (EIA) or appropriate assessment (AA) at project level. These may still need to be undertaken for individual hydropower development projects.

Comprehensive species surveys within the EIA or AA at individual site level will be able to determine more precisely for each site which specific nature values and risks of impact are likely. In this context, the strategic level maps can already help to indicate the level of assessment that would be required for more detailed and stringent baseline studies at individual project level.

THE NATURA 2000 VIEWER: a useful tool for developers

http://natura2000.eea.europa.eu/

The Natura 2000 viewer is an online geographical information system (GIS) that enables developers to locate and explore each Natura 2000 site in the EU network. The sites can be examined at a very fine scale (1:500), showing the boundaries of the site and its main landscape features at a very high resolution. For each site, a standard data form can be downloaded which lists the species and habitat types for which it was designated, as well as their estimated population size or area and conservation condition in the site, and the importance of that site for the species or habitat type. Other search and display facilities are also available to overlay data from various sources on to the Natura 2000 sites.

ICPDR recommendations for national/regional assessment and criteria

The ICPDR guiding principles recommend a two-step process for strategic zonal planning of hydropower generation at national or regional level. As a first step, river stretches should be identified where hydropower development is forbidden under relevant international, national or regional legislation/agreements (exclusion zones). In a second step, all other stretches should be assessed using a predetermined classification scheme based on agreed criteria. It is important that the assessment at national/regional level is technically feasible and based on all data that can be acquired on this level. The resulting matrix provides a decision support tool to provide a balanced achievement of energy and environmental objectives. This weighing process should be carried out by the competent authority for the national/regional level within each Danube country as part of a public participation process. The results should also feed into the river basin management plans and the renewable energy action plans.

An eco-master plan mapping tool for Austria's rivers — WWF

For WWF Austria it is important that future hydropower developments follow a strategic approach so that the remaining significant, sensitive and intact stretches of river can be safeguarded. To support this, WWF has prepared an eco-master plan in order to provide a technically sound decision basis for assessing the need to protect Austrian waters (WWF Ökomasterplan, 2009).

The study was published in 2009 and assessed, for the first time, the ecological significance of 53 of the largest rivers in Austria with a catchment area larger than 500 square kilometres. It also presents the official data of the current status analysis of the ministry responsible for implementing the EU WFD and providing conservation-related information, such as on Natura 2000 sites and other protected areas. Each of the water stretches was categorised and prioritised in order of importance according to different selection criteria (for example, ecological status, situation in protected areas, hydromorphology, length of contiguous free flow path)

Thus, each river stretch was ranked according to the following sensitivity classes:

Sensitivity class 1: very high merit protection based on the ecological status

Sensitivity class 2: very high merit protection due to the situation in reserve(s)

Sensitivity class 3: highly deserving of protection on the basis of morphology

Sensitivity class 4: highly worthy of protection due to length of contiguous freeflow path

Sensitivity class 5: potentially worthy of protection as data base for safe environmental condition assessment is missing

Sensitivity class 6: potentially worthy of protection

Sensitivity class 7: low merit of protection

Sensitivity class 8: existing energy economic use

Data deficient (ecological status, hydromorphology)

Image

http://www.oekomasterplan.at/home.html

Planning instruments to balance hydropower development and restore aquatic environments in France

In 2008, the French Ministry of Ecology, Sustainable Development and Energy held a round table discussion on how to further develop sustainable hydropower while restoring the aquatic environment in France. Two objectives had to be achieved: the generation of an additional 3 TWh in terms of annual production by 2020 and the achievement of good status on 66 % of surface water bodies by 2015.

After extensive discussions with local elected authorities, hydropower producers, the national committee for professional freshwater fishing and a number of NGOs, the Ministry signed an agreement containing four key objectives:

to support hydropower through an ongoing process of shared research into environmental integration, monitoring and controls;

to modernise and optimise existing plants by working towards an effective implementation of the regulations on raising the minimum flow by January 2014 and the introduction of obligatory fish passes. Further, any renewal of concessions should be accompanied by measures to improve both the energy and environmental performance of the plant;

to remove the most problematic obstacles to ecological continuity which have been identified in the national programme and to implement these restoration schemes with the help of funds from water supply agencies;

to develop a ‘high environmental quality’ hydropower development scheme with minimum effect on the environment. Construction of new plants must be sought and placed preferentially in areas where few environmental stakes exist and must avoid areas of rich biodiversity (e.g. no-go rivers and continuity rivers).

Between 2012 and 2015 the government therefore adopted two lists of protected rivers to ensure compliance with the WFD. The first list contains no-go rivers or preserved rivers where the construction of any new obstacle cannot be authorised and existing dams must ensure ecological continuity at the moment their licence is renewed. The second list contains rivers where restoring continuity on existing dams is a priority. On these rivers, existing dams must be adjusted within 5 years to ensure both up- and downstream fish migration and a sufficient transfer of sediments.

The following are included in the first list: high status rivers (e.g. in Natura 2000), diadromous migratory fish rivers (also often in Natura 2000) and biological reservoirs. Together they represent around 25-30 % of the watercourses in France. The second list includes other diadromous migratory fish rivers, rivers at risk of failing the environmental objectives due to hydromorphological pressure and the inefficient functioning of biological reservoirs as determined in the river basin management plan. Together, they represent around 10 % of the watercourses.

The identification of potential areas for new hydropower under the regional renewable energy plans is based mainly on hydropower data and on compatibility with lists 1 and 2 which identifies areas that are considered appropriate, less appropriate or not appropriate.

Source: https://circabc.europa.eu/sd/a/85a4834a-5733-4474-9686-d6d94d722b95/Presentation-Planning%20instruments%20for%20hydropower%20and%20preserved%20rivers%20in%20France.pdf

4.4.   Early consultation

Early consultation with environmental stakeholders, and indeed all stakeholders, is important in ensuring that acceptable and sustainable solutions are found. It is equally important in reaching a common understanding of the issues at stake and encouraging cooperation in the search for solutions, especially if the ecological effects of a project prove not to be amenable to conventional mitigation approaches.

Often, conflicts have stemmed from a failure to involve environmental stakeholders sufficiently early in the planning procedure, and can result in lengthy and costly delays. Ideally, stakeholders and the wider public should participate in all stages of the project or plan development. Participation is especially important in the project or plan definition phase and during the interactive and iterative process of working out realistic alternative solutions for problematic areas.

European legislation and procedures are not very specific about the requirement for public consultation and participation and usually envisage formal steps for public consultation only after completion of environmental impact studies and submission of plans of projects for approval. However, this should not prevent developers from making their own arrangements for organising the process of public consultation from as early on as possible.

The objectives of any well organised public participation strategy should be to:

ensure a transparent planning and decision-making process for the infrastructure plan or project and openness regarding all relevant information and data;

raise awareness about the overall plan or project objectives and related issues;

gain public support for the planning process and for project or plan implementation;

integrate key stakeholders in the planning phase to create an atmosphere of mutual trust and respect, and thus facilitate the public acceptance and successful implementation of the plan or project.

In practice, the following are particularly important for ensuring a successful stakeholder consultation and participation process:

Timing of public participation: Stakeholder involvement should begin in the earliest stages of a plan or project so that environmental information can be used when considering alternatives for design, location and financial arrangements. Stakeholder consultation should continue throughout the environmental assessment process and the plan or project's cycle.

Identifying relevant interest groups: Identifying the relevant interest groups or stakeholders is critical to successful public involvement, be it in a policy, plan, programme (e.g. sectoral or regional) or project. Analysing the social composition of the society in which the plan or project is planned will also help ensure that all relevant social actors or stakeholders are identified and included in consultation.

Choosing the right form of communication and consultation: Public involvement can range from simple dissemination of information to consultation and through to full participation in decision making:

Informing: one-way flow of information from proponent to public.

Consulting: two-way flow of information between proponent and public, giving the public an opportunity to express views and the proponent to respond.

Participating: two-way flow of information and ideas in which the proponent and the public are involved in shared analysis and agenda-setting and the public/stakeholders are voluntarily involved in decision making on project design and management through consensus on the main points. The level of public involvement required for a specific plan or project will vary according to the social and political context. A participation matrix can be drawn up for each of the main stakeholder groups to help determine the appropriate degree of participation. The matrix also can be used as a systematic tool for defining the roles and responsibilities of a stakeholder and identifying areas of potential disagreement between groups.

Ownership and commitment: Early consultations with potentially affected groups can improve the environmental information supplied to decision makers (e.g. by identifying environmental effects or designing suitable mitigation measures) and help minimise potential conflicts and delays. Genuine efforts to provide the public with information and respond to suggestions or concerns also help prevent miss understandings and can result in more widely accepted projects with a greater sense of local ownership.

Undoubtedly, public consultation and participation can be time consuming and demanding, but when used positively they can reduce antagonism and enhance the potential for long-term success.

Strategic planning and collaborative working at catchment level in England

The catchment-based approach embeds collaborative working at a river catchment scale to deliver cross-cutting improvements to our water environments. Community partnerships, bringing local knowledge and expertise, are active in each of the 100+ Water Framework Directive catchments across England, including stretching across the border with Wales.

More than 1 500 organisations are engaged in catchment-based approaches nationwide including NGOs, water companies, local authorities, government agencies, landowners, angling clubs, farmer representative bodies, academia and local businesses.

Catchment-based approach partnerships drive cost-effective practical delivery on the ground, resulting in multiple benefits such as improvements to water quality, enhanced biodiversity, reduced flood risk, resilience to climate change and greater community engagement with their local river. Partnerships provide a catalyst to attract additional funds and to date some have levered up to eight times the initial investment.

A number of research projects have now been able to demonstrate that an empowered catchment area partnership comprised of diverse stakeholders and technical specialists from in and around a catchment can be responsible for coordinating the planning, funding and delivery of good ecological health for that river and its catchment.

They have also shown that an integrated stakeholder-driven assessment of a catchment can help develop a comprehensive understanding of the challenges and, following this, develop a strategic, targeted, balanced and therefore cost-effective catchment management intervention plan.

http://www.catchmentbasedapproach.org/

CABA KNOWLEDGEBASE

The aim of the Catchment based Approach website is to showcase all of the great work being undertaken by catchment partnerships across the country. By sharing best practice we aim to avoid duplication of effort and to ensure that CaBA Hosts can benefit from all of the lessons that have been learnt over the years by those engaged in catchment management. Ultimately, this website is designed to empower CaBA partnerships by showing them the huge and varied ways that participatory catchment planning and catchment management delivery can be done.

Image

Image

Image

Image

ENGAGE

USE DATA

DELIVER

MONITOR

catchment stakeholders and build an effective partnership

and evidence to inform stakeholder-led catchment planning

Targeted and integrated catchment management interventions

and model the environment to measure improvements

Learn More

Learn More

Learn More

Learn More

5.   THE ASSESSMENT PROCEDURE UNDER THE HABITATS DIRECTIVE

5.1.   Introduction

EU nature legislation requires that any plan or project likely to have a significant effect on one or more Natura 2000 sites undergo appropriate assessment (AA) under Article 6(3) of the Habitats Directive. This chapter provides a step-by-step guide to carrying out the AA for hydropower plans and projects in particular (45).

Article 6(3)

Any plan or project not directly connected with or necessary to the management of the site but likely to have a significant effect thereon, either individually or in combination with other plans or projects, shall be subject to appropriate assessment of its implications for the site in view of the site's conservation objectives. In the light of the conclusions of the assessment of the implications for the site and subject to the provisions of paragraph 4, the competent national authorities shall agree to the plan or project only after having ascertained that it will not adversely affect the integrity of the site concerned and, if appropriate, after having obtained the opinion of the general public.

Article 6(4)

If, in spite of a negative assessment of the implications for the site and in the absence of alternative solutions, a plan or project must nevertheless be carried out for imperative reasons of overriding public interest, including those of a social or economic nature, the Member State shall take all compensatory measures necessary to ensure that the overall coherence of Natura 2000 is protected. It shall inform the Commission of the compensatory measures adopted.

Because Natura 2000 concerns Europe's most valuable and endangered habitats and species, it is logical that the procedures for approving developments likely to have a significant negative effect on these sites must be sufficiently rigorous to avoid undermining the overall objectives of the Birds and Habitats Directives. Particular attention is therefore given to the need for decisions to be taken on the basis of sound scientific information and expertise. Delays in the approval process are very often caused by a poor quality AA obstructing the competent authorities' judgment of the effects of the plan or project.

It is also important not to confuse environmental assessments carried out under the Environmental Impact (EIA) and Strategic Environmental Assessment (SEA) Directives or the exemptions procedure under Article 4(7) of the Water Framework Directive (WFD) with the AA carried out under Article 6(3) of the Habitats Directive. While such assessments are very often carried out together and can benefit from coordination, each has a different purpose and assesses effects on different aspects of the environment. So although they should all ideally be coordinated, the others cannot replace, or be a substitute for, an AA.

The focus of the AA is on species and habitat types protected by the Birds and Habitats Directives, and in particular those species and habitats for which the Natura 2000 site has been designated. An AA under Article 6(3) is therefore narrower in scope than an assessment under the WFD, EIA or SEA Directives, being confined to implications for Natura 2000 sites in view of their conservation objectives.

The effects of each assessment procedure are also different. For the AA and the WFD, the outcome is legally binding on the competent authority and determines its final decision. So if the AA determines that there will be an adverse effect on the integrity of the Natura 2000 site, despite the introduction of mitigation measures, then the plan or project can only be approved if the conditions set out in Article 6(4) are met.

5.2.   When is the Article 6 procedure required?

The procedural and substantive safeguards to be applied to any plan or project likely to have a significant effect on a Natura 2000 site are laid down in Article 6 of the Habitats Directive.

This procedure is designed to:

assess the implications of a plan or project that is likely to have a significant effect on a Natura 2000 site in view of the site's conservation objectives;

ascertain whether these implications will adversely affect the integrity of the site;

provide a mechanism for approving a plan or project that has an adverse effect if there are no alternative solutions that are less damaging and if it is considered necessary for imperative reasons of overriding public interest;

ensure that in the latter case, compensatory measures are taken to ensure the overall coherence of Natura 2000 is protected.

Several terms are used in Article 6(3) to specify whether an AA is required. It concerns:

any plan or project;

which is likely to have a significant effect on at least one Natura 2000 site;

alone or in combination with other plans or projects;

but which is not directly connected with the conservation management of the site.

The Directive does not define the scope of the ‘plan’ or ‘project’. Instead, the deciding factor is whether or not it is likely to have a significant effect. The term ‘project’ should therefore be interpreted broadly, to include both construction works and any other interventions in the natural environment (46). It also covers projects that aim to restore, upgrade, maintain or modernise an existing hydropower plant if it is deemed these might have a significant effect on a Natura 2000 site.

As regards its geographical scope, Article 6(3) is not restricted to plans and projects in a Natura 2000 site; it also covers development anywhere outside a Natura 2000 site if it is likely to have a significant effect on the site. Just because a proposed development is outside the boundary of a Natura 2000 site, it is not exempt from requiring an AA under Article 6(3).

Thus, the need for an assessment depends on whether development is likely to have a significant effect on a Natura 2000 site either individually or in combination with other plans or projects, irrespective of whether the project is located within or outside Natura 2000. For instance, a project some distance upstream of a Natura 2000 site might still cause damage the integrity of site located downstream as a result of water flow disruption, changes in sediment transport, pollution or barriers to species movement and migration. In such cases, the project needs to be assessed under Article 6(3).

This should ideally also include consideration of any likely transboundary effects. If a plan or project in one country is likely to have a significant effect on a Natura 2000 site in another country, either individually or in combination with other plans or projects, then the AA must also assess the effects on the integrity of Natura 2000 sites in that other country. This is in line with the Espoo Convention, which is implemented in the EU through the EIA and SEA Directives.

5.3.   A step-by-step procedure

The procedure set out in Article 6(3) must be carried out in sequence. Each step determines whether a further step in the process is required. For instance if, after screening, it is concluded that there will be no adverse effects on the Natura 2000 site, then the plan or project can be approved without the need for further assessment.

The steps are as follows (see flow chart):

Screening — this first step determines whether a plan or project requires an AA or not. If it is impossible to exclude the likelihood that the plan or project will have a significant effect on any Natura 2000 site, then an AA is required.

Appropriate assessment — once it has been decided that an AA is required, a detailed analysis must be made of the potential effects of the plan or project, alone or in combination with other plans or projects, on the integrity of Natura 2000 site(s) in view of its conservation objectives.

Decision making — if the AA does not prove that there are no adverse effects on the integrity of the site, or that any adverse effects can be mitigated, then the competent authorities must reject the plan or project. On the other hand, if the AA proves that there will be no adverse effects on the integrity of a Natura 2000 site, the project can be approved.

Article 6(4) allows certain exceptions to this general rule. The proponent of the plan or project can ask for the plan or project to be approved in exceptional circumstances provided the conditions of Article 6(4) are met.

It is clear from the above that this decision-making process is underpinned by the precautionary principle. The emphasis is on objectively demonstrating, with reliable supporting evidence, that there will be no adverse effects on the Natura 2000 site; the onus lies on the proponent of the plan or project to demonstrate that there will be no adverse effects.

Figure

Flow chart of Article 6(3) and 6(4) procedure (based on European Commission methodological guide)

Image

Authorisation can only be granted for other imperative reasons of overriding public interest if the Commission issues a positive Opinion and adequate compensation measures are taken

Authorisation may be granted provided that adequate compensation measuresare taken

Are there human health or safety considerationsor important environmental benefits?

Are there imperative reasons of overriding public interest?

Does the site host a priority habitator species?

Derogation Article 6.4

No

Authorisation cannot be granted

Are there alternative solutions?

Can the negative impacts be removed e.g. through mitigation measures?

Authorisation may be granted

Can it be concluded that the PP will not adversely affect the integrity of the site?

Assess cumulative and in-combination effects with other plans and/or projects

Appropriate Assessment

Screening

Authorisation cannot be granted

Redesignthe plan / project

No

No

No

No

Yes

Yes

Yes

Yes

Yes

Yes

Yes

Yes

No

No

Assess implications in view of the site’s conservation objectives

Is the PP likely to have significant effects on the site?

Is the plan or project (PP) directly connected with, or necessary to the conservation management of the site?

5.3.1.   Screening

The first step in the Article 6(3) procedure is to determine whether or not an AA is needed, i.e. whether a plan or project is likely to have a significant effect on a Natura 2000 site. If it can be determined with sufficient certainty that the plan or project is not likely to have a significant effect, either individually or in combination with other plans or projects, then it can be approved without further assessment.

However, if there is any doubt whatsoever as to the likelihood of effects, an AA must be undertaken so that the potential effects can be studied in full. This was confirmed by the European Court of Justice in the Waddenzee ruling (C-127/02) in which the Court concluded that: ‘the environmental protection mechanism provided for in Article 6(3) does not presume that the plan or project considered definitely has significant effects on the site concerned but follows from the mere probability that such an effect attaches to that plan or project. In case of doubt as to the absence of significant effects such an assessment must be carried out, this makes it possible to ensure effectively that plans or projects which adversely affect the integrity of the site concerned are not authorised, and thereby contributes to achieving, the overall objectives of the Habitats Directive.’

The reasons for the final decision on whether to carry out an AA should be recorded. Sufficient information should be given to support the conclusion that has been reached.

Environmental permit for a hydropower scheme

The UK government has introduced an electronic application form — called the ‘Environmental site audit checklist for hydropower schemes’ — to assist with screening potential projects at a pre-planning stage. The checklist helps the applicant to identify the information that needs to be sent to the competent authorities so that they can fully assess the impact of the proposed hydroelectric scheme and provides them with an opportunity to seek initial advice on the planned project. This may help to avoid spending time and resources on projects that are unlikely to obtain a permit.

Applicants are specifically asked to complete a checklist containing questions on:

1.

Water abstraction and flow management

2.

Conservation

3.

Water quality

4.

Biodiversity and fisheries

5.

Managing flood risk

6.

Navigation

The government has also issued a series of guidance documents to help developers with applications for run-of-the-river hydropower schemes. These documents explain

how the UK Environment Agency regulates hydropower;

the environmental issues to consider;

advice on how to design a scheme;

how to apply for the necessary permits and licences.

https://www.gov.uk/government/publications/wr325-hydropower-schemes-environmental-site-audit-checklist

https://www.gov.uk/government/publications/good-practice-guidelines-to-the-environment-agency-hydropower-handbook

2.

Conservation

For further information, see our advice note on :

Water Framework Directive, nature conservation and heritage

 

YES

NO

Is the scheme within, or likely to affect, a Site of Special Scientific Interest (SSSI)?

(See note 2a)

 

 

Is the scheme within, or likely to affect, a Special Area of Conservation (SAC)?

(See note 2b)

 

 

Is the scheme within, or likely to affect, a Special Protected Area (SPA)?

(See note 2c)

 

 

Is the scheme within, or likely to affect, a national nature reserve?

(See note 2d)

 

 

Is the scheme within, or likely to affect, a local nature reserve?

(See note 2d)

 

 

Is the scheme within an Area of Outstanding Natural Beauty (AONB)?

(See note 2e)

 

 

Is the scheme within a national park?

(See note 2f)

 

 

Is the scheme likely to affect any waterfall, public footpath, heritage feature or conservation area?

(See note 2g)

 

 

Have formal ecological surveys been carried out on the site?

(See note 2h)

 

 

Does the scheme take account of protected species that may live at the site or nearby?

(See note 2i)

 

 

5.3.2.   Appropriate assessment

Once it has been decided that AA is required, the assessment must be carried out before the competent authority decides whether to authorise the plan or project (according to the Judgment of the Court in case C-127/02 (47)). The term ‘appropriate’ essentially means that the assessment needs to be appropriate to its purpose under the Birds and Habitats Directives, i.e. that of safeguarding species and habitat types for which the Natura 2000 site has been designated.

‘Appropriate’ also means that the assessment should lead to a reasoned conclusion. If the report does not include a sufficiently detailed assessment of the effects on the Natura 2000 site or does not provide enough evidence to draw clear conclusions about whether the site's integrity will be adversely affected, then the assessment has not fulfilled its purpose and cannot be considered ‘appropriate’ for the purposes of Article 6(3).

This has been confirmed by the European Court of Justice, which ruled that ‘Although it is true that the IREALP (48) report states that the main disturbance threatening fauna comes from the destruction of nests during the deforestation phase and from habitat fragmentation, it nonetheless contains numerous findings that are preliminary in nature and it lacks definitive conclusions . The report refers to the importance of assessments to be carried out progressively, in particular on the basis of knowledge and details likely to come to light during the process of implementation of the project. Furthermore, the report was designed as an opportunity to introduce other proposals for improvement of the environmental impact of the operations proposed.’

These factors mean that the IREALP report cannot be considered an appropriate assessment of the impact of the disputed works on SPA IT 2040044 either’. ‘It follows from all the foregoing that both the study of 2000 and the report of 2002 have gaps and lack complete, precise and definitive findings and conclusions capable of removing all reasonable scientific doubt as to the effects of the works proposed on the SPA concerned . Such findings and conclusions were essential in order that the competent authorities might gain the necessary level of certainty to take the decision to authorise the works’. (Case C-304/05, Commission v Italy, paragraphs 46-73)

The Court also emphasised the importance of using best scientific knowledge when carrying out the AA in order to enable the competent authorities to conclude with a sufficient degree of certainty that there will be no adverse effects on the site's integrity. It considered that ‘all the aspects of the plan or project which can, either individually or in combination with other plans or projects, affect those objectives must be identified in the light of the best scientific knowledge in the field.’ (C-127/02, para. 54)

The assessment report should in particular:

describe the project or plan in detail to understand its size, scale and objectives;

describe the baseline conditions and conservation objectives of the Natura 2000 site;

describe all possible effects that might occur;

analyse the interaction between those characteristics of the project and the ecological requirements of the species and habitat types for which the site has been designated in order to identify the potential effects of the project or plan on the Natura 2000 site and their level of significance;

explain how such effects will be avoided or mitigated to the extent possible;

set out a timescale and the mechanisms through which any mitigation measures will be secured, implemented and monitored;

contain a reference list of all sources of information.

Finally, the project proponent is responsible for commissioning and informing the AA and for ensuring that it is of a suitable quality. The authorities are responsible for ensuring a fair and complete evaluation of the data provided in the AA and for checking whether the findings on the effects and their significance are correct and that there will not be any adverse effects on the integrity of the Natura 2000 site, in light of its conservation objectives.

Assessing effects in view of the site's conservation objectives

As stated above, the assessment should assess the possible effects on the site of the plan or project in view of the site's conservation objectives. At a minimum, the conservation objective is to prevent any deterioration in the species and habitats for which the site was designated.

If more ambitious conservation objectives have been set under Article 6(1), then the potential effects of the plan or project must be assessed against these more ambitious objectives. For instance, if the objective is to restore the kingfisher population to a certain level within 8 years, one must assess whether the plan or project will prevent this recovery, and not merely whether the kingfisher population will remain steady.

Natura 2000 standard data form

Standard data forms have been compiled for each Natura 2000 site. They contain information on the surface area, representativeness and conservation condition of the habitats on the site, and a global assessment of the value of the site for their conservation. They also provide information on the species present, e.g. population, status (resident, breeding, wintering, migratory) and condition, and on the site's value for the species concerned (49).

Conservation condition of habitats and species on the site

The conservation status of a species or habitat is not to be confused with the conservation condition of that species or habitat. ‘Conservation status’ refers to the status of the species or habitat across its natural range in the EU and can only be assessed at a higher level (e.g. national, biogeographical or EU-wide). ‘Conservation condition’ refers to the condition of a particular species or habitat in a specific site. If its condition is poor, the authorities may have decided to set more ambitious conservation objectives for that species or habitat in that site, rather than simply prevent its deterioration.

Every 6 years, Member States report on the conservation status of habitats and species within their territory in accordance with Article 17 of the Habitats Directive. On the basis of these national reports, the Commission produces a consolidated report on their conservation status at biogeographical and EU level (50).

Natura 2000 management plans

Although not obligatory, the Habitats Directive recommends that management plans be drafted to set out conservation objectives and the measures needed to reach these objectives on the site in accordance with the ecological requirements of the species and habitats there. Management plans are therefore an invaluable source of information on Natura 2000 (51).

Collecting the necessary information for the AA

Gathering all the necessary information on both the project and the Natura 2000 site is an important first step in the AA. This is usually an iterative process. If initial research and analysis reveals important gaps in knowledge, then further baseline ecological and survey field work may be necessary to supplement existing data. As stated above, it is important to base the AA on the best scientific knowledge in the field so it can remove all reasonable scientific doubt as to the effects of the works proposed on the site concerned.

Detailed surveys and fieldwork should focus on the species and habitats for which the site was designated that are sensitive to the works proposed. Their sensitivity should be analysed taking into account possible interactions between project activities (type, extent, methods, etc.) and the habitats and species concerned (location, ecological requirements, vital areas, behaviour, etc.).

Any field studies must be sufficiently robust and long-lasting to take account of the fact that ecological conditions may vary significantly according to the seasons and indeed between years. For instance, doing a field survey on a species for a few days in winter will not capture their habitat usage in other, more important, periods of the year (e.g. the migration or breeding season).

Consulting nature authorities, scientific experts, scientists and conservation organisations early on in the process will also help to build up a complete picture of the site, the species/habitats there and the type of effects to be analysed. These different bodies can also offer advice on the latest scientific information available about the site and its EU-protected species and habitats, and on any additional baseline studies and field surveys that may be needed to assess the likely effects of the project.

Identifying adverse effects

Once all of the necessary baseline data has been gathered, the implications of the plan or project on the Natura site can be assessed. The description of potential adverse effects of hydropower facility projects, as outlined in Chapter 3, should help to identify the type of effects to look out for. It is evident that the effects of each project will be unique and must be evaluated on a case-by-case basis. This is in line with the Waddenzee ruling (see above): ‘in assessing the potential effects of a plan or project, their significance must be established in the light, inter alia, of the characteristics and specific environmental conditions of the site concerned by that plan or project.’

The first step is to analyse fully which EU protected species or habitats for which the site has been designated within each site could be potentially affected and should be subject to further in-depth assessment. This is important, as every species and habitat type has its own ecological lifecycle and conservation requirements. The effects on each will also vary from one site to another depending on their conservation condition and the underlying ecological conditions of that particular site. For each effect identified, the assessment should also look at the magnitude of the impact, type of impact, extent, duration, intensity and timing.

The AA also involves looking at all aspects of the plan or project that could have implications for the site. Each one should be examined in turn (e.g. not just the dam to be built but new access roads or any other infrastructure planned for the dam). The potential effects should also be considered for each of the species or habitat types for which the site has been designated (often referred to as ‘target features’ or ‘features’). The effects on the different features should then be looked at together, and in relation to one another, so that the interactions between them can also be identified.

Image

DEFINE STUDYAREA

DETERMINE IF THERE AREANY RESIDUAL EFFECTSON THE INTEGRITY OFTHE SITE

IDENTIFY /ASSESS PREVENTIVE AND MITIGATION MEASURES

to remove or reduce the effects to a non significant level

DESIGN A MONITORING PROGRAMME

GATHER EXISTING INFORMATION AND CARRY OUT ADDITIONAL FIELD STUDIES ANDSURVEYS ASREQUIRED

GATHER INFORMATION ABOUT OTHER PLANS AND PROJECTS

in order to be able to assess cumulative effects

ASSESS THE EFFECTS AND THEIR SIGNIFICANCE

On the targeted habitat types, thehabitats of the species and the speciesas well as on the ecological structureand function of the site

IDENTIFY THE ECOLOGICAL CHARACTERISTICS TO BE CONSIDERED IN THE ASSESSMENT

Analyse potential effects of project actions on species and habitats present

CONSULT COMPETENT AUTHORITIESANDSTAKEHOLDERS

IDENTIFY THE CONSERVATION OBJECTIVES OF THE NATURA 2000 SITE(S)

Steps to be taken as part of the appropriate assessment (adapted European Commission, 2014).

While the focus should be on the species and habitats of EU interest that justified the site designation, it should not be forgotten that these target features interact with other species and habitats and with the physical environment in complex ways. It is therefore important that all essential components of the structure, functioning and dynamics of the ecosystem are examined. Any alteration in these components, however small, could also have a negative effect on the habitat types and species present.

Effects should be predicted as precisely as possible, and the basis of these predictions should be made clear and recorded in the AA (so a clear explanation of the degree of certainty in the prediction of effects should also be included, as this is key — the assessment must be able to conclude that the effects are beyond reasonable scientific doubt). As with all impact assessments, the AA should be structured to ensure that predictions can be made as objectively as possible, using quantifiable criteria. This will also facilitate the task of designing mitigation measures that can help remove the predicted effects or reduce them to a non-significant level.

Finally, when assessing potential effects it is important to bear in mind that they may appear in any of the phases of the hydropower development, from initial construction to operation and management, and on to re-powering or decommissioning. So the effects may be temporary or permanent, on-site or off-site, or cumulative, and may come into play at different times in the project cycle.

Commonly used methods for predicting effects

The AA should apply best-practice techniques and methods to estimate the extent of effects.

Direct measurements may be taken, for example of areas of habitat lost or affected, proportionate losses from species populations, habitats and communities.

Flow charts, networks and systems diagrams can identify chains of effects resulting from direct effects; indirect effects are termed secondary, tertiary, etc. effects in line with how they are caused. Systems diagrams are more flexible than networks in illustrating interrelationships.

Quantitative predictive models can provide mathematically derived predictions based on data and assumptions about the force and direction of effects. Models may extrapolate predictions that are consistent with past and present data (trend analysis, scenarios, analogies which transfer information from other relevant locations) and intuitive forecasting. Normative approaches to modelling work backwards from a desired outcome to assess whether the proposed project will achieve these aims. Predictive modelling often plays an important role as the main effects often follow from changes in hydromorphological structures, resulting in changes in sedimentation regime with serious consequences for underwater biota.

Population-level studies are potentially beneficial for determining population-level effects of effects on bird or bat or marine mammal species, for instance.

Geographical information systems (GISs) are used to produce models of spatial relationships, such as constraint overlays, or to map sensitive areas and locations of habitat loss. GISs are a combination of computerised cartography, stored map data, and a database-management system storing attributes such as land use or slope. GISs enable the variables stored to be displayed, combined, and analysed speedily.

Information from previous similar hydropower projects may be useful, especially if quantitative predictions were made and have been monitored in operation.

Expert opinion and judgment can be obtained from previous experience and consultations on similar projects, and from local experts with experience and knowledge of the site.

Description and correlation: physical factors (e.g. the water regime, current, substrate) may be directly related to the distribution and abundance of species. If future physical conditions can be predicted then it may be possible to predict the future development of habitats and populations or the responses of species and habitats on this basis.

Capacity analyses involve identifying the threshold of stress below which populations and ecosystem functions can be sustained. It involves identifying potentially limiting factors, and devising mathematical equations to describe the capacity of the resource or system in terms of the threshold imposed by each limiting factor.

Methodological guidance on the provisions of Article 6(3) and 6(4) of the Habitats Directive.

Assessing potential cumulative effects

The cumulative effects form a crucial part of the assessment. Not only is this a legal requirement but it can also have major implications for the plan or project, and for other subsequent plans or projects proposed for the same area. This is especially relevant for hydropower, where the cumulative effects of even small installations can be unacceptably high.

A series of individually modest effects may on their own be insignificant but when assessed together may have a significant impact. Article 6(3) addresses this by taking into account the combination of effects from other plans or projects. It does not specify which other plans and projects are within the scope of this provision but it is clear that one should consider plans or projects which have been completed (i.e. already existing infrastructures) and approved. Here, information available in river basin management plans (RBMPs) under the WFD may be useful, as will any management plans developed for the relevant Natura 2000 sites.

It should be understood that, by considering a proposed plan or project, a Member State is not creating a presumption in favour of any other, similar plans or projects that might be proposed in future. On the contrary, if one or more projects have already been approved in an area, it may have the effect of lowering the ecological threshold for future plans or projects in that area.

For instance, if a series of hydropower facilities within or around Natura 2000 sites are submitted one after another, the assessment of the first project could well conclude that it will not adversely affect the site, while the second and third projects might not be approved because their effects, when combined with those of the previous project, will be enough to adversely affect the site's integrity.

In this context, it is important to look at hydropower projects strategically and in combination with each other over a reasonably large geographical area, and not simply view them as individual, isolated projects. The assessment of cumulative effects should consider all of the hydropower plants and other developments in the catchment area, irrespective of whether they are situated in or outside a Natura 2000 site.

The task of identifying cumulative effects should ideally be done in close consultation with the relevant authorities, who will have access to information about other plans and projects that need to be taken into account. The information contained in the WFD RBMPs should also be consulted, as it compiles information on all pressures and effects on the aquatic environment for the entire catchment area.

Potential cumulative effects should be assessed using sound baseline data and not rely on qualitative criteria only. They should also be an integral part of the overall assessment and not be treated merely as an ‘afterthought’ at the end of the assessment process.

Determining the significance of the effects

Once the effects have been identified (see also Section 4.7), there needs to be an appraisal of their significance (52) for the species and habitats in the site, in view of the site's conservation objectives.

The following parameters can be considered when assessing significance:

Quantitative parameters of the target feature (i.e. the species or habitat type for which the site has been designated): for instance, how much habitat is lost for that species or habitat type. For some, the loss of even single units or small percentage areas of occurrence within a given Natura 2000 site (e.g. for priority habitat types and species) should be taken as being a significant impact. For others, the significance threshold may be higher. Again, it depends on the species and habitat types, their conservation condition in that site and their future prospects.

Qualitative parameters of the target feature: independently of quantitative parameters, the significance of the effects should take into account the quality of the target feature's occurrence. For instance, it may be:

the only site in a particular region or country with that target feature (i.e. the target feature may be abundant in a given site but that is the only place where it occurs and is protected);

a site with an important occurrence of the species (e.g. a core area for the occurrence, larger areas of representative stands, etc.);

a site where the species is at the limit of its existing distribution range (bearing in mind the potential influences of climate change in the future).

The importance of the site for species biology, e.g. as a breeding site (nesting places, spawning areas, etc.); feeding habitat; place of shelter; migration pathway or stop-over.

Ecological functions and structures needed to maintain the target features and hence site integrity.

Where there is doubt or differences of opinion over the degree of significance, it is best to find broader agreement among relevant experts, e.g. regional and/or national specialists in the affected target feature, so that a consensus is built on this.

Determining whether the site's integrity is affected

Once the effects of the project have been predicted as accurately as possible, their level of significance assessed and all possible mitigation measures explored, the AA must conclude whether they will adversely affect the integrity of the Natura 2000 site.

The term ‘integrity’ clearly relates to ecological integrity. The ‘integrity of the site’ can be usefully defined as the sum of the site's ecological structure, function and ecological processes, across its whole area, or the habitats, complex of habitats and/or populations of species for which the site is designated. A site can be described as having a high degree of integrity if the inherent potential for meeting site conservation objectives is achieved, its capacity for self-repair and self-renewal under dynamic conditions is maintained, and a minimum of external management support is required.

If a plan or project adversely affects the site visual appearance of aesthetic quality or causes significant effects to habitat types or species other than those for which the site was designated as Natura 2000, this is not an adverse effect for the purposes of Article 6(3). On the other hand, if one of the species or habitat types for which the site has been designated is significantly affected then site integrity is necessarily also adversely affected.

The expression ‘integrity of the site’ shows that the focus is on the specific site. Thus, damage to part or all of a site cannot be justified by arguing that the conservation status of the habitat types and species it hosts will remain favourable overall in the European territory of the Member State.

In practice, the assessment of site integrity should focus in particular on determining whether the project prevents the site from meeting its conservation objectives, and:

causes changes to significant ecological functions necessary for the target features (i.e. the species or habitat type for which the site was designated);

significantly reduces the area of occurrence of habitat types (even of those of lower quality) or the viability of species populations that are target features of the given site;

reduces the site's diversity;

leads to the site's fragmentation;

leads to a loss or reduction of key site characteristics (e.g. tree cover, regular annual flooding) on which the status of the target feature depends;

causes mortality among the target species.

Introducing measures to remove adverse effects

If assessment of a hydropower development plan or project under Article 6 of the Habitats Directive identifies a number of adverse effects on a Natura 2000 site, the plan or project might not be automatically rejected. Depending on the severity of the potential effects, it may be possible to introduce (further) mitigation measures that will eliminate them, or at least render them insignificant, if such protective measures have not already been included in the project.

Approach to mitigation

Preference

Avoid impacts at source

Highest

Image

Reduce impacts at source

 

Abate impacts on site

 

Abate impacts at receptor

Lowest

Identifying mitigation measures, like impact assessment itself, must be based on a sound understanding of the species/habitats concerned and on dialogue between the proponent, the competent authority and conservation experts.

Mitigation measures can involve changes to the size, location, design and technology used by the hydropower plan or project (e.g. preventing migration barriers and/or injuries to fish caused by turbines). Or they can take the form of temporary adjustments during construction or operational phases (e.g. avoiding water pollution if sensitive parts or populations of target species are located downstream). See Chapter 3 for more information on potential mitigation measures for hydropower.

For each mitigation measure proposed, it is important to:

explain how the measures will prevent or render non-significant the known adverse effects on the site;

provide evidence of how they will be secured and implemented and by whom;

provide evidence of the degree of confidence in their likely success;

provide a timescale, relative to the project or plan, for their implementation;

provide evidence of how the measures will be monitored and how additional measures will be introduced if mitigation proves insufficient.

Once suitable mitigation measures have been identified and worked out in detail, the plan or project may be approved under the Article 6 (Habitats Directive) assessment procedure on condition that the mitigation measures: (1) ensure that the effects are not significant in view of the conservation objectives of the site, and (2) are implemented as an intrinsic part of the project.

If, however, there is still a significant residual effect on the site, even after mitigation measures have been introduced, then alternative solutions need to be examined instead (e.g. different location of the project, different scales or designs of development, or alternative processes). If there are none, then the plan or project may still be approved in exceptional cases, provided the conditions of Article 6(4) are met and suitable measures are approved that will compensate for the remaining adverse significant effects so that the Natura 2000 network is not compromised.

5.3.3.   Conclusions of the appropriate assessment

It is up to the competent national authorities, in the light of the conclusions of the AA, to approve the plan or project. This can be done only after having ascertained that it will not adversely affect the integrity of that site. If the conclusions are positive, in the sense that no reasonable scientific doubt remains as to the absence of effects on the site, the competent authorities can approve the plan or project.

The onus is therefore on proving the absence of effects rather than their presence, reflecting the precautionary principle (Case C-157/96). This has been confirmed in several ECJ rulings. In the Waddenzee case (C-127/02) the Court confirmed that ‘a plan or project […] may be granted authorisation only on the condition that the competent national authorities are convinced that it will not adversely affect the integrity of the site concerned. Where doubt remains as to the absence of adverse effects on the integrity of the site linked to the plan or project being considered, the competent authority will have to refuse authorisation. In other words they must have made certain, beyond reasonable scientific doubt that it will not adversely affect the integrity of that site’.

The AA and its conclusions should be clearly recorded. The report should be sufficiently detailed to demonstrate how the final decision was reached, and on what scientific grounds the decision was made.

5.4.   Exceptions under Article 6(4)

Article 6(4) provides for exceptions to the rule set out in Article 6(3). This is not an automatic process; it is up to the project or plan proponent to decide whether it wishes to apply for this. Article 6(4) lays down the conditions that need to be met in such cases and the steps that need to be followed before a competent national authority can authorise a plan or project that has been assessed as adversely affecting the integrity of a site under Article 6(3).

Article 6(4) requires the competent authorities to ensure the following conditions are met before a decision can be taken on whether or not to authorise a plan or project that may adversely affect a site:

The alternative put forward for approval is the least damaging for habitats, for species and for the integrity of a Natura 2000 site, and no feasible alternative exists that would not affect the integrity of the site.

There are imperative reasons of overriding public interest for authorising the plan or project.

All compensatory measures required to ensure protection of the overall coherence of the Natura 2000 network have been taken.

The order in which these conditions are examined is important, as each step determines whether the next step is required. If, for instance, an alternative to the plan or project in question is found, there is no point in examining whether the original plan or project is of overriding public interest or devising suitable compensation measures, since the plan or project cannot be authorised if a viable alternative exists.

Demonstrating the absence of alternative solutions

The search for alternatives can be quite broad and should be linked to the public interest objectives of the plan or project. It could involve alternative locations, different scales or designs of development, different methods of construction or alternative processes and approaches to producing renewable energy. This requirement is also closely linked to WFD Article 4(7)(d), which requires the authorities to ensure that there is no better environmental option (53).

Although the requirement to search for alternatives falls within the scope of Article 6(4), in practice it is useful for the planner to consider all possible alternatives as early as possible when first planning the development project. If an appropriate alternative is found at that stage which is not likely to have a significant effect on a Natura 2000 site, then it can be approved immediately and an AA will not be required (although other environmental assessment might still be needed).

However, if the project goes through an AA which concludes that an adverse effect on the integrity of the site is unavoidable, the competent authority must then determine whether alternative solutions exist. All feasible alternatives should be analysed, and in particular their relative performance on the conservation objectives of the Natura 2000 site and the site's integrity.

If there is a feasible alternative solution that meets the project aims, it should also undergo a new appropriate assessment if it is likely to have a significant effect on the same or another Natura 2000 site. Usually, if the alternative is similar to the original proposal, the new assessment may be able to draw a lot of the information needed from the first AA.

Imperative reasons of overriding public interest

In the absence of alternative solutions, or if the alternative has even more adverse effects on the conservation objectives or integrity of the site concerned, the competent authorities must examine whether there are imperative reasons of overriding public interest (54) that justify authorising the plan or project even though it may adversely affect the integrity of one or more Natura 2000 sites.

The concept of ‘imperative reason of overriding public interest’ is not defined in the Directive. However, it is clear from the wording that, for a plan or project to be authorised under Article 6(4), it must meet all three of the following conditions:

It must be in the public interest — it is clear from the wording that only the public interest can be balanced against the conservation aims of the Directive. Thus, projects developed by private bodies can only be considered if the public interest it serves is demonstrated (Case C-182/10 Solvay and Others, para. 71-79).

There must be imperative reasons for undertaking the plan or project — imperative in this sense clearly means that the project is essential for society, rather than merely desirable or useful.

The plan or project must be of overriding interest — in other words it must be demonstrated that implementing the plan or project is even more important than safeguarding the particular N2000 site in question in line with its conservation objectives. It is clear that not every kind of public interest of a social or economic nature is sufficient, in particular when seen against the particular weight of the interests protected by the Directive (see e.g. its fourth recital, referring to ‘the Community's natural heritage’). It seems also reasonable to assume that the public interest can only be overriding if it is a long-term interest; short-term economic interests or other interests which would only yield short-term benefits for the society would not be sufficient to outweigh the long-term conservation interests protected by the Directive.

