REPORT
on the annual accounts of the European Institute of Innovation and Technology for the financial year 2011, together with the Institute’s replies
2012/C 388/19
INTRODUCTION
1. |
The European Institute of Innovation and Technology (hereinafter "the Institute"), which is located in Budapest, was created by Regulation (EC) No 294/2008 of the European Parliament and of the Council (1). The Institute's objective is to contribute to sustainable European economic growth and competitiveness by reinforcing the innovation capacity of the Member States and the European Union. The Institute awards grants to "Knowledge and Innovation Communities", which link the higher education, research and business sectors with one another thereby boosting innovation and entrepreneurship (2). |
2. |
The Commission granted financial autonomy to the Institute on 8 June 2011. Therefore the audited period for the 2011 financial year runs from 8 June to 31 December 2011. |
INFORMATION IN SUPPORT OF THE STATEMENT OF ASSURANCE
3. |
The audit approach taken by the Court comprises analytical audit procedures, direct testing of transactions and an assessment of key controls of the Institute’s supervisory and control systems. This is supplemented by evidence provided by the work of other auditors (where relevant) and an analysis of management representations. |
STATEMENT OF ASSURANCE
4. |
Pursuant to the provisions of Article 287 of the Treaty on the Functioning of the European Union, the Court has audited the annual accounts (3) of the Institute, which comprise the "financial statements" (4) and the "reports on the implementation of the budget" (5) for the financial year ended 31 December 2011, and the legality and regularity of the transactions underlying those accounts. |
The Management’s responsibility
5. |
As authorising officer, the Director implements the revenue and expenditure of the budget in accordance with the financial rules of the Institute, under his own responsibility and within the limits of the authorised appropriations (6). The Director is responsible for putting in place (7) the organisational structure and the internal management and control systems and procedures relevant for drawing up final accounts (8) that are free from material misstatement, whether due to fraud or error, and for ensuring that the transactions underlying those accounts are legal and regular. |
The Auditor’s responsibility
6. |
The Court’s responsibility is to provide, on the basis of its audit, the European Parliament and the Council (9) with a statement of assurance as to the reliability of the annual accounts of the Institute and the legality and regularity of the transactions underlying them. |
7. |
The Court conducted its audit in accordance with the IFAC International Standards on Auditing and Codes of Ethics and the INTOSAI International Standards of Supreme Audit Institutions. These standards require that the Court plans and performs the audit to obtain reasonable assurance as to whether the annual accounts of the Institute are free of material misstatement and the transactions underlying them are legal and regular. |
8. |
An audit involves performing procedures to obtain audit evidence about the amounts and disclosures in the accounts and the legality and regularity of the transactions underlying them. The procedures are selected based on the auditor’s judgment, including an assessment of the risks of material misstatement of the accounts and of material non-compliance of the underlying transactions with the requirement of the legal framework of the European Union, whether due to fraud or error. In assessing those risks, the auditor considers internal controls relevant to the preparation and fair presentation of the accounts and supervisory and control systems implemented to ensure legality and regularity of underlying transactions, in order to design audit procedures that are appropriate in the circumstances. An audit also includes evaluating the appropriateness of accounting policies used and reasonableness of accounting estimates made, as well as evaluating the overall presentation of the accounts. |
9. |
The Court considers that the audit evidence obtained is sufficient and appropriate to provide a basis for the opinions set out below. |
Opinion on the reliability of the accounts
10. |
In the Court’s opinion, the Institute’s Annual Accounts (10) present fairly, in all material respects, its financial position as of 31 December 2011 and the results of its operations and its cash flows for the year then ended, in accordance with the provisions of its Financial Regulation and the accounting rules adopted by the Commission’s accounting officer (11). |
Opinion on the legality and the regularity of the transactions underlying the accounts
11. |
In the Court’s opinion, the transactions underlying the annual accounts of the Institute for the financial year ended 31 December 2011 are legal and regular in all material respects. |
12. |
The comments which follow do not call the Court’s opinions into question. |
COMMENTS ON BUDGETARY AND FINANCIAL MANAGEMENT
13. |
The rate of execution of the Institute’s budget for the audited period of financial autonomy (see paragraph 2) was low. Comparing payments with appropriations committed, the rate was 56 % for Title I (staff expenditure), 30 % for Title II (administrative expenditure) and 11 % for Title III (operational expenditure). |
14. |
Grant agreements resulting in payments in 2011 were systematically signed by the European Commission (Directorate General for Education and Culture) and the Institute after most of the activities had already been implemented. Between September and December 2011, the Institute made final payments (12), amounting to 4,2 million euro, related to three grant agreements that were signed well after the start of activities (13). This is an issue in terms of good financial management. |
This Report was adopted by Chamber IV, headed by Dr Louis GALEA, Member of the Court of Auditors, in Luxembourg at its meeting of 11 September 2012.
For the Court of Auditors
Vítor Manuel da SILVA CALDEIRA
President
(2) The Annex summarises the Institute's competences and activities. It is presented for information purposes.
(3) These accounts are accompanied by a report on the budgetary and financial management during the year which gives further information on budget implementation and management.
