Case C-402/17 P: Order of the Court (Tenth Chamber) of 17 May 2018 — JYSK sp. z o.o. v European Commission (Appeal — Article 181 of the Rules of Procedure of the Court of Justice — Refusal to grant a financial contribution from the European Regional Development Fund (ERDF) to the major project ‘European Shared Services Centre’ — Action for annulment — Undertaking responsible for project implementation — Conditions of admissibility — Lack of direct concern)
Order of the Court (Tenth Chamber) of 17 May 2018 — JYSK sp. z o.o. v European Commission
(Case C-402/17 P) ( 1 )
‛(Appeal — Article 181 of the Rules of Procedure of the Court of Justice — Refusal to grant a financial contribution from the European Regional Development Fund (ERDF) to the major project ‘European Shared Services Centre’ — Action for annulment — Undertaking responsible for project implementation — Conditions of admissibility — Lack of direct concern)’
2018/C 276/13Language of the case: EnglishParties
Appellant: JYSK sp. z o.o. (represented by: H. Sønderby Christensen, advokat)
Other party to the proceedings: European Commission (represented by: R. Lyal and B.-R. Killmann, acting as Agents)
Operative part of the order
|
1. |
The appeal is dismissed as manifestly inadmissible. |
|
2. |
JYSK sp. z o.o. shall pay the costs. |
( 1 ) OJ C 309, 18.9.2017.