Note that the conditions relating to an overriding public interest are even stricter for a plan or project that is likely to adversely affect the integrity of a Natura 2000 site that hosts priority habitat types and/or species, if those habitat types and/or species are affected. Imperative reasons of overriding public interest can only be accepted in that case if they concern:

human health and public safety, or

overriding beneficial consequences for the environment, or

other imperative reasons if, before the plan or project is approved, the Commission has given an opinion.

Image

Flowchart of Article 6.4 conditions

Authorisation may not be granted

Authorisation may be granted. Compensation measures mustbe taken

Authorisation may be granted forother IROPI, following consultationwith the Commission.

Compensation measures mustbe taken

Are there human health orsafety conditions or important environmental benefits

Does the site hosts a priority habitator species which could be affectedby the PP?

Are there imperative reasons of overriding public interest ( IROPI)?

Are there alternative solutions?

No

PP could adversely affect the integrity of a site

Yes

No

No

No

Yes

Yes

Yes

Compensatory measures

If there are no alternatives and there are imperative reasons of overriding public interest, the authorities must then ensure that compensatory measures are adopted and put in place before the project can begin. Compensatory measures are therefore a ‘last resort’ and are used only when the decision has been taken under the conditions described above.

Strictly speaking, compensatory measures are independent of the project and, as a rule, implemented outside the project area. They must be able to compensate fully for the damage caused to the site and to its target features and must be sufficient to ensure that the overall coherence of the Natura 2000 Network is protected.

To ensure that the overall coherence of Natura 2000 is protected, the compensatory measures proposed for a plan or project should in particular:

contribute to the conservation of affected habitat types and species within the biogeographical region concerned or within the same range, migration route or wintering area for species in the Member State concerned;

provide functions comparable to those which justified the selection of the original site, particularly regarding adequate geographical distribution;

be additional to the normal duties under the Directive, i.e. they cannot substitute for existing commitments, such as the implementation of Natura 2000 management plans.

According to existing Commission guidance, compensatory measures under Article 6(4) may consist of one or more of the following:

the recreation of a comparable habitat or the biological improvement of a degraded habitat within an existing designated site, provided this goes beyond the site's conservation objectives and does not damage other Natura 2000 target features in that site;

the recreation of a comparable habitat or the biological improvement of a degraded habitat outside a designated site which is then included in the Natura 2000 network;

the addition to the Natura 2000 network of a new site, of a quality and condition comparable to or better than the original site (55).

The habitat types and species adversely affected must, as a minimum, be compensated for in comparable proportions, but, considering the high risks and scientific uncertainty involved in attempting to recreate or restore degraded habitats it is strongly recommended that ratios well above 1:1 are applied, to be sure that the measures really do provide the necessary compensation.

Member States should pay particular attention when the adverse effects of a plan or project are felt in vulnerable natural habitats or in natural habitats of species that need a long time to regain the same ecological function. For some habitats and species it may simply not be possible to compensate for any loss within a reasonable time, as their development may take decades.

Moreover, some habitat types and habitats of species cannot be compensated for at all because their ecological characteristics cannot be artificially simulated or created. Therefore, proponents of every new hydropower development should inform themselves about the scope for compensating for particular habitat types and species well before starting to draft the plan or project.

Finally, the compensatory measures should be in place and fully functional before work on the plan or project has begun. This is to help buffer the damaging effects of the project on species and habitats by offering them suitable alternative locations in the compensation area. If this is not fully achievable, the competent authorities should require extra compensation for the interim losses to occur in the meantime. The information on compensatory measures should be submitted to the Commission as soon as they have been adopted in the planning process, to allow the Commission, in its role as guardian of the Treaties, to assess whether the Directive is being correctly applied.

ABBREVIATIONS

AA

Appropriate assessment according to the Article 6.3 of the Habitats Directive

AWB

Artificial water body under the WFD

ECJ

European Court of Justice (Court of Justice of the EU — CJEU) https://curia.europa.eu/jcms/jcms/j_6/en/

EEA

European Environment Agency (http://www.eea.europa.eu/)

EIA

Environmental impact assessment of projects

EU

European Union (EU-28)

FCS

Favourable conservation status — main objective of the Habitats Directive

HMWB

Heavily modified water body under WFD

GES

Good ecological status — main objective of the Water Framework Directive

Natura 2000

Sites designated under the Habitats and Birds Directives (pSCI, SCI, SAC and SPAs) and included in the Natura 2000 Network

NGOs

non-governmental organisations

PCIs

Projects of community interest

pSCI

proposed site of community importance to the Commission

RBMP

River basin management plan according to the Water Framework Directive

SAC

Special area of conservation with necessary conservation measures applied

SCI

Site of community importance approved by the Commission

SDF

Standard data form for a Natura 2000 site

SEA

Strategic environmental assessment of plans and programmes

SPA

Special protection area designated under the Birds Directive

WFD

Water Framework Directive


(1)  https://www.eea.europa.eu/soer

(2)  http://ec.europa.eu/environment/nature/natura2000/management/guidance_en.htm

(3)  https://ec.europa.eu/energy/en/topics/renewable-energy/renewable-energy-directive

(4)  http://ec.europa.eu/environment/nature/biodiversity/comm2006/2020.htm

(5)  EU action plan for nature, people and the economy http://ec.europa.eu/environment/nature/legislation/fitness_check/action_plan/index_en.htm

(6)  Cf Article 2 of the Habitats Directive. ‘Measures taken pursuant to this Directive shall be designed to maintain or restore, at favourable conservation status, natural habitats and species of wild fauna and flora of Community interest.’ The concept of ‘favourable conservation status’ is not mentioned in the Birds Directive but there are analogous requirements for special protection areas.

(7)  Details of all the guidance available on the management of Natura 2000 is given on http://ec.europa.eu/environment/nature/natura2000/management/index_en.htm

(8)  Commission web pages on EIA and SEA — http://ec.europa.eu/environment/eia/eia-legalcontext.htm and http://ec.europa.eu/environment/eia/sea-legalcontext.htm

(9)  Commission guidance document on the strict protection of animal species of Community interest under the ‘Habitats’ Directive http://ec.europa.eu/environment/nature/conservation/species/guidance/index_en.htm

(10)  See the Commission FAQ on the WFD and Nature Directives: http://ec.europa.eu/environment/nature/natura2000/management/docs/FAQ-WFD%20final.pdf

(11)  Heavily modified water bodies are ones which as a result of physical alterations by human activity are substantially changed in character and cannot, therefore, meet the ‘good ecological status’ (GES).

(12)  More detailed information on the specific requirements can be obtained from CIS Guidance Document No 4 on the ‘Identification and Designation of Heavily Modified and Artificial Water Bodies’.

(13)  For jurisprudence on the application of Article 4.7 see Court rulings in case C-461/13 and C-346/14.

(14)  CIS Guidance Document No 36 on WFD Article 4: https://circabc.europa.eu/sd/a/e0352ec3-9f3b-4d91-bdbb-939185be3e89/CIS_Guidance_Article_4_7_FINAL.PDF

(15)  The EIA Directive defines ‘project’ as the execution of construction works or of other installations, schemes, or interventions in the natural surroundings and landscape.

(16)  Projects that fall under Annex I include those for ‘dams and other installations designed for the holding back or permanent storage of water, where a new or additional amount of water held back or stored exceeds 10 million cubic meters’.

(17)  Projects falling under Annex II include dams and other installations designed to hold water or store it on a long-term basis (projects not included in Annex I).

(18)  OJ C 273, 27.7.2016, p. 1.

(19)  C-177/11, EU:C:2012:378, p. 19-24.

(20)  http://www.eea.europa.eu/soer

(21)  http://www.eea.europa.eu/publications/state-of-nature-in-the-eu

(22)  Commission Communication: Towards Sustainable Water Management in the European Union' First stage in the implementation of the Water Framework Directive 2000/60/EC [COM(2007) 128 final].

(23)  Arcadis 2011: Hydropower generation in the context of the EU WFD. EC DG Environment. 168 pp.

http://bookshop.europa.eu/pl/hydropower-generation-in-the-context-of-the-eu-water-framework-directive-pbKH3013438/downloads/KH-30-13-438-EN-N/KH3013438ENN_002.pdf;pgid=y8dIS7GUWMdSR0EAlMEUUsWb0000A6euO_e0;sid=E0EKwHHfLLsKwiJMudqUZxP6sYJ2kNMcbxE=?FileName=KH3013438ENN_002.pdf&SKU=KH3013438ENN_PDF&CatalogueNumber=KH-30-13-438-EN-N

See also ‘Water management, Water Framework Directive & Hydropower. Common Implementation Strategy Workshop’.

(24)  Further details provided in Common Implementation Strategy for the Water Framework Directive, WFD and hydromorphological pressures, Technical Report, Good practice in managing the ecological impacts of hydropower schemes. https://circabc.europa.eu/sd/a/68065c2b-1b08-462d-9f07-413ae896ba67/HyMo_Technical_Report.pdf

(25)  Available under: http://eur-lex.europa.eu/legal-content/en/TXT/?uri=CELEX%3A32007R1100

(26)  ‘Ecological flows in the implementation of the Water Framework Directive’ — https://circabc.europa.eu/sd/a/4063d635-957b-4b6f-bfd4-b51b0acb2570/Guidance%20No%2031%20-%20Ecological%20flows%20%28final%20version%29.pdf

(27)  Arcadis 2011: Hydropower generation in the context of the EU WFD. EC DG Environment.168 pp.

(28)  References: Ferguson, Absolon, Carlson and Sandford 2006. Transaction of the American Fisheries Society 135:139-150). Calles and Greenberg 2009. River Research and Applications 25:1268-1286. Gustafsson 2010.

(29)  European Court of Justice Ruling C-142/16.

(30)  European Court of Justice Ruling C- C-127/02.

(31)  Lambrecht H., Trautner J. (2007) Fachinformationssystem und Fachkonventionen zur Bestimmung der Erheblichkeit im Rahmen der FFH-VP — Endbericht zum Teil Fachkonventionen, Schlussstand Juni 2007. (Expert information system and expert rules for significance assessment within the framework of appropriate assessment — Final report part Expert rules, final status June 2007. In German).

(32)  This scale has been recommended to and used by experts licensed for AA by law in the Czech Republic since 2007 - http://www.mzp.cz/cz/hodnoceni_vyznamnosti_vlivu_koncepci

(33)  See also C-75/01, C-418/04, C-508/04.

(34)  See also Cases C-166/97, C-96/98, C-57/89, C-44/95, C-75/01, C-415/01, C-6/04, C-508/04, C-241/08, C-491/08, C-90/10.

(35)  It is important to note the significant difference between mitigation measures and compensation or ecological restoration measures (see Section 5.3, page 80).

(36)  See ECJ Ruling 142/16 http://curia.europa.eu/juris/liste.jsf?num=C-142/16 discussed on page 45. See also page 47 for examples of potential mitigation measures for hydropower.

(37)  https://ec.europa.eu/jrc/en/publication/working-group-ecostat-report-common-understanding-using-mitigation-measures-reaching-good-ecological

(38)  https://restorerivers.eu/wiki/index.php?title=Case_study%3AAustria_Upper_Mur_-_River_widening_Lässer_Au_(LIFE%2B_(LIFE%2B_08_NAT_A_614)_„Inner-Alpine_river_basin_management_–_Upper_River_Mur_-_murerleben_II%22_2010-2015)

(39)  Conclusions of the second CIS Workshop on the EU WFD and hydropower held in Brussels 2011, https://circabc.europa.eu/sd/a/23d94d2d-6b9c-4f17-9e15-14045cd541f3/Issue.pdf

(40)  Informal meeting of water and marine directors of the European Union, candidate and EFTA countries, Segovia, 27-28 May 2010, https://circabc.europa.eu/w/browse/6414c39b-3d08-433a-8e00-0d20bcb249ad

(41)  Common implementation strategy for the Water Framework Directive 2006: WFD and hydro- morphological pressures — policy paper. December 2006, https://circabc.europa.eu/sd/a/3dac5b10-1a16-4a31-a178-2f5401f30c50/.pdf

(42)  Common implementation strategy for the Water Framework Directive 2009: Guidance document No 20 on exemptions to the environmental objectives. Technical report — 2009-027, https://circabc.europa.eu/sd/a/2a3ec00a-d0e6-405f-bf66-60e212555db1/Guidance_document.pdf

(43)  Key conclusions, common implementation strategy workshop on WFD & hydropower, Berlin, 4-5 June 2007, https://circabc.europa.eu/w/browse/062ef598-2126-4e76-a481-cfa68a28435c

(44)  ECJ ruling on case C-6/04, Commission v United Kingdom, 20 October 2005.

(45)  The Commission has produced guidance documents to help people understand and apply the appropriate assessment procedure. They are available from the Commission's Natura 2000 website, http://ec.europa.eu/environment/nature/natura2000/management/guidance_en.htm

(46)  European Court of Justice Ruling C-127/02.

(47)  Judgment of the Court C-127/02 — Waddenvereniging and Vogelsbeschermingvereniging.

(48)  (Research Institute for Applied Ecology and Economics in the Alpine Region).

(49)  Commission Implementing Decision of 11 July 2011 concerning a site information format for Natura 2000 sites (notified under document C(2011) 4892) (OJ L 198, 30.7.2011, p. 39).

(50)  http://ec.europa.eu/environment/nature/knowledge/rep_habitats/index_en.htm

(51)  http://ec.europa.eu/environment/nature/natura2000/management/guidance_en.htm

(52)  ‘Significance’ here refers to the significance of the effects. It is not to be confused with the screening stage which places the emphasis on the likelihood of significant effects.

(53)  See CIS guidance No 20.

(54)  This concept is also used in Article 4(7) of the WFD.

(55)  This addition must be formally designated by the Member State authorities after EC approval.


18.6.2018   

EN

Official Journal of the European Union

C 213/62


Commission notice: ‘Energy transmission infrastructure and EU nature legislation’

(2018/C 213/02)

TABLE OF CONTENTS

Page

ABOUT THIS DOCUMENT 65
Purpose 65
Structure and contents 65
Scope of the document 65

1.

A RENEWED ENERGY INFRASTRUCTURE FOR EUROPE 67

1.1.

The need for a renewed energy infrastructure in Europe 67

1.2.

Infrastructure challenges 68

1.2.1.

Electricity grids and storage 68

1.2.2.

Natural gas grids and storage 69

1.2.3.

Oil and olefin transport and refining infrastructure 69

1.2.4.

CO2 capture, transport and storage (CCS) 69

1.3.

Types of transmission and distribution facilities in use 69

1.3.1.

Gas and oil transmission and distribution facilities 69

1.3.2.

Electricity transmission and distribution facilities 70

1.4.

Projects of Common Interest (PCIS) 70

2.

EU NATURE LEGISLATION 72

2.1.

Introduction 72

2.2.

The Habitats and Birds Directives 72

2.3.

The protection and management of Natura 2000 Sites 73

2.3.1.

Taking positive conservation measures and ensuring non-deterioration 73

2.3.2.

The permit procedure for plans and projects affecting Natura 2000 sites 74

2.4.

Species protection provisions 75

3.

POTENTIAL IMPACTS OF ENERGY TRANSMISSION FACILITIES ON NATURA 2000 AND EU PROTECTED SPECIES 76

3.1.

Introduction 76

3.2.

The need for a case-by-case approach 76

3.3.

An overview of potential impacts on EU protected species and habitats 77

3.3.1.

Habitat loss, degradation or fragmentation 77

3.3.2.

Disturbance and displacement: 77

3.3.3.

Collision and electrocution risk: 77

3.3.4.

Barrier effects 77

3.4.

Distinguishing between significant and insignificant effects 78

3.5.

Cumulative effects 78

4.

POTENTIAL IMPACTS OF ELECTRIC GRID INFRASTRUCTURES ON WILD BIRDS 79

4.1.

Introduction 79

4.2.

Electric grid infrastructures 79

4.3.

Potential negative impacts of electricity infrastructure on wild birds 80

4.3.1.

Electrocution 80

4.3.2.

Collision 83

4.3.3.

Habitat loss and fragmentation 84

4.3.4.

Disturbance/Displacement 84

4.3.5.

Electromagnetic fields 84

4.4.

Potential positive effects of electricity infrastructure on wild birds 84

5.

POTENTIAL MITIGATION MEASURES FOR ELECTRIC GRID INFRASTRUCTURES AFFECTING WILD BIRDS 86

5.1.

What are mitigation measures? 86

5.2.

Potential measures to mitigate negative effects of electricity plans or projects on wild bird species 88

5.2.1.

Introducing proactive measures at the planning level 88

5.2.2.

Investigating potential mitigation and preventive measures at the project-level 90

5.3.

Detailed technical recommendations for remedial and mitigation measures 91

5.3.1.

Mitigation of electrocution 91

5.3.2.

Mitigation of collision 92

6.

THE IMPORTANCE OF ADOPTING A STRATEGIC APPROACH TO PLANNING 93

6.1.

The benefits of integrated planning 93

6.2.

Determining suitable locations for energy transmission facilities 94

6.3.

Looking for ways to streamline the permitting procedures for energy transmission facilities 96

6.3.1.

Early planning, ‘roadmapping’ and scoping of assessments 96

6.3.2.

Early and effective integration of environmental assessments and of other environmental requirements 97

6.3.3.

Procedural coordination and time limits 98

6.3.4.

Quality of the reports 98

6.3.5.

Cross-border co-operation 98

6.3.6.

Early and effective public participation 99

7.

THE PERMITTING PROCEDURE UNDER ARTICLE 6 OF THE HABITATS DIRECTIVE 99

7.1.

Introduction 99

7.2.

The scope of the Article 6 permit procedure 100

7.3.

A step-by-step procedure for carrying out appropriate assessments 102

7.3.1.

Step one: screening 102

7.3.2.

Step two: the Appropriate Assessment 102

7.3.3.

Step 3: approving or refusing the plan or project in light of the conclusions of the appropriate assessment 109

7.4.

The derogation procedure under Article 6.4 109

8.

ENERGY TRANSMISSION INFRASTRUCTURE IN THE MARINE ENVIRONMENT 113

8.1.

An overview of current energy infrastructure in EU marine waters 114

8.1.1.

Oil and gas 114

8.1.2.

Offshore wind, wave and tidal current power 115

8.1.3.

Carbon Capture and Storage (CCS) 117

8.1.4.

Transmission grids 117

8.1.5.

Projections for the future 117

8.2.

NATURA 2000 in the marine environment 119

8.2.1.

The protection of marine environment, habitats and species 119

8.2.2.

Supporting measures and useful sources of information 123

8.3.

Potential impacts and approaches to mitigation 124

8.3.1.

Installation 126

8.3.2.

Operation 129

8.3.3.

Decommissioning 131

8.3.4.

Cumulative effects 131

8.3.5.

Potential mitigation measures 132

8.4.

The importance of strategic planning 133
REFERENCES 136
ANNEX 1 — NATIONAL AND INTERNATIONAL INITIATIVES 150
ANNEX 2 — A SYSTEMATIC PRIORITISED LIST OF IMPACTS OF BIRD/POWER LINE INTERACTIONS (BIRDLIFE, 2013) 157
ANNEX 3 — A SUMMARY OF EVIDENCE ON THE POPULATION-LEVEL IMPACT OF POWER LINES ON GLOBALLY THREATENED (IUCN, 2012) BIRD SPECIES 159
ANNEX 4 — EXAMPLES OF IMPACTS OF POWER LINES ON META-POPULATIONS OF SPECIES LISTED IN ANNEX I OF BIRDS DIRECTIVE 161
ANNEX 5 — PROPOSED LIST OF PRIORITY SPECIES FOR PREVENTION AND MITIGATION OF POWER LINE IMPACT WITHIN THE EU 163
ANNEX 6 — COMPARISON OF PROCEDURES UNDER APPROPRIATE ASSESSMENT (AA), EIA AND SEA 168

ABOUT THIS DOCUMENT

Purpose

In November 2010, the European Commission published the communication ‘Energy infrastructure priorities for 2020 and beyond - A Blueprint for an integrated European energy network’. It calls for a significant increase in energy transmission infrastructures in order to ensure a safe, sustainable and affordable energy supply across Europe, whilst, at the same time, reducing CO2 emissions.

The new TEN-E Regulation (EU) No 347/2013 establishes an EU-wide framework for the planning and implementation of energy infrastructure in the EU. It establishes nine strategic infrastructure priority corridors in the domains of electricity, gas and oil, and three Union-wide priority thematic areas for electricity highways, smart grids and carbon dioxide transportation networks. It also introduces a transparent and inclusive process to identify and select concrete Projects of Common Interest (PCIs), which are needed to implement the priority corridors.

Like all development activities within the EU, energy transmission infrastructures must be fully compliant with the EU's environmental policy, including the Habitats and Birds Directives (the EU Nature directives). This document provides guidance on how best to achieve this in practice. It pays particular attention to the correct application of the permitting procedure under Article 6 of the Habitats Directive which requires that all plans and projects likely to have a significant negative effect on a Natura 2000 site undergo an appropriate assessment (AA) before authorisation. It also addresses the requirements for protection of species in the wider landscape.

Natura 2000 sites are not designed to be ‘no go zones’ and new developments are not excluded. Instead developments must be undertaken in a way that safeguards the rare and endangered species and habitat types for which the site has been designated. Often this can be achieved through careful planning, good and inclusive dialogue and, where appropriate, the use of suitable mitigation measures to remove or pre-empt any potential negative impacts of individual projects as well as cumulative impacts on the site's conservation objectives at the outset.

This document is designed principally for project developers, transmission system operators (TSOs) and authorities responsible for the permitting of energy transmission plans and projects, but it should also be of interest to impact assessment consultants, Natura 2000 site managers, NGOs and any other practitioners who are concerned by or involved in the planning, design, implementation or approval of energy infrastructure plans and projects. It is intended to give them an overview of the implications of energy infrastructure proposals on Natura 2000 and EU protected species and habitats and approaches to mitigating any negative effects.

This document might also be useful for assessment procedures carried out under the Environmental Impact Assessment Directive and Strategic Environmental Assessment Directive for energy transmission facilities plans and projects for which it is determined that Appropriate Assessment of their impact on Natura 2000 is not necessary.

Scope

The document provides guidance and best practices on the installation, operation and decommissioning of electricity, gas and oil transmission and distribution facilities in relation to Natura 2000 sites and species protected under the EU Habitats and Birds Directives in the wider landscape. It focuses on energy transmission infrastructures only and not on energy production facilities such as oil platforms, hydroelectric dams, wind turbines, power stations, etc.

The types of energy transmission infrastructures covered include gas and oil pipelines, as well as high and medium voltage electricity transmission cables and distribution facilities with the focus on the latter on land. A separate chapter is included regarding energy transmission infrastructure in the marine environment.

Structure and contents

The document contains eight chapters:

Chapters 1 and 2: provide an overview of the EU policy context as regards energy infrastructure and the need for a modern, interconnected energy grid across Europe in line with the TEN-E Regulation. It highlights the legal provisions of the Birds and Habitats Directives that energy transmission developers, operators and authorities should be aware of including giving special attention to the permitting procedure under Article 6 for any plans or projects likely to have a significant effect on Natura 2000 sites as well as to the requirements on EU protected species across the wider landscape.

Chapter 3: provides a general overview of the different types of potential impacts that energy transmission infrastructures might have on habitat types and species protected under the two EU nature Directives. Being aware of these potential impacts will not only ensure that the Appropriate Assessment under Article 6 of the Habitats Directive is carried out correctly but should also help to identify suitable mitigation measures that can be used to avoid or reduce any significant negative effects from arising in the first place.

Chapters 4 and 5: focuses on the potential effects of electric grid infrastructures in particular and on identifying appropriate mitigation measures during different stages of the plan or project cycle. Detailed technical recommendations are given for remedial and mitigation measures wherever possible based on good practice experiences and latest research across Europe.

Chapter 6: outlines the benefits of taking a more strategic and integrated approach to planning energy transmission infrastructures in a way that avoids or minimises the potential for conflicts with requirements of the EU nature legislation later on in the planning process when the options are much more limited. It also provides an overview of how the various impact assessments required under EU environmental laws, including under the Habitats Directives, can be effectively streamlined for PCIs, in particular in light of the shortened timelines for PCI permitting procedures under the TEN-E Regulation.

Chapter 7: describes the permitting procedure under Article 6 of the Habitats Directive. It aims to provide practical advice on how to apply this permitting procedure in the context of energy transmission infrastructures in particular.

Chapter 8: analyses the implications of energy transmission infrastructures on the marine environment. It first provides an overview of current energy infrastructure in EU marine waters and predicted future developments. Then, it introduces the implications for marine Natura 2000 sites and protected species with reference to provisions in the Habitats Directive and Birds Directive, as well as relevant supporting measures and guidance from the EU and elsewhere. Thirdly, it reviews the potential impacts of transmission infrastructure (cables and pipelines) associated with oil, gas, wind, wave and tidal power, and Carbon Capture, transport and Storage (CCS) on marine species and habitats protected by the EU Habitats Directive and the EU Birds Directive. Examples of good practice are included as part of a discussion on ways to mitigate such effects. Fourthly, it examines the benefits of strategic planning for energy transmission infrastructure in the marine environment including the importance of setting this in the context of other EU legislation and policies such as the Marine Strategy Framework Directive and Marine Spatial Planning.

Throughout the document good practice examples are provided wherever possible to show how energy transmission facilities and EU nature legislation can be effectively reconciled in practice. They provide a useful source of ideas on the different types of techniques and approaches that can be used.

Nature of the document

This guidance document seeks to clarify the provisions of the Habitats and Birds Directives and place them in the context of energy transmission development and operation in particular. The document is not legislative in character but rather provides practical guidance and best practices on the application of existing rules. As such, it reflects only the views of the Commission services. It rests with the European Court of Justice to provide definitive interpretation of EU directives.

The document complements the Commission's existing general interpretative and methodological guidance documents on Article 6 of the Habitats Directive (1). It is recommended that these guides be read in conjunction with the present document.

Finally, the document fully recognises that the two Nature Directives are enshrined in the principle of subsidiarity and it is for Member States to determine how best to implement the procedural requirements arising from them. The good practice procedures and proposed methodologies described in this document are therefore not prescriptive in their intent; rather they aim to offer useful advice, ideas and suggestions based on feedback and input from competent authorities, energy business representatives, NGOs and other experts and stakeholders.

The Commission would like to thank all those who participated in the preparation of this guidance document for their valuable contributions and discussions.

1.   A RENEWED ENERGY INFRASTRUCTURE FOR EUROPE

1.1.   The need for a renewed energy infrastructure in Europe

EU countries have agreed on a new 2030 Framework for climate and energy, including EU-wide targets and policy objectives on greenhouse gas emissions, renewable energy, energy efficiency and electricity interconnections. These targets and policy objectives aim to help the EU achieve a more competitive, secure and sustainable energy system and to meet its long-term 2050 greenhouse gas reductions target.

Figure 1

2030 Framework for Energy and Climate – agreed headline targets

Image

10 %Interconnection

-20 %GreenhouseGas

20%RenewableEnergy

15 %Interconnection

≥ 30%EnergyEfficiency

≥ 27 %RenewableEnergy

≥ - 40 % Greenhouse Gas Emissions

20 %EnergyEfficiency

The Commission has presented, as one of its key priorities, a Framework Strategy for a Resilient Energy Union with a Forward-Looking Climate Change Policy (2). Its goal is to help the EU deliver on its 2030 targets and objectives and give European consumers access to secure, sustainable, competitive and affordable energy and allow them to benefit from the ongoing fundamental transformation of Europe's energy system.

In order to meet the 2030 targets and objectives, it is essential that Europe's energy transmission and storage facilities are modernised (3). Out-dated and poorly interconnected infrastructures are a major constraint on Europe's economy. The development of wind electricity generation in the North and Baltic Sea regions, for instance, is hampered by insufficient grid connections both off- and onshore. The risk and cost of disruptions and wastage is also expected to increase unless the EU invests in smart, effective and competitive energy networks, and exploits its potential for energy efficiency improvements.

The new EU energy infrastructure policy will help coordinate and optimise network development on a continental scale and so enable the EU to reap the full benefits of an integrated European grid, which goes well beyond the value of its single components.

A European strategy for fully integrated energy infrastructures based on smart and low-carbon technologies will not only reduce the costs of making the low-carbon shift through economies of scale for individual Member States. It will also improve security of supply and help stabilise consumer prices by ensuring that electricity and gas goes to where it is needed. European networks will also facilitate competition in the EU's single energy market, build up solidarity among Member States and ensure that European citizens and businesses have access to affordable energy sources.

In order to help implement this important step change in energy transmission, the EU adopted a new TEN-E Regulation (EU) No 347/2013 (4) in 2013. This provides a comprehensive EU-wide framework for the planning and implementation of energy infrastructure.

It establishes nine strategic infrastructure priority corridors in the domains of electricity, gas and oil, and three Union-wide priority thematic areas for electricity highways, smart grids and carbon dioxide transportation networks to optimise network development at European level by 2020 and beyond.

Figure 2

Priority Corridors for Electricity gas and Oil

Image

1.2.   Infrastructure challenges

The challenge of interconnecting and adapting Europe's energy infrastructure to new needs concerns all sectors and all types of energy transmission facilities.

1.2.1.   Electricity grids and storage

Electricity grids will need to be upgraded and modernised to meet increasing demand due to a major shift in the overall energy value chain and mix and also because of the multiplication of applications and technologies relying on electricity as an energy source. The grids must also be extended and upgraded to foster market integration and maintain the existing levels of system security, but especially to transport and balance electricity generated from renewable sources, which is expected to more than double in the period 2007-2020.

A significant share of generation capacities will be concentrated in locations further away from the major centres of consumption or storage. Significant shares will come from offshore installations, ground-mounted solar and wind farms in Southern Europe or biomass installations in Central and Eastern Europe. Decentralised generation is also expected to gain ground.

Beyond these short-term requirements, electricity grids need to evolve more fundamentally to enable the shift to a decarbonised electricity system in the 2050 horizon, supported by new high-voltage long distance and new electricity storage technologies which can accommodate ever-increasing shares of renewable energy, from the EU and beyond.

At the same time the grids also need to become smarter. Reaching the EU's 2020 energy efficiency and renewable targets will not be possible without more innovation and intelligence in the networks at both transmission and distribution level, in particular through information and communication technologies. These will be essential in the take-up of demand side management and other smart grid services.

1.2.2.   Natural gas grids and storage

Natural gas is expected to continue to play a key role in the EU's energy mix in the coming decades and will gain importance as the back-up fuel for variable electricity generation. However, gas networks face additional flexibility requirements in the system, the need for bi-directional pipelines, enhanced storage capacities and flexible supply, including liquefied (LNG) and compressed natural gas (CNG).

1.2.3.   Oil and olefin transport and refining infrastructure

If climate, transport and energy efficiency policies remain as they stand today, oil would be expected to still represent 30 % of primary energy, and a significant part of transport fuels are likely to remain oil based in 2030. Security of supply depends on the integrity and flexibility of the entire supply chain, from the crude oil supplied to refineries to the final product distributed to consumers. At the same time, the future shape of crude oil and petroleum product transport infrastructure will also be determined by developments in the European refining sector, which is currently facing a number of challenges.

1.2.4.   CO2 capture, transport and storage (CCS)

CCS technologies can reduce CO2 emissions on a large scale but are still at an early stage of development. CCS commercial roll-out in electricity generation and industrial applications is expected to start after 2020. Due to the fact that potential CO2 storage sites are not evenly distributed across Europe and that some Member States have only limited potential storage within their national boundaries, construction of European pipeline infrastructure spanning across State borders and in the maritime environment could become necessary.

1.3.   Types of transmission and distribution facilities in use

The way in which different forms of energy are transported, distributed and stored varies of course in function of the type of energy in question and whether it is occurring on land or in the marine environment. For example, the transmission of electricity is generally realised by powerlines or cables, whilst the transmission of gas and oil is done by pipelines.

This document focuses in particular on the following facilities (5):

Terrestrial gas and oil transmission facilities: buried pipelines, above-ground pipelines including those crossing watercourses as well any associated components (initial injection stations, pump (oil) and compressor (gas) stations, partial delivery station, block valve stations, regulator stations and final delivery stations);

Terrestrial electricity transmission facilities: buried/ underground powerlines, overhead powerlines, and associated components (towers, substations and converter stations).

1.3.1.   Gas and oil transmission and distribution facilities

Pipelines are generally used to transport large quantities of crude oil, processed oil products or natural gas over land. Oil pipelines are made from steel or plastic tubes with an inner diameter typically from 100 to 1 200 mm. Most pipelines are buried at a depth of about 1 to 2 m. The oil is kept in motion by pump stations. Natural gas pipelines are constructed of carbon steel and vary from 51 to 1 500 mm in diameter. The gas is pressurised by compressor stations.

The pipeline is routed along what is known as a right-of-way (ROW). The steps for building a pipeline include the route selection that must then be surveyed to ensure any physical obstacles are anticipated, and cleared. Where needed, trenching is implemented, especially for main route and crossings. The pipe is later installed with its associated components (valves, intersections, etc.). Where relevant, the pipe and trench are then covered.

1.3.2.   Electricity transmission and distribution facilities

As electricity still cannot be stored in large quantities, it has to be generated in real-time. This means that its constant transport to users should be as effective as possible. In terrestrial environments, electricity transmission is the transfer of electricity from generating power plants to high-voltage electrical substations located near demand centres. Large amounts of electricity are transmitted at high voltages (110 - 750 kV in Europe, ENTSO, 2012) to reduce the energy lost in long-distance to a substation.

Transmission lines mostly use high-voltage three-phase alternating current (AC), that deliver large amounts of power over long distances (APLIC, 2006). High-voltage direct-current (HVDC) technology provides greater efficiency in very long distances (typically greater than 600 km). Electrical power may be transmitted through overhead lines or underground cables. In all cases, the voltages are high because, with present technologies, large amounts of power can only be transmitted efficiently with high voltages.

Electric power distribution carries electricity at a medium voltage from the transmission system to the final customers (often less than 33 kV). The distinction between high voltage power lines and medium voltage distribution lines is an important one from a nature conservation point of view as the risk of electrocution only exists for medium voltage distribution power lines whereas the risk of collision however exists for both transmission and distribution lines (6) (see chapter 4).

Electricity is usually transmitted through overhead power lines suspended by towers or utility poles, but buried/ underground power lines are also sometimes used, especially in urban areas or sensitive locations. Overhead power lines have specific impacts on biodiversity, health and the landscape, which are different from underground power lines. On the other hand the initial investment costs of underground cables can often be significantly higher than overhead powerlines.

1.4.   Projects of Common Interest (PCIs) (7)

The existing TEN-E Regulation, which entered into force on 15 May 2013, sets out the legal and policy framework to optimise network development at European level by 2020 and beyond. It identifies 12 strategic priority corridors and thematic areas for energy infrastructure with a trans-European/cross-border dimension. The Regulation sets out a process to establish on a biennial basis Union-wide lists of Projects of Common Interest (so-called PCIs) (8), which contribute to the development of energy infrastructure networks in each of the 12 priority corridors and thematic areas.

For a project to be included in the Union list, it has to have significant benefits for at least two Member States; contribute to market integration and further competition; enhance security of supply, and reduce CO2 emissions. The process of identification is based on regional cooperation, involving Member States and different stakeholders, who provide their knowledge and expertise with regard to the technical feasibility and market conditions, both from a national and a European perspective.

The third Union list of 173 energy infrastructure PCIs (9) was adopted in November 2017. The list covers 106 electricity projects, including electricity transmission lines and electricity storages, 4 smart grids projects and 53 gas projects. For the first time, the PCI list also includes 4 carbon-dioxide network projects. The list of PCIs is updated every two years to integrate newly needed projects and remove completed ones.

These PCIs may now be eligible for financial support under the Connecting Europe Facility (CEF). A budget of €5.35 billion has been earmarked for trans-European energy infrastructure under this new Facility for the 2014-2020 period. In 2016, under the second and third call for proposals a total of €707 million in grants was allocated to 27 PCIs. Of these grants, 11 were for projects in the electricity sector and 15 for projects in the gas sector; 1 was for a smart grid project. 8 grants were for construction works and 19 for studies. €800 million in CEF grants were set aside for PCIs in 2017.

Because of their strategic EU importance, PCIs benefit from a streamlined planning and permit granting procedure. This includes, for instance, the appointment of a single competent national authority to act as a ‘one-stop-shop’ for all permits and a binding three-and-a-half-years' time limit for project authorisation. The aim is to speed up procedures and ensure swift permitting and operation of projects which are considered necessary to bring about energy security and to help meet the EU's climate and energy targets, whilst at the same time ensuring that the highest standards imposed by Union environmental legislation are met, as well as to increase transparency and to improve public participation. This should, in turn, enhance the attractiveness of PCIs for investors thanks to an enhanced regulatory framework.

Energy Projects of Common interest: interactive map

The European Commission has developed A Transparency Platform (10) that enables the user to identify and explore each of the 173 PCIs adopted in 2017 through an on-line map viewer. Projects can be mapped according to type of energy (whether electricity, gas, oil or other), type of infrastructure, country and/or priority corridor. Technical summaries are also made available for each project shortly after adoption.

It should be noted however that the Union list contains PCIs in different stages of development. Some are still in the early phases of development, therefore studies are still needed to demonstrate that the project is feasible.

The inclusion of such projects in the Union list of PCIs is also without prejudice to the outcome of relevant environmental assessments and permitting procedures. If a project included in the Union list of PCIs turns out not to be in compliance with the EU acquis, it will be removed from the Union list.

To support Member States in defining adequate legislative and non-legislative measures to streamline the various environmental assessment procedures, and to ensure a coherent application of those required under Union law for PCIs, the Commission issued a Guidance document in July 2013 (11).

What does ‘Streamlining’ mean?

Streamlining means: improving and better co-ordinating environmental assessment procedures, with a view to reducing unnecessary administrative burden, creating synergies and hence shortening the time needed to conclude the assessment process, whilst at the same time ensuring a high level of environmental protection through comprehensive environmental assessments in accordance with the EU environmental acquis.

Source: Guidance Document ‘Streamlining environmental assessment procedures for energy infrastructure “Projects of Common Interest” (PCIs)’ July 2013

The Guidance document provides six main recommendations to streamline the procedures. These are based on, but also go beyond, the implementation experience and the good practices identified in the Member States so far (see chapter 4 for more details).

The recommendations focus in particular on:

Early planning, ‘roadmapping’ and scoping of assessments

Early and effective integration of environmental assessments and of other environmental requirements

Procedural co-ordination and time limits

Data collection, data sharing and quality control

Cross-border co-operation, and

Early and effective public participation.

Subsequent chapters in this guide focus in particular on the permitting procedure under the Habitats Directive in the context of energy transmission plans and projects. Other environmental permitting procedures are not covered in detail, but are mentioned when relevant.

The present document therefore complements the above-mentioned Streamlining Guide for PCIs but has a wider remit, covering all types of oil, gas and electricity transmission infrastructures, irrespective of whether they are PCIs or not.

2.   EU NATURE LEGISLATION

2.1.   Introduction

Some energy transmission infrastructure plans and projects may potentially affect one or more Natura 2000 sites included in the EU Natura 2000 network or may impact on certain rare and threatened species protected under EU legislation. The Habitats and Birds Directives lay down the provisions that need to be respected in such cases. An overview of these provisions is provided in this chapter. Subsequent chapters present specific elements of the permitting procedure under Article 6 of the Habitats Directive in particular as it relates to energy transmission plans or projects.

2.2.   The Birds and Habitats Directives

Halting the loss of EU's biodiversity is recognised as an important element of the Europe 2020 Strategy, calling for a smart, inclusive and sustainable growth policy that takes account of the important socio-economic benefits that nature provides society.

In March 2010, the EU Heads of State and Government set themselves the ambitious target of halting, and reversing, the loss of biodiversity in Europe by 2020. In May 2011, the European Commission adopted a new EU Biodiversity Strategy 2020 (COM(2011) 244) (12) which sets out a policy framework for achieving this.

The Birds (13) and Habitats (14) Directives are the cornerstones of the EU's biodiversity policy. They enable all EU Member States to work together, within a common legislative framework, to conserve Europe's most endangered and valuable species and habitats across their entire natural range within the EU, irrespective of political or administrative boundaries.

The two directives do not cover every species of plant and animal in Europe (i.e. not all of Europe's biodiversity). Instead, they focus on a sub-set of around 2000 species which are in need of protection to prevent their decline or degradation. These are often referred to as species of Community interest or EU protected species. Some 230 rare or endangered habitat types are also protected in their own right under the Habitats Directive.

The overall objective of the two directives is to ensure that the species and habitat types they protect are maintained and restored to a favourable conservation status (15) throughout their natural range within the EU. This target is defined in positive terms, oriented towards a favourable situation, which needs to be reached and maintained. It is therefore more than just avoiding deterioration.

To achieve this objective, the EU Nature directives require Member States to:

Designate and conserve core sites for the protection of species and habitat types listed in Annex I and II of the Habitats Directive and Annex I of the Birds Directive, as well as for migratory birds. These sites form part of the EU-wide Natura 2000 Network;

Establish a species protection regime for all wild European bird species and other endangered species listed in Annex IV and V of the Habitats Directive. This protection regime applies across the species' entire natural range in the EU, that is across the broader landscape (ie both inside and outside Natura 2000 sites).

2.3.   The management and protection of Natura 2000 sites

To date, over 27,000 sites have been designated as Natura 2000 sites. Together they cover around 18 % of the European land area as well as significant marine areas.

THE NATURA 2000 VIEWER: a useful tool for developers

The Natura 2000 viewer is an on-line Geographic Information System ( GIS) mapping system that enables developers to locate and explore each Natura 2000 site in the EU Network. The sites can be examined at a very fine scale (1:500) which shows the boundaries of the site and its main landscape features at a very high resolution. For each site, a Standard Data Form (SDF) is available which lists the species and habitat types for which it was designated, as well as their estimated population size and conservation status on the site, and the importance of that site for the species or habitat types in question within the EU.

http://natura2000.eea.europa.eu/

The protection and conservation of Natura 2000 sites is governed by the provisions of Article 6 of the Habitats Directive. It is divided into two types of measures – the first (governed by Article 6.1 and 6.2) (16) concerns the conservation management of all Natura 2000 sites at all times, whilst the second (governed by Article 6.3 and 6.4) lays down a permitting procedure for plans or projects likely to have a significant negative effect on a Natura 2000 site.

It is clear from this Article that Natura 2000 are not ‘no-go zones' for development’. New plans and projects are entirely possible provided certain procedural and substantive safeguards are respected. The permitting procedure is in place to ensure that such plans and projects are implemented in a way that is compatible with the conservation objectives of the Natura 2000 site.

2.3.1.   Taking positive conservation measures and ensuring non-deterioration

Article 6 of the Habitats Directive:

6.1.

For special areas of conservation, Member States shall establish the necessary conservation measures involving, if need be, appropriate management plans specifically designed for the sites or integrated into other development plans, and appropriate statutory, administrative or contractual measures which correspond to the ecological requirements of the natural habitat types in Annex I and the species in Annex II present on the sites.

6.2.

Member States shall take appropriate steps to avoid, in the special areas of conservation, the deterioration of natural habitats and the habitats of species as well as disturbance of the species for which the areas have been designated, in so far as such disturbance could be significant in relation to the objectives of this Directive.

Articles 6.1 and 6.2 of the habiatts directive require Member States to:

Take positive conservation measures that are necessary to maintain or restore habitat types and species for which the site has been designated (Article 6.1);

Take measures to avoid any deterioration of habitat types or any significant disturbance of the species present (Article 6.2).

In respect of the former, Member States are required to set clear conservation objectives for each Natura 2000 site based on the conservation status and ecological requirements of the habitat types and species of EU interest present. At a minimum, the conservation objective should aim to maintain the conservation condition of species and habitats for which it was designated and not to allow this to deteriorate further.

However, as the overall objective of the Nature Directives is for the species and habitat types to reach a favourable conservation status across their natural range, more ambitious conservation objectives may be necessary to improve their conservation condition in individual sites. Being aware of the conservation objectives for a Natura 2000 site is particularly important for energy transmission developers, planners and authorities since the potential negative effects of the plan or project will need to be assessed against these conservation objectives (17).

Although not obligatory, the Habitats Directive encourages nature authorities to elaborate Natura 2000 management plans in close cooperation with local stakeholders (18). These plans can be a very useful source of information as they usually provide detailed information on the species and habitat types for which the site has been designated, explain the site's conservation objectives and, where appropriate, the relationship with other land-uses in the area. They also outline the practical conservation measures that needed to achieve the site's conservation objectives.