(4) The financial statements include the balance sheet and the economic outturn account, the cash-flow table, the statement of changes in net assets and a summary of the significant accounting policies and other explanatory notes.
(5) The budget implementation reports comprise the budget outturn account and its annex.
(6) Article 33 of Commission Regulation (EC, Euratom) No 2343/2002 (OJ L 357, 31.12.2002, p. 72).
(7) Article 38 of Regulation (EC, Euratom) No 2343/2002.
(8) The rules concerning the presentation of the accounts and accounting by the Agencies are laid down in Chapters 1 and 2 of Title VII of Regulation (EC, Euratom) No 2343/2002, as last amended by Regulation (EC, Euratom) No 652/2008 (OJ L 181, 10.7.2008, p. 23), and are integrated as such in the Financial Regulation of the Institute.
(9) Article 185(2) of Council Regulation (EC, Euratom) No 1605/2002 (OJ L 248, 16.9.2002, p. 1).
(10) The Final Annual Accounts were drawn up on 28 June 2012 and received by the Court on 10 July 2012. The Final Annual Accounts, consolidated with those of the Commission, are published in the Official Journal of the European Union by 15 November of the following year. These can be found on the following website: http://eit.europa.eu.
(11) The accounting rules adopted by the Commission’s accounting officer are derived from International Public Sector Accounting Standards (IPSAS) issued by the International Federation of Accountants or, in their absence, International Accounting Standards (IAS)/International Financial Reporting Standards (IFRS) issued by the International Accounting Standards Board.
(12) Advance payments had been made by the European Commission.
(13) In one case, the contract was signed 14 days before the end of the 13 month implementation period.
ANNEX
European Institute of Innovation and Technology (Budapest)
Competences and activities
Areas of Union competence deriving from the Treaty (Article 173 of the Treaty on the Functioning of the European Union) |
The Union and the Member States shall ensure that the conditions necessary for the competitiveness of the Union’s industry exist. For that purpose, in accordance with a system of open and competitive markets, their action shall be aimed at:
|
||||||||||||||||||||||||
Competences of the Institute (Council Regulation (EC) No 294/2008) |
Objectives The Institute’s objective is to contribute to sustainable European economic growth and competitiveness by reinforcing the innovation capacity of the Member States and the Community. It shall do this by promoting and integrating higher education, research and innovation of the highest standards. Tasks In order to achieve its objective, the Institute shall:
|
||||||||||||||||||||||||
Governance |
Governing Board Composition: The Institute’s Governing Board (GB) consists of 18 appointed members providing a balance between experience and excellence in business, higher education and research, and four representative members proposed by the Knowledge and Innovation Communities (KICs). As foreseen in the Regulation, the four representative members identified by KICs joined the Board in 2011. The European Commission is observer. Tasks: The Governing Board is responsible for steering the activities of the Institute, for the selection, designation and evaluation of the KICs, and for all other strategic decisions. Executive Committee Composition: The Executive Committee consists of five GB members, including the Chairperson and Vice-Chairperson. It is chaired by the Chairperson of the Governing Board. Tasks: The Executive Committee oversees the running of the Institute and takes such decisions as are necessary between meetings of the Governing Board. Director Appointed by and responsible to the Governing Board for the administrative and financial management of the Institute; the Institute’s legal representative. Mr Jose Manuel Leceta was appointed on 19 May 2011. External audit Court of Auditors. Discharge Authority Parliament, acting on a recommendation from the Council. |
||||||||||||||||||||||||
Resources made available to the Institute in 2011 |
Final Budget 65,85 million euro (The Institute was granted financial autonomy on 8 June 2011, the budget having been implemented by the European Commission until that date.) Staff as at 31 December 2011 Authorised: 52 (35) Occupied: 40 (24) Other posts: 0 (0) Total: 40 (24), assigned to the following duties:
|
||||||||||||||||||||||||
Products and services in 2011 |
|
||||||||||||||||||||||||
Source: Information supplied by the Institute. |
THE INSTITUTE’S REPLIES
14. |
There is a seasonal distribution of expenditures particularly as regards grants. Grant agreements were concluded at the beginning of the year, and consequently the pre-financing payments were executed prior to the Institute’s financial autonomy. As grants represent about 90 % of the Institute’s budget, their impact on budget execution is significant. Execution rates are considerably higher for the entire calendar year than for the audited period of financial autonomy. However, in order to improve budget execution, the Institute has introduced a monthly reporting on budget implementation and a review process for assessing in detail the implementation of the budget and the EIT work programme, thereby formulating corrective and reorientation actions in due course if needed, through the year. |
Other comments
EIT acknowledges the Court’ comment and is committed to decrease the gap between the starting date of the grant agreements and the date of signature. The gap was reduced from 2010 to 2012 (i.e. the grant agreement 2012 was signed in March and April with the KICs). Meanwhile, the EIT, in cooperation with the KICs, has established a roadmap, including the issuance of templates for business plan and reports, which will lead to the signature of the grant agreements 2013 in early 2013 (i.e. January).