COMMISSION STAFF WORKING DOCUMENT Implementation Plan Accompanying the document Proposal for a REGLATION OF THE EUROPEAN PARLIAMENT AND OF THE COUNCIL establishing a framework on the market access to port services and the financial transparency of ports
COMMISSION STAFF WORKING DOCUMENT Implementation Plan Accompanying the document Proposal for a REGLATION OF THE EUROPEAN PARLIAMENT AND OF THE COUNCIL establishing a framework on the market access to port services and the financial transparency of ports
COMMISSION STAFF WORKING DOCUMENT Implementation Plan Accompanying the document Proposal for a REGLATION OF THE EUROPEAN PARLIAMENT AND OF THE COUNCIL establishing a framework on the market access to port services and the financial transparency of ports
/* SWD/2013/0183 final */
COMMISSION STAFF WORKING DOCUMENT Implementation Plan Accompanying the document Proposal for a REGLATION OF THE EUROPEAN PARLIAMENT AND OF THE COUNCIL establishing a framework on the market access to port services and the financial transparency of ports /* SWD/2013/0183 final */
Implementation plan[1] 1. Contact point: Rémi Mayet (remi.mayet@ec.europa.eu – tel.
64677), Unit B.3 (Ports and Inland Navigation), DG MOVE 2. Deliverables
and implementation challenges The proposal relates to a Regulation directly and uniformly
applicable. The implementation challenges are therefore limited and listed
below. The main challenges relate in particular to: 1. Developing common
practices in the different national independent supervisory bodies; 2. Organising the required
transparency in the case of public financial funds attributed to a managing
body of the port or a port service provider; 3. Determining the criteria
for modulating port infrastructure charges; 4. Laying down the rules on sanctions
applicable to infringements of the provision of this Regulation. 3. Support Actions Commission Actions: The
Commission's proposal for a Regulation foresees the adoption of implementing
acts in support of the above mentioned challenges 1 and 3. The implementing
acts will help the Member States in developing both the methodology for the
charging principles in case of environmental charging as well as for the common
principles to be applied by the independent supervisory bodies. The Commission is at the disposal for the Member States to address
implementation challenges either bilaterally or in the context of the
Committee. The latter will be established under Article 15 of the proposed
Regulation. This Committee will serve as a platform and a network to exchange
good practices and experience. On top of that, the Commission will provide
where appropriate technical assistance in different forms like explanatory
guidance, expert meetings, working groups, Commission recommendations. The Commission
proposes to issue a report on the functioning and effect of the Regulation
three years after the entry into force. This will be an appropriate opportunity
to see if further action from the side of the Commission, including possible
further legislative proposals, would be required. Member State Actions: The Member States have one year to take the necessary actions to
apply this proposed Regulation. More specifically and related to the challenges identified above: 1. The Member States will
have the opportunity in the Committee to work together with the Commission in
order to come to the final adoption of an implementing act in order to support
the Member States with common principles to be applied by the independent
supervisory bodies. 2. On the issue of ensuring
transparency in the case of us of public funding, the Member States are
considered to have the appropriate experience in other domains to organise
this. If requested, the Commission can assist both the managing body of the
port and the Member State with pointing to specific practices in other ports
and Member States. 3. On the modulation of
infrastructure charges, the Commission will assist the managing bodies of the
port and the Member States with an implementing act related to the
environmental modulation. For other matters, managing bodies and Member States
can contact the Commission for further guidance and advice either bilaterally
or in the context of the Committee procedure. 4. When laying down the rules
on sanctions, Member States are advised to be proportionate. Member States can
contact the Commission for further guidance and advice either bilaterally or in
the context of the Committee procedure. Implementation challenge || Support action || Timing 1. Adopt common principles based on good practices to be applied by the independent supervisory bodies when implementing this regulation || Implementing act || 2016 2. Ensuring transparent use of public funding || Multilateral contact via Committee Art. 15 Ad hoc advice and guidance by the Commission if requested by Member States. || 2015 If requested 3. Adopting a methodology defining common classifications and common charging principles facilitating a uniform application of environmental charging || Implementing act || 2013 4. Laying down rules for sanctions || Multilateral contact via Committee Art. 15 || 2015 General and specific issues regarding implementation || Bilateral contact Multilateral contact via Committee Art. 15 || 2013 2015 [1] This Implementation Plan is provided for information
purposes only. It does not legally bind the Commission on whether the
identified actions will be pursued or on the form in which they will be
pursued.