2.3.2.   The permit procedure for plans and projects affecting Natura 2000 sites

Article 6 of the Habitats Directive:

6.3.

Any plan or project not directly connected with or necessary to the management of the site but likely to have a significant effect thereon, either individually or in combination with other plans or projects, shall be subject to appropriate assessment of its implications for the site in view of the site's conservation objectives. In the light of the conclusions of the assessment of the implications for the site and subject to the provisions of paragraph 4, the competent national authorities shall agree to the plan or project only after having ascertained that it will not adversely affect the integrity of the site concerned and, if appro- priate, after having obtained the opinion of the general public.

6.4.

If, in spite of a negative assessment of the implications for the site and in the absence of alternative solutions, a plan or project must nevertheless be carried out for imperative reasons of overriding public interest, including those of a social or economic nature, the Member State shall take all compensatory measures necessary to ensure that the overall coherence of Natura 2000 is protected. It shall inform the Commission of the compensatory measures adopted.

Where the site concerned hosts a priority natural habitat type and/or a priority species, the only considerations which may be raised are those relating to human health or public safety, to beneficial consequences of primary importance for the environment or, further to an opinion from the Commission, to other imperative reasons of overriding public interest.

Articles 6.3 and 6.4 of the Habitats Directive lay down the permit procedure that must be followed when a plan and project is proposed that could affect one or more Natura 2000 site (19). This permit procedure is applicable not just to plans or projects inside a Natura 2000 site but also those that are outside but could have a significant effect on the conservation of species and habitats within the site.

Article 6.3 of the Habitats Directive requires that any plan or project likely to have significant negative effect on a Natura 2000 site undergoes an appropriate assessment (AA) to study these effects in detail, in view of that particular site's conservation objectives. The competent authority can only agree to the plan or project if, based on the findings of the Appropriate Assessment, it has ascertained that it will not have an adverse affect the integrity of the site concerned. It is important to note that the onus is on demonstrating the absence (rather than the presence) of negative impacts.

Depending on the type and severity of the impacts identified, it may sometimes be possible to adjust the plan or project and/or introduce certain mitigation measures to avoid or pre-empt, remove or reduce them to a non-significant level so that the plan or project may be approved.

If this is not the case, then the plan or project must be rejected and alternative less damaging solutions explored instead. In exceptional circumstances, a derogation procedure under Article 6.4 may be invoked to approve a plan or project having an adverse effect on the integrity of one or more Natura 2000 sites, if it can be demonstrated that there is an absence of alternatives and the plan or project is considered to be necessary for imperative reasons of overriding public interest. In such cases, adequate compensation measures will need to be put in place to ensure that the overall coherence of the Natura 2000 network is protected.

Finally, it is important to note that the permit procedure under the Habitats Directive is not the same as that foreseen under the Environmental Impact Assesssment Directive (EIA) and Strategic Environmental Assessment Directive (SEA), even if they may be integrated (see chapter 7 for details). Unlike the EIA/SEA assessments, the result of which needs to be taken into consideration when deciding to approve the plan or project, the conclusions of the Appropriate Assessment are definitive and will determine whether the plan or project can be authorised.

2.4.   Species protection provisions

The second set of provisions of the two EU Nature Directives concerns the protection of certain species across their entire range across the EU, i.e. both within and outside Natura 2000 sites.

Some protected species are potentially vulnerable to certain types of energy infrastructure projects, such as overhead electricity cables. Therefore, these provisions also must be taken into account when considering such plans and projects in potentially sensitive areas outside Natura 2000 sites in the framework of the EIA/SEA procedures

The species protection provisions cover all naturally occurring wild bird species in the EU as well as other species listed in Annex IV and V of the Habitats Directive.

In essence they require Member States to prohibit:

their deliberate disturbance during breeding, rearing, hibernation and migration;

the deterioration or destruction of breeding sites or resting places;

the deliberate destruction of nests or eggs, or the uprooting or destruction of protected plants.

The exact terms are laid down in Article 5 of the Birds Directive and Article 12 (for animals) and Article 13 (for plants) of the Habitats Directive (20).

Article 5 of the Birds Directive:

Without prejudice to Articles 7 and 9, Member States shall take the requisite measures to establish a general system of protection for all species of birds referred to in Article 1, prohibiting in particular:

(a)

deliberate killing or capture by any method;

(b)

deliberate destruction of, or damage to, their nests and eggs or removal of their nests;

(c)

taking their eggs in the wild and keeping these eggs even if empty;

(d)

deliberate disturbance of these birds particularly during the period of breeding and rearing, in so far as disturbance would be significant having regard to the objectives of this Directive;

(e)

keeping birds of species the hunting and capture of which is prohibited;

Article 12 of the Habitats Directive:

1.

Member States shall take the requisite measures to establish a system of strict protection for the animal species listed in Annex IV (a) in their natural range, prohibiting:

(a)

all forms of deliberate capture or killing of specimens of these species in the wild;

(b)

deliberate disturbance of these species, particularly during the period of breeding, rearing, hibernation and migration;

(c)

deliberate destruction or taking of eggs from the wild;

(d)

deterioration or destruction of breeding sites or resting places.

2.

For these species, Member States shall prohibit the keeping, transport and sale or exchange, and offering for sale or exchange, of specimens taken from the wild, except for those taken legally before this Directive is implemented

3.

The prohibition referred to in paragraph 1 (a) and (b) and paragraph 2 shall apply to all stages of life of the animals to which this Article applies

Article 13 of the Habitats Directive

1.

Member States shall take the requisite measures to establish a system of strict protection for the plant species listed in Annex IV (b), prohibiting:

(a)

the deliberate picking, collecting, cutting, uprooting or destruction of such plants in their natural range in the wild;

(b)

the keeping, transport and sale or exchange and offering for sale or exchange of specimens of such species taken in the wild, except for those taken legally before this Directive is implemented.

2.

The prohibitions referred to in paragraph 1 (a) and (b) shall apply to all stages of the biological cycle of the plants to which this Article applies.

Derogations to these provisions are allowed in some circumstances (e.g. to prevent serious damage to crops, livestock, forests, fisheries and water) provided that there is no other satisfactory solution and the consequences of these derogations are not incompatible with the overall aims of the Directives.

The conditions for applying derogations are set out in Article 9 of the Birds Directive and Article 16 of the Habitats Directive. With reference to energy transmission infrastructures, it is primarily reasons related to ‘the interests of public health and public safety’, or ‘other imperative reasons of public interest’ (ref. Article 16(1c)) that might apply.

3.   POTENTIAL IMPACTS OF ENERGY TRANSMISSION FACILITIES ON NATURA 2000 AND EU PROTECTED SPECIES

3.1.   Introduction

Energy infrastructure projects do not usually pose a major threat to biodiversity. There are many cases where well-designed and appropriately sited developments have no or only limited impacts. There are also examples of where projects have delivered net overall benefits for nature, especially in areas where the natural environment is already seriously impoverished. But this does not remove the obligation to examine, under the various legal environment assessment procedures in force such as EIA/SEAs and Appropriate Assessments (see chapter 7 for details), the potential effects that individual plans or projects can have on the natural environment.

This chapter reviews the type of possible impacts that energy infrastructures could have on the habitats and species protected under the Birds and Habitats Directives. It aim to provide developers, energy transmission operators and relevant authorities with an overview of the types of potential impacts to watch out for when preparing an energy transmission infrastructure plans or projects; and when carrying out an Appropriate Assessment under the permitting procedure foreseen in Article 6 of the Habitats Directive or assessment pursuant the EIA/SEA Directives.

3.2.   The need for a case-by-case approach

It must be stressed that the potential effects are very much dependent on the design and location of the specific energy infrastructure in question and on the sensitivity of the EU protected habitats and species present. That is why it is essential to examine each plan or project on a case-by-case basis.

The design of each energy transmission facility project, including PCIs, will depend, of course, on a wide range of factors, including the type and volume of energy being transmitted, the receiving environment (e.g. whether on land or at sea), the distances required for transmission, and the capacity needed for reception or storage. Projects may concern not only the construction, but also for the renovation and/or decommissioning of any one or more of the facilities or infrastructures needed to transmit, receive or store energy on land.

When assessing the potential impacts on nature and wildlife it is important to consider not just the main infrastructure itself, but also all associated installations and facilities such as temporary access roads, contractors facilities and equipment storage, construction compounds, concrete foundations, temporary cabling, spoils and areas for soil surplus etc. The impacts may be temporary or permanent, on-site or off-site, cumulative and may come into play at different times during the project cycle (e.g. during construction, renovation, maintenance and/or decommissioning phases). All these factors must be taken into consideration.

The EU Nature Directives' species protection provisions must to be taken into account where there is a risk that the energy infrastructure plan or project may cause the death or injury, or deliberate disturbance during breeding, rearing, hibernation and migration, or the deterioration or destruction of breeding sites or resting places of species protected under the two Directives (e.g. such as eagles and marine mammals). This strict protection regime applies across the wider countryside, i.e. both inside and outside Natura 2000 sites.

Mitigation measures

The negative impacts mentioned in this chapter can sometimes be effectively mitigated against. Mitigation involves introducing measures into the plan or project to eliminate these potential negative effects or reduce them to a level where they are no longer significant. This means that they must be directly linked to the likely impacts and based on a sound understanding of the species/ habitats concerned.

Mitigation measures can involve a change in location of the project, but they can also involve modifications to the size, design and configuration of various aspects of the energy infrastructure. Or they can take the form of temporal adjustments during the construction and operational phases. Further details, with examples of possible mitigation measures, are given in the next chapter.

3.3.   An overview of potential impacts on EU protected species and habitats

The type and scale of impact is very much dependent on the EU protected species or habitat types present in the site, their ecology, distribution and state of conservation. Hence the need to examine each plan or project individually on a case by case basis. The following is an overview of the most frequent types of impacts that can occur:

3.3.1.   Habitat loss, degradation or fragmentation

Energy transmission infrastructure projects may require the clearance of land and the removal of surface vegetation (often referred to as direct land-take). Through this process existing habitats may be altered, damaged, fragmented or destroyed. The scale of habitat loss and degradation depends on the size, location and design of the project and the sensitivity of the habitats affected.

It is important to note that, whilst the actual land take may seem limited, the indirect effects could be much more widespread, especially where developments interfere with hydrological regimes or geomorphological processes, and water or soil quality. Such indirect effects can cause severe habitat deterioration, fragmentation and loss, sometimes even at quite a distance from the actual project site.

The significance of loss also depends on the rarity and sensitivity of the habitats affected and/or of their importance as a feeding, breeding or hibernating place for species. Also, the potential role of some habitats as components of corridors or stepping stones important for dispersal and migration, as well as for more local movements between e.g. feeding and nesting sites, needs to be considered when assessing the significance of any habitat loss or degradation.

3.3.2.   Disturbance and displacement

Disturbance of species in their habitual breeding, feeding or resting sites, as well as along migration routes, can lead to displacement and exclusion, and hence loss of habitat use. The species may be displaced from areas within and around the project site due for instance to increased traffic, presence of people as well as noise, dust, pollution, artificial lighting or vibration caused during or after the construction works.

The scale and degree of disturbance, and the sensitivity of the species affected, determines the significance of the impact, as does the availability and quality of other suitable habitats nearby that can accommodate the displaced animals. In the case of rare and endangered species even small or temporary disturbances can have serious repercussions for their long term survival in the region.

3.3.3.   Collision and electrocution risk

Birds, and possibly bats, may collide with various parts of electricity overhead powerlines and other above-ground electrical facilities. The level of collision risk depends very much on site location and on the species present, as well as on weather and visibility factors and the specific design of the powerlines themselves (especially in the case of electrocution). Species that are long-lived, have low reproductive rates and/or that are rare or are already in a vulnerable conservation state (such as eagles, vultures and storks) may be particularly at risk.

The risk of collision and electrocution of birds is examined further in the chapters 4 and 5. As for bats, there is unfortunately a general lack of studies on the potential risks and impacts of collision with overhead power lines, due to the difficulties in monitoring the death of small animals along such long linear infrastructures.

3.3.4.   Barrier effects

In the case of electricity, large transmission, receiving and storage infrastructures may force species to bypass the area altogether, both during migrations and, more locally, during regular foraging activities. Whether or not this is a problem depends on a range of factors such as the size of the sub-station, the spacing and routing of electricity cables, the extent of displacement of species and their ability to compensate for increased energy expenditure as well as the degree of disruption caused to linkages between feeding, roosting and breeding sites.

New emerging evidences that animals could be scared away from power cables because these give off UV flashes invisible to humans were reported by several scientific teams. A study (21) inspired by observations that reindeers avoid power lines running across the Arctic tundra was carried out by international team of researchers. Although the knowledge is still very limited in some particular cases this type of avoidance and fragmentation is relevant when establishing the significance of the impact.

3.4.   Distinguishing between significant and insignificant effects

Identifying the species and habitats that are likely to be affected by an energy transmission infrastructure plan or project is the first step of any impact assessment, be it undertaken under Article 6 of the Habitats Directive, if the project affects a Natura 2000 site, or under the EIA or SEA Directive if it affects protected species outside the Natura 2000 network. After that, it is necessary to determine whether the impact is significant or not. The legal procedure for determining ‘significance’ for plans or projects specifically affecting Natura 2000 sites are described in chapter 7. Here, some of the general principles involved in determining the level of ‘significance’ in the case of wildlife (irrespective of whether it is in a Natura 2000 site or not) are briefly explained to help with the overall understanding of this concept.

The assessment of significance needs to be done on a case-by-case basis and in light of the species and habitats potentially affected. The loss of a few individuals may be insignificant for some species but may have serious consequences for others. Population size, distribution, range, reproductive strategy and life-span will all influence the significance of the effects. This is likely to vary from one site to another.

The interconnectivity of effects is also to be taken into account, for instance land take on its own may not be significant for a particular species, but when combined with major disturbance or displacement risks, it may reduce the fitness, and ultimately the survival rate, of that species to a significant level.

The assessment of significance needs also to be considered over an appropriate geographical scale. For migratory species that travel over long distances, the impact at a specific site may have consequences for the species over a much larger geographical area. Likewise, for resident species with large territories or changing habitat uses, it may still be necessary to consider potential impacts on a regional, rather than a local scale.

Finally, the considerations above should be based on the best available data. This may require dedicated field surveys or monitoring programmes some time in advance of the project.

3.5.   Cumulative effects

Assessments of cumulative effects should also be taken into consideration when determining the impacts on Natura 2000 sites, as required by art 6.3 of the habitats directive. The cumulative effects of plans and projects can often be very important and need to be assessed carefully. They may arise when several energy infrastructures are present within an area or along a flyway corridor, or when an energy infrastructure project takes place in the same area as another type of plan or project (e.g. other industrial developments). The cumulative effect is the combined effect of all these activities taken together. It may be that one energy infrastructure project, on its own, will not have a significant effect, but if its effects are added to those of other plans or projects in the area their combined impacts could become significant.

For instance, an oil pipeline project that traverses part of a wetland may give rise to a small but acceptable level of temporary habitat degradation, which lies well within the capacity of that habitat to accommodate. But, if the wetland is also subjected to a land drainage scheme and/or a road construction project, the hydrological effects of all these projects, taken together, could lead to its permanent loss, fragmentation or desiccation. In this case, whereas the impact of the first and second projects, each on their own, is not discernible, the impact of both taken together could be significant. This influences the planning decision for both project proposals.

Cumulative impacts need to be taken into considerations also under the EIA/SEA procedures.

Because energy infrastructure developments are proceeding at a fast pace across the EU, it is therefore important that cumulative effects are assessed already in the early stages of an environmental assessment rather than merely as an ‘afterthought’ at the end of the process and thus delaying the decisions on the compatibility of the project proposals with the provisions of the EU legislation.

4.   POTENTIAL IMPACTS OF ELECTRIC GRID INFRASTRUCTURES ON WILD BIRDS

4.1.   Introduction

The previous chapter provided a general overview of the types of potential effects to look out for when developing energy infrastructure projects, particularly in and around Natura 2000 sites and in the vicinity of other sensitive areas used by species that are protected under the two EU nature Directives.

This chapter concentrates on analysing the potential effects of electricity infrastructure on wild European birds in particular. This is a subject that has received a lot of attention in recent years and one where the effects may be more frequent and more significant than for other types of terrestrial energy infrastructures.

4.2.   Electric grid infrastructures

Unlike other commodities, electricity cannot be stored, so it needs to be produced and transported to the users in real-time. The electrical transmission system is consequently more complex and dynamic than other utility systems, such as water or natural gas. Once electricity has been generated at a power facility, high-voltage (110 - 750 kV in Europe, ENTSO, 2012) transmission lines carry large amounts of electricity across long distances to substations. From substations medium-voltage (1 – 60 kV) and low-voltage (1 kV >) distribution power lines carry electricity to residential and business consumers.

Figure 3

Image

(USDA, 2009)

The electricity system is highly meshed. The transmission grid includes not only transmission lines that run from power plants to load centres, but also from transmission line to transmission line, providing a system that helps ensure the smooth flow of power. If a transmission line is taken out of service in one part of the power grid, the power is normally rerouted to other power lines so that it can continue to be delivered to the customer (PSCW, 2009).

Electrical power may be transmitted through overhead lines or underground cables, using alternating or direct current. In all cases, the voltages are high because they provide greater efficiency over long distances (typically greater than 600 km). Overhead lines with alternating currents (AC lines) are the traditional way to transmit electrical energy (EASAC, 2009).

The advantages of overhead lines over underground cables are that, so far, the costs of building overhead lines have been significantly less than installing underground cables, and their capacity has been higher. The expected lifetime of overhead lines is high and can be up to 70 or 80 years. The main drawbacks of overhead lines are their use of land, their visual and different environmental impacts (EASAC, 2009) (22).

Transmission line structures support at least one three-phase circuit. They have three energized conductors (more if bundled), and may have one or two grounded conductors (usually referred to as static wires) installed above the phase conductors for lightning protection. Distribution line structures may support a variety of conductor configurations (APLIC, 2006).

Most AC commercial overhead power lines utilize some form of support structure from which insulators and electrical conductors are attached. Support structures may consist of wood poles, hollow or lattice steel structures, steel-reinforced concrete poles, or composite poles made from fiberglass or other materials. Insulators are made of porcelain or polymer materials that do not normally conduct electricity. Electrical conductors are usually manufactured from copper or aluminium (Bayle, 1999, Janss, 2000, APLIC, 2006).

Three-phase systems are used for both distribution and transmission lines. One of the primary benefits of three-phase systems is the ability to deliver large amounts of power over long distances (APLIC, 2006).

4.3.   Potential negative impacts of electricity infrastructure on wild birds

The following provides an overview of the main types of impacts on wild bird species. Some protected European species are clearly more vulnerable to certain types of impacts – especially from electrocution and collision – due to their size, morphology, behaviour and distribution.

The table in Annex 2 presents a systematic prioritised list of impacts of bird populations/power line interactions (Birdlife, 2013). This table does not imply that these impacts will occur as described in all circumstances. Much will depend on the particular species and particular circumstances surrounding each individual case and on the availability of corrective measures for their mitigation.

Why are some bird species more vulnerable to power lines than others?

This is often due to the following physiological, behavioural and ecological features:

Large body size;

Poor frontal vision;

Preference for nocturnal activity;

‘Poor fliers’, less manoeuvrable birds (collision);

Inexperienced flyers, young birds (electrocution and collision);

Preference for elevated places for roosting, perching or nesting;

Preference for treeless, open habitats (electrocution);

Flocking and gregarious behaviour;

Species susceptible to disturbance;

Preference for low altitude habitats (i.e. in relation to higher density of electric grid);

Rare and threatened species (coupling with low density, low-fecundity etc., see below);

Low density species (with lower replacement potential);

Species with low reproductive potential (through the increase in adult mortality it takes more time to recover from population losses);

Species with low-fecundity, low mortality, long life expectancy (through decrease in recruitment potential during constant population loss)

Long-distant intercontinental migrants (large spatial scale and very different level of mitigation of power line impacts).

4.3.1.   Electrocution

Electrocution can have a major impact on several bird species, and causing the death of thousands of birds annually (23). Electrocution may take place when a bird touches the two phase conductors or one conductor and an earthed device simultaneously, especially when the feathers are wet (Bevanger, 1998). Species that are particularly frequently affected by electrocution include Ciconiiformes; Falconiformes, Strigiformes and Passeriformes (Bevanger, 1998) – see table below.

There is a strong consensus that the risk posed to birds depends on the technical construction and detailed design of power facilities. In particular, electrocution risk is high with ‘badly engineered’ medium voltage power poles (‘killer poles’) (BirdLife International, 2007).

Factors influencing the likelihood of bird electrocution include the following:

Bird morphology: Large birds are more vulnerable because the likelihood of spanning electrical components with out - stretched wings or other body parts is higher than for small birds (Olendorff et al., 1981; APLIC, 2006).

Bird behaviour: Birds that use power poles to perch, roost and nest on are more vulnerable (Bevanger, 1998). Ground-nesting species (harriers and some owls) appear to infrequently get electrocuted because they typically hunt while in flight and perch on or near the ground (Benson, 1981).

Pole type and configuration:

Most casualties occur at power poles of medium voltage distribution lines (1kV to 60 kV), which is due to the close spacing of the different parts (Haas & Nipkow, 2006).

Poles with a special function (strain poles, transposition poles, junction poles or transformer units) take much more victims than simple tangent structures (Demeter et al., 2004).

López-López and his colleagues (2011) demonstrated that bird casualties could have been dramatically reduced by retrofitting dangerous, poorly-designed poles.

Environmental factors:

Prey abundance: the number of electrocuted raptors increases as the number of prey animals increases (Benson, 1981; Guil et al., 2011).

Vegetation structure and coverage: vegetation structure may affect prey availability and the predator foraging performance (Guil et al., 2011).

Habitat: birds more often use and get electrocuted on power poles in areas where places to perch are rare, e.g. grasslands, wetlands (Haas et al., 2005; Lehman et al., 2007).

Topography: In the case of electrocution, topography affects where birds will perch and roost, and vegetation height affects the availability of natural perches in the area. The mortality rates for eagles increased with slope, possibly due to the habit of hunting from perches. Studies have demonstrated that pylons located in dominant sites, surrounded by high slopes tend to produce higher electrocution rates. (Guil et al., 2011)

Sex: Within the same species females bigger in size are more threatened by electrocution (Ferrer & Hiraldo, 1992).

Age: Juvenile and immature birds are more prone to electrocution than adults. This is likely to be due to that lack of experience in landing and taking off (Benson, 1981; Harness, 1997; Bevanger, 1998; Harness & Wilson, 2001; Janss & Ferrer, 2001; González et al., 2007).

Spatial: In certain key areas for birds electrocution rate is higher than in low density areas (e.g. high density breding areas, dispersal zones, congregation sites, bottleneck areas) (González et al., 2006; Cadahia et al., 2010).

Seasonal: Most casualties are reported from late summer, from the period of fledging or post-fledging. Large eagles are more threatened in autumn and winter maybe because of the feather wetting during inclement weather (rain, snow), which is extremely important to electrocution risk. (Benson, 1981; Bevanger, 1998; Lasch et al., 2010; Manville, 2005; Lehman et al., 2007)

Direction of the prevailing wind relative to the crossarm also may contribute to raptor electrocutions. It is suspected that poles with crossarms perpendicular to the prevailing winds produced fewer eagle mortalities than those with crossarms diagonal or parallel to the wind, because of difficulties associated with crosswind take-offs and landings. (Nelson and Nelson (1976))

The following table provides an overview of European bird families that have been identified as vulnerable to electrocution and/ or collision (Birdlife, 2013).

Table 1

Severity of impacts on bird populations of mortality due to electrocution and collision with power lines for different bird families in Eurasia

Bird families in Eurasia identified as vulnerable to electrocution and collision internationally

Casualties due to electrocution

Casualties due to collision

Loons (Gaviidae) and Grebes (Podicipedidae)

0

II

Shearwaters, Petrels (Procellariidae)

0

II

Boobies, Gannets (Sulidae)

0

I

Pelicans (Pelicanidae)

I

II-III

Cormorants (Phalacrocoracidae)

I

I

Herons, Bitterns (Ardeidae)

I

II

Storks (Ciconidae)

III

II

Ibisses (Threskiornithidae)

I

II

Flamingos (Phoenicopteridae)

0

II

Ducks, Geese, Swans, Mergansers (Anatidae)

0

II

Raptors (Accipitriformes and Falconiformes)

II-III

I-II

Partridges, Quails, Grouse (Galliformes)

0

II-III

Rails, Gallinules, Coots (Rallidae)

0

II

Cranes (Gruidae)

0

III

Bustards (Otidae)

0

III

Shorebirds/Waders (Charadriidae + Scolopacidae)

I

II-III

Skuas (Sterkorariidae) and Gulls (Laridae)

I

II

Terns (Sternidae)

0-I

I-II

Auks (Alcidae)

0

I

Sandgrouse (Pteroclididae)

0

II

Pigeons, Doves (Columbidae)

I-II

II

Cuckoos (Cuculidae)

0

I-II

Owls (Strigiformes)

II-III

II

Nightjars (Caprimulgidae) and Swifts (Apodidae)

0

I-II

Hoopoes (Upudidae) and Kingfishers (Alcedinidae)

I

I-II

Bee-eaters (Meropidae)

0-I

I-II

Rollers (Coraciidae)

I-II

I-II

Woodpeckers (Picidae)

I

I-II

Ravens, Crows, Jays (Corvidae)

II

I-II

Medium-sized and small songbirds (Passeriformes)

I

I-II

0= no casualties reported or likely;

I= casualties reported, but no apparent threat to the bird population;

II= regionally or locally high casualties, but with no significant impact on the overall species population;

III= casualties are a major mortality factor, threatening a species with extinction, regionally or at a larger scale.

4.3.2.   Collision

Collisions with power lines cause the death of millions of birds worldwide and can cause high mortality in some species of birds (Bevanger 1994, 1998; Janss 2000; APLIC, 2006; Drewitt & Langston, 2008; Jenkins et al., 2010; Martin, 2011; Prinsen et al., 2011). Empirical data and theoretical considerations indicate that species with high wing loading and low aspect run a high risk of colliding with power lines. These birds are characterised by rapid flight, and the combination of heavy body and small wings restricts swift reactions to unexpected obstacles (Bevanger, 1998). When the number of reported collision victims is considered relative to the abundance and population size of the species concerned, some Galliformes, Gruiformes, Pelecaniformes and Ciconiiformes species seem to be affected in disproportionately high numbers (Bevanger, 1998) - see Table 1.

Factors influencing collision include the following:

Bird morphology: Birds with a high body mass and relatively short wings and tails, described as ‘poor fliers’, are at greatest risk of collision (Bevanger, 1998; Janss, 2000).

Bird physiology: Certain bird species are at least temporarily blind in the direction of travel (Martin, 2011).

Bird behaviour:

Flocking behaviour, with species making daily flock movements across power lines to and from feeding, nesting, and roosting areas being particularly vulnerable (Janss, 2000).

Bird species that regularly fly low at night or in twilight are more susceptible to collision than species that mostly fly during the day.

Other factors such as weather conditions, line configuration, routing of lines, habitat use, vegetation along lines, topography, disturbance, choice of migration routes and stopover sites should also be taken into considerations

Bird electrocution and collision cause economic losses

Bird-caused outages reduce power reliability and increase power delivery costs. Some outages may impact only a few customers temporarily, yet they can still affect a utility's service reliability and customer guarantees. Larger outages can have dramatic consequences and may cause significant economic loss at utility companies and at consumers (APLIC, 2006).

Costs associated with bird-related outages include those related to:

Lost revenue,

Power restoration,

Equipment repair,

Nest removal and other animal damage-control measures,

Administrative and managerial time,

Lost service to customers and negative public perception, and

Reduced electrical system reliability (APLIC, 2006).

4.3.3.   Habitat loss and fragmentation

The open rights-of-way corridors along power lines can fragment forests and other natural habitats. Power lines can also result in habitat loss through causing accidental forest fire (Rich et al., 1994). Whilst the actual land take from electricity infrastructure may be relatively small, it can nevertheless be significant if that loss takes place in a core habitat for a particular species, or if there are cumulative effects resulting for other projects in the same area and must therefore be examined on a case by case basis.

4.3.4.   Disturbance/Displacement

During the construction phase and during the maintenance of power lines, some habitat destruction and alteration inevitably takes place (van Rooyen, 2004; McCann, 2005). Above-ground power lines can lead to the loss of useable feeding areas in breeding places as well as in staging and wintering habitats. For example recent studies showed that the presence of a power line influenced the flight direction of Great Bustards and restricted the use of suitable habitats (Raab et al., 2010), and that transmission power lines are avoided by Little Bustards, being the most important factor determining breeding densities in sites with suitable habitat for the species (Silva, 2010; Silva et al., 2010).

4.3.5.   Electromagnetic fields

All electrical currents, including those running through power lines, generate electro-magnetic fields (EMFs). Therefore, many bird species, like humans, are exposed to EMFs throughout their lives (Fernie and Reynolds, 2005). A great deal of research and controversy exists as to whether or not exposure to EMFs affects the cellular, endocrine, immune, and reproductive systems of vertebrates. The research examining the effects of EMFs on birds indicate that EMF exposure of birds generally changes, but not always consistently, their behaviour, reproductive success, growth and development, physiology and endocrinology, and oxidative stress (Fernie, 2000; Fernie and Reynolds, 2005).

4.4.   Potential positive effects of electricity infrastructure on wild birds

Electrical power lines, towers, and distribution poles can have a number of beneficial effects for wild bird species too. For instance they may offer:

Breeding substrate, nest site: There are a variety of reasons why birds sometimes breed on electricity structures including: lack of alternative nesting sites such as trees and cliffs; electricity structures offer a mammalian-predator-safe and sturdy platform for birds to build their nests (van Rooyen, 2004; McCann, 2005). Utility structures can provide nesting substrates in habitats where natural elements are scarce, and offer some protection thereby facilitating the range expansion of some species or increasing the local density of some species, (APLIC, 2006).

Perching, roosting and hunting post: Vultures and storks often seek power line structures for roosting since they are more protected from harsh weather and ground predators. The presence of electric poles in open-country habitats is beneficial to some raptors by providing perches with commanding views of hunting areas. Power line structures in relatively treeless areas have made millions of kilometres of suitable habitat available to perch-hunting raptors (Olendoff et al., 1980).

Habitat management: Power lines can also provide continuous habitat for species that require low vegetation. Research undertaken in the United States has shown that open rights-of-way along utility lines provide habitat for declining species of birds (Confer & Pascoe, 2003; Askins, 2012).

ELIA / RTE LIFE+ project: bringing benefits to nature (24)

Image

ELIA (high-voltage electricity transmission system operator in Belgium), and RTE (electricity transmission system operator in France) led a 5-year project (2011-2017) to manage and restore over 300 hectares under medium and high-voltage overhead power lines in Wallonia and in France.

This project illustrates nature conservation measures, and how energy stakeholders may take infrastructure development as an opportunity to benefit biodiversity.

Ponds (objective: 100 ponds on the 130 km project area)

Wherever the soil is appropriate (presence of an impermeable layer: peat, white clay and gleyed clay soils) and primarily in the areas which offer good potential for certain rare species, ponds were dug or dams constructed on drainage channels to flood areas of at least 25 m2 (minimum size to limit the silting process, i.e. natural filling of ponds by leaves). The network of intra-forest ponds will enable the colonisation of amphibians, dragonflies, damselflies, Dytiscidae and wetland birds and prevent populations from becoming isolated.

Orchards (objective: 20 ha with 8 000 trees)

A number of very rare and local species of fruit trees, mainly European Wild Pear (Pyrus pyraster), European wild apple (Malus sylvestris) and common medlar (Mespilus germanica), small-sized species, were planted under overhead power lines. Their presence brings diversity to the forest stands and also shelter and food to a whole range of local fauna (large animals, birds and insects).

Simple flower meadows (objective: 20 ha)

Simple flower meadows have been recreated on the access routes for the high-voltage power lines serving as refuge for rare flora, insects, birds and small mammals. Regular mowing and removal of the mowed vegetation will impoverish the soil and allow rare or lost plants to reappear. In extreme cases, flower meadows were recreated by sowing seeds from local plant varieties

Peatlands and moors (objective: restore or appropriately manage 20 additional hectares)

The restoration of wetlands and moors under power lines is possible through removing the uppermost layer of soil, promoting the development of pioneer species from the underlying dormant seed bank. In some of the areas the water level was also locally restored by sealing drains, revitalising wet moorlands and peatlands. The objective is to maintain and improve exchanges of plants and animals between existing peatlands and moors, including those recently restored.

Pasturing (objective: manage 20 ha through pasturing and 20 ha through mowing)

Pasturing supported the restoration of damaged peatlands, moors, sparse meadows and valley bottoms, helping solving the problem of dominant species such as moor grass. In other cases (hay meadows, dry moors, sparse meadows), mowing (through contracts with local farmers), adapted in terms of periods and rhythm, helped maintaining the vegetation at the right level for a multitude of plant, insect and reptile species.

Invasive species (objective: treat 20 to 30 ha)

Under the project the growth of plant species on the Walloon list of invasive species was eradicated or brought under control, in particular, the black cherry (Prunus serotina), the summer lilac (Buddleja davidii), the giant hogweed (Heracleum mantegazzianum), the Himalayan balsam (Impatiens glandulifera), the Japanese knotweed (Fallopia japonica), the narrow-leaved ragwort (Senecio inaequidens) and, to a certain extent, the black locust (Robinia pseudoacacia).

Fragmentation (objective: create edges on 30 km (90 ha) and restore 40 km (120 ha))

Currently, in the work areas of the project, the power line corridors created in forests are mainly U-shaped: at the centre is short grass, regularly cut, with an abrupt transition to the forest with tall trees on both sides. The project created V-shaped edge areas between the corridor and the forest.

These edges, with sizable trees from a variety of species, as ecotones, may provide food and shelter habitat for a whole range of insect, mammal and bird species which are absent in the corridors where the surrounding areas are ‘clean’ and regularly maintained. The forest is enriched with secondary tree species that are often absent. These edges also reduce the damage that the wind can cause to the forest stand, creating a slope. These edges can also be very rich in deadwood, providing shelter for a huge number of insects and offering useful habitats for birds and bats. Once the density of these edges has increased, the growth of tall trees (birch, spruce, beech) that constitute a danger to the lines slows down.

Image

Initial situation and situation after the project

5.   POTENTIAL MITIGATION MEASURES FOR ELECTRIC GRID INFRASTRUCTURES AFFECTING WILD BIRDS

5.1.   What are mitigation measures?

When the assessment of an energy infrastructure plan or project undertaken under Article 6 of the Habitats Directive identifies a number of negative effects on a Natura 2000 site, the plan or project is not automatically rejected. Depending on the severity of the potential impacts, it may be possible to introduce mitigation measures that will remove, pre-empt, or reduce to an insignificant level the potential negative impacts of a plan or project.

While this chapter is focusing on the Natura 2000 sites, measures that reduce the negative impacts should also be envisaged under EIA/SEA for plans and projects for which there is no need to undergo appropriate assessments but would have a negative impact on protected species.

In order to decide which mitigation measures are required, it is essential first to assess the effects of the plan or project on the EU protected species and habitat types present in the Natura 2000 site (alone or in combination with other projects or plans). This will identify the nature and extent of the negative effects and provide a baseline against which to determine the type of mitigation measures required.

In short, effective mitigation of adverse effects on Natura 2000 sites can only take place once the potential negative effects have been fully recognised, assessed and reported. The identification of mitigation measures, like the impact assessment itself, must be based on a sound understanding of the species/ habitats concerned.

Mitigation measures can involve modifications to the size, location, design and configuration of various aspects of the energy infrastructure plan or project (e.g. insulate the conductors to avoid electrocution). Or they can take the form of temporal adjustments during the construction and operational phases (e.g. avoiding construction works during the breeding season).

Once suitable mitigation measures have been identified and worked out in detail, the plan or project can be approved under the Article 6 Habitats Directive procedure on condition that these mitigation measures are implemented in accordance with the instructions given by the competent authority.

Figure 4

Hierarchical approach to adopting mitigation measures. Mitigation should always aspire to the top of the mitigation hierarchy (i.e. avoiding impacts at source)

Approach to mitigation

Preference

Avoid impacts at source

Highest

Image

Reduce impacts at source

Abate impacts on site

Abate impacts at receptor

Lowest

If there is still a significant residual effect on the site, even after the introduction of mitigation measures, then alternative solutions will need to be examined instead (e.g. different location of the project, different scales or designs of development, or alternative processes). If these do not exist then the plan or project may still be approved, in exceptional cases, provided that the conditions of Article 6.4 are respected and suitable compensation measures are approved that will compensate for the remaining negative effects (see chapter 7 for details) so that the Natura 2000 network is not compromised.

For each mitigation measure proposed it is important to:

explain how the measures will avoid or reduce to a non significant level the identified adverse impacts on the site;

provide evidence of how they will be secured and implemented and by whom;

provide evidence of the degree of confidence in their likely success;

provide a timescale, relative to the project or plan, when they will be implemented;

provide evidence of how the measures will be monitored and how additional measures will be introduced if the mitigation proves not to be sufficient.

EcoMOL project (Ecological Management of Overhead Lines) (25)

As part of the German project ‘Southwest Interconnecting Line / Thuringian Power Link’, a study was undertaken (Erfurt University of Applied Sciences et al. 2010) which presents an interdisciplinary concept for the ecological management of overhead power line corridors (EcoMOL). This could be adapted and applied to various European regions.

The study recognises that operators have technical requirements, such as safety distances and construction work, in order to guarantee the transmission reliability for a high voltage overhead power line corridor. It gives methods to mitigate impacts such as habitat loss and degradation during construction and to implement compensation measures. It classifies biotope types of the corridor by growth height classes, derived from the natural growth characteristics of the species and possibly modified by management. Therefore, during line routing, the study distinguishes the corridor into areas not forested in the future, areas forested for the time being, and areas without felling requirements.

The combination of felling priority and current and potential growth height zones defines the range for possible creation or restoration measures. Detailed planning should be conducted separately for each of the three forest edge components (fringe, sheltering belt and low-density windbreak) differentiated by growth height

Figure 5

Ideally staggered composition of an outer forest edge along the OL corridor (FVA, 1996 modified) showing a schematic pilot

Image

5.2.   Potential measures to mitigate negative effects of electricity plans or projects on wild bird species

The remainder of this chapter looks at the range of potential mitigation measures that can be used for electricity infrastructure plans and projects in relation to wild bird species in particular. Mitigation measures can be introduced at the level of a plan or at various stages in the project cycle.

5.2.1.   Introducing proactive measures at the planning level

A range of measures can be introduced early on in the decision making process, especially at the initial planning stage to pre-empt, avoid or reduce the risk of potential impacts on Natura 2000 sites and on wild bird species. These may include the following:

Legislation

Create and endorse specific national legislative tools or amend existing ones in order to ensure that:

Birds are protected from the negative effects of power lines (eg through the obligation to use underground cables in sensitive areas),

New and fully reconstructed power lines are safe for birds by design and do not need further modification or retrofitting,

Retrofitting of existing power lines and especially ‘killer’ power poles is accomplished in a foreseeable time scale.

Planning

Use the Appropriate Assessment/SEA of national power line infrastructure development plans to ensure that Natura 2000, and wild bird conservation considerations and priorities, are fully taken into account early on in the decision making process and,

Wherever possible, adjust the plans to avoid sensitive Natura 2000 sites and other sites of importance for the bird species listed in chapter 4.

Identify particularly sensitive bird species based on their vulnerability to power lines, conservation status, population size and distribution within the country

Identify priority areas and sites based on the distribution, density and abundance of priority bird species and the existing and planned infrastructure and prepare a national sensitivity map to identify conflict hotspots and other priority (high-risk) sites for prevention and mitigation measures

Prioritise powerlines for mitigation in function of bird mortality and distribution data.

Avoid priority areas and sites (breeding and wintering areas, migration bottlenecks, breeding colonies, congregation sites, coast lines, wetlands) when possible during infrastructure planning/routing.

Produce guidelines for technical solutions to mitigate bird strikes or electrocution hazard (for example Haas et al. 2005, Haas & Nikow, 2006, Prinsen et al., 2011).

Conduct prior evaluation of the potential effectiveness of planned preventive and reactive strategies, to ensure management interventions are evidence-based.

Set up an implementation plan for mitigation measures.

Establish a national database and GIS for managing data of bird/power lines interactions and for adequate spatial planning including optimal routing of power lines based on ecological, technical and economic criteria.

Monitoring, research, evaluation and reporting progress of implementation

Assess progress against objectives, milestones and timeframe of strategic plans.

Evaluate lessons learnt to improve the future operation.

Prepare implementation reports for key stakeholders.

Support international exchange of experience.

Collaborate in efforts to save threatened long-distance migratory birds from the negative effects of power lines.

Initiate and support relevant research projects regarding prevention and mitigation measures and the development and production of bird-safety products.

Develop a set of monitoring protocols standardised for different conditions.

A proposed general concept of area and site prioritisation

There are a number of steps that national authorities can follow to prioritise areas where electricity power line safety measures need be taken into account as priority. The general principle behind this approach is that areas holding or supporting the larger number of priority species as well as significant part of the populations of such species should be favoured for selection as national priorities for prevention and mitigation.

Both designated and non-designated areas and sites have to be prioritised according to their importance (temporal or permanent density & abundance) for priority species as High, Medium and Low priority areas.

Area's level of priority

Type of site

HIGH PRIORITY AREAS

Importance: International

(For example:

Special Protection Areas (SPAs which have a specific function to provide resting area for an internationally significant number of vulnerable species)

sites under IBA categories - Global: A1, A4i-iv; European: B1i-iv,B2; EU: C1, C2, C3, C4, C5, C6;)

Conflict hotspots for several priority species with the high species densities, such as

Key breeding areas for ‘source’ populations of several priority species

Congregations,

Key stopover sites,

Key roosting areas,

Key wintering areas,

Bottleneck areas,

Key migration routes,

Key flyways between roost sites and foraging areas.

MEDIUM PRIORITY AREAS

Importance: National

Nationally important areas for one or few priority species.

Core breeding areas and source populations of several priority species,

The most important temporary settlement areas,

Nationally important congregation sites.

LOW PRIORITY AREAS

Importance: Regional or Local

Regionally or locally important areas for priority and for non-priority species.

Agreement on the Conservation of African-Eurasian Migratory Waterbirds AEWA guidelines on how to avoid or mitigate impacts of electricity grids

The ‘Guidelines on how to avoid or mitigate impact of electricity power grids on migratory birds in the African-Eurasian region’ adopted in 2012 by AEWA recommend seven essential steps (Prinsen et al. 2012):

 

Step 1: Develop and support strategic long term planning of nationwide electricity grid networks, including putting low to medium voltage power lines below ground. Apply appropriate SEA procedures for decisions on the need of power lines on a national scale and apply similar appropriate EIA procedures on the construction of a power line once it has been decided that such a power line is needed. Aspects of the risk for bird collision and electrocution have to be integrated into the EIA procedures.

 

Step 2: Develop and support collaboration between all stakeholders (utility companies, conservationists, governmental organisations) through support of Memoranda of Understanding on a volunteer basis, for example, or, if necessary, impose the cooperation of utility companies for strategic planning and mitigation of negative effects on birds through legislation.

 

Step 3: Develop scientifically based databases and spatial datasets on the presence of protected areas and other key bird areas and presence of susceptible bird species, including flight routes of these species between breeding, feeding and resting areas as well as important migration corridors. These datasets enhance strategic planning in steps 1 and 2 and define priorities in step 4. If no data are available, such as from regular national bird monitoring projects, then field data must be collected for a minimum of one year.

 

Step 4: Routing new above ground power lines away from key areas for birds, taking into account the presence of protected areas (with either a national or international status), abiotic factors that influence the bird/power line conflicts and the susceptibility of relevant bird species.

 

Step 5: Develop priority lists of key conservation areas and species in order to identify priorities for mitigating sections of new power lines and retrofitting existing power lines.

 

Step 6: Mitigate problematic sections of power lines, both existing and planned, to minimise the effects of electrocution and collisions on birds by using state-of-the-art techniques.

 

Step 7: Develop and support evaluation programs that use standardised protocols to monitor the effectiveness of mitigation measures as well as to improve mitigation techniques, including monitoring of incidents (electrocution and collision) and the presence and movements of birds in order to assess the (species-specific) scale of impact.’

5.2.2.   Investigating potential mitigation and preventive measures at the project-level

At the project level, it is recommended that the following aspects be taken into consideration during the Appropriate Assessment or when carrying out an impact assessment under EIA for projects that may affect protected species outside Natura 2000 (ref Article 5 of the Birds Directive and Article 12 of the Habitats Directive).

Phase I. Pre-construction

Investigate different options of mitigation of bird/power line conflict in the EIA/AA of new power lines and of line reconstructions.

Plan avian-safe solutions (underground cable, plastic-covered conductor ‘PAS cable’) in transmission and distribution lines where technically and financially feasible, but especially in areas of high relevance to birds.

Ensure that new overhead power lines are safe for birds by design.

Cluster lines together.

Site lines away from obvious flyways, roosting areas or other areas of concentration of birds if possible.

Plan vegetation, topography, or man-made structures to shield lines.

Plan Before-After Control-Impact (BACI) assessment and supporting monitoring.

Replace reactive, per pole responses, where poles are retrofitted or overhead wires modified after bird death findings, by a structured, pro-active program to avoid most mortalities before they occur.

Phase II. Construction of new lines

Ensure that fully reconstructed lines are safe for birds by design (e.g. underground cable, plastic-covered sheathed cable (PAS cable), pole heads safe by design).

Avoid pole design with pin-insulators on new overhead lines.

Use poles with suspended insulators.

Avoid using neutral (ground) cable above conductor cables when possible.

Phase III. Operation - maintenance, modernisation, re-construction, retrofitting of existing lines

Ensure that fully reconstructed lines are safe for birds by design (e.g. underground cable, plastic-covered PAS cable, pole heads safe by design).

Ensure that priority power lines in term of bird conservation/distribution and the most dangerous pole types in all lines are retrofitted/changed to bird-friendly lines and pole types with state-of-the-art technical standards for bird safety.

Conduct standardised monitoring of the impacts of power lines on birds and monitoring to evaluate the effectiveness of mitigation measures.

Enhance habitats for mitigation of the impact of power lines on biodiversity.

Create habitats on the same side of the power line to minimize crossings.

Minimize human activities/disturbance near the line (educational process).

Prepare report regularly on the results of monitoring and mitigation activities and share it with key stakeholders.

Phase IV. Decommissioning

Ensure that no infrastructure is left along the path of power lines.

Ensure habitat integrity along the path of former power lines.

5.3.   Detailed technical recommendations for remedial and mitigation measures

To ensure avian safe electricity transmission and distribution facilities, the following mitigation measures and technical parameters are recommended:

5.3.1.   Mitigation of electrocution

Principles of mitigation

1.

Replace steel power poles with less hazardous concrete or wooden poles.

2.

Because temporary insulation materials erode and retrofitted pylons may deteriorate to lethal structures over time, the use of safer pylon designs (for example with suspension insulators and with distances over the sufficient minimum safety spacing, see below) have to be given priority over temporary solutions.

3.

Replace pin insulators with hanging insulators or retrofit pin insulators with the latest generation of insulating cover in the sufficient length.

4.

Ensure that there is sufficient spacing between different conductors and between conductors and grounded wires or hardware.

5.

Ensure that distances between conductors are not less than 1 400 mm.

6.

Ensure that distances between perch sites (cross-arm, pole top) and energised elements are not less than 600 mm.

7.

Discourage birds from perching in unsafe locations.

Recommended mitigation methods

Poles with pin insulators

Insulate insulators and conductors with plastic insulating caps, 1 400 mm in length.

Apply cable tubing, 1 400 mm in length.

Insulate the centre conductor attached to a pin insulator on horizontal-configuration intermediate poles with no conducting cross-arm in order to achieve necessary clearance between outer conductors.

Poles with suspended insulators

Use of pole types where the distance between the middle hanging insulator and the pole top is at least 1 000 mm.

In poles (triangle- or vault-shape type) with hanging insulators the insulation of the middle conductor over a total length of 2 000 mm is recommended if there is a dangerous perching site below the middle insulator on the top of the pole.

Strain poles and junction poles

Use insulator-chains which are at least 700 mm in length.

Route at least two jumper wires below the cross-arm, and insulate the third jumper.

Use insulated jumper wires.

Transformers, terminal structures

Construct terminal structures with sufficient insulation on jumper wires and surge arresters.

Poles with switching devices

Design switch poles so that perching by birds on switch gear is unlikely, and/or all dangerous components are insulated.

Mount switches below the cross-arm, and jumper wires have to be insulated.

Use bushing covers.

Install insulated (not conductive) perches above the switch gear over the whole length or on the sides of the pole head satisfying minimum required distances for bird safety.

Use effective perch deterrents in unsafe locations.

Re-construction of lines

Replace overhead lines with underground lines when possible.

Avoid pole design with pin-insulators on new overhead lines.

Use poles with suspended insulators.

5.3.2.   Mitigation of collision

Decrease the number of collision planes (vertically separated number of conductors),

Avoid to use neutral (ground) cable above conductor cables when possible,

Install clearly visible large high contrast (i.e. black and white) markers and/or moving and reflecting bird flight diverters in energised conductors and ground wires.

6.   THE IMPORTANCE OF ADOPTING A STRATEGIC APPROACH TO PLANNING

6.1.   The benefits of integrated planning

An ineffective way of developing a plan or project, be it for energy transmission infrastructures or for any other development activities, is to first design the plan or project for its purpose and then, later on, to consider the wider environmental and other use implications. This means that potential conflicts are taken into consideration at a relatively late stage in the planning process, at a time when there are fewer options available.

When the design concept is already so far progressed, the environmental impact assessment necessarily becomes an exercise in damage limitation and, even though all the rules governing environmental impact assessments are followed thoroughly, there is no guarantee of success. This type of approach to project design and planning can also lead to long discussions with planning authorities, other interest groups and NGOs during the public consultation phase which can, in turn, cause significant delays to the planning process and incur additional costs.

Adopting an integrated and forward-thinking approach to energy transmission infrastructure planning that considers both the energy transmission needs and the ecological needs together at the outset and during the initial project or plan design has numerous important advantages:

It promotes a more interactive and transparent planning process and encourages early and iterative dialogue, which can help to significantly reduce the overall time required for the permitting procedure.

If done correctly, strategic (spatial) planning can help to avoid or reduce the number of potential site-specific conflicts at a later stage in the development process, when financial and legal resources have been committed and there is less room for manoeuvre.

This can in turn also provide developers with a more transparent and stable regulatory environment and offer them greater certainty over the likely success of their permitting application because environmental concerns were taken into account already during the initial project concept.

It can also be more cost effective in the long run. Were potential avoidance or mitigation measures factored in already at an early design or planning stage they are likely to be technically easier and cheaper to integrate;

It can lead to the development of new, creative and innovative solutions and potential win-win situations which are unlikely to have been explored under the more classic sectoral approach to project planning.

It can contribute to an improved public image of the project and the institutions responsible.

Whilst preparing and executing such an integrated planning process may require a more substantial initial investment there is strong evidence to show that this type of approach almost invariably delivers substantial benefits that far exceed the initial extra investment required.

A more integrated planning approach will also have a major influence on the Article 6.3 permitting process for Natura 2000 sites under the Habitats Directive. Whilst it may not guarantee the success of the project application it is likely to considerably facilitate the authorisation process.

Experience has shown that taking environmental considerations into account early on in the decision making process can lead to solutions being found when there is still a wide choice of options available.

If, on the other hand, this inter-sectoral dialogue is left to the last stages of the Article 6.3 permitting procedure the range of solutions becomes much narrower (and more expensive to implement) and there is a greater tendency for the discussion to become polarized and more confrontational.

This is especially the case if a sectoral policy or development strategy has been given the green light at a high governmental level, without considering other policy implications. Then when it comes to more detailed plans and projects, people have difficulty understanding why the Article 6.3 procedure may block something that has already been politically agreed at the highest levels (even without any spatial information).

However, there may still be occasions where a project might simply not be compatible with conservation objectives of the Natura 2000 sites, or be irredeemably damaging for certain wild bird species. Nevertheless, thanks to the integrated planning approach this conclusion would become evident very early on and steps can be taken to avoid such impacts where possible.

6.2.   Determining suitable locations for energy transmission facilities

One of the most effective ways of avoiding potential conflicts with Natura 2000 sites and EU protected species is to consider the location of new energy transmission developments at a strategic planning level – for instance through a regional or national development plan – which allows for the sensitivities of Natura 2000 sites to be taken fully into account. This will help to identify the best sites for energy transmission whilst also wherever possible minimising the risk of potential conflicts with Natura 2000 sites at the individual project level.

‘Accessible skies’ agreement in Hungary (26)

As a result of decade-long cooperation, the Hungarian Ornithological and Nature Conservation Society (MME / BirdLife Hungary) signed the ‘Accessible Sky’ agreement with the Ministry of Environment and Water, and relevant electricity companies in Hungary on 26 February 2008. The objective of the agreement is to provide a long-term solution to the problem of bird electrocution.

Under this agreement, MME produced a map in 2008 showing key areas of conflict between power lines and bird populations in Hungary. Electric companies promised a ‘bird-friendly’ transformation of all dangerous power lines in Hungary by 2020, and the use of ‘bird-friendly’ management methods for newly constructed power lines.

Bird conservation priorities along the medium voltage power line network in Hungary

Image

The Coordinating Committee with representatives from each signatory guarantees a regular and structured cooperation. Electric companies and conservation experts cooperate to produce guidelines for the associated best available technology that are constantly updated and to field-test new solutions. The Amendment of the Act on nature conservation has further strengthened the cooperation.

The lessons learnt from the implementation of the agreement include that the co-ordination, progress monitoring and evaluation of the implementation of non-legally binding agreements need much capacity, preferably on the side of the lead nature conservation partner. Finding sufficient funding for priority actions remains a major challenge. Recent actions have been carried out thanks to the voluntary undertaking by the electricity utilities to provide 25 % co-financing to EU LIFE Nature projects.

National planning in Slovenia

In Slovenia, the transmission system operator (Elektro-Slovenija, d.o.o.) and a nature conservation NGO (DOPPS – BirdLife Slovenija) collaborated on planning and installing bird-friendly transmission power lines.

The study reviews several topics closely related to bird conservation and transmission power lines: [1] the concept of threatened species and threatening factors to bird populations in Slovenia, [2] bird species in Slovenia and their conservation status, [3] legislation and legal practice relevant to power lines and bird conservation in Slovenia, [4] impacts of transmission power lines on birds, [5] possible measures to mitigate negative and enhance positive impacts of transmission power lines on birds, [6] assessment of effectiveness of possible mitigation measures.

Elektro-Slovenija, the transmission system operator in Slovenia, has recently funded an extensive review study about interactions between birds and transmission power lines in order to find ways to operate not only in favour of consumers of electricity but as well in favour of birds. The study was elaborated by the DOPPS – BirdLife Slovenija.

Nearly 242 km of existing transmission power lines cross Special Protection Areas (Natura 2000) in Slovenia and additional 123 km of planned transmission power lines are overlapping these areas. Not every bird species in these areas is susceptible to interact with transmission power lines but most of the areas support important populations of birds which could be threatened by transmission power lines.

Therefore as an outcome of their cooperation, the following guidance for installation of bird-friendly transmission power lines are suggested:

collaborate with bird (nature) conservation institutions from the beginning of the project

plan the route of the transmission power lines with consideration to specific circumstances in the area, based on concrete all-year-round data on birds occurring in the area

avoid installing transmission power lines in areas of high concentrations, regular flight routes and migration corridors of birds susceptible to collision

use existing power line routes and merge the power lines with other existing linear infrastructure

adjust configuration of conductors and earth wires

equip the power lines with markers which increase visibility of conductors and especially earth wires

if not possible to avoid highly vulnerable spots and if feasible, put cables underground

put safe nesting platforms and nestboxes on power line towers to support certain nesting birds

German SEA on the ten-year electricity network development plan

The German Federal Network Agency (Bundesnetzagentur) has carried out a SEA on the German ten-year electricity network development plan. The following electricity transmission facilities had been taken into account: DC and AC high voltage terrestrial power lines (overhead and underground), submarine cables, hybrid networks, and associated components.

The goals of the SEA is to:

Identify, describe and assess early the direct and indirect impacts of the development plan on the environment (notably animals, plants and biological diversity, and particularly Natura 2000 sites), as completely as possible

Systematise and reinforce the integration of environmental issues in the decision-making process

Improve the transparency of the weighting between notably economic, social and environmental issues in the decision-making process

The various environmental assessments on different individual projects that have been initiated and drafted by various institutions such as ministries, federal authorities, universities, consulting companies and network operators were collected and used for the purposes of the SEA. There was also public consultation to discuss the scope of analysis and the development of a joint methodology, aiming to avoid environmental assessments of individual network development projects to start from scratch.

As a result the scope was, however, appreciably wider and for the first time the Bundesnetzagentur examined the environmental impact not only of onshore projects but also of those in the territorial waters. In certain cases, the environmental effects of the projects using underground cables were also considered.

Furthermore, the analysis of alternative options in the environmental report becomes more extensive. Alternatives to individual projects were assessed as well as an alternative grid connection system in the territorial waters and different transmission technologies. In addition, the Bundesnetzagentur assessed the environmental impacts on different scenarios of development which helped them to make informed choices and select the least environmental damaged projects.

6.3.   Looking for ways to streamline the permitting procedures for energy transmission facilities

Another benefit of adopting a more strategic approach to energy transmission planning is that it helps to organise the various permit procedures and environmental impact assessments in a more efficient way.

This streamlining process has been formalised in the case of PCIs under the TEN-E Regulation and specific Commission guidance has been produced on how to implement such streamlining mechanisms in practice whilst at the same time ensuring the maximum level of environmental protection in accordance with EU environmental law.

The guidance makes a series of recommendations which, although designed with PCIs in mind, are also very relevant for all other energy transmission infrastructure plans or projects. They are therefore summarised again here (27).

The recommendations focus in particular on:

Early planning, ‘roadmapping’ and scoping of assessments

Early and effective integration of environmental assessments and of other environmental requirements

Procedural co-ordination and time limits

Data collection, data sharing and quality control

Cross-border co-operation, and

Early and effective public participation.

6.3.1.   Early planning, ‘roadmapping’ and scoping of assessments

As stated earlier in this chapter, an early planning and ‘roadmapping’ of the different assessments and other environmental requirements to be met is vital for a successful streamlining of environmental assessment procedures. Ideally, this will happen at the very early concept stage of a plan or project (e.g. definition of connection points), and will lead to a concise assessment roadmap, indicating which type of assessment should take place at what point in the overall assessment / permit procedure. This roadmapping should be the main responsibility of the project promoter, in close co-operation with the co-ordinating authority.

In case of a staged assessment, the roadmap would also indicate which aspects could be assessed at what stage in the process to ensure complementarity and to avoid both non-consideration of certain elements and reduce the risk of repetitive assessments. The roadmap could also set out how and at what point in the process other environmental requirements should be met.

In order to adequately roadmap the different assessments required and other environmental requirements at stake, a very early scoping of all potential environmental effects of a project is recommended already at the conceptual stage. More detailed scoping could happen in line with the further development of the project, e.g. at the pre-application phase (as required under Article 10(4a) of the new TEN-E Regulation) or as part of the EIA/AA process.

Scoping stimulates early dialogue, helps identify relevant legislation or necessary assessments and regulatory controls, or potential impacts that may be relevant to the project but not immediately perceived by the project promoter. It also helps to identify relevant data, possible alternatives, information gathering methods and their scope and level of detail, and issues of particular concern to affected stakeholders and the public. By agreeing the expectations of the assessment with the relevant authorities at the start, the project promoter can confidently and effectively plan the collection of environmental information well in advance.

6.3.2.   Early and effective integration of environmental assessments and of other environmental requirements

It is highly advisable that environmental assessments are performed as early as possible, and to the level of detail possible and at an as early stage as possible in the overall process. Effective tiering (hierarchical linking) (28) (29) should be applied to ensure that different assessments required under different pieces of EU legislation, or in different phases of the process, build on, and complement each other. Environmental requirements other than assessments (e.g. as regards the strict species protection regime under the two Nature Directives) could also be integrated as early as possible, in the overall process to identify and remedy problems at an early stage, and to avoid delays and public acceptance problems in the run-up to project permitting.

As for early integration of environmental assessments, it is strongly recommended that SEAs and, where applicable, AAs, are made mandatory already at the planning stage for national energy programmes and plans (e.g. network development plans submitted by TSOs and approved by the competent authorities, in accordance with Directive 2009/72/EC (30)). This allows the environmental suitability of different types of energy sources as well as different locations for energy projects to be assessed from the start.

It encourages a more integrated and efficient approach to territorial planning where environmental considerations are taken into account much earlier in the planning process and at a much more strategic level. It also ensures that the level of assessment always matches the level of planning/decision-making and avoids that faits accomplis are created by inclusion of projects in national energy plans, for which no relevant assessments have been carried out. This will lead to fewer conflicts at the individual project level, both in substance and in terms of public acceptance.

Integration of Appropriate Assessment at different levels of the planning and permitting process

The AA at the level of national energy or grid planning will focus on avoiding sensitive locations, i.e. locations where siting of the proposed energy infrastructure might jeopardise Natura 2000 site conservation objectives as well as EU protected species outside Natura 2000 sites. This does not mean that energy infrastructure cannot be built inside Natura 2000 areas, nor that energy infrastructure outside Natura 2000 sites will not harm Natura 2000 site conservation objectives. This has to be investigated case-by-case.

At the level of project-driven spatial planning, AA will focus in greater detail on the potential Natura 2000 impacts of the more narrowly defined location alternatives. These may be routing alternatives which differ by as little as a few kilometres or less. In some cases, the AA at this level will allow identification of the need for compensation measures and even the location of these measures.

Finally the AA in the framework of the permit granting process for a concrete project will focus on additional fine-tuning of the type and significance of impacts and any required mitigation measures. This fine-tuning might involve defining a more suitable location as well as the precise nature of measures to reduce the impact. In case of projects justified for Imperative Reasons of Overriding Public Interest (IROPI), if the need for re-routing or compensation only arises at the very last phase of the planning and permitting process, considerable time may be lost. Therefore, such issues need to be considered an early stage.

6.3.3.   Procedural coordination and time limits

Under the new TEN-E Regulation, Member States are required to choose between an integrated, coordinated or collaborative permit scheme when implementing the so-called ‘one-stop-shop’ permit for PCIs. Whilst the organisation of the overall permitting process is not directly related to the streamlining of relevant environmental assessment procedures, it is strongly recommended that Member States choose either the integrated or the co-ordinated approach to the permitting process, as both imply a level of overall co-ordination which is likely to maximise the streamlining effects also in the co-ordination of relevant environmental assessment procedures.

A further powerful tool to streamline environmental assessment procedures could be to set time limits for parts or all of the environmental assessment procedures. In view of the very specific scientific and technical surveys required for Appropriate Assessments under the Habitats Directive, time limits for such assessments need to be set on a case by case basis depending on the nature and duration of the field surveys required for the EU protected species and habitat types present.

It is also important to recall that time limits could only serve to reduce unnecessary delays in assessment procedures and encourage the creation of synergies between assessments where possible, but can in no way lower the quality of the environmental assessments performed.

The revised EIA Directive 2014/52/EU has introduced specific obligations as regards the introduction of time-frames and of ‘one-stop shop’ procedures.

6.3.4.   Quality of the reports

The use of suitably qualified external experts and independent quality control can also ensure that assessment reports are robust and the data used are valid and relevant. This will help to avoid delays caused by an incomplete or poor quality assessment. In addition, according to the revised EIA Directive 2014/52/EU, MS have to ensure the completeness and quality of EIA reports.

This issue is especially relevant in the case of the Article 6 permit procedure where the onus is on proving the absence of effects (rather than their presence) and where the findings of the AA are binding on the competent authority.

6.3.5.   Cross-border co-operation

For cross-border projects Member States will have to co-operate and coordinate amongst themselves, especially regarding the definition of the scope and level of detail of the information to be submitted by the project promoter and the schedule for the permit granting procedure. This can be done by a joint procedure, particularly with regard to the assessment of environmental impacts and the likelihood of their transboundary nature. Such procedures could be jointly organised by the competent authorities of the Member States concerned, or a third body (coordination body) could be set up specifically for cross-border co-ordination.

The EU is party to the Convention on Environmental Impact Assessment in a Transboundary Context (Espoo Convention) and the Protocol on Strategic Environmental Assessment (SEA Protocol) (31). In addition to the EIA and SEA Directives they provide that plans and projects which are likely to have significant effects on the environment of another Member State, or where a Member State likely to be significantly affected so requests, the Member State in whose territory the plan, programme or project is being prepared, or intended to be carried out, shall before its adoption, and as soon as possible inform the other Member State about it (32). In 2013 the Commission produced a guidance on the application of the environmental impact assessment procedure for large-scale transboundary projects, aiming to facilitate the authorisation and efficient implementation of such projects in the future (33).

Under the new TEN-E Regulation, such cross-border cooperation is obligatory for transboundary PCIs (Article 8.3). Moreover, where a PCI encounters significant implementation difficulties, the Commission can, in agreement with the Member States concerned, designate a European coordinator to assist in and facilitate amongst others the public consultation and permitting process (Article 6). Such a co-ordinator could also be designated by Member States themselves at an earlier stage in the process and to avoid any implementation difficulties to arise at a later stage.

6.3.6.   Early and effective public participation

The EU environmental assessment legislation (e.g. the EIA and SEA Directives) and other relevant EU and international instruments (Aarhus Convention) place public participation requirements on the process of approval for PCIs. In the case of the Habitats Directive, public consultation is not obligatory but it is strongly recommended, if appropriate.

It will be important for Member States to determine the ideal scope and timing of public involvement in the preparatory and permit granting processes. The early planning and roadmapping of environmental assessment procedures recommended above need to include also an early planning and roadmapping of public participation. Similarly, early scoping could not only look at potential environmental effects of a future project, but also at its specificities and potential problems with regard to public participation.

It is recommended that the public is already informed of and involved in the early scoping and roadmapping of the project at the conceptual stage. Public scoping events might be very helpful to inform and receive early feedback by the public.

7.   THE PERMITTING PROCEDURE UNDER ARTICLE 6 OF THE HABITATS DIRECTIVE

7.1.   Introduction

As stated before, EU nature legislation does not exclude development activities in and around Natura 2000 sites. Instead, it requires that any plan or project that is likely to have a significant negative effect on one or more Natura 2000 sites undergoes an appropriate assessment (AA) in accordance with Article 6.3 of the Habitats Directive in order to assess the implications of that plan or project on the site(s).

This chapter explains how to carry out an appropriate assessment under Article 6, paying particular attention to energy transmission infrastructure plans and projects.

Because Natura 2000 concerns Europe's most valuable and endangered habitats and species, the procedures for approving developments that are likely to have a significant negative effect on these sites are sufficiently rigorous to avoid undermining the overall objectives of the Birds and Habitats Directives.

Delays in the approval process are very often caused by poor quality assessments that do not allow the competent authorities to make a clear judgement on the impacts of the plan or project. Particular attention is therefore given to the need for decisions to be taken on the basis of sound scientific information and expertise.

It is also important to avoid confusion over the impact assessments carried out under the EIA and SEA Directives and the Appropriate Assessment carried out under Article 6.3 of the Habitats Directive. Whilst these assessments are very often carried out together, as part of an integrated procedure, each one has a different purpose and assesses impacts on different aspects of the environment. An SEA or an EIA cannot therefore replace, or be a substitute for, an Appropriate Assessment.

The outcome of each assessment procedure is also different. In the case of the EIA or SEA assessment, the authorities have to take the impacts into account. For the AA, however, the outcome is legally binding for the competent authority and conditions its final decision. Thus, if the AA cannot ascertain that there will be no adverse effect on the integrity of the Natura 2000 site, despite the introduction of mitigation measures, then the plan or project can only be approved if the conditions in the derogation procedure foreseen under Article 6.4 are met.

Annex 6 provides comparison between the impact assessments under the Habitats directive, EIA and SEA.

Article 6(3) of the Habitats Directive

Any plan or project not directly connected with or necessary to the management of the site but likely to have a significant effect thereon, either individually or in combination with other plans or projects, shall be subject to appropriate assessment of its implications for the site in view of the site's conservation objectives. In the light of the conclusions of the assessment of the implications for the site and subject to the provisions of paragraph 4, the competent national authorities shall agree to the plan or project only after having ascertained that it will not adversely affect the integrity of the site concerned and, if appropriate, after having obtained the opinion of the general public.

7.2.   The scope of the Article 6 permitting procedure

The focus of the permit procedure and therefore of the Appropriate Assessment is on species and habitat types protected by the Birds and Habitats Directives, and in particular on those species and habitats for which the Natura 2000 site has been designated.

This means that the appropriate assessment does not have to assess the impact on other fauna and flora unless they are ecologically relevant for the EU protected species and habitats present on this site. An appropriate assessment under Article 6.3 is therefore narrower in scope than an assessment under EIA and SEA Directives, being confined to implications for Natura 2000 sites in view of their conservation objectives.

As regards its geographical scope, the provisions of Article 6.3 are not restricted to plans and projects carried out exclusively in a Natura 2000 site; they also target developments situated outside Natura 2000 sites but which are likely to have a significant effect thereon. The trigger for such an assessment is not based on whether the project is located inside the Natura 2000 or not but on whether it is likely to have a significant effect on a Natura 2000 site and its conservation objectives.

This includes the consideration of any likely transboundary effects. If a plan or project in one country is likely to have a significant effect on Natura 2000 site in a second country, either individually or in combination with other plans or projects, then the effects on the integrity of Natura 2000 sites in that second country will have be assessed as well. This is in line with the Espoo Convention and its SEA Protocol which are implemented within the EU through the EIA and SEA Directives (see point 6.3.5 of this guidance document)

The effects need to be determined in function of the species and habitat types for which a particular site has been designated. This will influence how far from the project area one should look for possible effects. For instance, a rare plant which is very localised and only occurs in specialised habitat conditions may only be affected by projects in the immediate vicinity compared to a migratory species which has wider habitat requirements and may therefore be affected by plans or projects further afield.

Figure 6

Flow chart of Art 6.3 and 6.4 procedure (Based on Commission Article 6 methodological guide)

Image

Are there human health or safety considerationsor important environmental benefits?

Are there imperative reasons of overriding public interest?

Authorisation cannot be granted

Authorisation may be grantedprovided that adequate compensation measures are taken

Authorisation can only be granted for other imperative reasons of overriding public interest if the Commission issues a positive Opinion and adequate compensation measures are taken

Yes

Does the site host a priority habitator species?

Derogation Article 6.4

No

Authorisation cannot be granted

Are there alternative solutions?

Can the negative impacts be removed e.g. through mitigation measures?

Authorisation may be granted

Can it be concluded that the PP will not adversely affect the integrity of the site?

Assess cumulative and in-combination effects with other plans and/or projects

Appropriate Assessment

Screening

Redesignthe plan / project

No

No

No

No

Yes

Yes

Yes

Yes

Yes

Yes

Yes

Yes

No

No

Assess implications in view of the site’s conservation objectives

Is the PP likely to have significant effects on the site?

Is the plan or project (PP) directly connected with, or necessary to the conservation management of the site ?

7.3.   A step-by-step procedure for carrying out appropriate assessments

The procedure laid out in Articles 6.3 must be carried out in sequential order. Every step determines whether a further step in the process is required. For instance if, after the screening, it is concluded that there will be no negative effects on the Natura 2000 site, then the plan or project can be approved without the need for further assessment.

The steps are as follows (see diagram):

Step one: screening – this initial step is to determine whether a plan or project has to undergo an appropriate assessment or not. If it is likely to have a significant negative effect on a Natura 2000 site, then an appropriate assessment is required.

Step two: appropriate assessment – once it has been decided that an AA is required, a detailed analysis must be undertaken of the potential impacts of the plan or project, alone or in combination with other plans or projects, on the integrity of Natura 2000 site(s) in view of its conservation objectives.

Step three: decision making – If the appropriate assessment concludes that there is an adverse effect on integrity of the site and these cannot be mitigated against, then the competent authorities will need to refuse the plan or project.

Article 6.4 provides for certain derogations to this general rule. Thus, if it is concluded that the plan or project will have an adverse effect on a Natura 2000 site, it can still be approved under exceptional circumstances provided the conditions of Article 6.4 are met. It is clear from the above that this decision-making process is underpinned by the precautionary principle. The emphasis is on objectively demonstrating, with reliable supporting evidence, that there will be no adverse effects on the Natura 2000 site.

7.3.1.   Step one: screening

The first step in the Article 6.3 procedure is to determine whether or not an AA is actually needed, i.e. if a plan or project is likely to have a significant effect on a Natura 2000 site. If it can be determined with sufficient certainty that the plan or project is not likely to have a significant effect, either individually or in combination with other plans or projects, then it can be approved without further assessment.

However, if there is any doubt, an appropriate assessment must be undertaken so that these effects can be studied in full. This was confirmed by the ECJ in the Waddensea ruling (C-127/02) in which the Court concluded that: ‘the triggering of the environmental protection mechanism provided for in Article 6(3) of the Habitats Directive does not presume – as is, moreover, clear from the guidelines for interpreting that article drawn up by the Commission, entitled ‘Managing Natura 2000 Sites: The provisions of Article 6 of the “Habitats” Directive (92/43/EEC)’ – that the plan or project considered definitely has significant effects on the site concerned but follows from the mere probability that such an effect attaches to that plan or project.’. In the same ruling the Court confirmed that in case of doubt as to the absence of significant effects such an assessment must be carried out, in order to be ensured effectively that plans or projects which adversely affect the integrity of the site concerned are not authorised.

The reasons for the final decision as to whether or not to carry out an appropriate assessment should be recorded and sufficient information should be given to justify the conclusion that has been reached.

7.3.2.   Step two: the Appropriate Assessment

Once it has been decided that an appropriate assessment is required, such an assessment will need to be carried out before the competent authority makes its decision on whether or not to authorise the plan or project. As stated above the purpose of the appropriate assessment is to assess the implications of the plan or project on the site in view of its conservation objectives, either individually or in combination with other plans or projects.

The term ‘appropriate’ essentially means that the assessment needs to be appropriate to its purpose under the Birds and Habitats Directives, i.e. that of safeguarding species and habitat types listed under the two directives. ‘Appropriate’ also means that the assessment has to be a reasoned decision. If the report does not include a sufficiently detailed assessment of the effects on the Natura 2000 site or does not provide enough evidence to draw clear conclusions as to whether or not the site's integrity is adversely affected then the assessment does not fulfil its purpose and cannot be considered ‘appropriate’.

Assessments that confine themselves to general descriptions and provide only a superficial review of existing data on nature within the area are not considered as ‘appropriate’ for the purposes of Article 6.3. This has been confirmed by the European Court of Justice which has ruled that ‘the appropriate assessment should contain complete, precise and definitive conclusions capable of removing all reasonable scientific doubt as to the effects of the works proposed on the site concerned’ (Commission/Italy, C-304/05).

The Court also emphasised the importance of using best scientific knowledge when carrying out the appropriate assessment in order to enable the competent authorities to conclude with a sufficient degree of certainty that there will be no adverse effects on the site's integrity. In this respect it considered that ‘all the aspects of the plan or project which can, either individually or in combination with other plans or projects, affect those objectives must be identified in the light of the best scientific knowledge in the field.’ (C-127/02, Para 54).

Because of the specialised nature of the appropriate assessment, it is strongly recommended that the assessment is based on analyses carried out by suitably qualified ecologists.

Finally, it should be noted that, whilst it may be the project proponent who undertakes or commissions the AA, it is the competent authorities' responsibility to ensure that the AA has been carried out correctly and is capable of objectively demonstrating, with supporting evidence, that there will not be any adverse effects on the integrity of the Natura 2000 site, in light of its conservation objectives.

—    Assessing effects in light of the site's conservation objectives

As stated above, the assessment will assess the possible implications for the site of the plan or project in view of the site's conservation objectives. To understand what the conservation objectives are, it is necessary to look back at how Natura 2000 sites are selected. As explained earlier each site is included in the Natura 2000 network because it is of conservation value for one or more of the habitat types listed in Annex I or species listed in Annex II of the Habitats Directive, or species listed in Annex I of the Birds Directive as well as regularly occurring migratory bird species.

The conservation value of the site at the time of designation is recorded in a Standard Data Form (SDF). This provides the site's formal identification code, its name, location and size, and detailed map. It also records the ecological characteristics of the site which led to its designation as a Natura 2000 site and provides a broad assessment of the conservation condition of each species or habitat type on that site (scored A to D).

The SDF is therefore the reference base for setting conservation objectives for the site, in line with the overall objectives of the Habitats Directive (Article 6.1). At a minimum, the sites' conservation objective will be to maintain the species and habitats for which it was designated in the same condition (as recorded in the SDF). This means ensuring that they will not deteriorate below that level.

However, the overall objectives of the Habitats and Birds Directives go beyond simply preventing further deterioration. They aim to ensure that EU protected species and habitat types reach a favourable conservation state across their natural range in the EU. Thus more ambitious conservation objectives may be required to restore and improve the conservation condition of the EU protected species and habitat types present on that site (under Article 6.1).

If more ambitious conservation objectives have been set, then the impacts of the plan or project must be measured against these more ambitious objectives. For instance, if the objective is to restore the population of the Bearded vulture to a certain population level within 8 years, it has to be assessed if the plan or project will or will not prevent this conservation objective from being realised, and not merely whether the vulture population will remain stable.

It is recommended that the project proponent consults with the authorities responsible for Natura 2000 sites as early as possible to find out more about the site, its conservation objectives and the conservation condition of the habitat types and species for which it is designated. They will also be able to indicate if there are more detailed sources of information available on this – for instance a management plan adopted for the site or monitoring reports and studies about the conservation condition of the species and habitat types concerned within that region, or country

—    Collecting the necessary information for the AA

Potential source of information for the Natura 2000 sites include:

Natura 2000 Standard Data Forms;

Natura 2000 management plans;

up-to-date data published in technical and scientific literature;

nature conservation authorities, scientific experts and species or habitat specialist, conservation organisations, local experts;

Article 12 of the Birds Directive and article 17 of the Habitats Directive reports on the conservation status of species and habitats

Figure 7

Steps to be undertaken as part of the appropriate assessment

Image

DETERMINE IF THERE AREANY RESIDUAL EFFECTSON THE INTEGRITY OFTHE SITE

DEFINE STUDYAREA

IDENTIFY /ASSESS PREVENTIVE AND MITIGATION MEASURES

to remove or reduce the effects to a non significant level

DESIGNA MONITORING PROGRAMME

GATHER EXISTING INFORMATION AND CARRY OUT ADDITIONAL FIELD STUDIES ANDSURVEYS ASREQUIRED

GATHER INFORMATION ABOUT OTHER PLANS AND PROJECTS

in order to be able to assess cumulative effects

ASSESS THE EFFECTS AND THEIR SIGNIFICANCE

On the targeted habitat types, thehabitats of the species and the speciesas well as on the ecological structureand function of the site

IDENTIFY THE ECOLOGICAL CHARACTERISTICS TO BE CONSIDERED IN THE ASSESSMENT

Analyse potential effects of project actions on species and habitats present

CONSULT COMPETENT AUTHORITIESANDSTAKEHOLDERS

IDENTIFY THE CONSERVATION OBJECTIVES OF THE NATURA 2000 SITE(S)

Gathering all the necessary information on both the project and the Natura 2000 site is an important initial step of the appropriate assessment. This is usually an iterative process. If the first identification and analysis reveals that there are important gaps in knowledge, then further baseline ecological and survey field work may be necessary to supplement existing data.

As stated before, it is important that the appropriate assessment is based on the best scientific knowledge in the field and is capable of removing all reasonable scientific doubt as to the effects of the works proposed on the site concerned. This has been confirmed by several ECJ rulings. In the Waddensea case (C-127/02) the Court confirmed that ‘the competent national authorities are to authorise (a plan or project) only if they have made certain that it will not adversely affect the integrity of that site. That is the case where no reasonable scientific doubt remains as to the absence of such effects.’

Detailed surveys and fieldwork have to focus on those habitats and species that are potentially sensitive to the project actions. Sensitivity needs to be analysed taking into account the possible interactions between the project activities (nature, extent, methods, etc.) and the habitats and species concerned (location, ecological requirements, vital areas, behaviour, etc.).

Any field studies must be sufficiently robust and long-lasting to take account of the fact that ecological conditions may vary significantly according to the seasons. For instance, undertaking a field survey on a species for a few days in winter will not capture their habitat usage during other more important periods of the year (e.g. during migration or breeding).

Consulting with nature authorities, other scientific experts and conservation organisations early on will help ensure that as complete a picture as possible is built up about the site, the species/habitats present and the type of effects to be analysed. They can also offer advice on the updated scientific information that is available on the site and its EU protected species and habitat types (including Natura 2000 management plans) and on what additional baseline studies and field surveys may be needed in order to assess the likely impacts of the project.

Other stakeholders such as conservation NGOs, research institutions or local organisations may also be able to provide further local knowledge and ecological information useful for the appropriate assessment.

—    Identifying negative impacts

Once all the necessary baseline data has been gathered and checked for completeness, the assessment of the implications of the plan or project on the Natura 2000 site can begin. The description of potential negative impacts of energy transmission infrastructure plans and projects as described in chapters 3 and 4 should help to identify the type of effects to look out for.

This could concern in particular:

habitat loss, degradation or fragmentation

electrocution or collision

species disturbance and displacement

barrier effects

The effects of each project will be unique and must be evaluated on a case- by-case basis. This is in line with the Waddensea case: ‘in assessing the potential effects of a plan or project, their significance must be established in the light, inter alia, of the characteristics and specific environmental conditions of the site concerned by that plan or project.’

The first step is to identify which EU protected habitats and species present within each site could be potentially affected and need to be subject to further assessment. This is important as every species and habitat type has its own ecological lifecycle and conservation requirements. The impacts on each will also vary from one site to another depending on their conservation state and the underlying ecological conditions of that particular site.

For each effect identified, the assessment will also look at the magnitude of the impact, type of impact, extent, duration, intensity and timing.

The AA also involves looking at all aspects of the plan or project that could have implications for the site. Each element of the plan or project needs to be examined in turn and the potential effects of that element should be considered first in relation to each of the species or habitat types for which the site has been designated. Thereafter, the effects of the different features will be looked at together, and in relation to one another, so that the interactions between them can be identified.

Whilst the focus should be on the species and habitats of EU interest that have justified the site designation, it should not be forgotten that these target features also interact closely with other species and habitats, as well as with the physical environment in complex ways. It is therefore important that all the elements considered essential for the structure, functioning, and dynamics of the ecosystem are examined as any alteration could also have a negative effect on the habitat types and species present.

Impacts have to be predicted as precisely as possible, and the basis of these predictions should be made clear and recorded in the AA (this means also including some explanation of the degree of certainty in the prediction of effects).

As with all impact assessments, the appropriate assessment should be undertaken within a structured framework to ensure that the predictions can be made as objectively as possible, using quantifiable criteria wherever possible. This will also greatly facilitate the task of designing mitigation measures that can help remove the predicted effects or reduce them to a non-significant level.

Predicting the likely impacts can be a complex task as one needs to have a solid understanding of ecological processes and conservation requirements of particular species or habitat types likely to be affected. It is therefore strongly recommended that the necessary expert advice and scientific support is secured when carrying out the appropriate assessment.

Commonly used methods for predicting impacts:

The AA should apply the best available techniques and methods to estimate the extent of the effects. Some of the techniques commonly used are listed in the following box.

Direct measurements, for example of areas of habitat lost or affected, proportionate losses from species populations, habitats and communities.

Flow charts, networks and systems diagrams to identify chains of impacts resulting from direct impacts; indirect impacts are termed secondary, tertiary, etc. impacts in line with how they are caused. Systems diagrams are more flexible than networks in illustrating interrelationships and process pathways.

Quantitative predictive models to provide mathematically derived predictions based on data and assumptions about the force and direction of impacts. Models may extrapolate predictions that are consistent with past and present data (trend analysis, scenarios, analogies which transfer information from other relevant locations) and intuitive forecasting. Normative approaches to modelling work backwards from a desired outcome to assess whether the proposed project will achieve these aims.

Population level studies are potentially beneficial for determining population level effects of impacts to bird or bat or marine mammal species, for instance.

Geographical information systems (GIS) used to produce models of spatial relationships, such as constraint overlays, or to map sensitive areas and locations of habitat loss. GIS are a combination of computerised cartography, storing map data, and a database-management system storing attributes such as land use or slope. GIS enable the variables stored to be displayed, combined, and analysed speedily.

Information from previous similar projects may be useful, especially if quantitative predictions were made and have been monitored in operation.

Expert opinion and judgment derived from previous experience and consultations on similar inland waterway development projects.

Description and correlation: physical factors (e.g. water regime, current, substrate) may be directly related to distribution and abundance of species. If future physical conditions can be predicted then it may be possible to predict future developments of habitats and populations or responses of species and habitats on this basis.

Capacity analyses involve identifying the threshold of stress below which populations and ecosystem functions can be sustained. It involves the identification of potentially limiting factors, and mathematical equations are developed to describe the capacity of the resource or system in terms of the threshold imposed by each limiting factor.

Adapted from: ‘Methodological guidance on the provisions of Article 6(3) and (4) of the Habitats Directive’ http://ec.europa.eu/environment/nature/natura2000/management/docs/art6/natura_2000_assess_en.pdf

—    Assessing potential cumulative effects

Cumulative effects must not be overlooked during the assessment; not only is this a legal requirement by art 6.3 of the Habitats directive but it can also have major implications for the plan or project, as well as other subsequent plans or projects which are put forward in the same area.

The energy infrastructure developments are proceeding at a fast pace across the EU, it is therefore important that cumulative effects are fully assessed in the early stages of the assessment and not treated merely as an ‘afterthought’ at the end.

Article 6.3 does not explicitly define which other plans and projects are within the scope of the combination provision but the underlying intention is to take account of cumulative impacts that may occur over time. In that context, one should consider plans or projects which are completed, approved but uncompleted, or actually proposed.

In considering a proposed plan or project, Member States do not create a presumption in favour of other similar, but as yet un-proposed, plans or projects in the future. On the contrary, if one or more projects have already been approved in an area, this may lower the ecological threshold as regards the significance of the impacts for future plans or projects in that area.

For instance, if electricity infrastructure projects within or around a series of Natura 2000 sites are submitted one after another, it could well be that the assessment of the first or second projects concludes that they will not adversely affect the Natura 2000, but then later projects may not be approved because their effects, when combined with those of the previous projects, becomes significant enough that the site's integrity will be adversely affected.

In this context, it is important that energy infrastructure projects are looked at strategically and in combination with each other over a larger geographical area, and not simply viewed as individual isolated projects.

—    Steps in Cumulative assessment

Figure 8

(Adapted from: ‘Methodological guidance on the provisions of Article 6(3) and (4) of the Habitats Directive’

http://ec.europa.eu/environment/nature/natura2000/management/docs/art6/natura_ 2000_assess_en.pdf)

Steps in the assessment

Activity to be completed

Identify all projects/plans which might act in combination

Identify all possible sources of effects from the project or plan under consideration, together with all other sources in the existing environment and any other effects likely to arise from other proposed projects or plans.

Impact identification

Identify the types of impacts (e.g. noise, water resource reduction, chemical emissions, etc.) that are likely to affect aspects of the structure and functions of the site vulnerable to change.

Define boundaries for assessment

Define boundaries for examination of cumulative effects: note these will be different for different types of impact (e.g. effects upon water resources, noise) and may include remote (off-site) locations.

Pathway identification

Identify potential cumulative pathways (e.g. via water, air, etc.; accumulation of effects in time or space). Examine site conditions to identify where vulnerable aspects of the structure and function of the site are at risk.

Prediction

Prediction of magnitude/extent of identified likely cumulative effects.

Assessment

Comment on whether or not the potential cumulative impacts are likely to be significant.

—    Determining the significance of the effects

Once the effects have been identified, an appraisal needs to be made of their significance for the site and its target features. The following parameters can be considered when assessing significance:

Quantitative parameters: for instance, how much habitat is lost for that species or habitat type. For some the loss of even single units or small areas of occurrence within a given Natura 2000 site (e.g. for priority habitat types and species) will be taken as being a significant impact. For others the significance threshold may be higher. Again it depends on the species and habitat types, their state of conservation in that site as well as their future prospects.

Qualitative parameters: the significance of the impacts should also take account of the quality of. the habitat type or species within that site, for instance it may be a site with an important occurrence of the species (e.g. a core area for the occurrence, larger areas of representative stands, etc.) or a site where the species is at the limit of its existing distribution range. The habitat or species may be in good conservation condition within the site or alternatively in a poor condition and in need of restoration.

Importance of the site from the point of view of the species biology e.g. site of reproduction (nesting places, spawning area, etc.); feeding habitat; sheltering possibilities; migration pathways.

Ecological functions necessary for maintenance or restoration of species and habitats present, and for overall site integrity.

Where there is doubt or differences over the degree of significance, it is best to find a broader agreement amongst relevant experts, e.g. regional and/or national specialists in the affected target feature so that a consensus can be built up over this.

—    Introducing mitigation measures to remove adverse effects

Once the negative effects have been identified, it will be possible to consider whether mitigation measures can be introduced to remove, pre-empt or reduce these effects to a non-significant level (see chapter 5 for suggestions on different types of mitigation measures that could be used for energy infrastructure projects). When exploring suitable mitigation measures it is important to consider first those that can remove impacts at source and, only if these are not possible, should other mitigation measures be examined that can at least significantly reduce or abate the negative effects of the project.

Mitigation measures must be specifically designed to eliminate or reduce negative effects identified during the AA. They must not be confused with compensation measures which are intended to compensate for the damage caused. Compensation measures can only be considered if the plan or project has been accepted as being necessary for imperative reasons of overriding public interest and where no alternatives exist (under Article 6.4 – see below).

Proposed mitigation measures can contain:

details of each of the measures proposed and an explanation of how it will eliminate or reduce the adverse impacts which have been identified;

evidence of how they will be implemented and by whom;

a timetable for implementation relative to the plan or project (some may need to be put in place before the development can proceed);

details of how the measure will be monitored and how the results will be fed back into the day to day operation of the project (adaptive management – see below).

This will enable the competent authority to determine whether or not they are capable of removing the negative effects identified (and do not inadvertently cause other adverse effects on the species and habitat types in question). If the mitigation measures are deemed sufficient, they will become an integral part of the specification of the final plan or project or may be listed as a condition for the approval of the project.

—    Determining whether the site's integrity is affected

Once the effects of the project have been predicted as accurately as possible, their level of significance assessed and all possible mitigation measures have been explored, the AA must reach a final conclusion as to whether they will adversely affect the integrity of the Natura 2000 site.

The term ‘integrity’ clearly relates to ecological integrity. The ‘integrity of the site’ can be usefully defined as the coherent sum of the site's ecological structure, function and ecological processes, across its whole area, or the habitats, complex of habitats and/or populations of species for which the site is designated. A site can be described as having a high degree of integrity where the inherent potential for meeting site conservation objectives is realised, the capacity for self-repair and self-renewal under dynamic conditions is maintained, and a minimum of external management support is required.

If a plan or project adversely affects the integrity of a site only in a visual sense or causes significant effects to habitat types or species other than those for which the site was designated as Natura 2000, this is not an adverse effect for purposes of Article 6.3. On the other hand, if one of the species or habitat types for which the site has been designated is significantly affected then the site integrity is necessarily also adversely affected.

The expression ‘integrity of the site’ shows that the focus is on the specific site. Thus, an argumentation that damage to a site or part of it can be justified on the basis that the conservation status of the habitat types and species it hosts will anyway remain favourable within the European territory of the Member State cannot be accepted.

In practice the assessment of site integrity will focus in particular on identifying whether the project:

causes changes to significant ecological functions necessary for the target features;

significantly reduces the area of occurence of habitat types (even of those of lower quality) or viability of species populations in the given site which are target features;

reduces the site diversity;

leads to the site fragmentation;

leads to a loss or reduction of the key site characteristics (e.g. tree cover, regular annual floodings) which the status of the target feature depends on;

prevents meeting the site conservation objectives.

7.3.3.   Step 3: approving or refusing the plan or project in light of the conclusions of the appropriate assessment

It lies with the competent national authorities, in the light of the conclusions of the AA, to approve the plan or project. This can be done only after having ascertained that it will not adversely affect the integrity of that site. If the conclusions are positive, in the sense that no reasonable scientific doubt remains as to the absence of effects on the site, the competent authorities can give their consent to the plan or project.

The onus is clearly on proving the absence of effects rather than their presence. This has been confirmed by several ECJ rulings. In the Waddensea case (C-127/02) the Court confirmed that ‘a plan or project […] may be granted authorisation only on the condition that the competent national authorities are convinced that it will not adversely affect the integrity of the site concerned. Where doubt remains as to the absence of adverse effects on the integrity of the site linked to the plan or project being considered, the competent authority will have to refuse authorization.

The appropriate assessment and its conclusions should be clearly recorded and the AA report should be sufficiently detailed and conclusive to demonstrate how the final decision was reached and on what scientific grounds the decision was made.

7.4.   The derogation procedure under Article 6.4

Article 6(4)

If, in spite of a negative assessment of the implications for the site and in the absence of alternative solutions, a plan or project must nevertheless be carried out for imperative reasons of overriding public interest, including those of a social or economic nature, the Member State shall take all compensatory measures necessary to ensure that the overall coherence of Natura 2000 is protected. It shall inform the Commission of the compensatory measures adopted.

Where the site concerned hosts a priority natural habitat type and/or a priority species, the only considerations which may be raised are those relating to human health or public safety, to beneficial consequences of primary importance for the environment or, further to an opinion from the Commission, to other imperative reasons of overriding public interest.

Article 6.4 provides for exceptions to the general rule of Article 6.3. This is not an automatic process, it is up to the project or plan proponent to decide whether they wish to apply for a derogation. Article 6.4 lays down the conditions that need to be respected in such cases and the steps that need to be followed before a competent national authority can authorise a plan or project that has been assessed as adversely affecting the integrity of a site under Article 6.3.

Article 6.4 requires that the competent authorities ensure the following conditions are respected before a decision can be taken on whether or not to authorise a plan or project that may adversely affect a site:

The alternative put forward for approval is the least damaging for habitats, for species and for the integrity of a Natura 2000 site, and no other feasible alternative exists that would not affect the integrity of the site.

There are imperative reasons of overriding public interest that justify the authorisation of the plan or project, including those of a social or economic nature.

All compensatory measures required to ensure the protection of the overall coherence of the Natura 2000 network have been taken.

The order in which these conditions are examined is important as each step determines whether the next step is required. If, for instance, it is found that there is an alternative to the plan or project in question, then there is no point in examining whether the original plan or project is of overriding public interest or to develop suitable compensation measures since that plan or project could not, in any case, be authorised if a viable alternative exists.

Figure 9

Flowchart of Article 6.4 conditions

Image

Authorisation may not be granted

Authorisation may be granted. Compensation measures mustbe taken

Authorisation may be granted forother IROPI, following consultationwith the Commission.

Compensation measures mustbe taken

Are there human health orsafety conditions or important environmental benefits

Does the site hosts a priority habitator species which could be affectedby the PP?

Are there imperative reasons of overriding public interest ( IROPI)?

Are there alternative solutions?

PP could adversely affect the integrity of a site

Yes

No

No

No

Yes

Yes

Yes

—    Demonstrating the absence of alternative solutions

The search for alternatives can be quite broad and should be linked to the public interest objectives of the plan or project. It could involve alternative locations, different scales or designs of development, different methods of construction or alternative processes and approaches.

Although the requirement to search for alternatives falls within the scope of Article 6.4, in practice it is useful for the planner to consider all possible alternatives as early as possible when initially planning their development project. If an appropriate alternative is found at this stage which is not likely to have a significant effect on a Natura 2000 site, then it can be approved immediately and an appropriate assessment will not be required.

However, in the case where the project has gone through an AA which has concluded that there will be an adverse effect on the integrity of the site, it is then for the competent authority to determine whether alternative solutions exist. All feasible alternatives, in particular, their relative performance with regard to the conservation objectives of the Natura 2000 site and the site's integrity should be analysed.

The alternative solutions chosen will also have to be subject to a new appropriate assessment if it is likely to have a significant effect on the same or another Natura 2000 site. Usually, if the alternative is similar to the original proposal, the new assessment may be able to draw a lot of the information needed from the first appropriate assessment.

—    Imperative reasons of overriding public interest (IROPI)

In the absence of alternative solutions, or in the presence of solutions having even more negative effects on the conservation objectives or integrity of the site concerned, the competent authorities must examine whether there are imperative reasons of overriding public interest which justify the authorisation of the plan or project in spite of the fact that it may adversely affect the integrity of a Natura 2000 site.

The concept of ‘imperative reason of overriding public interest’ is not defined in the directive. However it is clear from the wording that, for a plan or project to be authorised in the context of Article 6.4, it must meet all three of the following conditions:

there must be imperative reasons for undertaking the plan or project – imperative in this sense clearly means that the project is essential for society, rather than merely desirable or useful;

the plan or project must be of overriding interest – in other words it must be demonstrated that implementing the plan or project is even more important than fulfilling the objectives of the Birds and Habitats Directives. It is clear that not every kind of public interest of a social or economic nature is sufficient, in particular when seen against the particular weight of the interests protected by the directive. It is also reasonable to assume that the public interest can only be overriding if it is a long-term interest; short term economic interests or other interests which would only yield short-term benefits would not be sufficient to outweigh the long-term conservation interests protected by the directive.

be of public interest - it is clear from the wording that only public interests, can be balanced against the conservation aims of the directive. Thus, projects developed by private bodies can only be considered where such public interests are served and demonstrated.

Article 6.4 second subparagraph mentions human health, public safety and beneficial consequences of primary importance for the environment as examples of such imperative reasons of overriding public interests. It also refers to ‘other imperative reasons of overriding public interest’ of social or economic nature.

In the case of PCIs under the TEN-E Regulation, they shall be considered as being of public interest from an energy policy perspective, and may be considered as being of overriding public interest, provided that all the conditions set out in Article 6.4 are met.

It should be noted that the conditions of overriding public interest are even stricter when it comes to the realisation of a plan or project likely to adversely affect the integrity of a Natura 2000 site that hosts priority habitat types and/or species, where those habitat types and/or species are affected.

These can only be justified if the imperative reasons of overriding public interest concern:

human health and public safety or;

overriding beneficial consequences for the environment, or;

for other imperative reasons if, before granting approval to the plan or project, the opinion of the Commission has been given.

—    Compensatory measures

If the above conditions are met then the authorities must also ensure that compensatory measures are adopted and put in place before the project can begin. Compensatory measures therefore constitute the ‘last resort’ and are used only when the decision has been taken to proceed with a plan or project because it has been demonstrated that there are no alternative solutions and that the project is necessary for imperative reasons of overriding public interest under the conditions described above.

Compensatory measures under Article 6.4 are clearly distinct from the mitigation measures introduced through Article 6.3. Mitigation measures are those measures which aim to minimise, or even cancel, the negative impacts on a site that are likely to arise as a result of the implementation of a plan or project.

Compensatory measures on the other hand are sensu stricto independent of the project. They are intended to compensate for the negative effects of the plan or project (after all possible mitigation measures have been introduced to the plan or project) so that the overall ecological coherence of the Natura 2000 network is maintained. The compensatory measures must be able to compensate fully for the damage caused to the site and to the EU protected habitats and species present and must be sufficient to ensure that the overall coherence of Natura 2000 is protected.

To ensure that the overall coherence of Natura 2000 is protected, the compensatory measures proposed for a plan or project will in particular:

contribute to the conservation of affected habitat types and species within the biogeographical region concerned or within the same range, migration route or wintering area for species in the Member State concerned;

provide functions comparable to those which had justified the selection of the original site, particularly regarding the adequate geographical distribution;

have to be additional to the normal duties under the directive, i.e. they cannot substitute existing commitments, such as the implementation of Natura 2000 management plans.

According to existing Commission guidance (34), compensatory measures under Article 6.4 can consist of one or more of the following:

the recreation of a comparable habitat or the biological improvement of a substandard habitat within an existing designated site provided this goes beyond the site's conservation objectives;

the addition to the Natura 2000 network of a new site of comparable or better quality and condition to the original site;

the recreation of a comparable habitat or the biological improvement of a substandard habitat outside a designated site which is then included in the Natura 2000 network.

The habitat types and species negatively affected must as a minimum be compensated for in comparable proportions, but, considering the high risks and scientific uncertainty involved in attempting to recreate or restore substandard habitats, it is strongly recommended that ratios well above 1:1 or more are applied to be sure that the measures really do deliver the necessary compensation.

It is considered good practice to adopt compensatory measures as close as possible to the affected area in order to maximise chances of protecting the overall coherence of the Natura 2000 network. Therefore, locating compensation within or nearby the Natura 2000 site concerned in a location showing suitable conditions for the measures to be successful is the most preferred option. However, this is not always possible and it is necessary to set a range of priorities to be applied when searching locations that meet the requirements of the Habitats Directive. Under these circumstances, the likelihood of long-term success is best evaluated by peer-reviewed scientific studies of trends.

Member States have to pay particular attention when the negative effects of a plan or project are produced in rare natural habitats or in natural habitats that need a long period of time to provide the same ecological functionality. For some habitats and species it may simply not be possible to compensate for any loss within a reasonable time frame as their development may take decades or simply be technically impossible.

Finally, the compensatory measures need to be in place and fully functional before the work on the plan or project has begun. This is to help buffer the damaging effects of the project on the species and habitats by offering them suitable alternative locations in the compensation area. If this is not fully achievable, the competent authorities should require extra compensation for the interim losses that would occur in the meantime.

The information on the compensatory measures should be submitted to the Commission before they are implemented and before the realisation of the plan or project concerned. It is therefore advised that information on compensatory measures be submitted to the Commission as soon as they have been adopted in the planning process in order to allow the Commission to assess whether the provisions of the directive are being correctly applied.

8.   ENERGY TRANSMISSION INFRASTRUCTURE IN THE MARINE ENVIRONMENT

This section of the document is concerned with impacts relating to the installation, operation, and decommissioning of energy transmission infrastructure in the marine environment, and its connection to the onshore grid across intertidal areas. The principle components of this infrastructure are subsea cables and pipelines. Impacts from offshore electricity substations and LNG terminals as well as the transport of oil and gas by shipping, and associated infrastructure such as port facilities, as well as offshore production platforms are not covered in this document. Information is available on the potential environmental effects associated with these activities and infrastructure, and it should be noted that these can be significant e.g. major oil spills and impact on marine Natura 2000 habitats and species. There is also relevant guidance available from a number of sources including the European Commission, Convention for the Protection of the Marine Environment of the North-East Atlantic (OSPAR), Convention on the protection of the marine environment of the Baltic Sea Area (HELCOM) and the International Maritime Organisation( IMO, on potential mitigation measures (35).

The environmental impact of marine energy transmission in Europe associated with the offshore oil and gas industry has been the subject of extensive study for more than 50 years. Over that period lessons learnt, new technologies, and improved understanding of impacts have resulted in a significant body of information on how to avoid and/or mitigate potential impacts. This information is not only relevant to the oil and gas industry but also to the newer marine energy technologies such as offshore wind, marine current turbines and potential future infrastructure associated with Carbon Capture and Storage (CCS). Opportunities and approaches to mitigating effects, based on good practice experiences from across the EU and beyond are introduced in this section and the reader is also directed to other sources of information on this subject.

8.1.   An overview of current energy infrastructure in EU marine waters

The unequal global distribution of energy sources such as oil, gas, coal and even some renewables, compared to locations where energy demand is greatest means that there is considerable transport of energy, in all its forms, around the world. A significant amount of the infrastructure which has been built to transmit the necessary materials is in the marine environment. In Europe this is not only located in the relatively shallow waters of the Continental Shelf, the Baltic, the Irish Sea and the North Sea but also in the deeper waters of the Mediterranean, the Norwegian Trench and the Atlantic to the north and west of the British Isles.

Cables and pipelines provide the main infrastructure, and there are also potential new uses for existing pipelines such as deployment as part of CCS operations.

8.1.1.   Oil and gas

Oil and gas has been the mainstay of the offshore energy industry in European waters for nearly 50 years starting with the discovery of the Brent and Forties field in the North Sea in the 1960s. Pipelines of different sizes and construction materials provide the essential infrastructure to transport fluids involved in oil and gas production (Table 2). Ancillary equipment which forms part of the infrastructure includes concrete mattresses which secure flow lines to the seabed, and crossings which may be constructed using mattresses, grout filled bags and cast concrete structures with protective rock dumps. An estimated 35,000- 45,000 concrete mattresses have been deployed on and around oil and gas subsea infrastructure in the UK sector of the North Sea for example, and more than 45,000km of pipeline and cabling (Oil & Gas UK, 2013).

Table 2

High level categorisation of pipelines in operation in the North Sea

(Figure 1 from Oil & Gas UK, 2013)

Pipeline Description

Typical Dimensions

Applications

Primary Materials of Construction

Additional Coatings

Trunklines

Up to 44 inches diameter, up to 840 kilometres long

Major export infrastructure for oil and gas

Carbon steel

Anti-corrosion coating plus concrete weight coating

Rigid flowlines

Up to 16 inches diameter, less than 50 kilometres long

Infield flowlines and tie-in spools

Carbon steel or high specification alloy

Polymer anti-corrosion coating

Flexible flowline

Up to 16 inches diameter, up to 10 kilometres long

Infield flowlines and tie-in-spools

Carcass of high specification alloys and polymer layers; alloy-end-fittings

Polymer external coatings

Umbilical

Between 2 and 8 inches diameter, up to 50 kilometres long

Chemical, hydraulic and communication distribution

Thermoplastic polymer or high alloy steel tubes; wire armoured protection

Polymer external coatings

Power Cables

Between 2 and 4-inches diameter; up to 300 km. long

Power distribution between and within fields

Copper cores with wire armoured protection

Polymer external coatings

Oil and gas pipelines are present in all the regional seas of Europe. In the Mediterranean three pipelines transport gas directly from North Africa to Spain and Italy. Pipelines and cables associated with major oil and gas developments in the northern North Sea, gas developments in the southern North Sea as well as production wells in the Irish Sea, Celtic Sea, Bay of Biscay and Gulf of Cadiz also form part of the transmission infrastructure (OSPAR, 2010).

Undersea cables associated with offshore oil and gas are another component. Four different types are used for Alternating Current transmission; single or three conductor oil-insulated cables and single or three-conductor PolyEthylene (PEX) insulated cables. These have not only increased in number as the sector has developed over the last 50 years but also in their technical complexity to the point where some offshore installations, such as Floating Production Storage and Offloading facilities (FPSOs) can be powered from shore based facilities via submarine cables.

8.1.2.   Offshore wind, wave and tidal current power

In the last two decades, the growth of the renewable energy industry in Europe has included an expansion into the marine environment. Initially small numbers of wind turbines were built close to the shore in the North Sea and Baltic Sea with generation capacities of less than 1MW. Turbine size and the scale of projects have increased and changes in the technology and economics of offshore wind has enabled construction to take place in deeper waters, sometimes more than 20 km from the shore. Most of the current offshore wind farm capacity in Europe is in the North Sea (Figures 10, Table 3) (36). The largest of these, the London Array in the outer Thames estuary (175 turbines with a combined capacity of 630MW), is currently the largest offshore wind farm in the world.

Figure 10

Installed capacity - Cumulative share by country (MW)

The UK has the largest amount of installed offshore wind capacity in Europe representing 40.8 % of all installations. Germany follows with 32.5 %. Despite no additional capacity in 2016, Denmark remains the third largest market with 10.1 % and the Netherlands (8.8 %) displaces Belgium (5.6 %) to have the fourth largest share in Europe

Image


Table 3

Installed Offshore wind capacity in Europe in by the end of 2016 (Wind Europe, 2016)

COUNTRY

BE

DE

DK

ES

FI

IE

NL

NO

SE

UK

TOTAL

No. of Farms

6

18

13

1

2

1

6

1

5

28

81

No. of turbines connected

182

947

517

1

11

7

365

1

86

1,472

3,589

Capacity Installed

712 MW

4,108 MW

1,271 MW

5 MW

32 MW

25 MW

1,118 MW

2 MW

202 MW

5,156 MW

12,631 MW

The infrastructure associated with energy transmission from offshore wind farms includes subsea transmission cables with landfall and transition pits. As the number and size of these facilities has grown there has been a corresponding increase in the density of cable networks close to the shore as well as in the export and inter-array/in-field cabling. The Horns Rev 2 offshore windfarm has 70km of inter-array cabling for example (37) (Figure 11) and more than 200 km of inter-array cabling has been laid for the London Array offshore windfarm. Both Alternating Current (AC) and High-voltage Direct Current (HVDC) cables are used depending on transmission requirements and cost considerations.

Figure 11

Inter array cabling at the Horns Rev 2 offshore windfarm

Image

Compared to offshore wind, the technology to convert energy from waves and tidal streams is at a relatively early stage of commercial development. Nevertheless it has reached the point where large-scale prototype devices are being deployed and in some cases, these are feeding energy into the grid. They include devices which are buoyant, semi-submerged, and fixed to the seabed by anchoring, monopoles and gravity base foundations. (38) Specific development zones in EU Member States, including testing facilities, grid infrastructure and licensing rounds are available to developers in Ireland, Denmark, the UK, Portugal, Finland, Spain, France and Italy. Within Europe there was over 14 MW of installed capacity as of end 2016 (39) most of which was in UK waters. The European Marine Energy Centre (EMEC) in Orkney provides the first full scale grid connected testing and accreditation facility in real sea conditions and ‘Wave Hub’ off the North Cornish coast provides shared offshore infrastructure for the demonstration and testing of arrays of wave energy devices.

The transmission infrastructure needed from wave and current devices is likely to be similar to the AC transmission infrastructure for offshore wind, although HVDC cables may also be considered in the future. Given the more energetic environments in which they need to be deployed, including current scoured rocky seabed, there may however be a need for more sophisticated mooring arrangements. At this stage of development the generation facilities are close to shore, with fewer cable and substation infrastructure requirements, compared to the more mature offshore wind sector.

8.1.3.   Carbon Capture and Storage (CCS)

The capture of CO2 from burning fossil fuels, and its transport and storage to geological formations under the seabed, is a relatively recent development in the energy sector. The process may involve transporting CO2 in pipelines from land based plants to offshore storage reservoirs as well as from offshore production facilities to land for treatment and then offshore again for storage. Relevant experience to date in the marine environment includes Enhanced Oil Recovery (EOR) (at the Norwegian Sleipner West gas field in the Northern North Sea) and the capture and storage of CO2 from the Sohvit gas field which has been piped 152km back to the field for injection into an offshore deep saline formation. (40) CO2 is compressed into its dense phase (i.e. liquid or supercritical phase) to allow for efficient flow.

8.1.4.   Transmission grids

Several medium and large HVDC interconnections cross the Baltic. They include links between Finland and Sweden, Sweden and Poland, Denmark and Germany, and Sweden and Germany. The 580km long NorNed link in the North Sea, which connects the power grids of Norway and the Netherlands, is the longest submarine high-voltage cable in the world. At the present time there is only one power transmission route between southern and eastern Mediterranean countries and EU Member States, between Morocco and Spain, but there are plans for other schemes such as between Tunisia and Italy (operational by 2017). Other examples are the subsea connections between Italy and Greece, Corsica and Italy, and from Sardinia to the Italian mainland.

8.1.5.   Projections for the future

Future energy transmission infrastructure in the seas around Europe will involve maintenance, upgrading to expansion, as well as some decommissioning. This will be needed to make best use of existing resources to accommodate more capacity (for offshore renewables generation) and take advantage of newer marine generation technologies. Changes are also being driven by strategic issues such as the need for better energy security, system optimisation and the cost of transmission.

The North Sea offers a unique opportunity to supply a substantial amount of low carbon, indigenous energy, produced close to the part of Europe where a large part of its GDP is generated. Until 2030, the expectation is that this new generation will mainly come from offshore wind generation. There is also a significant potential for electricity trade and market integration, which would address the structural electricity (wholesale) price differences between markets in the region (UK prices being significantly higher than those on the continent). The North Sea also allows for the demonstration and large scale deployment of new low carbon technologies, such as CCS, wave and tidal energy and offshore energy storage.

Improved interconnectivity and the coordinated development of an offshore grid will be key to capturing this potential. An integrated energy resource system in the Northern Seas will boost economic growth and the creation of highly-skilled jobs in the region. The development of such a system would benefit all countries, given the many complementarities in the energy profiles of the countries.

Existing marine infrastructure transports large volumes of oil and gas across Europe and beyond. This is not only set to continue but is likely to be supplemented as production becomes viable further offshore and new discoveries are made such as in the hydrocarbon fields in the Levant basin in the Eastern Mediterranean. There are infrastructure proposals aiming at transporting gas from Russia, the Caspian Region, the Middle East, the East Mediterranean and North Africa to the European Union Several of these proposals would include sections of subsea pipelines in the Black Sea, the Mediterranean Sea and the Adriatic Sea.

The infrastructure needs for CCS in Europe are unclear with future associated pipeline requirements difficult to predict although some proposals have reached a public consultation stage.

Infrastructure to integrate an increasing amount of offshore generation from renewable sources is another predicted requirement. Any growth of this sector will require an associated increase in cabling to transmit electricity between the generation sites and onshore grids as well as reinforcement of the onshore grid. The European Wind Energy Association (now Wind Europe) estimates that by 2020 there will be 24.6 GW installed capacity, By 2030 offshore wind capacity could reach 150 GW which would meet around 14 % of the predicted EU electricity demand (41). In the medium term the industry predicts that the North Sea will continue to be the main region for offshore deployment although the Atlantic and Baltic will contribute to attract important developments.

Commercial scale generation of electricity from wave and tidal current energy is less well advanced than offshore wind. This sector is estimated to deliver 120 MW by 2020 in the UK (42) while the Spanish Government's Renewable Energy Plan includes a target for an annual installation rate for marine energy of 20-25 MW between 2016 and 2020. An estimated 2GW of projects are being considered by Europe's largest utilities.

A meshed offshore grid, linking clusters of offshore wind farms to hubs, and linking these hubs to interconnections, would bring significant welfare benefits compared to the traditional practice of linking each windfarm radialy to the shore. These benefits would also include a significant reduction in total subsea cabling length, and by bundling the cables to shore the fragile and valuable coastal zone would have to be traversed less often. The North Seas Countries Offshore Grid Initiative (NSCOGI), set up in 2009 and involving nine EU Member States and Norway and also the Commission has been researching potential grid designs for the evolution of an offshore grid, including through the NorthSeaGrid project (43) and a study on the benefits of a meshed offshore grid (44). In the Mediterranean, MEDRING is promoting interconnections between the Mediterranean Basin's power systems. This includes plans for several interconnectors to supply the north with power from significant renewable wind and solar potential in the southern Mediterranean. (45)

Given the identified need for an increase in grid capacity, various infrastructure projects are being suggested. These include submarine power cable links to improve the connections between the littoral states. Norway and the UK are planning a 700km interconnector by 2020, and an interconnector between Germany and Norway is due to come on line in 2018. A number of projects are also foreseen to improve the interconnection level between the UK and Ireland and the continent. Various options for offshore grid designs to incorporate electricity from offshore wind farms are also being discussed. The North Sea Grid project has identified 16 interconnection projects in the pipeline, some of which have the potential to evolve towards a North Sea Grid (46).

Energy infrastructure priority corridors and areas identified in Annex I of the TEN-E Regulation (47) include the Northern Seas Offshore Grid (NSOG) as a priority electricity corridor, and the Baltic Energy Market Interconnection Plan as a priority gas corridor. The priority thematic areas in TEN-E which are most relevant to marine energy infrastructure are accommodating wind surplus generation in and around the Northern and Baltic Seas, and infrastructure for a cross-border carbon dioxide network.

Finally, it should be noted that decommissioning of energy infrastructure is also becoming relevant. In the North Sea this has been ongoing since the 1990s as systems reach the end of their economic life.

8.2.   NATURA 2000 in the marine environment

By December 2014, more than 3000 marine Natura 2000 sites had been established covering about more than 300 000 km2. This corresponds to just over 5 % of European Seas. The extent of coverage varies depending on distance from the shore with the majority close to the coast. For example marine Natura 2000 sites cover 33 % of European Seas within 0-1 nm of coastlines but only 2 % between 12nm and the exclusive economic zone (EEZ) boundaries. There has been significant progress in establishment of sites in the last few years and Member State efforts are still ongoing. However the assessment for the period 2007-2012 under Article 17 of the Habitats directive indicated that only 9 % of marine habitats and 7 % of marine species are in favourable status while 64 % of the marine species assessments and about 25 % of the marine habitat assessments were classed as unknown. (48)

The general requirements of the Habitats and Birds Directive, including the establishment and management of the Natura 2000 network, are described in Section 2 of this document. This section highlights and elaborates on aspects that are especially relevant to planning or implementing new energy infrastructure plans and projects in the marine environment, including links with the Marine Strategy Framework Directive (MSFD).

8.2.1.   The protection of marine environment, habitats and species

The Habitats Directive lists around 230 habitats in Annex I for which the designation of protected sites as well as other measures are required to achieve their favourable conservation status (FCS). Ten of these habitats are treated as ‘marine’ for reporting purposes;

1110 Sandbanks which are slightly covered by sea water all the time

1120 Posidonia beds

1130 Estuaries

1140 Mudflats and sandflats uncovered at low tide

1150 Coastal lagoons

1160 Large shallow inlets and bays

1170 Reefs

1180 Submarine structures made by leaking gas

1650 Boreal Baltic narrow inlets

8330 Submerged or partly submerged caves.

Some of these habitats are coastal whilst others occur in both shallow seas and deeper offshore waters (49) Submerged or partly submerged caves are probably the least likely habitat type to coincide with marine energy infrastructure but all of the remainder could potentially overlap and may be sensitive to activities associated with the construction, maintenance and decommissioning of marine energy infrastructure.

The Habitats Directive and Birds Directive also require protective measures to be introduced for certain marine species, most of which are highly mobile. In the case of the Habitats Directive these are the cetaceans, seals, reptiles, fish, invertebrates and plants listed in Annex II or IV. The Birds Directive establishes a general system of protection for all naturally occurring wild bird species in the EU, including seabirds.

Developers and planners need to assess the vulnerability and potential impacts of marine energy infrastructure on these marine habitats and species both within and outside the boundaries of Natura 2000 sites.

Where it is considered that the activity is not a plan or project in the sense of Article 6.3, Member States must nevertheless ensure the species and habitats for which a site has been designated do not deteriorate in accordance with Article 6.2. If the activities are directly connected with or necessary to the management of the site (in line with Art 6.3), then an Appropriate Assessment may not be necessary either.

Article 12 of the Habitats Directive and Article 5 of the Birds Directive require Member States to protect respectively Annex IV species of Community interest and all wild birds throughout their natural range within the EU.

The EU Marine Strategy Framework Directive (MSFD) was adopted in June 2008. The Directive establishes a framework within which Member States shall take the necessary measures to achieve or maintain good environmental status (GES) of the EU's marine waters by 2020 (Art.1.1). The main purpose is to protect, preserve, prevent deterioration or, where practical, restore Europe's oceans and seas where they have been adversely affected and to prevent and reduce impacts to the marine environment (Art 1.2(a) & (b)). Eleven qualitative descriptors for determining GES are listed in Annex I, several of which may be affected by the installation, maintenance and decommissioning of marine energy infrastructure. They include Descriptor 1 (Biological Diversity), Descriptor 6 (Sea Floor Integrity), Descriptor 11 (Introduction of energy including underwater noise), Descriptor 7 (hydrographical conditions), Descriptor 8 (pollution from contaminants) and Descriptor 10 (marine litter).

Two broad categories of habitats are considered in assessments, determination, and monitoring of GES: predominant habitats and special habitats. The latter refers especially to those recognised or identified under Community legislation (e.g. Habitats and Birds Directives) or International Conventions, as being of special scientific or biodiversity interest. The overlap with marine habitats listed under the Habitats Directive is shown in Table 4. MSFD does not focus on particular species but rather addresses all elements of marine biodiversity. All species covered by the Birds and Habitats Directive will therefore also fall under the remit of MSFD as part of an assessment of GES.

Table 4

Potential overlap between MSFD and Habitats Directive marine habitat types (50)

Predominant seabed habitat types for MSFD

HABITAT TYPES LISTED IN ANNEX 1 OF THE HABITATS DIRECTIVE AND CONSIDERED ‘MARINE’ FOR ARTICLE 17 REPORTING

1110

Sandbanks slightly covered all the time

1120

Posidonia beds

1130

Estuaries

1140

Mudflats & sandflats not covered at low tide

1150

Coastal lagoons

1160

Large shallow inlets and bays

1170

Reefs

1180

Submarine structures made by leaking gas

1650

Boreal Baltic narrow inlets

8330

Submerged or partially submerged sea caves

Littoral rock & biogenic reef

 

 

 

 

 

 

 

These structures may occur in a range of predominant habitat types

 

 

Littoral sediment

 

 

 

 

 

 

 

 

 

Shallow sublittoral rock & biogenic reef

 

 

 

 

 

 

 

 

 

Shallow sublittoral coarse sediment

 

 

 

 

 

 

 

 

 

Shallow sublittoral sand

 

 

 

 

 

 

 

 

 

Shallow sublittoral mud

 

 

 

 

 

 

 

 

 

Shallow sublittoral mixed sediment

 

 

 

 

 

 

 

 

 

Shelf sublittoral rock & biogenic reef

 

 

 

 

 

 

 

 

 

Shelf sublittoral coarse sediment

 

 

 

 

 

 

 

 

 

Shelf sublittoral sand

 

 

 

 

 

 

 

 

 

Shelf sublittoral mud

 

 

 

 

 

 

 

 

 

Shelf sublittoral mixed sediment

 

 

 

 

 

 

 

 

 

Upper bathyal rock & biogenic reef

 

 

 

 

 

 

 

 

 

Upper bathyal sediment

 

 

 

 

 

 

 

 

 

Lower bathyal rock & biogenic reef

 

 

 

 

 

 

 

 

 

Lower bathyal sediment

 

 

 

 

 

 

 

 

 

Abyssal rock & biogenic reef

 

 

 

 

 

 

 

 

 

Abyssal sediment

 

 

 

 

 

 

 

 

 

Estuaries (1130) typically fall within transitional waters of WFD and therefore may mostly fall outside the scope of MSFD. Coastal lagoons (1150) are considered under marine reporting if there is a permanent connection with the sea. Coastal habitats (e.g. Atlantic salt meadows (1330), Spartina swards (1320)) are covered under terrestrial reporting of HD but may occur within ‘coastal waters’ of WFD and hence fall within scope of MSFD

8.2.2.   Supporting measures and useful sources of information

The European Union and its Member States, as well as other European countries are Contracting Parties to various relevant international environmental Conventions and Agreements. These have helped to shape the legal framework for biodiversity policy and legislation within the EU and also helped define the relationship between the EU and other countries. European and national legal frameworks on nature and biodiversity conservation must take full account of the commitments entered into under these Conventions and Agreements. The most relevant to biodiversity conservation in Europe in the context of marine energy infrastructure are described below.

The Convention for the Protection of the Marine Environment of the North-East Atlantic (OSPAR) provides a mechanism for fifteen Governments of the western coasts and catchments of Europe, together with the European Union to cooperate to protect the marine environment of the North East Atlantic. The OSPAR Biological Diversity and Ecosystem Strategy identifies the laying, maintenance and decommissioning of cables and pipelines as one of the human activities that can adversely affect the marine environment. The potential impact of pipelines has been assessed by the OSPAR Joint Assessment and Monitoring Programme (JAMP) as part of an evaluation of the extent, input and impact of offshore oil and gas industry (OSPAR, 2009a), whilst the OSPAR Biodiversity Committee have assessed the environmental impacts of sub-sea cables (OSPAR, 2009). OSPAR has also produced Guidelines on Best Environmental Practice in Cable Laying and Operation, including the scope for potential mitigation measures (OSPAR, 2012). OSPAR's sister organisation, the BONN Agreement (51) is also working on an integrated approach to managing the impact of accidental spills of oil and other hazardous substances in the marine environment.

The Convention on the Protection of the Marine Environment of the Baltic Sea Area (HELCOM, ‘Helsinki Convention’) covers the Baltic Sea basin plus all inland waters in its catchment areas. All countries bordering the Baltic Sea plus the EU are Contracting Parties. The Baltic Sea Action Plan (2007) developed under the auspices of HELCOM and adopted by all the coastal states and the EU includes agreement that Contracting Parties will follow relevant processes to prevent, reduce or offset as fully as possible the environmentally significant adverse impacts caused by any offshore installation, including subsea cables and pipelines.

The Contracting Parties of the Convention for the Protection of the Marine Environment and Coastal Region of the Mediterranean (‘Barcelona Convention’) undertake ‘to prevent, abate and combat pollution of the Mediterranean Sea and to protect and enhance the marine environment in that area’ (Art 4(1)). The obligations which are particularly relevant to marine energy infrastructure are those concerned with pollution resulting from exploration and exploitation of the continental shelf and the seabed and its subsoil (the ‘Offshore Protocol’), dealing with pollution emergencies, and monitoring, which has been ratified by the EU.

The Convention on Environmental Impact Assessments in a Transboundary Context (ESPOO Convention) promotes international cooperation and participation of the public when the environmental impact of a planned activity is expected to cross a border. Large diameter oil and gas pipelines are on the list of activities that are likely to cause significant adverse transboundary impact and which should be subject to the EIA procedure set out in the Convention.

The Convention on the Conservation of Migratory Species of Wild Animals (‘Bonn Convention’) aims to preserve migratory species throughout their natural range. Several agreements signed under this Convention are relevant to the management of conflicts between migrating animals and marine energy infrastructure

Agreement on the Conservation of Small Cetaceans of the Baltic, North East Atlantic, Irish and North Seas (ASCOBANS): this aims to co-ordinate measures to reduce negative impact of by-catches, habitat loss, marine pollution and acoustic disturbances among the ten parties. A resolution on adverse effects of underwater noise on marine mammals during offshore construction activities for renewable energy production was adopted in 2009 and a resolution on the adverse effects on sound, vessels and other forms of disturbance on small cetaceans was adopted in 2006. Both are relevant to considering the potential impact associated with marine energy infrastructure

The Agreement on the Conservation of Cetaceans in the Black Sea, Mediterranean Sea and contiguous Atlantic area (ACCOBAMS) is a cooperative framework for the conservation of marine biodiversity in the Mediterranean and Black Seas. Its main purpose is to reduce the threat to and improve knowledge about cetaceans in these seas. The agreement includes resolutions on the assessment and impact assessment of man-made noise which is relevant to managing the conflicts between cetaceans, which are protected by the Habitats Directive, and marine energy infrastructure. Guidance on underwater noise mitigation measures have also been published (ACCOBAMS-MOP5, 2013).

8.3.   Potential impacts and approaches to mitigation

Environmental impacts of energy infrastructure on marine biodiversity can arise from biological, physical and chemical pressures, with precise effects depending on a range of factors. These include whether the infrastructure is at an installation, operational or decommissioning phase; the timing and frequency of works; the scale of the infrastructure; and where it is located. Pressures on protected habitats and species can be indirect as well as direct, and impacts may be acute or chronic. The potential impacts on Natura 2000 habitats and species are summarised in Table 5. The effects and potential mitigation measures are described below. Projects will need to be assessed on a case by case basis to determine whether such measures are sufficient to safeguard the Natura 2000 interest.

However, for marine energy infrastructure plans and projects limitations which may affect the adequacy of AAs include:

Data availability, accessibility and ability to gather relevant data

Scientific understanding – of ecological processes, sensitivity of marine Natura 2000 habitats and species to particular pressures, and of potential cumulative effects

Mitigation strategies – short timescale over which to determine effectiveness, experimental or poorly developed as yet

Development type – novel, still under development, and complex in that they may have both terrestrial and marine components

It is also the case that for marine renewables [wave and tidal power], much of the impact assessment work to date has been concerned with the generation devices. These have still to be operationalised at scales where they might become commercially viable operations. The potential environmental impacts of arrays and their required transmission infrastructure has therefore still to be tested. There is also uncertainty in our understanding of the scale and complexity of the combined and cumulative effects of the marine energy infrastructure in association with other maritime activities, hence the need for strategic planning as suggested in Section 4. A case by case assessment will typically be required in order to identify the type and severity of likely impacts with reference to the site specific circumstances and available data.

Table 5

The potential sensitivity of habitats and species protected under Natura 2000 to pressures associated with the construction, maintenance and decommission of marine energy infrastructure

 

PHYSICAL LOSS/DAMAGE

BIOLOGICAL DISTURBANCE/DAMAGE/LOSS

HYDRO-LOGICAL CHANGE

HAZARDOUS SUBSTANCES

ELECTRO-MAGNETIC FIELDS+

Sandbanks

V

V

V

V

 

Posidonia beds

V

V

V

V

 

Estuaries

V

V

V

V

 

Mudflats & sandflats

V

V

V

V

 

Coastal lagoons

V

V

V

V

 

Inlets & bays

V

V

V

V

 

Reefs

V

V

V

V

 

Structures made by leaking gas

V

V

V

V

 

Boreal Baltic narrow inlets

V

V

V

V

 

Caves*

?

?

?

V

 

 

Cetaceans

?

V

?

V

 

seals

?

V

?

V

 

reptiles

?

V

?

V

 

fish

?

V

V

V

V

invertebrates

V

V

?

V

 

plants

V

V

V

V

 

seabirds

 

V

 

V

 

*

as unlikely routeing location

+

mechanisms and impacts still poorly understood

?

unknown/poorly understood

—    Summary of potential impacts

There is a significant body of information on the potential impacts of subsea pipelines because of their extensive and longstanding use to transport oil and gas in the marine environment. Cable laying is also a widely used technology although most information on potential environmental impacts come from the telecommunications sector. Cables used for energy transfer are generally heavier, stiffer and have a larger diameter. Ways in which to avoid or mitigate environmental impacts of both cables and pipelines have also been subject to investigation and include avoidance and mitigation strategies relevant to Natura 2000 habitats and species.

The most obvious direct effects are damage, disturbance or loss of benthic habitats during cable and pipeline laying operations. This is because routeing is mostly across areas of soft sediment involving trenching or burial operations. The affected space is strongly dependent on the techniques and machinery used as well as the type of sediment and may cover a zone within 10-20m of the line. The benthos in this disturbed zone can recover although not necessarily to the same suite of species and the rate of recovery will be influenced by the sediment type and local conditions. Impacts will depend on the scale and longevity of any changes as well as site specific characteristics. Different sediment types may also be introduced into the site, potentially changing its character. Subtidal sandbanks, the soft sediment habitats of inlets and bays, intertidal mudflats and sandflats, seagrass beds, Posidonia beds and reefs are some of the Natura 2000 habitats which are vulnerable to direct habitat damage or change associated with routeing cables and pipelines. In some cases cables may need to cross areas of rocky seabed. Habitat damage, for example to reef environments, may occur if trenches need to be cut into the rock.

The introduction of the artificial hard surfaces of the cables and pipelines as well as rock armour and concrete mattresses to protect operational infrastructure or decommissioned pipelines can have a localised effect by enabling colonisation by species untypical of soft sediment habitats. There is also the potential for invasive alien species to colonise and disperse from such structures. Changes in turbidity, seabed currents and topography are another potential pressure on benthic communities in the vicinity of cables and pipelines, whilst changes in feeding behaviour, disturbance, and displacement during installation works may have an impact on marine mammals and seabirds protected under the Habitats and Birds Directives. Less is known about the effects of the electromagnetic fields (EMF) around cables but this could be an issue for fish like the sturgeon, a protected species under the Habitats Directive, which are known to be able to detect these types of fields. Heat emissions may also impact some species which are sensitive to even minor increases in the ambient temperature but the type and significance of any effects on benthic communities such as those associated with sandbank habitats are not known. Reduction and avoidance of such emissions by cable design is discussed in the section on mitigation measures.

The risks and potential impacts of chemical contamination on Natura 2000 habitats and species are other aspects which need to be considered. These could arise from damaged pipelines, disturbance of contaminated sediments or hazardous substances, or from the breakdown of cables. Emissions from vessels involved in construction and maintenance of infrastructure may have water quality implications although it is difficult to separate these out from emissions associated more generally with offshore construction and maintenance works.

—    Summary of potential mitigation measures

The OSPAR Commission has provided a useful summary of the potential mitigation measures to minimise or avoid environmental impacts associated with sub-sea cables (Table 6) (52). Foremost amongst these are careful routeing and scheduling of installation activities, suitable choice of cable types, appropriate burial of the cable, and use of inert materials if protective covering is necessary. Disturbance of the seabed, noise, contamination, smothering, habitat loss, corridors for dispersal for alien species and cumulative effects are also relevant to the construction and maintenance of sub-sea pipelines.

Table 6

Possible mitigation measures to avoid or minimise environmental impacts of various anthropogenic pressures due to cable laying and operation (from OSPAR, 2009)

 

Mitigation measures

Environmental impacts

Route selection

Construction times

Burial technique

Burial depth

Cable type

Removal

Disturbance

x

x

x

(x)

(x)

See text

Noise

(x)

(x)

(x)

 

 

 

Heat emission

(x)

 

 

x

x

 

Electromagnetic

 

 

 

x

x

 

Contamination

x

 

(x)

(x)

x

x

Cumulative effects*

x

x

x

x

x

 

x: Important measure; (x) less important measure; * Knowledge insufficient

The following sections provide more detail on the potential impacts and mitigation measures concerned with the installation, operation and decommissioning of cables and pipelines.

8.3.1.   Installation

A variety of methods are used to deploy sub-sea cables and pipelines. In areas of soft sediment, ploughs and water jetting equipment individually and in combination can be used to create trenches, typically 1-3 m deep, and simultaneously bury cables and pipelines within them. Alternatively, spoil from the trench is temporarily removed from the site or deposited alongside the works with cable or pipeline placement and infilling of the pre-cut trenches taking place sometime later. Invertebrate mortality along the proposed cable route is likely to be higher when jetting is used (liquefying the sediment below the cable to let it sink to a specified depth) as there is more disturbance to the sediment and the likely exposure of many of the animals to predation. When ploughs are used the skids that support the plough can leave a surface footprint, particularly in zones of soft sediment. Potential impacts under these circumstances are increased sediment compaction and disruption of marine fauna. The zone of disturbance will depend on the characteristics of the environment and installation method. (53)

Whilst some mobile species can avoid the disturbed areas, most sessile species cannot and certain biogenic reef habitats such as horse mussel beds and maerl beds, two sub-habitat types of subtidal sand banks, as well as seagrass beds can be particularly vulnerable to direct loss or smothering by suspended sediments (e.g. OSPAR 2010). Localised damage of benthic communities of reef habitats may also result when cabling crosses areas of rocky seabed either through abrasion or the excavation of trenches through soft and hard rock.

The re-suspension and remobilisation of nutrients and hazardous substances during trenching operations poses risks in areas of contaminated sediment while changes in seabed profile may lead to changes to the hydrodynamic regime. This can affect the stability of subtidal habitats, such as sand banks, as well as potentially altering the associated marine communities. A final consideration is the potential impact of commissioning activities. In the case of pipelines this involves pumping through test water containing biocides and corrosion inhibitors. The composition and dispersion of test waters needs to be determined, although increased concentrations at the discharge points are generally considered to be short-term. There is insufficient information to gauge the potential effects on the marine communities associated with Natura 2000 habitats and on protected species.

CHANGES TO BENTHIC HABITATS, COMMUNITIES AND SPECIES

The immediate impacts of laying cables and pipelines are localised damage, abrasion, displacement and the disturbance of seabed habitats and species in a swathe around the construction works (Söker et al. 2000). Benthic communities within and close to trenches can be affected by sediment spill, burial, stirring, settling of fine sediment, and changes in chemical properties through the resuspension of contaminants or disturbance of anoxic layers but these effects may only be short-term or result in subtle longer term changes whose significance is difficult to evaluate.

A study of impacts and recovery associated with a cable trench in the Lagoon of Rødsand, a Natura 2000 site in Denmark, for the Nysted offshore wind farm showed significant differences in the shallow water Macoma community, immediately following the works. The shoot density and biomass of eelgrass rhizomes was also reduced close to the trench (attributed to the combined effect of shading and burial), but recovered within two years to pre-construction values (Birklund, 2003). The benthic macrofauna along a submarine cable in the Baltic between Sweden and Poland also showed recovery with no significant changes in the composition, abundance or biomass that could be clearly related to cable installation after one year (Andrulewicz et al., 2003).

These studies suggest that although impacts on subtidal soft sediment communities such as those found on shallow sandbanks can be significant, they may be relatively short-lived and limited to a cable corridor of perhaps 10 m wide (OSPAR, 2009). Longer term effects may be seen on biogenic reefs comprised of species sensitive to smothering such as maerl beds, on submarine structures made by leaking gas or on species which are particularly long lived and slow to re-establish, such as horse mussel reefs. The precise effects will depend on the habitats present and the characteristics of the site.

Apart from direct damage other potential pressures from construction works on benthic habitats and species are increases in turbidity, contaminate release and changes in sediment composition. Impacts will depend on the scale and longevity of any changes as well as site specific characteristics. Soft sediment being redistributed onto rocky reef habitats, or habitats sensitive to smothering such as Posidonia beds and maerl beds, will be more of an issue than resettlement in areas with similar sediment characteristics (Zucco et al., 2006; Hall-Spencer & Moore, 2000). Different sediment types may also be introduced into the site, potentially changing its character. At the Nysted offshore windfarm in Denmark, for example, the need to cover exposed cables sometime after the initial laying operation meant that shingle had to be imported to fill the trench in an area dominated by soft sediments (Andrulewicz et al., 2003).

In areas of rock, highly mobile sand, or deep waters, where the seabed is unsuitable for the burial of cables and pipelines, infrastructure may be protected or stabilised by rock amour and concrete mattresses. A temporary increase in turbidity in the vicinity of operations is likely even when no trenching takes place. Rock dumping can involve the placement of 1 tonne of rock per square meter, 5m either side of the pipeline, and therefore could introduce a significant amount of material of a different character to existing sediments in the area prior to installation.

Examples of mitigation measures applied to subtidal habitats in the Natura 2000 network

The route of the SwePol transmission line between Sweden and Poland to parts of the Slupsk Bank Natura 2000 site was partially rerouted as a mitigation measure. Whilst most of the cable route passes through endangered habitats, the stone and boulder areas of the Slupsk Bank which support declining red algae species was avoided. The same project eliminated potential chemical contamination from Chlorine by changing the proposal from a monopolar design which would require sacrificial anodes to a bipolar system (Andrulewicz et al., 2003).

DAMAGE TO INTERTIDAL HABITATS AND SPECIES

Intertidal habitats and species protected by the Habitats and Birds Directives may be subject to disturbance, damage and loss from cables and pipelines laying operations. The Natura 2000 habitat types most likely to be affected are marine inlets and bays, Boreal Baltic narrow inlets, estuaries, intertidal mudflat and sandflats, and Posidonia beds. The most vulnerable protected species include waders and wildfowl.

The effects on infauna are often dramatic but may be short-term. A study of the effects of trenching for pipeline installation across an area of intertidal mud and sandflats in Ireland, for example, showed a total loss of benthic invertebrates and a change in sediment structure immediately after the works were completed. The affected area was subsequently recolonized to the point where there was no discernible difference in the number of individuals of all species collected in sediment cores six months later, although the taxa represented were different (Lewis et al., 2002). Other studies have reported similar effects and although species richness may be restored, total biomass may take several years to reach similar levels to that of the surrounding undisturbed area. Recovery will depend on the species present in the surrounding areas, their lifecycle and mobility, and the timing of any construction works.

Examples of mitigation measures applied to protect intertidal habitats

Mitigation measures relating to cable landfall and the transition pit across intertidal habitats such as those in estuaries, range from rerouting to avoid sensitive areas, minimising the affected area, careful timing of construction works to avoid disturbance and using less damaging excavation techniques. These are some of the mitigation measures that were agreed when laying export cables across an intertidal area of the Swale Estuary to connect the London Array offshore windfarm to the transmission grid (London Array/National Grid 2007).

No works to be undertaken within the Swale SPA and Ramsar site, or within 500 m of their seaward boundary, during the period 1 Oct – 31 March

No works at any time within areas supporting eelgrass beds or within the main mussel beds. This encompasses all works associated with cable laying, including the position of the anchor points for barges (if needed).

Cables installed across the intertidal area should be buried to a depth of not less than 1m, and normally installed by means of ploughing or and trenching. If trenching is used within the intertidal area, excavation and subsequent backfilling of the cable trench should be carried out in such a way as to maintain the sediment profile. Jetting should only be considered as an exceptional technique, subject to prior approval and monitoring

Ornithological surveys of the foreshore, intertidal and onshore areas should be carried out between October and March in each year of construction and for at least one year

No works to be carried out until measures regard handling and storage of potentially hazardous substances, response to spillages and provision for surface water drainage have been approved by the appropriate regulatory bodies

Staff/contractors to be briefed on the locations of environmentally sensitive features and on the working practise required to safeguard these features

Intertidal cable laying methods should be selected that reduce the liberation of suspended sediment to a minimum

Construction activities should be undertaken in a way that minimises disturbance to birds e.g. directional lighting techniques.

DISTURBANCE AND DISPLACEMENT OF HIGHLY MOBILE SPECIES

Noise and the presence of people, machinery and activities associated with construction works in both intertidal and offshore locations are known to affect the behaviour of highly mobile species including seabirds, waders and wildfowl, cetaceans, seals, turtles and fish protected under the Habitats and Birds Directives. The main effects are disturbance and displacement. The potential impacts, which are species specific, include loss of feeding opportunities, collision risk, and barriers to movement, both of which could have energetic costs. Diving birds are known to be very sensitive to visual disturbance and are displaced by ship traffic (Mendel et al., 2008). Longer term impacts may occur such as auditory damage to marine mammals that are exposed to high levels of sound for long periods. A critical issue is the level of background noise relative to construction noise since this influences the ability of animals to detect and respond to the pressure (Robinson & Lepper, 2013).

Noise from pipeline and cable laying is typically associated with trenching, pipe laying, and rock placement. In the case of the proposed 65 km export cable from the Beatrice Offshore Wind Farm in the Moray Firth installation noise was distinguished by modelling which identified the potential disturbance zone for different species (see box below). The OSPAR assessment is that there are no clear indications that underwater noise caused by the installation of sub-sea cables poses a high risk to marine fauna (OSPAR, 2009).

Scoping to assess risks to mobile marine species

Assessment of the likely impact of noise associated with the installation of 65 km of export power cables at the Beatrice Offshore Windfarm to landfall in Moray Firth, North –East coast of Scotland, was undertaken by modelling the potential behavioural impact on a number of species (Nedwell et al., 2012). The results suggest that trenching was likely to have the greatest impact on the various marine species and that the greatest likely impact was on harbour porpoise.

Image

The dBht (Species) metric has been developed as a means for quantifying the potential for a behavioural impact on a species in the underwater environment (Nedwell et al., 2007). The sound will be perceived differently by different species. Levels above 90 dBht were considered to elicit a strong avoidance reaction by virtually all individuals.

Image

 

In this case there was predicted to be a short-term localised noise disturbance during cable laying operations which could lead to temporary displacement of marine mammals from a very small proportion of their suitable habitat (Arcus, 2012). Other aspects of the construction works were considered to be significant for bottlenose dolphin and harbour seal and consequently subject to mitigation measures e.g. ‘soft starts’ for pile driving operations, and the use of marine mammal observers.

8.3.2.   Operation

The negative impacts associated with operational cables and pipelines are most likely to arise from pollution. This could be from acute incidents such as accidental discharges from operational support vessels or from the rupture of pipelines. Chronic effects resulting from the breakdown of cables and pipelines and the leaching of chemicals may occur. The likely effects of electromagnetic fields (EMF) and increases in temperature around cables are less well studied. Maintenance and repair works which result in re-suspension of sediments and hazardous substances would result in similar effects to those described during the installation work.

POLLUTION

Pipeline damage may result from corrosion, seabed movements, and contact with anchors and bottom fishing gear. The consequences can be small short-term or long-term leakages or more catastrophic blow outs resulting in major pollution incidents. The European Gas pipeline incident database identifies external interference as the most common cause of incidents (48.4 %) followed by construction defect/material failure and corrosion but do not distinguish between subsea and other gas pipelines (EGIG, 2011). Hydrocarbons, and gases such as carbon dioxide, methane, and hydrogen sulphide are some of the contaminants that may be introduced to the water column.

A further source of contaminants are sacrificial anodes used to slow the corrosion of pipelines in seawater. Components of these anodes (mercury, copper, cadmium and lead) can migrate through sediment and accumulate in some marine species. The rate of corrosion of these anodes will depend on the site characteristics such as water depth, temperature, and salinity. The likelihood of effects on Natura 2000 habitats and species is unclear.

In the case of CCS operations, temperature and pressure will determine whether the CO2 is transported through pipelines as a liquid or as a gas. This needs to be carefully controlled as hydrate formation in the pipeline increases internal corrosion and could cause blockages, increasing the risk of pipeline failure. The principal effect of pipeline damage or failure would be acidification of surrounding water.

The acute and chronic effects of oil pollution on marine species and habitats listed in the Habitats and Birds Directive such as marine mammals, seabirds, seagrass beds and mudflats and sandflats are extensively studied and well documented (54). So is the need for monitoring and contingency planning to avoid escalation of incidents and reduce the impact. There is also information on the effects of other pollutants such as heavy metals in marine mammals, and the potential effects of ocean acidification, but not specifically in relation to marine energy infrastructure.

The main approach to mitigating pollution from cables and pipelines is to minimise the risk of discharges, by design and regular inspection. Regular monitoring acts as an early warning system, and contingency planning sets out measures to reduce any impacts on marine habitats and species should incidents occur.

ELECTROMAGNETIC FIELDS AND EFFECTS ON FISH

Low-frequency electromagnetic fields (EMF) are emitted during the transmission of electricity, including along subsea cables. Electrical fields can also be induced in the surrounding environment by the movement of water and organisms through the magnetic field. Marine organisms that use EMFs for spatial location, large scale movement, small-scale orientation, feeding or finding mates could therefore show some effects if the EMF is large enough and/or discernible from background levels. The likelihood and significance of any impacts are not well understood (Boehlert & Gill, 2010). Simulation of magnetic fields around the bipolar transmission line between Sweden and Poland suggested that any changes of inclination would not exceed natural changes in the terrestrial field at a distance exceeding 20m from the cables. In-situ measurements of the underwater magnetic field once the cabling was in place showed that they did not exceed those predicted by the simulations (Andrulewicz et al., 2003).

Fish species known to detect electric fields include Elasmobranchs and sturgeons and some of these show behavioural changes within the range of EMF which may be emitted around cables. In the case of magnetic fields, monitoring of migrating European eel (A.anguilla) in the Baltic Sea reported temporary responses with the eels diverting from cables in their path during migration but there was no evidence that this was a permanent obstacle. In the case of electrical fields, changes in behaviour of Lesser Spotted Dogfish (S.canicula), Thornback Ray (R.clavata) and Spurdog (S.acanthias), which may be associated with sandbank habitats, have been reported although the effects differed between individuals (55).

Some mitigation is already incorporated through industry standard shielding which restricts the directly emitted electric fields but not the magnetic component. Other possibilities are modifications in cable design, reductions in current flow, and deeper burial.

The mechanisms and impacts of EMF on marine organisms are not fully understood nor is the significance of the levels emitted compared to those of the Earth's geomagnetic field. Current practice in Europe involves consideration of EMF in EIA and consent processes but with different levels of obligation regarding the monitoring and investigation of any potential effects in different Member States.

CHANGES TO BENTHOS

In the longer term, for surface laid cables and pipelines, the introduction of hard substrates can have a ‘reef effect’ as they are colonised by a variety of species (56). By way of example, species predicted to colonise rock dumps and concrete mattresses around pipelines in the northern North Sea Mariner Area Development include hydroids, soft corals, anemones, tubeworms, barnacles, tunicates and mobile organisms like crustaceans, polychaetes and echinoderms (Statoil, 2012). At the Nysted and Horns Rev offshore windfarms colonisation around the base of the turbines has increased biomass and habitat heterogeneity. The introduction of hard surfaces in an area dominated by sandy sediments has resulted in a significant change in the benthos. There is also the potential for invasive alien species to disperse through colonisation of these structures especially if there are associated changes in temperature. Small rises in temperature can occur within a few centimetres of power transmission cables depending on burial depth, type of cable and characteristics of the surrounding sediment. These increases are likely to be more significant for AC cables than HVDC cables at equal transmission rates. Heat emission may alter the physico-chemical conditions in the sediment and increase bacterial activity which could have secondary impacts on benthic fauna and flora (Meissner & Sordyl, 2006).There is evidence that some species are sensitive to even minor increases in the ambient temperature but the type and significance of any effects on benthic communities such as those associated with sandbank habitats are not known.

8.3.3.   Decommissioning

There are various international obligations on the decommissioning of offshore installations, such as those agreed by OSPAR (Decision 98/3) but these do not cover cables and pipelines. The potential impacts of decommissioning cables and pipelines on marine habitats and species are similar to those described for installation and can be supported by similar mitigation measures. In the case of pipelines the starting point is purging and cleaning pipelines. This is followed by removal from the seabed or cutting and abandonment in-situ with appropriate protection and subsequent monitoring. Buried cables may need to be exposed by ploughing or water jetting prior to removal disturbing the sediment and associated benthic communities. Other associated infrastructure such as mattresses may need to be removed by grabs, depending on their condition.

Techniques used for pipeline removal such as reverse reeling, cutting and lifting, and towing at the surface or a controlled depth may directly damage seabed habitats, disturb or displace mobile species and reduce water quality if there are discharges to sea from vessel traffic and operations. The physical disturbance to the seabed, increases in turbidity, potential smothering of benthos and recovery rates are likely to be similar to those described for installation, impacting the same habitats and species in a zone either side of the pipeline. Older mattresses or those which have broken up may need to be removed by conventional grabs. Where rock dumps need to be placed on the seabed to protect sections of decommissioned pipelines these will provide a hard surface for attachment in what are predominantly soft sediment areas, changing the marine communities in these areas.

Decommissioning plans are usually required at the outset of a project, with a case by case assessment as they will vary depending on pipeline type, diameter, length, integrity and condition. Options include leaving in situ, reuse in situ, reuse in other locations, or removal and disposal onshore. In the Danish Field to the west of Jutland, for example, an investigation into decommissioning options identifies the first and last of these as meriting further consideration. Where pipelines are left on the seabed long-term monitoring is likely to be needed to ensure stability and safety for other sea users as they may take decades to deteriorate (HSE, 1997).

8.3.4.   Cumulative effects

Marine energy infrastructure projects do not take place in isolation. They are part of oil and gas, CCS, offshore wind and marine renewable schemes and may also be located near other plans and projects. The combined effect of these activities, whether past, present or planned for the future, can result in cumulative environmental effects on Natura 2000 habitats and species. Highly mobile species such as marine mammals, fish and seabirds may be particularly vulnerable as they could be affected by activities in a variety of locations, including some which are widely separated.

Cumulative effects may arise within an individual project, for example, because of the density of infrastructure and activities in one place (cables, pipelines, platforms, maintenance vessel traffic). The potential for cumulative effects also arises when there are other schemes in the vicinity. In the case of the Beatrice field offshore wind farm in the northern North Sea the predicted noise from cable laying and an increase in suspended solids in the vicinity of the transmission works were not considered to be significant. However when considered together with other activities on site and another nearby offshore renewables scheme, simultaneous construction noise was assessed as potentially having a cumulative effect on herring, European eel, salmon and sea trout. On the other hand when the two developments were considered together, no additional effects on sediment transport were considered to be likely (Arcus, 2012).

Cumulative impact assessment needs to be undertaken as part of EIAs, SEAs and is a legal requirement for the Appropriate Assessment of plans and projects under the Habitats Directive. Scoping potential impacts, suggesting mitigation and monitoring measures as well as reporting on areas of uncertainty are key elements. There is both generic and sector specific guidance on assessing cumulative effects (e.g. RenewableUK, 2013) with further detail provided in Section 7.3 of this document.

8.3.5.   Potential mitigation measures

Guidance on the approach to mitigation is set out in Section 5 of this document. Key opportunities for mitigating the potential impacts of marine energy infrastructure projects on Natura 2000 habitats and species are listed below.

Possible options for mitigation measures at different stages of energy infrastructure projects

Assessment

Scoping, screening and initial appraisal of installation, operation and decommission stages to identify potential pressures, effects and impacts on Natura 2000 habitats and species. Mitigation measures to be proposed as part of this process.

Routeing/Placement

Route cable and pipeline corridors to avoid Natura 2000 habitats and impacts on EU protected species e.g. avoiding Posidonia beds, seal haul out sites, intertidal feeding areas for waders and wildfowl.

Avoid construction of substations/converter stations in Natura 2000 sites

Avoid routeing through areas where there is a risk of disturbing hazardous substances or contaminated sediments

Footprint

Reduce zone of disturbance by minimising trench corridors for example by considering infrastructure type, size, spacing between trenches, bundling cables, and parallel routeing

Minimise cable runs connections between generation devices (inter-array), converter stations and substations and grid entry points on land.

Deploy installation methods (e.g. ploughing, jetting, horizontal directional drilling, coffer dams) which minimise disturbance to seabed and intertidal habitats.

Consider opportunities to co-ordinate installation work in trenches and to install spare capacity in anticipation of future development

Minimise the amount of material to be dumped on the seabed

Time frame

Minimise installation and decommissioning times to reduce period of disturbance.

Scheduling

Minimise time between trenching and burial of cables and pipelines

Schedule installation and decommissioning operations to avoid periods when disturbance of protected species is likely to have significant effects such as breeding and migration seasons.

Design

Assess size and type of infrastructure required with reference to likely environmental impacts e.g. cable types to reduce magnitude and extent of EMFs.

Operational issues

Avoid installation and decommissioning methods that are likely to result in noise and visual disturbance e.g. underwater explosives

Use mitigation measures to reduce risk of pollution incidents and have contingency measures to deal with incidents should they occur

Use mitigation measures to reduce risk of impact where noise is likely to be an issue e.g. active sound mitigation measures (bubble curtains, isolation of piles, coffer dams), soft start and marine mammal observers when pile driving.

Reduce the magnitude and extent of the EMF by reviewing cable type and burial depths

Consistent with legal obligations, select decommissioning options which minimise potential environmental impact.

Monitoring

Enabling rapid response/ intervention if thresholds likely to be breached e.g. in relation to pipeline integrity, coverage of cables, noise, EMFs

Framework

Work within existing international, European and national legislation with reference to relevant guidance e.g. MARPOL, OSPAR, SEA/AA

8.4.   The importance of strategic planning

Marine energy infrastructure is one of many uses competing for space in European seas. In many parts of the world the potential conflicts which arise are being identified through a process of Maritime Spatial Planning (MSP). MSP is also being used to take a more integrated and strategic approach to planning the use of our seas across different sectors, including environmental protection and nature conservation.

Potential Benefits of Marine Spatial Planning (on the basis of UNESCO/IOC (57) )

Economic Benefits

Creation of greater certainty to the private sector when it plans new investments, often with a 30-year lifetime;

Identification of compatible uses within the same area for development;

Reduction of conflicts among incompatible uses and between uses and nature;

Streamlined permitting process; and

Promotion of the efficient use of resources and space.

Environmental Benefits

Identification of areas of biological or ecological importance;

Incorporation of biodiversity and ecosystem objectives at the heart of marine spatial planning and management, applying the ecosystem approach

Allocation of space for biodiversity and nature conservation; also of space for renewable energies for climate reasons

Provision of a planning context for a network of marine protected areas; and

Reduction of negative impacts of human uses on marine ecosystems based on an Strategic Environmental Assessment (SEA) taking cumulative impacts into account

Preserving the typical vast open space of the sea by keeping large areas free from concrete uses

Social Benefits

Improved opportunities for public and administrative participation, for transboundary consultation and cooperation;

Identification of impacts of decisions on the allocation of ocean space for certain use (or non-use) for onshore communities and economies;

Identification and improved protection of cultural heritage; and

Identification and preservation of social and spiritual values related to ocean use.

Within the EU, the MSFD requires Member States to develop marine strategies for their own waters, and coordinated strategies with other Member States for the Baltic Sea, North-East Atlantic Ocean, Mediterranean Sea and Black Sea. This is the environmental pillar of the EU Integrated Maritime Policy, promoting an ecosystem approach to management and the integration of environmental concerns into different policies. Maritime Spatial Planning (MSP) has been identified as a cross-sectoral tool supporting these objectives. The EU Directive 2014/89/EU establishing the framework for maritime spatial planning (MSP Directive) (58) calls on the Member States to establish and implement maritime spatial planning with the aim to support sustainable development of marine areas, applying an ecosystem approach and promoting the co-existence of relevant activities and uses. Its recital 23 acknowledges that where maritime spatial plans are likely to have significant effect on the environment they are subject to the SEA Directive, as well as where maritime spatial plans include Natura 2000 sites, such an environmental assessment can be combined with the requirements of Article 6 of the Habitats Directive, to avoid duplication.

The strategic planning for marine areas includes;

Development of sustainable maritime activities and the protection of the marine environment based on a common framework and similar legislative implications

Reducing the risk of spatial conflicts between expanding maritime uses, including the protection of the marine environment, in such a way that the social and economic demands on marine areas are compatible with safeguarding the marine environment and its ecological functions.

Supporting the implementation of existing EU legislation

A common approach providing Member States who apply MSP with an opportunity to share their expertise with others.

Experience has shown time and again that taking environmental considerations into account early on in the decision making process can lead to solutions being found when there is still a wide choice of options available. It also fosters a more open and imaginative decision making process where co-benefits and win-win solutions may be easier to identify and are less costly or onerous to implement. This also may include informal strategies and processes in advance or in parallel to formal planning procedures, such as the Integrated Coastal Management (ICM), especially in order to take into account land-sea-interactions or the use of matrices to analyse the significance of an impact.

If, on the other hand, this inter-sectoral dialogue is left to the last stages of the Article 6.3 permitting procedure the range of solutions becomes much narrower and less effective as in a spatial and sectoral overall context (and more expensive to implement) and there is a greater tendency for the discussion to become polarised and more confrontational.

The increasingly transboundary nature of many marine energy infrastructure projects is another reason why strategic planning is beneficial, ensuring a consistent approach to project level where many parties and legal frameworks are involved.

Transboundary planning is also being undertaken within the marine energy sector (e.g. North Seas Countries Offshore Grid Initiative) as well as for all sea uses (e.g. BaltSeaPlan and the TPEA project (Transboundary Planning in the European Atlantic) involving Spain Portugal, Ireland and the UK). Grid planning for offshore windfarms in the German EEZ is an example of applying a sector specific approach, incorporating environmental safeguards as key principles, and integrating this into a multi-sectoral spatial plan. A similar approach but cross-border and during the planning of options for transmission and generation would also enable cumulative impacts at a large scale to be identified and addressed before consenting.

Spatial planning including designations of pipelines and cables in the German EEZ and Offshore grid planning in the German North Sea EEZ

The German Spatial Plan sets out guidelines for spatial development, alongside targets and principles for functions and uses of the German EEZ according to the German Spatial Planning Act. It includes provisions for co-ordinating the laying of pipelines and submarine cables with other activities such as shipping, fisheries, and nature conservation. Priority areas have been designated for shipping, pipelines, and offshore wind energy production and, where consistent with international law; other uses are prohibited in these areas unless they are compatible. In NATURA 2000 areas, however, wind turbines are not allowed. At the transition to the territorial sea and to the crossing of the traffic separation schemes submarine cables for the transport of power generated in the EEZ shall be routed along designated cable corridors. With the establishment of the plan a SEA has been carried out. To minimise possible negative impacts on the marine environment when laying pipelines and cables, the plan states that sensitive habitats should not be crossed during periods of high vulnerability of particular species. Damage to or destruction of sandbanks, reefs and areas of benthic communities of conservation concern, which constitute particularly sensitive habitat are to be avoided during the laying and operation of pipelines and cables and best environmental practices according to the OSPAR Convention are to be followed. The plan has also sought to overlap designation for pipeline and windfarm priority areas.

Offshore grid connections for the windfarms are planned by the Federal Maritime and Hydrographic Agency (BSH) according to the German Energy Act. An Offshore Grid Plan as a sectoral spatial approach has been in force for the North Sea since March 2013 and is under development for the Baltic Sea. This identifies offshore wind farms suitable for bundled grid connections, sites for converter stations, routes for grid connections, cross border cables (interconnectors) and routes for possible cross connections between grid infrastructures. Planning principles in the document such as maximum bundling of cables and avoiding routes through Natura 2000 sites are aimed at reducing the area needed for grid infrastructure and lowering potential impacts on the marine environment. The plan, which was subject to a SEA set out the capacity and expected timing of offshore grid connections to be built over the next 10 years. The spatial regulations from these plans will be integrated into updated MSPs for the German EEZs of the North Sea and Baltic Sea (BSH, 2012).

Spatial Offshore Grid Plan for the German Executive Economic Zone of the North Sea 2012

Image

REFERENCES

ACCOBAMS-MOP5, 2013 Methodological Guide: Guidance on underwater noise mitigation measures. ACCOBAMS-MOP5/2013/Doc24.

AEWA (2008) International Single Species Action Plan for the Conservation of the Lesser White-fronted Goose (Western Palearctic Population) Anser erythropus. Agreement on the Conservation of African-Eurasian Migratory Waterbirds (AEWA). Technical Document.

Anderson, D.R. (2001) The need to get the basics right in wildlife field studies. Wildlife Society Bulletin, 29: 1294-1297.

Andrews, A., 1990. Fragmentation of habitat by roads and utility corridors: a review. Australian Zoologist, 26(3-4), pp.130-141. Available at: shanespark.com/Documents/Andrews (1990) Fragmentation of Habitat by Roads and Utility Corridors A Review.pdf [Accessed April 11, 2012].

Andrulewicz, E., Napierska, D., & Otremba, Z. (2003). The environmental effects of the installation and functioning of the submarine SwePol Link HVDC transmission lie: a case study of the Polish Marine Area of the Baltic Sea. J.Sea.Res 49:337-345.

Angelov, I., Hashim, I., Oppel, S. (2012) Persistent electrocution mortality of Egyptian Vultures Neophron percnopterus over 28 years in East Africa. Bird Conservation International (published online).

Arcus, 2012 Beatrice Offshore Wind Farm Environmental Statement .Non-Technical Summary. Arcus Renewable Energy Consulting Ltd

Askins, R.A, Folsom-O'Keefe, C.M., Hardy, M.C. (2012) Effects of vegetation, corridor width and regional land use on early successional birds on power line corridors. PloS one, 7(2): e31520.

Avian Power Line Interaction Committee (APLIC) (2006) Suggested Practices for Avian Protection on Power Lines: The State of the Art in 2006. Edison Electric Institute, APLIC, and the California Energy Commission. Washington, D.C and Sacramento, CA.

Ayers, D. & Wallace, G., 1997. Pipeline trenches: an under- utilised resource for finding fauna. In P. Hale & D. Lamb, eds. Conservation Outside Nature Reserves. Brisbane: Centre for Conservation Biology, The University of Queensland, pp. 349-357.

Barber, J.R., Crooks, K.R. & Fristrup, K.M., 2010. The costs of chronic noise exposure for terrestrial organisms. Trends in ecology & evolution, 25(3), pp.180-9. Available at: www.sciencedirect.com/science/article/pii/S0169534709002614 [Accessed March 17, 2012].

Bayle, P. (1999) Preventing Birds of Prey Problems at Transmission Lines in Western Europe. Journal of Raptor Research, 33(1): 43-48.

Bayne, E.M., Habib, L. & Boutin, S., 2008. Impacts of chronic anthropogenic noise from energy-sector activity on abundance of songbirds in the boreal forest. Conservation biology: the journal of the Society for Conservation Biology, 22(5), pp.1186-93. Available at: www.ncbi.nlm.nih.gov/pubmed/18616740 [Accessed April 26, 2012].

BCTC, 2006. Environmental Assessment Certificate Application - Vancouver Island Transmission Reinforcement Project,

Bell, S.S. et al., 2001. Faunal response to fragmentation in seagrass habitats: implications for seagrass conservation. Biological Conservation, 100(1), pp.115-123. Available at: linkinghub.elsevier.com/retrieve/pii/S0006320700002123 [Accessed May 2, 2012].

Bennett, P.M. & Owens, I.P.F. 1997. Variation in extinction risk among birds: chance or evolutionary predisposition? Proceedings of the Royal Society of London B:401-408.

Benson, P.C. (1981) Large raptor electrocution and power pole utilization: a study in six western states. Ph.D. Dissertation, Brigham Young University, Provo, UT, USA.

BERR, 2008. Review of Cabling Techniques and Environmental Effects Applicable to the Offshore Wind Farm Industry - Technical Report,

Bevanger, K. (1994b) Bird interactions with utility structures: collision and electrocution, causes and mitigating measures. Ibis, 136: 412-425.

Bevanger, K. (1995) Estimates and population consequences of Tetraonid mortality caused by collisions with high tension power lines in Norway. Journal of Applied Ecology, 32: 745-753.

Bevanger, K. (1998) Biological and Conservation Aspects of Bird Mortality Caused by Electricity Power Lines: a Review. Biological Conservation, 86: 67-76.

Bevanger, K. (1999) Estimating bird mortality caused by collision and electrocution with power lines; a review of methodology. In: Ferrer, M., Janss, G.F. (Eds.), Birds and Power Lines: Collision, Electrocution, and Breeding. Quercus, Madrid, Spain, pp. 29-56.

Bevanger, K., Overskaug, K. (1998) Utility Structures as a mortality factor for Raptors and Owls in Norway. In: Chancellor, R.D., B.-U. Meyburg & J.J. Ferrero (Eds.) Holarctic Birds of Prey. ADENEX-WWGBP, Berlin, Germany.

Binetti, R. et al., 2000. Environmental risk assessment of linear alkyl benzene, an intermediate for the detergency industry. International Journal of Environmental Health Research, 10(2), pp.153-172. Available at: www.tandfonline.com/doi/abs/10.1080/09603120050021155 [Accessed April 27, 2012].

BirdLife International (2004) Birds in Europe: population estimates, trends and conservation status. Cambridge, UK: BirdLife International. (BirdLife Conservation Series No. 12).

BirdlifeInternational (2007) Position statement on birds and power lines. Birdlife Birds and Habitats Directives Task Force adopted position papers. www.birdlife.org/action/change/europe/habitat_directive/index.html

Birklund, J. (2003) Marine Biological Surveys along the cable trench in the Lagoon of Rødsand in September 2002 and March 2003. DHI Water & Environment. 37pp.

Bocquené, G., Chantereau, S., Clérendeau, C., Beausir, E., Ménard, D., Raffin, B., Minier, C., et al. (2004). Biological effects of the ‘Erika’ oil spill on the common mussel (Mytilus edulis). Aquatic Living Resources, 17(3), 309-316.

Boehlert, G.W. & Gill, A.B. (2010) Environmental and ecological effects of ocean renewable energy development. A current synthesis. Oceanography 23(2); 68-81.

Borrmann, C.B., 2006. Wärmeemission von Stromkabeln in Windparks - Laboruntersuchungen zum Einfluss auf die benthische Fauna. Rostock University, Institute of Applied Ecology Ltd.

Bruderer, B., Peter, D. & Steuri, T. (1999) Behaviour of migrating birds exposed to x-band radar and a bright light beam. The Journal of Experimental Biology, 202, 1015–1022.

Budzinski, H., Mazéas, O., Tronczynski, J., Désaunay, Y., Bocquené, G., & Claireaux, G. (2004). Link between exposure of fish (Solea solea) to PAHs and metabolites: Application to the ‘Erika’ oil spill. Aquatic Living Resources, 17(3), 329-334.

Bulgarian Society for the Protection of Birds (BSPB) (2010) Safe Ground for Redbreasts. LIFE+ project website. bspb-redbreasts.org/?page_id=6

Bulgarian Society for the Protection of Birds (BSPB) Save the Raptors. Conservation of Imperial Eagle and Saker Falcon in Bulgaria. LIFE+ project website. www.saveraptors.org

Bundesamt für Seeschifffahrt und Hydrographie (2012) Spatial Offshore Grid Plan for the German Exclusive Economic Zone of the North Sea. Comprehensive Summary. Unofficial translation.

Cadahía, L., López-lópez, P., Urios, V. (2010) Satellite telemetry reveals individual variation in juvenile Bonelli's eagle dispersal areas. Ibis, 147(2): 415-419.

Cadiou, B., Riffaut, L., McCoy, K. D., Cabelguen, J., Fortin, M., Gélinaud, G., Le Roch, A., et al. (2004). Ecological impact of the ‘Erika’ oil spill: Determination of the geographic origin of the affected common guillemots. Aquatic Living Resources, 17(3), 369-377.

Camphuysen, C.J., Dieckhoff, M.A., Fleet, D.M. & Laursen, K. (2009) Oil Pollution and Seabirds. Thematic Report No. 5.3. In: Marencic, H. & Vlas, J. de (Eds), 2009. Quality Status Report 2009. Wadden Sea Ecosystem No. 25. Common Wadden Sea Secretariat, Trilateral Monitoring and Assessment Group, Wilhelmshaven, Germany.

Carrete, M., Sánchez-Zapata, J.A., Benítez, J.R., Lobón, M., Donázar, J.A. (2009) Large scale risk-assessment of wind-farms on population viability of a globally endangered long-lived raptor. Biological Conservation, 142(12): 2954-2961.

Carter, L., Burnett, D., Drew, S. et al., 2009. Submarine Cables and the Oceans – Connecting the World. UNEP-WCMC Biodiversity Series No. 31. ICPC/UNEP/UNEP-WCMC.

Chandrasekara, W.U. & Frid, C.L.J., 1998. A laboratory assessment of the survival and vertical movement of two epibenthic gastropod species, Hydrobia ulvae (Pennant) and Littorina littorea (Linnaeus), after burial in sediment. Journal of Experimental Marine Biology and Ecology, 221(2), pp.191-207. Available at: www.sciencedirect.com/science/article/B6T8F-3S967BY-3/2/8d8547d6fd13b48bcdb40c1fe171482c [Accessed April 20, 2012].

Clarke, D.J. & White, J.G., 2008. Towards ecological management of Australian powerline corridor vegetation. Landscape and Urban Planning, 86(3-4), pp.257-266. Available at: linkinghub.elsevier.com/retrieve/pii/S0169204608000509 [Accessed April 27, 2012].

CONCAWE, 2011. Performance of European cross-country oil pipelines - Statistical summary of reported spillages in 2010 and since 1971,

Confer, J.L., Pascoe, S.M. (2003) Avian communities on utility rights-of-ways and other managed shrublands in the northeastern United States. Forest Ecology and Management, 185: 193–205.

Cooney, R. (2004) Better safe than sorry? The precautionary principle and biodiversity conservation. Oryx 38: 357–358.

Crivelli, A.J., Jerrentrup, H., Mitchev, T. (1987) Electric power lines: a cause of mortality in Pelecanus crispus Bruch, a world endangered bird species, in Porto-Lago, Greece. Colonial Waterbirds 11: 301-305.

Curtis, M.R., Vincent, A.C.J. (2008) Use of population viability analysis to evaluate CITES trade-management options for threatened marine fishes. Conservation Biology 22: 1225–1232.

Daan, R. & Mulder, M., 1996. On the short-term and long-term impact of drilling activities in the Dutch sector of the North Sea. ICES Journal of Marine Science, 53, pp.1036–1044. Available at: icesjms.oxfordjournals.org/content/53/6/1036.short [Accessed April 27, 2012].

Daan, R., Mulder, M. & Van Leeuwen, A., 1994. Differential sensitivity of macrozoobenthic species to discharges of oil-contaminated drill cuttings in the North Sea. Netherlands Journal of Sea Research, 33(1), pp.113-127. Available at: linkinghub.elsevier.com/retrieve/pii/0077757994900566 [Accessed April 27, 2012].

Deeks, J.J., Higgins J.P.T., Altman D.G. (2005) Analysing and presenting results. In: Cochrane Handbook for Systematic Reviews of Interventions 4.2.5 [updated May 2005]; Section 8. (ed by J.P.T. Higgins and S. Green.). Available at: www.cochrane.org/resources/handbook/hbook.htm.

De la Huz, R., Lastra, M., Junoy, J. et al. (2005) Biological impacts of oil pollution and cleaning in the intertidal zone of exposed sandy beaches: Preliminary study of the ‘Prestige’ oil spill. Est.Coast.Shelf.Sci. 65:19-29.

Demeter, I. (2004) Medium-Voltage Power Lines and Bird Mortality in Hungary. Technical Document. MME/BirdLife Hungary.

Department of Energy and Climate Change, 2010. Planning For New Energy Infrastructure, London.

Dernie, K.M., Kaiser, M.J. & Warwick, R.M., 2003. Recovery rates of benthic communities following physical disturbance. Journal of Animal Ecology, 72(6), pp.1043-1056. Available at: onlinelibrary.wiley.com/doi/10.1046/j.1365-2656.2003.00775.x/full [Accessed April 6, 2012].

Deutsche WindGuard GmbH & Greenpeace International, 2005. Offshore Wind Energy - Implementing a New Powerhouse for Europe,

Dierschke, V. & Bernotat, D. (2012): Übergeordnete Kriterien zur Bewertung der Mortalität wildlebender Tiere im Rahmen von Projekten und Eingriffen – unter besonderer Berücksichtigung der deutschen Brutvogelarten. Stand 01.12.2012, 175 S. http://www.bfn.de/0306_eingriffe-toetungsverbot.html.

Dodd, A.M. et al., 2007. The Appropriate Assessment of Spatial Plans in England: a guide to why, when and how to do it, Available at: www.rspb.org.uk/Images/NIAA_tcm9-196528.pdf.

Doody, J.S. et al., 2003. Fauna by-catch in pipeline trenches: conservation, animal ethics, and current practices in Australia. Australian Zoologist, 32(3), pp.410-419.

Drewitt, A.L., Langston, R.H.W. (2008) Collision effects of wind-power generators and other obstacles on birds. Annals of the New York Academy of Sciences, 1134: 233-66.

Duhamel, B & Beaussant, H. (2011) EU Energy Strategy in the South Mediterranean. Directorate-General for Internal Policies. Policy Department A. Economic and Scientific Policy. 110pg

EASAC (2009) Transforming Europe' s Electricity Supply – An Infrastructure Strategy for a Reliable, Renewable and Secure Power System. The Royal Society. London, UK.

EGIG, 2011 Gas Pipeline incidents. 8th report of the European Gas Pipeline Incident Data group. EGIG 11.R.0402 (version 2).

Ellis, D.H., Smith, D.G., Murphy, J.R. (1969) Studies on raptor mortality in western Utah. Great Basin Naturalist 29: 165-167.

ENTSO (2012) ENTSO-E Grid Map. Available at: www.entsoe.eu/nc/resources/grid-map/?sword_list[]=Kv

Environ & InterGen, 2010. Spalding Energy Expansion - Gas Pipeline - Environmental statement - Non-technical summary - Volume 1,

Erfurt University of Applied Sciences, IBU Ingenieurbüro Schöneiche GmbH & Co. KG and 50 Hertz Transmission GmbH (2010). Ecological management of overhead lines (EcoMOL): General overview. Available at: www.50hertz.com/en/file/100304_EcoMOL_ShortReport_eng_final_med.pdf.

ERM Iberia, 2004. MEDGAZ natural gas transportation system - Environmental impact assessment - Final report,

European Commission (2000) Managing Natura 2000 sites. The provisions of Article 6 of the ‘Habitats’ Directive 92/43/EEC. Brussels, Belgium. Available at: ec.europa.eu/environment/nature/natura2000/management/guidance_en.htm

European Commission (2002) Assessment of plans and projects significantly affecting Natura 2000 sites Methodological guidance on the provisions of Article 6(3) and (4) of the Habitats Directive 92/43/EEC. Impacts Assessment Unit School of Planning Oxford Brookes University, Oxford, UK.

European Commission (2007) Guidance document on Article 6(4) of the ‘Habitats Directive’ 92/43/EEC. Brussels, Belgium.

European Commission (2011) Our life insurance, our natural capital: an EU biodiversity strategy to 2020. Brussels, Belgium.

European Commission (2012) Natura 2000 network. Brussels, Belgium. Available at: ec.europa.eu/environment/nature/natura2000/index_en.htm

European Commission (2013) Streamlining environmental assessment procedures for energy infrastructure Projects of Common Interest (PCIs). European Commission. Energy & Environment.

European Commission, 2000. Managing Natura 2000 sites - The provisions of Article 6 of the ‘Habitats’ Directive 92/43/EEC, Luxembourg: Office for Official Publications of the European Communities.

European Commission, 2001a. Assessment of plans and projects significantly affecting Natura 2000 sites - Methodological guidance on the provisions of Article 6(3) and (4) of the Habitats Directive 92/43/EEC, Luxembourg.

European Commission, 2001b. Guidelines for the Assessment of Indirect and Cumulative Impacts as well as Impact Interactions, Luxembourg: Office for Official Publications of the European Communities.

European Commission, 2007. Guidance document on Article 6(4) of the ‘Habitats Directive’ 92/43/EEC - Clarification of the concepts of: alternative solutions, imperative reasons of overriding public interest, compensatory measures, overall coherence, opinion of the Commission: ec.europa.eu/environment/nature/natura2000/management/docs/art6/guidance_art6_4_en.pdf.

European Commission, 2010. Communication from the Commission to the European Parliament, the Council, the European Economic and Social Committee and the Committee of the Regions - Energy infrastructure priorities for 2020 and beyond - A Blueprint for an integrated European energy network,

European Commission, 2011a. Communication from the Commission to the European Parliament, the Council, the Economic and Social Committee and the Committee of the Regions - Our life insurance, our natural capital: an EU biodiversity strategy to 2020 - COM(2011) 244 final,

European Commission, 2011b. Communication from the Commission to the European Parliament, the Council, the European Economic and Social Committee and the Committee of the Regions - Energy Roadmap 2050 - COM(2011) 885 final,

European Commission, 2011c. Proposal for a REGULATION OF THE EUROPEAN PARLIAMENT AND OF THE COUNCIL on guidelines for trans-European energy infrastructure and repealing Decision No 1364/2006/EC /* COM/2011/0658 final - 2011/0300 (COD) */,

European Commission, Energy infrastructure - Energy infrastructure priorities for 2020 and beyond. Available at: ec.europa.eu/energy/infrastructure/strategy/2020_en.htm.

European Environment Agency, 2010a. The European Environment - State and Outlook 2010 - Biodiversity,

European Environment Agency, 2010b. The European Environment - State and Outlook 2010 - Land use,

European Environment Agency, 2011. Landscape fragmentation in Europe - EEA Report No 2/2011 - Joint EEA-FOEN report,

EWEA (2014) Wind in power. 2013 European Statistics. February 2014. The European Wind Energy Association. 12pp.

Faulkner, W., 1999. AGL Central West Project: Marsden- Dubbo gas pipeline. Fauna impact monitoring. Draft report to NSW National Parks and Wildlife Service and AGL.,

Fernie, K.J. & Reynolds, S.J., 2005. The effects of electromagnetic fields from power lines on avian reproductive biology and physiology: a review. Journal of toxicology and environmental health. Part B, Critical reviews, 8(2), pp.127-40. Available at: www.tandfonline.com/doi/abs/10.1080/10937400590909022 [Accessed March 21, 2012].

Fernie, K.J., Bird, D.M., Dawson, R.D., Lague, P.C. (2000) Effects of Electromagnetic Fields on the Reproductive Success of American Kestrels. Physiological and Biochemical Zoology, 73(1): 60-65.

Fernie, K.J., Reynolds, S. J. (2005) The effects of electromagnetic fields from power lines on avian reproductive biology and physiology: a review. Journal of Toxicology and Environmental Health, 8(2): 127-40.

Ferrer, M. (2001) The Spanish Imperial Eagle. Lynx Edicions. Barcelona, Spain.

Ferrer. M., Hiraldo. F. (1992) Man-induced sex-biased mortality in the Spanish Imperial Eagle. Biological Conservation. 60: 57-60.

Fischer, J. et al., 2007. Mind the sustainability gap. Trends in ecology & evolution, 22(12), pp.621-4. Available at: www.ncbi.nlm.nih.gov/pubmed/17997188 [Accessed March 7, 2012].

Freemark, K., 1995. Impacts of agricultural herbicide use on terrestrial wildlife in temperate landscapes: A review with special reference to North America. Agriculture, Ecosystems & Environment, 52(2-3), pp.67-91. Available at: linkinghub.elsevier.com/retrieve/pii/016788099400534L [Accessed April 26, 2012].

Frost, M.T., Rowden, A.A. & Attrill, M.J., 1999. Effect of habitat fragmentation on the macroinvertebrate infaunal communities associated with the seagrass Zostera marina L. Aquatic Conservation: Marine and Freshwater Ecosystems, 9(3), pp.255-263. Available at: doi.wiley.com/10.1002/(SICI)1099-0755(199905/06)9:3<255::AID-AQC346>3.0.CO;2-F [Accessed May 2, 2012].

Garcia-del-Rey, E., Rodriguez-Lorenzo, J.A. (2011) Avian mortality due to power lines in the Canary Islands with special reference to the steppe-land birds. Journal of Natural History, Volume 45, Numbers 35-36: 2159-2169.

Gesteira, J.L.G. & Dauvin, J.-C., 2000. Amphipods are Good Bioindicators of the Impact of Oil Spills on Soft-Bottom Macrobenthic Communities. Marine Pollution Bulletin, 40(11), pp.1017-1027. Available at: linkinghub.elsevier.com/retrieve/pii/S0025326X00000461 [Accessed April 27, 2012].

GIE (2012) Gas Infrastructure Europe Key Messages on Energy roadmap 2050. http://www.gie.eu/index.php/13-news/gie/161-gie-publishes-its-new-qkey-messages-energy-roadmap-2050q-brochure

Gleason, N.C., 2008. Impacts of Power Line Rights-of-Way on Forested Stream Habitat in Western Washington. In J. W. Goodrich-Mahoney et al., eds. Environment Concerns in Rights-of-Way Management 8th International Symposium. Amsterdam: Elsevier, pp. 665-678. Available at: www.sciencedirect.com/science/article/pii/B9780444532237500757.

González, L.M., Margalida, A., Mañosa, S., Sánchez, R., Oria, J., Molina, J.I., Caldera, J. (2007) Causes and Spatio-temporal Variations of Non-natural Mortality in the Vulnerable Spanish Imperial Eagle Aquila adalberti During a Recovery Period. Oryx, 41(04): 495-502.

Goosem, M. & Marsh, H., 1997. Fragmentation of a Small-mammal Community by a Powerline Corridor through Tropical Rainforest. Wildlife Research, 24(5), p.613. Available at: www.publish.csiro.au/paper/WR96063 [Accessed April 27, 2012].

Grande, J.M., Serrano, D., Tavecchia, G., Carrete, M., Ceballos, O., Tella, J.L. and Donázar, J.A. (2009) Survival in a long-lived territorial migrant: effects of life- history traits and ecological conditions in wintering and breeding areas. Oikos, 118: 580–590.

Granström, A., 2001. Fire management for biodiversity in the European boreal forest. Scandinavian Journal of Forest Research, 16(Supplement 3), pp.62-69. Available at: www.tandfonline.com/doi/abs/10.1080/028275801300090627 [Accessed April 26, 2012].

GRT gaz, Dossier du maître d'ouvrage - Débat public sur le projet Eridan,

Guil, F., Fernández-Olalla, M., Moreno-Opo, R., Mosqueda, I., Gómez, M.E., Aranda, A., Arredondo, A. (2011) Minimising Mortality in Endangered Raptors due to Power Lines: The Importance of Spatial Aggregation to Optimize the Application of Mitigation Measures. PloS one, 6(11), e28212.

Haas, D., Nipkow, M. (2006) Caution: Electrocution! NABU Bundesverband. Bonn, Germany.

Haas, D., Nipkow, M., Fiedler, G., Schneider, R., Haas, W., Schürenberg, B. (2005) Protecting birds from powerlines. Nature and Environment, No. 140. Council of Europe Publishing, Strassbourg.

HABIB, L., BAYNE, E.M. & BOUTIN, S., 2006. Chronic industrial noise affects pairing success and age structure of ovenbirds Seiurus aurocapilla. Journal of Applied Ecology, 44(1), pp.176-184. Available at: doi.wiley.com/10.1111/j.1365-2664.2006.01234.x [Accessed April 18, 2012].

Hall-Spencer, J.M. & Moore, P.G. (2000) Scallop dredging has profound, long-term impacts on maerl habitats. ICES J.Mar.Sci 57:1407-1415

Harness, R.E. (1997) Raptor electrocutions caused by rural electric distribution power lines. Ft. Collins: Colorado State University; 110 p. M.S. thesis.

Harness, R.E., Wilson, K.R., (2001) Utility structures associated with raptor electrocutions in rural areas. Wildlife Society Bulletin 29, 612-623.

Heubeck, M., Camphuysen, K. C. J., Bao, R., Humple, D., Sandoval Rey, A., Cadiou, B., Bräger, S., et al. (2003). Assessing the impact of major oil spills on seabird populations. Marine pollution bulletin, 46(7), 900-2.

Hirst, J.A. & Attrill, M.J., 2008. Small is beautiful: An inverted view of habitat fragmentation in seagrass beds. Estuarine, Coastal and Shelf Science, 78(4), pp.811-818. Available at: linkinghub.elsevier.com/retrieve/pii/S0272771408000929 [Accessed May 2, 2012].

Hirst, R.A. et al., 2005. The resilience of calcareous and mesotrophic grasslands following disturbance. Journal of Applied Ecology, 42(3), pp.498-506. Available at: onlinelibrary.wiley.com/doi/10.1111/j.1365-2664.2005.01028.x/full [Accessed April 9, 2012].

Hollmen, A. et al., 2007. The value of open power line habitat in conservation of ground beetles (Coleoptera: Carabidae) associated with mires. Journal of Insect Conservation, 12(2), pp.163-177. Available at: www.springerlink.com/index/510hq085388q826h.pdf [Accessed April 12, 2012].

Horváth, M., Demeter, I., Fatér, I., Firmánszky, G., Kleszó, A., Kovács, A., Szitta, T., Tóth, I., Zalai, T., Bagyura, J. (2011) Population Dynamics of the Eastern Imperial Eagle (Aquila heliaca) in Hungary between 2001 and 2009. Acta Zoologica Bulgarica, Suppl. 3, 2011: 61-70.

Horváth, M., Nagy, K., Papp, F., Kovács, A., Demeter, I., Szügyi, K., Halmos, G. (2008) Assessment of the Hungarian medium-voltage electric grid based on bird conservation considerations. MME/BirdLife Hungary, Budapest (in Hungarian).

Hovel, K.A. & Lipcius, R.N., 2001. HABITAT FRAGMENTATION IN A SEAGRASS LANDSCAPE: PATCH SIZE AND COMPLEXITY CONTROL BLUE CRAB SURVIVAL. Ecology, 82(7), pp.1814-1829. Available at: www.esajournals.org/doi/abs/10.1890/0012-9658(2001)082[1814:HFIASL]2.0.CO;2 [Accessed May 2, 2012].

Hovel, K.A. & Lipcius, R.N., 2002. Effects of seagrass habitat fragmentation on juvenile blue crab survival and abundance. Journal of Experimental Marine Biology and Ecology, 271(1), pp.75-98. Available at: linkinghub.elsevier.com/retrieve/pii/S0022098102000436 [Accessed May 2, 2012].

Hovel, K.A., 2003. Habitat fragmentation in marine landscapes: relative effects of habitat cover and configuration on juvenile crab survival in California and North Carolina seagrass beds. Biological Conservation, 110(3), pp.401-412. Available at: linkinghub.elsevier.com/retrieve/pii/S0006320702002343 [Accessed May 2, 2012].

Howard, D.C., Wadsworth R.A., Whitaker J.W., Hughes N., Bunce R.G.H. (2009) The impact of sustainable energy production on land use in Britain through to 2050. Land Use Policy 26S pp. 284-292.

HSE, (1997). The abandonment of offshore pipelines. Methods and Procedures for Abandonment. Health and Safety Executive. Offshore Technology Report 535. HSE Books.

Jenssen, B.M. (1996) An overview of exposure to, and effects of, petroleum oil and organochlorine pollution in Grey Seals (Halichoerus grypus). The Science of the Total Environment 186:109-118.

IMO, 2011a. Ballast Water Management. Available at: www.imo.org/ourwork/environment/ballastwatermanagement/Pages/Default.aspx [Accessed April 13, 2012].

IMO, 2011b. International Convention for the Control and Management of Ships' Ballast Water and Sediments (BWM). Available at: www.imo.org/About/Conventions/ListOfConventions/Pages/International-Convention-for-the-Control-and-Management-of-Ships%27-Ballast-Water-and-Sediments-(BWM).aspx.

Infante, S., Neves, J., Ministro, J. & Brandão, R. (2005). Estudo sobre o Impacto das Linhas Eléctricas de Média e Alta Tensão na Avifauna em Portugal. Quercus Associação Nacional de Conservação da Natureza e SPEA Sociedade Portuguesa para o Estudo das Aves, Castelo Branco (relatório não publicado). Available at: www.spea.pt/fotos/editor2/relatorio_edp_icn_spea_quercus_avifaunai.pdf

IPCC, 2005. IPCC Special Report on Carbon dioxide capture and storage Working Group III of the Intergovernmental Panel on Climate Change et al., eds., Cambridge, UK, New York, USA: Cambridge University Press.

Jackson, C.W. et al., 2011. Static electric fields modify the locomotory behaviour of cockroaches. The Journal of experimental biology, 214(Pt 12), pp.2020-6. Available at: jeb.biologists.org/content/214/12/2020.short [Accessed April 12, 2012].

Jackson, M.J. & James, R., 1979. The influence of bait digging on cockle, Cerastoderma edule, populations in North Norfolk. Journal of Applied Ecology, 16(3), pp.671-679. Available at: www.mendeley.com/research/influence-bait-digging-cockle-cerastodermaedule-populations-north-norfolk-england-uk-13/ [Accessed April 11, 2012].

Jacques Whitford Limited, 2006. Vancouver Island Transmission Reinforcement Project Technical Data Report: Potential Effects of Alkylbenzene Release to the Marine Environment.,

Janss, G.F.E, Ferrer, M. (2001) Avian Electrocution Mortality in Relation to Pole Design and Adjacent Habitat in Spain. Bird Conservation International, 3-12.

Janss, G.F.E. (2000) Avian Mortality from Power Lines: a Morphologic Approach of a Species-specific Mortality. Biological Conservation, 95: 353-359.

Jenkins, A.R., Smallie, J.J., Diamond, M. (2010) Avian collisions with power lines: a global review of causes and mitigation with a South African perspective. Bird Conservation International, 20(03): 263-278.

Johnson, M. & Heck KL, J., 2006. Effects of habitat fragmentation per se on decapods and fishes inhabiting seagrass meadows in the northern Gulf of Mexico. Marine Ecology Progress Series, 306, pp.233-246. Available at: www.int-res.com/abstracts/meps/v306/p233-246/ [Accessed May 2, 2012].

JRC-report ‘Evaluation of Smart Grid projects within the Smart Grid Task Force Expert Group 4 (EG4)

Karyakin, I.V. (2012) Birds of prey and power lines in northern Eurasia: What are the prospects for survival? Raptors Conservation 24: 69 - 86.

King, D.I. et al., 2009. Effects of width, edge and habitat on the abundance and nesting success of scrub–shrub birds in powerline corridors. Biological Conservation, 142(11), pp.2672-2680. Available at: www.sciencedirect.com/science/article/pii/S0006320709002717 [Accessed March 23, 2012].

Klarić, S., Pavičić-Hamer, D. & Lucu, Č., 2004. Seasonal variations of arsenic in mussels Mytilus galloprovincialis. Helgoland Marine Research, 58(3), pp.216-220. Available at: www.springerlink.com/index/10.1007/BF01606105 [Accessed April 27, 2012].

Ko, J.-Y. & Day, J.W., 2004. A review of ecological impacts of oil and gas development on coastal ecosystems in the Mississippi Delta. Ocean & Coastal Management, 47(11-12), pp.597-623. Available at: linkinghub.elsevier.com/retrieve/pii/S0964569104000973 [Accessed April 13, 2012].

Kuijper, D.P.J., Schut, J., Van Dullemen, D., Toorman,H., Goossens, N., Ouwehand, J. & Limpens, H.J.G.A. (2008) Experimental evidence of light disturbance along the commuting routes of pond bats (Myotis dasycneme). Vereniging voor Zoogdierkunde en Zoogdierbescherming, 51(1), 37–49.

Kunz, T.H. et al., 2007. Ecological impacts of wind energy development on bats: questions, research needs, and hypotheses. Frontiers in Ecology and the Environment, 5(6), pp.315-324. Available at: www.esajournals.org/doi/abs/10.1890/1540-9295(2007)5%5B315:EIOWED%5D2.0.CO;2 [Accessed April 12, 2012].

Kuussaari, M. et al., 2003. Voimajohtoaukeiden merkitys niittyjen kasveille ja perhosille - Significance of Power Line Areas for Grassland Plants and Butterflies Finnish Environment Institute, ed., Helsinki.

Kyläkorpi, L. & Grusell, E., 2001. Livsmiljö i kraftledningsgatan, Available at: scholar.google.fr/scholar?hl=fr&q=“Livsmiljö+i+Kraftledningsgatan”&btnG=Rechercher&lr=&as_ylo=&as_vis=0#0 [Accessed April 30, 2012].

Lasch, U., Zerbe, S., Lenk, M. (2010) Electrocution of Raptors at Power Lines in Central Kazakhstan. Waldökologie, Landschaftforschung und Naturschutz, 9: 95-100.

Lehman, R.N., Kennedy, P.L., Savidge, J.A. (2007) The state of the art in raptor electrocution research: A global review. Biological Conservation, 136, 2: 159-174.

Lensu, T. et al., 2011. The role of power line rights-of-way as an alternative habitat for declined mire butterflies. Journal of environmental management, 92(10), pp.2539-46. Available at: www.sciencedirect.com/science/article/pii/S0301479711001745 [Accessed April 12, 2012].

Lévesque, L.M. & Dubé, M.G., 2007. Review of the effects of in-stream pipeline crossing construction on aquatic ecosystems and examination of Canadian methodologies for impact assessment. Environmental monitoring and assessment, 132(1-3), pp.395-409. Available at: www.springerlink.com/index/cu76l5guk3u28106.pdf [Accessed March 20, 2012].

Lewis, L.J., Davenport, J. & Kelly, T.C., 2002. A Study of the Impact of a Pipeline Construction on Estuarine Benthic Invertebrate Communities. Estuarine, Coastal and Shelf Science, 55(2), pp.213-221. Available at: www.sciencedirect.com/science/article/pii/S0272771401908984 [Accessed March 9, 2012].

López-López, P., Ferrer, M., Madero, A., Casado, E., McGrady, M. (2011) Solving Man-induced Large-scale Conservation Problems: the Spanish Imperial Eagle and Power Lines. PloS one, 6(3), e17196.

London Array/National Grid (2007) Ecological Mitigation and Management Plan. London Array Offshore Wind Farm Project and associated grid connection works. October 2007. 17 pgs.

Lorne, J.K. & Salmon, M. (2007) Effects of exposure to artificial lighting on orientation of hatching sea turtles on the beach and in the ocean. Endangered species research, 1, 23–30.

Macreadie, P.I. et al., 2009. Fish Responses to Experimental Fragmentation of Seagrass Habitat. Conservation biology: the journal of the Society for Conservation Biology. Available at: www.ncbi.nlm.nih.gov/pubmed/19183213 [Accessed March 23, 2012].

Manville, A.M. (2005) Bird Strikes and Electrocutions at Power Lines, Communication Towers, and Wind Turbines: State of the Art and State of the Science – Next Steps Toward Mitigation 1. USDA Forest Service Technical report, 1051-1064.

Marshall, J.S. & Vandruff, L.W., 2002. Impact of selective herbicide right-of-way vegetation treatment on birds. Environmental management, 30(6), pp.801-6. Available at: www.ncbi.nlm.nih.gov/pubmed/12402095 [Accessed April 17, 2012].

Martin, G.R. (2011) Review article Understanding bird collisions with man-made objects: a sensory ecology approach. Ibis, 239-254.

Meissner, K. & Sordyl, H. (2006). Literature Review of Offshore Wind Farms with Regard to Benthic Communities and Habitats. In. Zucco, C., Wende, W., Merck, T., Köchling, I. & Köppel, J. (eds.):Ecological Research on Offshore Wind Farms: International Exchange of Experiences - PART B: Literature Review of the Ecological Impacts of Offshore Wind Farms. BfN-Skripten 186: 1-45.

Meißner, K., Bockhold, J. & Sordyl, H., 2006. Problem Kabelwärme? - Vorstellung der Ergebnisse von Feldmessungen der Meeresbodentemperatur im Bereich der elektrischen Kabel im Offshore-Windpark Nysted Havmøllepark (Dänemark). In Bundesamt für Seeschifffahrt und Hydrographie (BSH), ed. Meeresumwelt- Symposium. Hamburg, Rostock. Available at: scholar.google.fr/scholar?hl=fr&q=Problem+Kabelwärme?&btnG=Rechercher&lr=&as_ylo=&as_vis=0#0 [Accessed April 13, 2012].

Mendel, B., Sonntag, N., Wahl, et al., (2008) Profiles of seabirds and waterbirds of the German North and Baltic Seas. Distribution, ecology and sensitivities to human activities within the marine environment. Naturschutz und Biologische Vielfalt 61, Bundesamt für Naturschutz, Bonn – Bad Godesberg, 427 pp

MME/BirdLife Hungary (2011) ‘Budapest Declaration on bird protection and power lines’. Available at: www.mme.hu/termeszetvedelem/budapest-conference-13-04-2011.html

Myers, N. (1993) Biodiversity and Precautionary Principle. Ambio, 22: 74-79.

Nedwell, J.R., Brooker, A.G. & Barham, R.J. (2012) Assesment of underwater noise during the installation of export power cables at the Beatrice Offshore Wind Farm. Subacoustech Environmental Report No. E318R0106

Nedwell, J., Langworthy, J. & Howell, D., 2003. Assessment of sub-sea acoustic noise and vibration from offshore wind turbines and its impact on marine wildlife; initial measurements of underwater noise during construction of offshore windfarms, and comparison with background noise - Report No. 544 R,

Nekola, J.C., 2012. The impact of a utility corridor on terrestrial gastropod biodiversity. Biodiversity and Conservation, 21(3), pp.781-795. Available at: www.springerlink.com/index/3357H23G15537M77.pdf [Accessed April 11, 2012].

Nellemann, C. et al., 2003. Progressive impact of piecemeal infrastructure development on wild reindeer. Biological Conservation, 113(2), pp.307-317. Available at: linkinghub.elsevier.com/retrieve/pii/S000632070300048X [Accessed March 16, 2012].

Nikolaus, G. (1984) Large numbers of birds killed by electric power line. Scopus, 8: 42.

Nikolaus, G. (2006) Where have all the African vultures gone? Vulture News, 55: 65–67.

Oil and Gas UK, (2013) Decommissioning of Pipelines in the North Sea Region. Oil & Gas UK. 48pp.

OGB, 2010. Riser & pipeline release frequencies, London, Brussels.

Olendorff, R.R., Motroni, R.S., Call, M.W. (1980) Raptor Management: The State of the Art in 1980. Bureau of Land Management Technical Note No. 345. US Department of Interior, Denver, USA.

Olson, C.V. (2002) Human-related causes of raptor mortality in western Montana: things are not always as they seem. In: Carlton, R.G. (Ed.), Avian Interactions with Utility and Communication Structures, Proceedings of a Workshop. Electric Power Research Institute, Palo Alto, CA, USA, pp. 71-82.

OSPAR Commission, 2008. Background document on potential problems associated with power cables other than those for oil and gas activities,

OSPAR (2009) Assessment of the environmental impacts of cables. Biodiversity Series. 18pp.

OSPAR (2010) Background document for maerl beds. OSPAR Commission. 34pp.

OSPAR (2012) Guidelines on Best Environmental Practice (BEP) in Cable Laying and Operation. Agreement 2012-2. OSPAR 12/22/1, Annex 14.

Parsons Brinkerhoff & Cable Consulting International Ltd, 2012. Electricity Transmission Costing Study - An Independent Report Endorsed by the Institution of Engineering & Technology,

Prinsen, H.A.M., G.C. Boere, N. Píres & J.J. Smallie (Compilers), 2011. Review of the conflict between migratory birds and electricity power grids in the African-Eurasian region. CMS Technical Series, AEWA Technical Series No. XX. Bonn, Germany. Available at: www.cms.int/bodies/COP/cop10/docs_and_inf_docs/inf_38_electrocution_review.pdf.

Prinsen, H.A.M., J.J. Smallie, G.C. Boere & N. Píres (Compilers), 2012. Guidelines on how to avoid or mitigate impact of electricity power grids on migratory birds in the African-Eurasian region. CMS Technical Series No. XX, AEWA Technical Series, Bonn, Germany. Available at: www.unep-aewa.org/meetings/en/stc_meetings/stc7docs/pdf/stc7_20_electrocution_guidelines.pdf.

Prommer, M. (2011) Electrocuted Sakers. Saker LIFE, BNPI, Hungary. sakerlife2.mme.hu/en/content/electrocuted-sakers

PSCW (2009) Electric Transmission Lines. Wisconsin, USA.

Pullin, A.S., Stewart, G.B. (2006) Guidelines for systematic review in conservation and environmental management. Conservation biology: the journal of the Society for Conservation Biology, 20(6), 1647-56.

Raab, R., Spakovszky, P., Julius, E., Schütz, C., Schulze, C.H. (2010) Effects of power lines on flight behaviour of the West-Pannonian Great Bustard Otis tarda population. Bird Conservation International: 1- 14.

Real, J., Grande, J.M., Mañosa, S., Antonio, J. (2001) Causes of Death in Different Areas for Bonelli's Eagle Hieraaetus fasciatus in Spain. Bird Study, 221-228.

Reed, B. & Hovel, K., 2006. Seagrass habitat disturbance: how loss and fragmentation of eelgrass Zostera marina influences epifaunal abundance and diversity. Marine Ecology Progress Series, 326, pp.133-143. Available at: www.int-res.com/abstracts/meps/v326/p133-143/ [Accessed May 2, 2012].

RenewableUK, (2013) cumulative Impact Assessment Guidelines. Guiding Principles for cumulative impacts assessment in offshore wind farms. June 2013.

Rheindt, F.E., 2003. The impact of roads on birds: Does song frequency play a role in determining susceptibility to noise pollution? Journal of Ornithology, 144(3), pp.295-306. Available at: www.springerlink.com/index/10.1007/BF02465629 [Accessed April 24, 2012].

Rich, A.C., Dobkin, D.S. & Niles, L.J., 1994. Defining Forest Fragmentation by Corridor Width: The Influence of Narrow Forest-Dividing Corridors on Forest-Nesting Birds in Southern New Jersey. Conservation Biology, 8(4), pp.1109-1121. Available at: onlinelibrary.wiley.com/doi/10.1046/j.1523-1739.1994.08041109.x/abstract [Accessed April 30, 2012].

Rich, A.C., Dobkin, D.S., Niles, L.J. (1994) Defining forest fragmentation by corridor width: the influence of narrow forest-dividing corridors on forest-nesting birds in southern New Jersey. Conservation Biology, 8: 1109–1121.

Rich, C. & Longcore, T. (Eds). (2006) Ecological Consequences of Artificial Night Lighting. Washington, Island Press.

Roberts, D.A., 2012. Causes and ecological effects of resuspended contaminated sediments (RCS) in marine environments. Environment international, 40, pp.230-43. Available at: www.sciencedirect.com/science/article/pii/S0160412011002704 [Accessed April 16, 2012].

Robinson, S.P & Lepper, P.A. (2013) Scoping study: Review of current knowledge of underwater noise emissions from wave and tidal stream energy devices. The Crown Estate, 2013.

RTE, 2011. Liaison électrique souterraine à courant continu à 320 000 volts SAVOIE - PIEMONT - Etude d'impact,

RTE, Projet de zone d'accueil de production d'électricité de Lavera-Fos - Etude d'impact,

Russell, K.N., Ikerd, H. & Droege, S., 2005. The potential conservation value of unmowed powerline strips for native bees. Biological Conservation, 124(1), pp.133-148. Available at: linkinghub.elsevier.com/retrieve/pii/S0006320705000467 [Accessed March 17, 2012].

Schaub, M., Aebischer, A., Gimenez, O., Berger, S., Arlettaz, R. (2010) Massive Immigration Balances High Anthropogenic Mortality in a Stable Eagle Owl Population: Lessons for Conservation. Biological Conservation, 143(8): 1911-1918.

Schreiber, M. et al., 2004. Maßnahmen zur Vermeidung und Verminderung negativer ökologischer Auswirkungen bei der Netzanbindung und -integration von Offshore-Windparks - Abschlussbericht, Bramsche.

Secretariat of the Convention on Biological Diversity, 2010. Global Biodiversity Outlook 3, Montréal. Available at: www.ncbi.nlm.nih.gov/pubmed/22532583 [Accessed April 27, 2012].

Sergio, F., Marchesi, L., Pedrini, P., Ferrer, M., Penteriani, V. (2004) Electrocution Alters the Distribution and Density of a Top Predator, the Eagle Owl Bubo bubo. Journal of Applied Ecology, December: 836-845.

Silva, J.P., Santos, M., Queirós,L., Leitão, D., Moreira, F., Pinto, M., Leqoc, M., Cabral, J.A. (2010): Estimating the influence of overhead transmission power lines and landscape context on the density of little bustard Tetrax tetrax breeding populations. Ecological Modelling 221: pp.1954–1963.

Skonberg, E.R. et al., 2008. Inadvertent Slurry Returns during Horizontal Directional Drilling: Understanding the Frequency and Causes. In J. W. Goodrich-Mahoney et al., eds. Environment Concerns in Rights-of-Way Management 8th International Symposium. Amsterdam: Elsevier, pp. 613–621.

Slabbekoorn, H. & Ripmeester, E. a P., 2008. Birdsong and anthropogenic noise: implications and applications for conservation. Molecular ecology, 17(1), pp.72-83. Available at: www.ncbi.nlm.nih.gov/pubmed/17784917 [Accessed March 4, 2012].

SmartGrids ERA-Net (2012) Mapping & Gap Analysis of current European Smart Grids Projects. Report by the EEGI Member States Initiative: A pathway towards functional projects for distribution grids. Austrian Institute of Technology, Austria.

Söker, H., Rehfeldt, K., Santjer, F. et al. (2000) Offshore Wind Energy in the North Sea. Technical Possibilities and Ecological Considerations – A study for Greenpeace. 83pp.

SP Transmission & National Grid, 2011a. Western HVDC Link - Environmental Appraisal Supporting Report - Northern Point of Connection: Hunterson - Ardneil Bay Undergournd HDVC Cable,

SP Transmission & National Grid, 2011b. Western HVDC Link - Environmental Report - Marine Cable Route,

Statoil, (2012) Mariner Area Development Environmental Statement. DECC Project Reference: D/4145/2012.

Strevens, T.C., 2007. Powerline easements: ecological impacts and effects on small mammal movement. University of Wollongong. Available at: ro.uow.edu.au/theses/691/ [Accessed February 23, 2012].

Strevens, T.C., Puotinen, M.L. & Whelan, R.J., 2008. Powerline Easements: Ecological Impacts and Contribution to Habitat Fragmentation from Linear Features. Pacific Conservation Biology, 14(3), pp.159-168.

Summers, P.D., Cunnington, G.M. & Fahrig, L., 2011. Are the negative effects of roads on breeding birds caused by traffic noise? Journal of Applied Ecology, 48(6), pp.1527-1534. Available at: onlinelibrary.wiley.com/doi/10.1111/j.1365-2664.2011.02041.x/full [Accessed March 29, 2012].

Swannell, R.P., Lee, K. & McDonagh, M., 1996. Field evaluations of marine oil spill bioremediation. Microbiological reviews, 60(2), pp.342-65. Available at: www.pubmedcentral.nih.gov/articlerender.fcgi?artid=239447&tool=pmcentrez&rendertype=abstract [Accessed July 6, 2012].

Swanson, C. & Isaji, T., 2006. Simulations of sediment transport and deposition from cable burial operations in Nantucket Sound for the Cape Wind Energy project, Available at: www.mms.gov/offshore/renewableenergy/DEIS/Report References-Cape Wind Energy EIS/Report No 4.1.1-2.pdf [Accessed April 17, 2012].

Temple, S.A. (1986) The problem of avian extinctions. In: Johnston, R.F (ed.) Current Ornithology, Vol. 3: 453-485 Plenum, New York.

Thompson, P.M., Wilson, B., Grellier, K., Hammond, P.S. (2001) Combining power analysis and population viability analysis to compare traditional and precautionary approaches to conservation of coastal cetaceans. Conservation Biology, 14: 1253–1263.

Tintó, A., Real, J., Manosa, S. (2001) Avaluació del risc d'electrocució d'aus en línies elèctriques situades a Sant Llorenç del Munt i rodalies. V Trobada d'estudiosos de Sant Llorenç del Munt i l'Obac. Monografies, 35: 129-133

Tri-State (2009) San Luis Valley - Calumet – Comanche Transmission Project. Southern Colorado Transmission Improvements. Working with Landowners. Colorado, USA.

Tucker, G.M., Evans, M.I. (1997) Habitats for birds in Europe: a conservation strategy for the wider environment. Cambridge, UK: BirdLife International (BirdLife Conservation Series no. 6).

UNEP (2011) UN Wildlife Meeting Pushes to Make Power Lines Safer for Birds. UNEP COP 10 communication. Bergen, Norway.

Ussenkov, S.M., 1997. Contamination of harbor sediments in the eastern Gulf of Finland (Neva Bay), Baltic Sea. Environmental Geology, 32(4), pp.274-280. Available at: www.springerlink.com/openurl.asp?genre=article&id=doi:10.1007/s002540050217 [Accessed April 27, 2012].

Vallejo, V.R., Arianoutsou, M. & Moreira, F., 2012. Fire Ecology and Post-Fire Restoration Approaches in Southern European Forest Types. In F. Moreira et al., eds. Post-Fire Management and Restoration of Southern European Forests. Springer Netherlands, pp. 93-119. Available at: dx.doi.org/10.1007/978-94-007-2208-8_5 [Accessed April 26, 2012].

Van Rooyen, C. (2004) The Management of Wildlife Interactions with Overhead Lines. In The fundamentals and practice of overhead line maintenance (132 kV and above), pp. 217-245. Eskom Technology, Services International, Johannesburg.

Van Rooyen, C. (2012) Bird Impact Assessment Report. Technical Document.

Venus, B., McCann, K. (2005) Bird Impact Assessment Study. Technical Document (pp. 1-45).

Vistnes, I. et al., 2001. Wild reindeer: impacts of progressive infrastructure development on distribution and range use. Polar Biology, 24(7), pp.531-537. Available at: www.springerlink.com/openurl.asp?genre=article&id=doi:10.1007/s003000100253 [Accessed April 27, 2012].

Walker, L. J. and Johnston, J. (1999) Guidelines for the Assessment of Indirect and Cumulative Impacts as well as Impact Interactions. European Commission. ec.europa.eu/environment/eia/eia-support.htm

Wetlands International, Wings Over Wetlands - UNEP-GEF African-Eurasian Flyways Project (2011) The Critical Site Network: Conservation of Internationally Important Sites for Waterbirds in the African-Eurasian Waterbird Agreement area. Wetlands International, Ede, the Netherlands and BirdLife International, Cambridge, UK.

Williams, R.J. & Bradstock, R.A., 2008. Large fires and their ecological consequences: introduction to the special issue. International Journal of Wildland Fire, 17(6), p.685. Available at: www.publish.csiro.au/?paper=WF07155 [Accessed April 25, 2012].

Woinarski, J.C.Z. et al., 2000. A different fauna?: captures of vertebrates in a pipeline trench, compared with conventional survey techniques; and a consideration of mortality patterns in a pipeline trench. Australian Zoologist, 31(3), pp.421-431.

Wolff, A., 2010. Plan de gestion 2010 - 2014 - Section A: Diagnostic et enjeux,

Xu, J., Pancras, T. & Grotenhuis, T., 2011. Chemical oxidation of cable insulating oil contaminated soil. Chemosphere, 84(2), pp.272-7. Available at: www.ncbi.nlm.nih.gov/pubmed/21571353 [Accessed April 26, 2012].

Zalles, J.I., Bildstein, K.L. (2000) Raptor watch: A Global directory of Raptor Migration Sites. Cambridge, UK: BirdLife International; and Kempton, PA, USA: Hawk Mountain Sanctuary (Birdlife Conservation Series, Vol. 9).

Zozaya, E.L., Brotons, L. & Saura, S., 2011. Recent fire history and connectivity patterns determine bird species distribution dynamics in landscapes dominated by land abandonment. Landscape Ecology, 27(2), pp.171-184. Available at: www.springerlink.com/index/10.1007/s10980-011-9695-y [Accessed March 13, 2012].

Zucco, C. et al., 2006. Ecological research on Offshore Wind Farms: International Exchange of Experiences - Part B: Literature Review of Ecological Impacts, Bonn.


(1)  All documents can be downloaded from: http://ec.europa.eu/environment/nature/natura2000/management/guidance_en.htm

(2)  COM(2015) 80 final.

(3)  Energy infrastructure: priorities for 2020 and Beyond – a blueprint for an integrate European energy network http://ec.europa.eu/energy/publications/doc/2011_energy_infrastructure_en.pdf

(4)  Regulation (EU) No 347/2013 of the European Parliament and of the Council of 17 April 2013 on guidelines for trans-European energy infrastructure and repealing Decision No 1364/2006/EC and amending Regulations (EC) No 713/2009, (EC) No 714/2009 and (EC) No 715/2009 (OJ L 115, 25.4.2013, p. 39).

(5)  Marine energy transmission infrastructures are covered in Section 8 of this document.

(6)  In this guidance the term ‘transmission’ refers to the whole system, from transmission strictly speaking to distribution. If impacts differ between transmission, sub-transmission and distribution power lines, the specific term will be used.

(7)  https://ec.europa.eu/energy/en/topics/infrastructure/projects-common-interest

(8)  The types of energy infrastructure categories to be developed under the TEN-E Regulation are specified in Annex II of the Regulation.

(9)  https://ec.europa.eu/energy/sites/ener/files/publication/MJ3010705ENC.pdf

(10)  http://ec.europa.eu/energy/infrastructure/transparency_platform/map-viewer

(11)  Guidance Document ‘Streamlining environmental assessment procedures for energy infrastructure “Projects of Common Interest” (PCIs)’ July 2013. http://ec.europa.eu/energy/infrastructure/pci/doc/20130724_pci_guidance.pdf

(12)  http://ec.europa.eu/environment/nature/biodiversity/strategy/index_en.htm

(13)  Directive 2009/147/EC Council (codified version of Council Directive 79/409/EEC on the conservation of wild birds, as amended) – see http://ec.europa.eu/environment/nature/legislation/index_en.htm

(14)  Council Directive 92/43/EEC of 21 May 1992 on the conservation of natural habitats and of wild fauna and flora, consolidated version 1.1.2007 - http://ec.europa.eu/environment/nature/legislation/index_en.htm

(15)  The concept of ‘favourable conservation status’ is not mentioned in the Birds Directive but there are analogous requirements in Art 4.1 and 4.2 of the Birds directive for Special Protection Areas (SPA).

(16)  It should be clarified that Article 6(1) of the Habitats Directive does not apply to SPAs. However, analogous provisions apply to SPAs by virtue of Article 4(1) and (2) of Birds Directive laying down ‘special conservation measures’ for the SPAs. However, pursuant to Article 7 of the Habitats directive the provisions of Article 6(2) -6(4) of the same directive, apply to both SCIs and already classified SPAs.

(17)  http://ec.europa.eu/environment/nature/natura2000/management/docs/commission_note/commission_note2_EN.pdf

(18)  http://ec.europa.eu/environment/nature/natura2000/management/docs/commission_note/comNote%20conservation%20measures_EN.pdf

(19)  Pursuant to Article 7 of the Habitats directive the provisions of Article 6(3) and 6(4) of the same directive, apply to both SCIs and already classified SPAs.

(20)  See Guidance document on the strict protection of animal species of Community interest under the Habitats Directive http://ec.europa.eu/environment/nature/conservation/species/guidance/index_en.htm

(21)  http://onlinelibrary.wiley.com/doi/10.1111/cobi.12262/full

(22)  http://www.easac.eu/fileadmin/PDF_s/reports_statements/Transforming.pdf

(23)  https://www.unenvironment.org/news-and-stories/story/planning-can-help-prevent-renewable-energy-surge-harming-wildlife

(24)  http://www.life-elia.eu/en/

(25)  Project summary available on: http://www.50hertz.com/en/file/100304_EcoMOL_ShortReport_eng_final_med.pdf

(26)  www.birdlife.org/datazone/sowb/casestudy/240

(27)  Guidance Document ‘Streamlining environmental assessment procedures for energy infrastructure “Projects of Common Interest” (PCIs)’ July 2013. http://ec.europa.eu/energy/infrastructure/pci/doc/20130724_pci_guidance.pdf

(28)  http://eur-lex.europa.eu/legal-content/EN/TXT/PDF/?uri=CELEX:52009DC0469&from=en

(29)  The concept of tiering can be defined as: distinguishing different levels of planning – policy, plans, programs – that are prepared consecutively and influence each other (EC 1999). Tiering is about how the different levels of planning relate to each other.

(30)  Directive 2009/72/EC on common rules for the internal market in electricity

(31)  Council Decision of 27 June 1997 on the conclusion, on behalf of the Community, of the Convention on environmental impact assessment in a transboundary context (ESPOO Convention) (proposal OJ C 104, 24.4.1992, p. 5; decision not published) and Council Decision 2008/871/EC of 20 October 2008 on the approval, on behalf of the European Community, of the Protocol on Strategic Environmental Assessment to the 1991 UN/ECE Espoo Convention on Environmental Impact Assessment in a Transboundary Context (OJ L 308, 19.11.2008, p. 33).

(32)  Article 7 of the SEA Directive and Article 7 of the EIA Directive

(33)  http://ec.europa.eu/environment/eia/pdf/Transboundry%20EIA%20Guide.pdf

(34)  http://ec.europa.eu/environment/nature/natura2000/management/docs/art6/new_guidance_art6_4_en.pdf

(35)  http://ec.europa.eu/environment/nature/natura2000/management/docs/Wind_farms.pdf; http://ec.europa.eu/news/energy/101013_en.htm; http://qsr2010.ospar.org/en/ch07_01.html http://www.ospar.org/content/content.asp?menu=00210305000000_000000_000000

(36)  https://windeurope.org/wp-content/uploads/files/about-wind/statistics/WindEurope-Annual-Offshore-Statistics-2016.pdf

(37)  http://www.4coffshore.com/windfarms/horns-rev-2-denmark-dk10.html

(38)  http://si-ocean.eu/en/upload/docs/WP3/Technology%20Status%20Report_FV.pdf

(39)  https://ec.europa.eu/jrc/en/news/jrc-ocean-energy-status-report-2016-edition

(40)  http://sequestration.mit.edu/tools/projects/index.html

(41)  https://windeurope.org/about-wind/reports/wind-energy-in-europe-scenarios-for-2030/

(42)  http://www.renewableuk.com/en/renewable-energy/wave-and-tidal/

(43)  http://northseagrid.info/project-description

(44)  http://ec.europa.eu/energy/infrastructure/studies/doc/2014_nsog_report.pdf

(45)  http://www.europarl.europa.eu/meetdocs/2009_2014/documents/itre/dv/160/160620/16062011_study_pe457373_en.pdf

(46)  http://e3g.org/showcase/North-Seas-Grid

(47)  http://eur-lex.europa.eu/LexUriServ/LexUriServ.do?uri=OJ:L:2013:115:0039:0075:EN:PDF

(48)  http://ec.europa.eu/environment/nature/knowledge/rep_habitats/index_en.htm

(49)  European Commission (2013) Interpretation Manual of European Union Habitats. EUR 28 April 2013. http://ec.europa.eu/environment/nature/legislation/habitatsdirective/docs/Int_Manual_EU28.pdf

(50)  http://ec.europa.eu/environment/nature/natura2000/marine/docs/FAQ%20final%202012-07-27.pdf

(51)  https://www.bonnagreement.org/

(52)  http://qsr2010.ospar.org/media/assessments/p00437_Cables.pdf;

(53)  A zone between 2-8m wide, depending on plough size is quoted by (Carter et al., 2009).

(54)  E.g. Camphuysen et al., (2009);Jenssen (1996); de la Huz et al., (2005)

(55)  Summarised in AMETS Foreshore Lease Application EIS, Appendix 4 (2010)

(56)  E.g. Meissner & Sordyl, 2006 http://www.bfn.de/fileadmin/MDB/documents/themen/meeresundkuestenschutz/downloads/Forschungsberichte/Ecological_Research_Offshore-Wind_Part_B_Skripten_186.pdf

(57)  http://www.unesco-ioc-marinesp.be/msp_faq

(58)  http://eur-lex.europa.eu/legal-content/EN/TXT/HTML/?uri=CELEX:32014L0089&from=EN


ANNEX 1

National and international initiatives

Examples of national legislations

This section describes examples among others of national legislation on biodiversity impacts of energy transmission facilities.

Germany

Article 41 of the German Law on Nature Protection and Landscape Conservation (Gesetz über Naturschutz und Landschaftspflege), indicates that the poles and technical components of the medium voltage cables to be constructed must be designed to protect birds from electrocution. For existing medium voltage cables with a high risk to birds, the necessary measures must be taken up to 31 December 2012 to protect birds from electrocution.

Slovakia

Under Slovakian law, article §4 of the Act No 543/2002 Coll. on Nature and Landscape Protection states (as amended): ‘everyone who constructs or carries out scheduled reconstruction of overhead electricity lines is obliged to use technical solutions that prevent killing birds’ and ‘if killing birds on electricity lines or telecommunication facilities is verifiable, the nature protection body may rule that an administrator of electricity lines or telecommunication facilities has to adopt measures to prevent killing birds’. The district or regional environmental offices give their opinion for each territorial decision or building permit (including those on electricity infrastructure). In 2007, a guidance was prepared to eliminate mortality of birds on electricity infrastructure. It contains the summary of legal tools, the description of appropriate technical solutions, both for mountainous and plain sites, and suggestions for further solutions (such as not legally binding meetings with the energy companies before the decision is made).

Spain

In Spain, regional and national laws were approved with regard to avian electrocution: decree 178/2006 (October 10th(1) establishing rules for the protection of birds from high-tension power lines in the Junta de Andalucía, and Royal Decree 1432/2008 (August 29th(2), establishing technical measures for high-tension power lines in order to protect birds. This national decree prevents companies from putting up dangerous power lines in sensitive areas for birds (including SPAs). This decree settles some binding technical prescriptions for the electricity pylon design, anti-collision measures, schedule of works, etc.

Implementation of international conventions

Several MS are also implementing recommendation no 110 of the Bern Convention by adopting in national legislation the technical standards for safety of power lines, planning and anti-collision measures.

Voluntary agreements and tools

This section describes examples among others of voluntary agreements relative to biodiversity impacts of energy transmission facilities.

European Grid Declaration on Electricity Network Development and Nature Conservation in Europe (3)

Several European NGOs, TSOs and supporters have signed this declaration on 10 November 2011. Its main objective is to provide an agreed framework of principles guiding the stakeholders in their efforts to minimise negative impacts on the natural environment (biodiversity and ecosystems) that can arise in developing electricity transmission facilities (both above and below ground lines). The declaration includes overarching principles, principles for strategic planning (including alignment on the need for consideration of environmental concerns at the earliest stages (principle 4.1.1), the use of spatial mapping tools (4.1.4), etc.), and principles for project planning and reducing impacts of existing power lines.

The Renewables Grid Initiative (4)

This is a collaboration of NGOs and TSOs from across Europe. We promote transparent, environmentally sensitive grid development to enable the further steady growth of renewable energy and the energy transition. RGI members originate from a variety of European countries, consisting of TSOs from Belgium (Elia), France (RTE), Germany (50 Hertz and TenneT), Italy (Terna), the Netherlands (TenneT), Spain (Red Eléctrica), Switzerland (Swissgrid) and Norway (Statnett), Spain (REE); and NGOs such as WWF International, BirdLife Europe, Fundación Renovables, Germanwatch, Legambiente, the Royal Society for the Protection of Birds (RSPB), Climate Action Network (CAN) Europe and Natuur&Milieu. RGI was launched in July 2009.

Accessible sky agreement (5)

On 26 February 2008, the Hungarian Ornithological and Nature Conservation Society (MME / BirdLife Hungary) signed this agreement with the Ministry of Environment and Water, and relevant electric companies in Hungary, to provide a long-term solution for the problem of bird electrocution. Under this agreement, MME produced a map in 2008 with priority areas of conflict between power lines and bird populations in Hungary. Electric companies promised a ‘bird-friendly’ transformation of all dangerous power lines in Hungary by 2020, and the use of ‘bird-friendly’ management methods for newly constructed power lines. In cooperation between electric companies and conservation experts, guidelines for the associated best available technology are constantly updated and new solutions are field-tested.

Budapest Declaration on bird protection and power lines (6)

This declaration has been adopted by the recent conference ‘Power lines and bird mortality in Europe’ (Budapest, 13 April 2011). This conference was co-organised by MME/BirdLife Hungary, the Ministry of Rural Development of Hungary and BirdLife Europe. It was attended by stakeholders of European and Central Asian countries, the European Commission, UNEP-AEWA, energy and utility companies, experts, businesses and NGOs. The declaration called on all interested parties to jointly undertake a programme of follow up actions leading to effective minimisation of the power line induced bird mortality across the European continent and beyond.

Slovakian technical norm

In 2009, the Eastern Slovakia Electricity Company issued an internal technical norm called: ‘Construction and amendment of aerial 22kV power lines with respect to bird protection.’

The Energy & Biodiversity initiative (7)

As leading energy companies came to recognize the value of integrating biodiversity conservation into upstream oil and gas development, several of them joined with leading conservation organizations to develop and promote biodiversity conservation practices for meeting this goal. Their partnership, the Energy and Biodiversity Initiative (EBI), which began in 2001 and ceased in 2007 produced practical guidelines, tools and models to improve the environmental performance of energy operations, minimize harm to biodiversity, and maximize opportunities for conservation wherever oil and gas resources are developed.

The LIFE+ programme (8)

Life+ is the EU's financial instrument supporting environmental and nature conservation projects. Several LIFE+ projects targeted electric infrastructures impacts on birds, and in many plans protecting birds, provisions about electricity lines are included. The table below presents a non-exhaustive overview of these projects from the year 2000.

LIFE+ projects linked to electricity infrastructures and birds

Reference

Title

MS

LIFE04 NAT/ES /000034 (9)

ZEPA eléct. Aragón - Adaptation of the electric power lines in the SPA of Aragón

The project's overall aim was to implement a strategy, devised by the government of Aragón, for the adaptation of the overhead electric power line network to the conservation needs of 16 SPAs in the region.

ES

LIFE06 NAT/E /000214 (10)

Tendidos Electricos Murcia - Correction of Dangerous Overhead Cables in Special Protection Areas for Birds in the Region of Murcia

The project implements the strategy devised by the Regional Government of Murcia for the correction of the overhead cables to the conservation needs of 5 SPAs of the Natura 2000 regional network.

ES

LIFE10 NAT/BE /000709 (11)

ELIA - Development of the beddings of the electricity transportation network as means of enhancing biodiversity

The aim of the ELIA Biodiversity project is to develop innovative techniques for the creation and maintenance of corridors under overhead lines, allowing the maximisation of their potential benefits for biodiversity.

BE

LIFE05 ENV/NL /000036 (12)

EFET - Demonstration of a new environmentally friendly high voltage overhead line

The project's aim was to demonstrate a new combination of high-voltage line and pylon that emits much lower magnetic field strengths, thereby reducing negative impacts on health and the environment.

NL

LIFE00 NAT/IT /007142 (13)

Po ENEL - Improvement of the habitats through restoration and/or transformation of electrical plants existing and under construction in the Po Delta Park

The main aim of this LIFE Nature project was to reduce and eliminate the risk of bird collision and electrocution in 20 areas identified as risky, involving a total of approximately 91 km of electric power lines.

IT

Other LIFE projects focus on the conservation of specific bird species and therefore include measures related to the impacts of power lines on birds, for example Aquila heliaca in the Carpathian basin (LIFE02 NAT/H/008627 and LIFE03 NAT/SK/000098), OTISHU on the conservation of Otis tarda in Hungary (LIFE04 NAT/HU/000109), ZEPA La Serena on the management of the PSA-SCI ‘La Serena y Sierras periféricas’ (LIFE00 NAT/E/007348), Grosstrappe - Cross-border Protection of the Great Bustard in Austria (LIFE05 NAT/A/000077 and LIFE09 NAT/AT/000225), Ochrona bociana białego - Protection of the white stork population in the OSO Natura 2000 Ostoja Warmińska (LIFE09 NAT/PL/000253), etc.

BESTGRID project (14)

Launched in April 2013, BESTGRID is made up of four pilot projects located in Belgium, Germany and the UK. During the project nine partners - TSOs, European NGOs and a research institute worked together to improve local and public acceptance for grid development processes. Objectives of the project were to enhance transparency and public participation, to speed up permitting procedures by proactively addressing or even surpassing environmental protection standards, and to encourage the implementation of constructive public engagement in permitting procedures for European energy infrastructure ‘projects of common interest.’ In the framework of the project a handbook on Protecting Nature in Power Grid Planning has been developed (15)

The European Business and Biodiversity Campaign (16)

The European Business and Biodiversity Campaign was initiated by a consortium of European NGOs and companies lead and coordinated by the Global Nature Fund in order to strengthen private sector commitment for biodiversity and ecosystem services. The campaign is supported by the European Union LIFE+ Programme. Business and Biodiversity initiatives are being developed in many parts of the world and initiated by different actors, be they non-business organisations or from businesses and business associations themselves.

The Portuguese Business and Biodiversity Initiative (17)

The Portuguese Business and Biodiversity Initiative seeks to promote, through voluntary agreements of long duration, a common ground for collaboration between these two distinct systems: business and biodiversity, which promotes the introduction of biodiversity strategies and policies of companies. Notably, guides on biodiversity impacts of energy transmission facilities have been developed among the Portuguese authority (ICNB, Institute for Nature Conservation and Biodiversity) and the Portuguese TSO and DSO.

Actions in the context of the State Nature Conservancy of the Slovak Republic (18)

The State Nature Conservancy of the Slovak Republic (expert body of the ministry of the environment) cooperates with three main electricity distribution companies (operating in east, central and west Slovakia). This cooperation, supported by the ornithological NGOs, has been strengthened by several LIFE projects. It varies from the written agreement to the strategy to eliminate threats of the 22 kV electricity power lines on birds. Setting annual plans, step-by-step identification of ‘priority’ sections, cooperation in methodology - promoting and testing mitigation measures are some of results of long-term cooperation that was strengthened via several LIFE projects.

Relevant international nature and biodiversity Conventions and Agreements

The European Union and its Member States, as well as most other European countries are contracting parties to various relevant international environmental Conventions and Agreements. Thus, European and national legal frameworks on nature and biodiversity conservation must take full account of the commitments entered into under these Conventions and Agreements as well.

These Conventions and Agreements have helped to shape the legal framework for biodiversity policy and legislation within the EU and also helped define the relationship between the EU and other countries. The following outlines the most relevant in the context of energy infrastructures and nature conservation in Europe. Several have also adopted specific recommendations and resolutions on energy infrastructures and wildlife, notably on overhead power lines (19).

Convention on Biological Diversity (20)

The CBD is a global treaty, adopted in Rio de Janeiro in June 1992. It widened the scope of biodiversity conservation from species and habitats to the sustainable use of biological resources to the benefit for mankind. To date, 193 countries are parties to the convention.

Convention on the Conservation of European Wildlife and Natural Habitats (21)

The ‘Bern Convention’ came into force in 1982. It has played a significant role in strengthening the work on biodiversity conservation in Europe. It has been ratified by 45 Member States of the Council of Europe, by the European Union and by four countries in Africa. An important objective of the convention is the creation of the Emerald Network (22) of Areas of Special Conservation Interest (ASCIs). This operates alongside the EU Natura 2000 Network. The Bern Convention Standing Committee adopted in 2004 a recommendation (no 110) on minimising adverse effects of above-ground electricity transmission facilities (power lines) on birds (23). In 2011, the Standing Committee requested from the Parties to the Convention to report on a bi-annual basis the progress in implementation of recommendation no 110.

Convention on the Conservation of Migratory Species of Wild Animals (24)

The CMS, or ‘Bonn Convention’, aims to preserve migratory species throughout their natural range. It entered into force in 1983 and has now been signed by 116 parties. Several resolutions, recommendations and agreements signed under this Convention are relevant to the management of conflicts between migrating animals and energy infrastructures, in particular overhead power lines:

 

Resolution 7.4 (25) of the Convention on Migratory Species (CMS) on the electrocution of migratory birds calls on all Parties and non-Parties to curb the electrocution risk by taking appropriate measures in planning and constructing lines.

 

Catalogue of measures contained in document UNEP/CMS/Inf.7.21.

 

Action Plan of the Memorandum of Understanding on the Conservation of Migratory Birds of Prey in Africa and Eurasia (Raptors MoU) (26) considers power lines as principle threats to birds and formulates a Priority Action to reduce their effect. The plan aims at ‘b. Promoting, as far as possible, high environmental standards, including through Environmental Impact Assessments, in the planning and construction of structures to minimise their impact on species, particularly by collision and electrocution, and seeking to minimise the impact of existing structures where it becomes evident that they constitute a negative impact for the species concerned;’

The Action Plan proposes the following four Activities regarding power lines and raptors:

1.4 Review relevant legislation and take steps where possible to make sure that it requires all new power lines to be designed to avoid bird of prey electrocution.

2.3 Conduct risk analysis at important sites (including those listed in Table 3 of the Raptors MoU) to identify and address actual or potential causes of significant incidental mortality from human causes (including fire, laying poisons, pesticide use, power lines, wind turbines).

3.2 Where feasible, take necessary actions to ensure that existing power lines that pose the greatest risk to birds of prey are modified to avoid bird of prey electrocution.

5.5 Monitor power line and wind farm impacts on birds of prey, including through analysis of existing data such as ringing data.

 

Agreement on the Conservation of African-Eurasian Migratory Waterbirds (27) (AEWA) calls for coordinated action throughout the migration routes or flyways. It came into force in 1999. The agreement covers 119 countries and 235 species of waterbirds. The European Community ratified AEWA in 2005.

Illustration: Guidance from UNEP/AEWA (28)

The German energy company, RWE Rhein-Ruhr Netzservice GmbH (RWE RR NSG) and the UNEP/AEWA Secretariat signed a partnership agreement at the 37th Meeting of the CMS Standing Committee (Bonn, 23-24 November 2010). As part of this agreement, RWE RR NSG provided funding for the preparation of an independent review on the conflict between migratory birds and electricity power grids in the African-Eurasian region (Prinsen et al. 2011) and the development of guidelines for mitigating and avoiding such a conflict (Prinsen et al., 2012).

At the end of 2010, the UNEP/AEWA Secretariat, also on behalf of the Convention on Migratory Species (CMS) and the CMS MoU on Birds of Prey, commissioned the preparation of the review and the guidelines to an international consortium of expert organisations. These guidelines offer various technical and legislative approaches for avoiding or mitigating the impact of electrocution and collision of migratory birds across the African-Eurasian region as well as suggestions for assessing and monitoring the effectiveness of mitigation and preventive measures.

Following formal consultations, the 5th Meeting of the Parties adopted these guidelines as Conservation Guidelines in the sense of Article IV of the Agreement (draft Resolution AEWA/MOP5 DR10 Revision and Adoption of Conservation Guidelines). The European Union is a Party to the Agreement as well as most MS. The Guidelines assist the Parties in the implementation of their obligations under the Agreement.

 

Agreement on the Conservation of Populations of European Bats (29) (EUROBATS) concerns the protection of all 45 species of bats found in Europe. It entered into force in 1994. Currently 32 countries have signed up. Implementation of common conservation strategies and international experience-sharing are its main activities.

 

Agreement on the Conservation of Small Cetaceans of the Baltic and North Sea (30) (ASCOBANS) aims to co-ordinate measures to reduce negative impact of by-catches, habitat loss, marine pollution and acoustic disturbances among the ten parties. It was launched in 1991. A resolution on adverse effects of sound on small cetaceans, and with relevance for potential impact from energy infrastructures, was adopted in 2006.

 

Agreement on the Conservation of Cetaceans in the Black Sea, Mediterranean Sea and contiguous Atlantic area (31) (ACCOBAMS) is a cooperative framework for the conservation of marine biodiversity in the Mediterranean and Black Seas. Its main purpose is to reduce the threat to and improve knowledge about cetaceans in these seas. The agreement came into force in 2001.

Convention of Wetlands of International Importance (32)

The ‘Ramsar Convention’ is an intergovernmental treaty providing a framework for national action and international cooperation for the conservation and wise use of wetlands. It was adopted in 1971 and amended in 1982 and 1987. There are to date 160 parties and so far 2006 sites worldwide have been added to the ‘Ramsar’ list of wetlands of international importance. The Convention does not foresee ratification by supra-national bodies such as the European Union but all Member States of the EU are contracting parties.

Convention for the Protection of the Marine Environment of the North-East Atlantic (33)

OSPAR guides international cooperation on a range of issues including the conservation of marine biodiversity and ecosystems, the impact of eutrophication and hazardous substances, and monitoring and assessment. It was launched in 1992, following of the merger of the previous Oslo and Paris Conventions (from 1972 and 1974). Several studies of potential impact of energy infrastructure on the marine environment have been initiated under the auspices of this Convention.

Convention on the protection of the marine environment of the Baltic Sea Area (34)

HELCOM, or the ‘Helsinki Convention’, covers the Baltic Sea basin plus all inland waters in its catchment area. It was adopted in 1980 and revised in 1992. All countries around the Baltic Sea plus the EU are contracting parties.

Convention for Protection against Pollution in the Mediterranean Sea (35)

The ‘Barcelona Convention’ aims primarily to regulate and reduce the negative impact of all kinds of pollutants in the Mediterranean basin. It was set up in 1976 and last amended in 1995. Most countries bordering the sea have signed up to it.

North Seas Countries' Offshore Grid Initiative

The North Seas Countries' Offshore Grid Initiative is an agreement between North Seas countries on developing offshore grids, notably with the objective ‘to facilitate a strategic, coordinated and cost-effective development of offshore and onshore grids’.


(1)  DECRETO 178/2006, de 10 de octubre, por el que se establecen normas de protección de la avifauna para las instalaciones eléctricas de alta tensión.

(2)  REAL DECRETO 1432/2008, de 29 de agosto, por el que se establecen medidas para la protección de la avifauna contra la colisión y la electrocución en líneas eléctricas de alta tensión.

(3)  For further details, please see: renewables-grid.eu/documents/eu-grid-declaration.html

(4)  For further details, please see: http://renewables-grid.eu/news.html

(5)  For further details, please see: www.birdlife.org/news/news/2008/03/Hungary_powerlines.html

(6)  For further details, please see: www.mme.hu/component/content/article/20-termeszetvedelemfajvedelem/1387-budapest-conference-13-04-2011.html

(7)  For further details, please see: www.theebi.org/abouttheebi.html

(8)  For further details, please see: ec.europa.eu/environment/life/

(9)  Project information: ec.europa.eu/environment/life/project/Projects/index.cfm?fuseaction=home.createPage&s_ref=LIFE04%20NAT/ES/000034&area=1&yr=2004&n_proj_id=2628&cfid=5499&cftoken=4d0dc811a13b045f-7045FECB-C948-3D16-E530CBE465C8D200&mode=print&menu=false

(10)  Project information: ec.europa.eu/environment/life/project/Projects/index.cfm?fuseaction=home.createPage&s_ref=LIFE06%20NAT/E/000214&area=1&yr=2006&n_proj_id=3158&cfid=5078&cftoken=60a9b7217d1cb752-60A07C25-BB06-B077-2930A6DC7B2ADB22&mode=print&menu=false

(11)  Project website: www.life-elia.eu/

(12)  Project information: ec.europa.eu/environment/life/project/Projects/index.cfm?fuseaction=search.dspPage&n_proj_id=2863

(13)  Project website: www.parcodeltapo.it/er/info/progetti.life/enel-parco/index.html

(14)  http://www.bestgrid.eu/

(15)  http://www.bestgrid.eu/uploads/media/D7.2_Guidelines_Protecting_Nature.pdf

(16)  For further details, please see: www.business-biodiversity.eu/

(17)  For further details, please see: www.business-biodiversity.eu/default.asp?Menue=132&News=70

(18)  For further details, please see: www.sopsr.sk/web

(19)  As of 2nd July 2012.

(20)  www.cbd.int

(21)  www.coe.int/t/dg4/cultureheritage/nature/bern/default_en.asp

(22)  www.coe.int/t/dg4/cultureheritage/nature/EcoNetworks/Default_en.asp

(23)  https://wcd.coe.int/wcd/ViewDoc.jsp?Ref=Rec(2004)110&Language=lanEnglish&Ver=original&Site=DG4-Nature&BackColorInternet=DBDCF2&BackColorIntranet=FDC864&BackColorLogged=FDC864

(24)  www.cms.int

(25)  E.g. available from www.cms.int/bodies/ScC/12th_scientific_council/pdf/English/Inf08_Resolutions_and_Recommendations_E.pdf

(26)  www.cms.int/species/raptors/index.htm

(27)  www.unep-aewa.org

(28)  Both documents are available respectively from www.cms.int/bodies/COP/cop10/docs_and_inf_docs/inf_38_electrocution_review.pdf and www.unep-aewa.org/meetings/en/stc_meetings/stc7docs/pdf/stc7_20_electrocution_guidelines.pdf

(29)  www.eurobats.org

(30)  www.ascobans.org

(31)  www.accobams.org

(32)  www.rasmsar.org

(33)  www.ospar.org

(34)  www.helcom.fi

(35)  www.unep.ch/regionalseas/regions/med/t_barcel.htm


ANNEX 2

Systematic prioritised list of impacts of bird/power line interactions (Birdlife, 2013)

Type of the Impact

Status of the Impact (1)

Severity / Significance (2)

Reversibility (3)

Scale of the Impact (4)

Cumulative Impact (5)

Negative – Ecological & Physiological

Mortality

Direct

High

Partly reversible

Multi-national

High

Electrocution

Proven

High

Partly reversible

Multi-national

High

Collision

Potential

Moderate

Partly reversible

Regional

High

Habitat loss and fragmentation

Potential

Moderate

Partly reversible

Regional

Medium

Disturbance/ Displacement

Potential

Moderate

Partly reversible

Local

Medium

Electromagnetic field

Potential

Unknown

Unknown

Multi-national

Unknown

Negative – Economic

 

 

 

 

 

Loss of income at electric utilities

Lost revenue

Proven

High

Partly reversible

Multi-national

High

Power restoration

Proven

High

Completely reversible

Multi-national

High

Equipment repair

Proven

High

Completely reversible

Multi-national

High

Nest removal and other animal damage-control measures

Proven

Moderate

Completely reversible

Multi-national

Medium

Administrative and managerial time

Proven

High

Partly reversible

Multi-national

High

Lost service to customers and negative public perception

Proven

High

Partly reversible

Multi-national

High

Reduced electrical system reliability

Proven

High

Partly reversible

Multi-national

High

Loss of income at land-users

Proven

High

Partly reversible

Multi-national

High

Hunting & game management

Proven

High

Partly reversible

National

High

Agricultural land-use, irrigation

Proven

Low

Irreversible

National

Low

Forestry

Proven

Moderate

Irreversible

National

Moderate

Positive –Ecological

Breeding substrate, nest site

Proven, direct

High

Multi-national

Perching, roosting and hunting post

Proven, direct

High

Multi-national

Habitat creation, management

Proven, direct

Moderate

National

(Based on McCann, 2005; APLIC, 2006 and van Rooyen, 2012 and supplemented with information from this review)


(1)  

Status of the impact: Potential – Proven

Direct impact: Impacts on the environment, which is a direct result of power lines. For example: mortality of birds through electrocution on or collision with power lines.

Indirect impact: Impact on the environment, which is not a direct result of power lines, often produced away from or as a result of a complex pathway. Sometimes referred to as second or third level impact, or secondary impact. For example: a development changes the water table and thus affects a nearby wetland causing an impact on the ecology of that wetland.

(2)  Severity/significance of the impact: Low – Moderate – High

(3)  Reversibility

Irreversible: The impact is irreversible and no mitigation measures exist.

Barely reversible: The impact is unlikely to be reversed even with intense mitigation measures.

Partly reversible: The impact is partly reversible but more intense mitigation measures are required.

Completely reversible: The impact is reversible with implementation of minor mitigation measures.

(4)  Scale of the impact: Site - Local - Regional - National - Multi-national

(5)  Cumulative impact: Negligible - Low - Medium - High

Impacts that result from incremental changes caused by other past, present or reasonably foreseeable actions together with the effect of power lines. For example: Several developments with insignificant impacts individually but which together have a cumulative effect, e.g. development of a power line section may have an insignificant impact on habitat use of birds, but when considered with several nearby power line sections there could be a significant cumulative impact on local ecology and landscape as power lines can form an effective line barrier between birds and their preferred habitats.

(Based on Walker and Johnston, 1999 and van Rooyen, 2012)


ANNEX 3

Summary of evidence on the population-level impact of power lines on globally threatened (IUCN, 2012) bird species

Species

Main impact

Location

Study period

Casualties

Conclusions

Key papers

Dalmatian Pelican

Pelecanus crispus

Additional mortality due to collision.

Porto-Lago, Greece (Wintering ground)

1985-1987

28 killed individuals (69 % 1st-year, 31 % immature)

Combined with the effects of illegal shooting an estimated 1.3-3.5 % decrease in breeding pairs in Greece and Bulgaria in a 3-year period.

Crivelli, 1988

Lesser White-fronted Goose

Anser erythropus

Additional mortality due to collision.

May increase mortality. A potential factor, but importance unknown. Has to be taken into account in EIAs.

AEWA, 2008

Red-brested Goose

Branta ruficollis

Additional mortality due to collision.

There are no quantitative data or predictive models to estimate the impact of collision mortality on Red-breasted Goose populations. A potential threat, but importance unknown.

BSPB, 2010

Egyptian Vulture

Neophron percnopterus

Additional mortality due to electrocution.

Port Sudan, Sudan

1982, 1983, 2005, 2010

48+2+5+17 killed individuals

All birds were found under the same 31-km segment of power line. 0,055 dead bird per pylon. The magnitude of the mortality is fully consistent with observed population declines in potential source populations in Israel, Syria, Turkey and Jordan, and highlights that electrocution-caused mortality may potentially have population-level effects over a broad geographic scale.

Angelov et al., 2012

Nikolaus, 1984, Nikolaus, 2006

Greater Spotted Eagle

Aquila clanga

Additional mortality due to electrocution.

Russia, Kazakhstan

1990-2010

6 individuals (in a 2 082 km survey)

A potential factor, but significance is presumably low.

Karyakin, 2012

Eastern Imperial Eagle

Aquila heliaca

Additional mortality due to electrocution.

Hungary

2001-2009

20 out of 90 individuals

22.22 % electrocution rate of total mortality. In spite of the almost 20-year effort for bird-friendly modification of electric pylons in Hungary, electrocution is still among the most important mortality factors of several raptor species, including the Imperial Eagle.

Horváth et al., 2011

Eastern Imperial Eagle

Aquila heliaca

Additional mortality due to electrocution.

Bulgaria

2010-2011

5 out of 15 individuals

Satellite tracking showed 33 % electrocution rate of total mortality.

BSPB, 2011

Spanish Imperial Eagle

Aquila adalberti

Additional mortality due to electrocution.

Doñana, Andalusia, Spain

1974-2009

63 electrocuted individuals

39.87 % electrocution rate of total mortality. Shift in the main causes of mortality between the two periods, before and after the approval of mandatory regulation against bird electrocution in the Andalucía region.

After mitigation there has been a strong decrease in electrocution in both Doñana (-96.90 %) and Andalucía (-61.95 %).

López-López, 2011

Spanish Imperial Eagle

Aquila adalberti

Additional mortality due to electrocution.

Doñana NP, Andalusia, Spain

1957-1989

6 adult 33 immature individuals

Responsible for 46.1 % of adult mortality and 39,8 % of immature mortality.

Ferrer, 2001

Spanish Imperial Eagle

Aquila adalberti

Additional mortality due to electrocution and collision.

Spain

1989-2004

115 + 6 individuals

Electrocution caused 47.7 % of the total mortality cases (probably overestimations), collision caused 2.48 %.

Subadults were electrocuted more frequently than expected and 1-2 cy birds were electrocuted more frequently than 3-4 cy birds.

Electrocution occurred most often in autumn and winter and on temporary settlement areas.

González et al., 2007

Saker Falcon

Falco cherrug

Additional mortality due to electrocution.

Hungary, Slovakia, Austria, Ukraine, Romania

2007-2010

5 out 71 satellite tagged Sakers

7.0 % proved mortality (n=71). Only proven cases have been considered for the calculation so the real numbers are certainly higher.

Prommer, Saker LIFE, 2011

Houbara Bustard

Chlamydotis undulata

Additional mortality due to collision.

Fuerteventura, Lanzarote, Canary Islands, Spain

2008

 

An estimated 25.5 % of the total population of the Houbara Bustard was killed in a year.

Garcia-del-Rey and Rodriguez-Lorenzo, 2011

Great Bustard

Otis tarda

Additional mortality due to collision.

south-west Spain

1991-1993

16 individuals

4+8+4 km line sections were studied

Janss, 2000


ANNEX 4

Examples of impacts of power lines on meta-populations of species listed in Annex I of Birds Directive

Species

Main impact

Location

Study period

Casualties

Conclusions

Key papers

White Stork

Ciconia ciconia

Additional mortality due to electrocution and collision.

Germany

In 226 cases out of 1 185 ring recoveries

The cause of recoveries was ‘overhead wires’.

Riegel & Winkel, 1971

White Stork

Ciconia ciconia

Additional mortality due to electrocution and collision.

Switzerland

1984-1999

195 out of 416 dead recoveries. Sample size: 2 912 ringed individuals.

Power line mortality is important for White Storks, with about one in four juveniles and one in 17 adults dying each year because of power line collision and electrocution.

Schaub & Pradel, 2004

White Stork

Ciconia ciconia

Additional mortality due to electrocution and collision.

Central Spain

1999-2000

51 individuals were found electrocuted and 101 individuals died by collision

Ca. 1 % of present storks died during post-breeding migration, while 5-7 % population did during winter.

Garrido & Fernández-Cruz, 2003

Bonelli's Eagle

Aquila fasciata

Additional mortality due to collision.

Catalonia, Spain

1990-1997

2 out of 12 breeding individuals

Collision itself accounts for 17 % of the annual mortality which is a serious problem on the population level. Annual adult mortality rate must not exceed 2-6 % for the population to remain at equilibrium.

Manosa & Real, 2001

Bonelli's Eagle

Aquila fasciata

Additional mortality due to electrocution.

Catalonia, Spain

1990-1997

6 out 12 breeding individuals

Electrocution itself accounts for 50 % of the annual mortality which is a serious problem on the population level. Annual adult mortality rate must not exceed 2-6 % for the population to remain at equilibrium .

Manosa & Real, 2001

Eurasian Eagle Owl

Bubo bubo

Additional mortality due to electrocution.

Switzerland

Electrocution and collision accounted for more than 50 % of all the unnatural causes. The population was at a critical level. It would have depended on immigration from nearby populations after mitigating the sources of all unnatural causes of death.

Schaub, 2010

Eurasian Eagle Owl

Bubo bubo

Additional mortality due to electrocution.

Italy

High electrocution-related territory abandonment resulting in a steeply declining, low-density population.

Sergio, 2004

Little Bustard

Tetrax tetrax

Additional mortality due to collision.

Portugal

1.5 % of the Portugese population dies by collision with overhead wires. High risk of potential avoidance of areas with transmission power lines (affecting reproductive success through limiting the size and density of leks).

Silva, 2010


ANNEX 5

Proposed list of priority species for prevention and mitigation of power line impact within the EU

Common name

Scientific name

Global IUCN Red List Category

Birds Directive

Casualties due to electrocution (1)

Casualties due to collision (2)

European Conservation Status (3)

Spatial scale by migration patterns

(Birdlife International, 2004)

Egyptian Vulture

Neophron percnopterus

EN

I

III

II

Unfavourable

Long-distance intercontinental migrant

Red-brested Goose (*1)

Branta ruficollis

EN

I

I

II

Unfavourable

Full migrant within Europe

Imperial Eagle

Aquila heliaca

VU

I

III

II

Unfavourable

Partial migrant within Europe

Spanish Imperial Eagle

Aquila adalberti

VU

I

III

II

Unfavourable

Resident

Saker Falcon

Falco cherrug

VU

I

II-III

II

Unfavourable

Partial migrant within Europe

Greater Spotted Eagle

Aquila clanga

VU

I

II

II

Unfavourable

Short-distance intercontinental migrant

Dalmatian Pelican

Pelecanus crispus

VU

I

I

II-III

Unfavourable

Partial migrant within Europe

Lesser White-fronted Goose (*1)

Anser erythropus

VU

I

I

II

Unfavourable

Full migrant within Europe

Red-footed Falcon

Falco vespertinus

NT

I

II-III

II

Unfavourable

Long-distance intercontinental migrant

Red Kite

Milvus milvus

NT

I

III

II

Unfavourable

Partial migrant within Europe

Great Bustard

Otis tarda

VU

I

0

III

Unfavourable

Partial migrant within Europe

Cinereous Vulture

Aegypius monachus

NT

I

III

II

Unfavourable

Resident

Black Stork

Ciconia nigra

 

I

III

III

Unfavourable

Long-distance intercontinental migrant

White Stork

Ciconia ciconia

 

I

III

III

Unfavourable

Long-distance intercontinental migrant

Houbara Bustard (*1)

Chlamydotis undulata

VU

 

0

III

Unfavourable

Resident

European Roller

Coracias garrulus

NT

I

I-II

I-II

Unfavourable

Long-distance intercontinental migrant

Booted Eagle

Aquila pennata

 

I

III

II

Unfavourable

Long-distance intercontinental migrant

Lesser Kestrel

Falco naumanni

 

I

II-III

II

Unfavourable

Long-distance intercontinental migrant

White-tailed Eagle

Haliaeetus albicilla

 

I

III

II

Unfavourable

Partial migrant within Europe

Northern Harrier

Circus cyaneus

 

I

III

II

Unfavourable

Partial migrant within Europe

Golden Eagle

Aquila chrysaetos

 

I

III

II

Unfavourable

Partial migrant within Europe

Little Bustard (*1)

Tetrax tetrax

NT

I

0

III

Unfavourable

Partial migrant within Europe

Eurasian Curlew

Numenius arquata

NT

 

I

II-III

Unfavourable

Short-distance intercontinental migrant

Black-tailed Godwit

Limosa limosa

NT

 

I

II-III

Unfavourable

Short-distance intercontinental migrant

Black-winged Kite (*1)

Elanus caeruleus

 

I

III

II

Unfavourable

Resident

Lammergeier

Gypaetus barbatus

 

I

III

II

Unfavourable

Resident

Bonelli's Eagle

Aquila fasciata

 

I

III

II

Unfavourable

Resident

Purple Heron

Ardea purpurea

 

I

II

II

Unfavourable

Long-distance intercontinental migrant

European Honey-buzzard (*1)

Pernis apivorus

 

I

III

II

Favourable

Long-distance intercontinental migrant

Black Kite

Milvus migrans

 

I

III

II

Favourable

Long-distance intercontinental migrant

Short-toed Snake-eagle

Circaetus gallicus

 

I

III

II

Favourable

Long-distance intercontinental migrant

Montagu's Harrier

Circus pygargus

 

I

III

II

Favourable

Long-distance intercontinental migrant

Osprey

Pandion haliaetus

 

I

III

II

Favourable

Long-distance intercontinental migrant

Merlin

Falco columbarius

 

I

II-III

II

Unfavourable

Partial migrant within Europe

Gyrfalcon

Falco rusticolus

 

I

II-III

II

Unfavourable

Partial migrant within Europe

Eurasian Spoonbill

Platalea leucorodia

 

I

II

II

Unfavourable

Short-distance intercontinental migrant

Common Crane

Grus grus

 

I

I

III

Unfavourable

Short-distance intercontinental migrant

Lanner Falcon

Falco biarmicus

 

I

II-III

II

Unfavourable

Resident

Ruff

Philomachus pugnax

 

I

I

II-III

Unfavourable

Long-distance intercontinental migrant

Eurasian Griffon

Gyps fulvus

 

I

III

II

Favourable

Partial migrant within Europe

Western Marsh-harrier

Circus aeruginosus

 

I

III

II

Favourable

Partial migrant within Europe

Northern Goshawk

Accipiter gentilis arrigonii

 

I

III

II

Favourable

Partial migrant within Europe

Eurasian Sparrowhawk

Accipiter nisus granti

 

I

III

II

Favourable

Partial migrant within Europe

Long-legged Buzzard

Buteo rufinus

 

I

III

II

Favourable

Partial migrant within Europe

Great White Pelican

Pelecanus onocrotalus

 

I

I

II-III

Unfavourable

Short-distance intercontinental migrant

Rock Ptarmigan (*1)

Lagopus mutus

 

I

I

III

Unfavourable

Resident

Eurasian Golden-plover

Pluvialis apricaria

 

I

I

II-III

Unfavourable

Full migrant within Europe

Steppe Eagle

Aquila nipalensis

 

 

III

II

Long-distance intercontinental migrant

Common Kestrel

Falco tinnunculus

 

 

II-III

II

Unfavourable

Partial migrant within Europe

Peregrine Falcon

Falco peregrinus

 

I

II-III

II

Favourable

Partial migrant within Europe

Eurasian Eagle-owl (*1)

Bubo bubo

 

I

II-III

II

Favourable

Resident

Ural Owl

Strix uralensis

 

I

II-III

II

Favourable

Resident

Tundra Swan

Cygnus columbianus

 

I

I

II

Unfavourable

Full migrant within Europe

Black Tern

Chlidonias niger

 

I

I

I-II

Unfavourable

Long-distance intercontinental migrant

European Turtle-dove

Streptopelia turtur

 

 

I-II

II

Unfavourable

Long-distance intercontinental migrant

Eurasian Hobby

Falso subbuteo

 

 

II-III

II

Favourable

Long-distance intercontinental migrant

Whimbrel

Numenius phaeopus

 

 

I

II-III

Unfavourable

Long-distance intercontinental migrant

Common Buzzard

Buteo buteo

 

 

III

II

Favourable

Partial migrant within Europe

Greater Flamingo

Phoenicopterus roseus

 

I

0

III

Unfavourable

Partial migrant within Europe

Corncrake

Crex crex

 

I

0

II

Unfavourable

Long-distance intercontinental migrant

Garganey

Anas querquedula

 

 

I

II

Unfavourable

Long-distance intercontinental migrant

Long-eared Owl

Asio otus

 

 

II-III

II

Favourable

Partial migrant within Europe

Northern Lapwing

Vanellus vanellus

 

 

I

II-III

Unfavourable

Partial migrant within Europe

Common Snipe

Gallinago gallinago

 

 

I

II-III

Unfavourable

Partial migrant within Europe

Common Redshank

Tringa totanus

 

 

I

II-III

Unfavourable

Partial migrant within Europe

Brent Goose

Branta bernicla

 

 

I

II

Unfavourable

Full migrant within Europe

Whooper Swan

Cygnus cygnus

 

I

I

II

Favourable

Full migrant within Europe

Greater White-fronted Goose

Anser albifrons flavirostris

 

I

I

II

Favourable

Full migrant within Europe

Barnacle Goose

Branta leucopsis

 

I

I

II

Favourable

Full migrant within Europe

Common Tern

Sterna hirundo

 

I

I

I-II

Favourable

Long-distance intercontinental migrant

Common Quail

Coturnix coturnix

 

 

I

II-III

Favourable

Long-distance intercontinental migrant

Northern Shoveler

Anas clypeata

 

 

I

II

Unfavourable

Partial migrant within Europe

Cattle Egret

Bubulcus ibis

 

 

II

II

Favourable

Partial migrant within Europe

Grey Heron

Ardea cinerea

 

 

II

II

Favourable

Partial migrant within Europe

Grey Phalarope

Phalaropus fulicarius

 

 

I

II-III

Not assessed (*1)

Short-distance intercontinental migrant

Eurasian Woodcock

Scolopax rusticola

 

 

0

II-III

Unfavourable

Partial migrant within Europe

Eurasian Oystercatcher

Haematopus ostralegus

 

 

I

II-III

Favourable

Partial migrant within Europe

Bean Goose

Anser fabilis

 

 

I

II

Favourable

Full migrant within Europe

Pink-footed Goose

Anser brachyrynchus

 

 

I

II

Favourable

Full migrant within Europe

Great Cormorant

Phalacrocorax carbo

 

 

I

II

Favourable

Partial migrant within Europe

Mute Swan

Cygnus olor

 

 

I

II

Favourable

Partial migrant within Europe

Greylag Goose

Anser anser

 

 

I

II

Favourable

Partial migrant within Europe

Eurasian Wigeon

Anas penelope

 

 

I

II

Favourable

Partial migrant within Europe

Mallard

Anas platyrhynchos

 

 

I

II

Favourable

Partial migrant within Europe

Great Black-backed Gull

Larus marinus

 

 

I

II

Favourable

Partial migrant within Europe

Herring Gull

Larus argentatus

 

 

I

II

Favourable

Partial migrant within Europe

Common Black-headed Gull

Larus ridibundus

 

 

I

II

Favourable

Partial migrant within Europe

Water Rail

Rallus aquaticus

 

 

0

II

Favourable

Partial migrant within Europe

Common Moorhen

Gallinula chloropus

 

 

0

II

Favourable

Partial migrant within Europe

Common Coot

Fulica atra

 

 

0

II

Favourable

Partial migrant within Europe

IUCN= Global Red List categories (IUCN, 2012).

EN= Endangered

VUL= Vulnerable

NT= Near threatened

Severity of impacts on bird populations (Haas et al., 2003; Prinsen et al., 2011):

0= no causalities reported or likely

I= casualties reported, but no apparent threat to the bird population

II= regionally or locally high casualties, but with no significant impact on the overall species population

III= casualties are a major mortality factor; threatening a species with extinction, regionally or at a larger scale


(1)  AEWA-CMS, 2011a

(2)  AEWA-CMS, 2011a

(3)  Birdlife International, 2004

(*1)  species not listed in Prinsen et al., (2011a).


ANNEX 6

Comparison of procedures under Appropriate Assessment (AA), EIA and SEA

 

AA

EIA

SEA

Which types of developments are targeted?

Any plan or project which - either individually or in combination with other plans/projects - is likely to have an adverse effect on a Natura 2000 site (excluding plans or projects directly connected to the conservation management of the site).

All projects listed in Annex I.

For projects listed in Annex II the need for an EIA shall be determined on a case by case basis or through thresholds or criteria set by Member States (taking into account criteria in Annex III).

Any plans and programmes or amendments thereof which are

(a)

prepared for agriculture, forestry, fisheries, energy, industry, transport, waste management, water management, telecommunications, tourism, town and country planning or land use and which set the framework for future development consent of projects listed in Annexes I and II to EIA Directive, or

(b)

which, in view of the likely effect on sites, have been determined to require an assessment pursuant to Article 6 or 7 of Directive 92/43/EEC.

What impacts need to be assessed relevant to nature?

The assessment should be made in view of the site's conservation objectives (which relate to the species/ habitat types for which the site was designated).

The impacts should be assessed to determine whether or not they will adversely affect the integrity of the site concerned.

Direct and indirect, secondary, cumulative, short, medium and long-term, permanent and temporary, positive and negative significant effects on, amongst others, fauna and flora.

Likely significant effects on the environment, including on issues such as biodiversity, population, human health, fauna, flora, soil, water, air, climatic factors, material assets, cultural heritage including architectural and archaeological heritage, landscape and the interrelationship between the above factors.

Who is responsible for the Assessment?

It is the responsibility of the competent authority to ensure that the AA is carried out. In that context the developer may be required to carry out all necessary studies and to provide all necessary information to the competent authority in order to enable the latter to take a fully informed decision. In so doing the competent authority may also collect relevant information from other sources as appropriate.

The developer supplies the necessary information to be taken into consideration by the competent authority issuing the development consent

The competent planning authority

Are the public/ other authorities consulted?

Not obligatory but encouraged (‘if appropriate’).

Compulsory – consultation to be done before adoption of the development proposal.

Member States shall take the measures necessary to ensure that the authorities likely to be concerned by the project are given an opportunity to express their opinion on the request for development consent. The same principles apply for consulting the public. In case of likely significant effects on the environment in another Member State, the relevant authorities and the public of the latter have to be consulted.

Compulsory – consultation to be done before adoption of the plan or programme.

The authorities and the public shall be given an early and effective opportunity within appropriate time frames to express their opinion on the draft plan or programme and the accompanying environmental report before the adoption of the plan or programme or its submission to the legislative procedure. Member States must designate the authorities to be consulted which, by reason of their specific environmental responsibilities, are likely to be concerned. In case of likely significant effects on the environment in another Member State, the relevant authorities and the public of the latter have to be consulted.

How binding are the outcomes of the Assessment?

Binding.

The competent authorities can agree to the plan or project only after having ascertained that it will not adversely affect the integrity of the site.

The results of consultations and the information gathered as part of the EIA shall be duly taken into account in the development consent procedure.

The environmental report, as well as the opinions expressed shall be taken into account during the preparation of the plan or programme and before its adoption or submission to the legislative procedure.