This document is an excerpt from the EUR-Lex website
Document 62022CJ0457
Judgment of the Court (Ninth Chamber) of 14 March 2024.
European Commission v Republic of Slovenia.
Failure of a Member State to fulfil obligations – Article 258 TFEU – Directive (EU) 2018/1972 – European Electronic Communications Code – Failure to transpose and to notify transposition measures – Article 260(3) TFEU – Application for the imposition of a lump sum and a periodic penalty payment – Criteria for determining the amount of the penalty – Discontinuance in part.
Case C-457/22.
Judgment of the Court (Ninth Chamber) of 14 March 2024.
European Commission v Republic of Slovenia.
Failure of a Member State to fulfil obligations – Article 258 TFEU – Directive (EU) 2018/1972 – European Electronic Communications Code – Failure to transpose and to notify transposition measures – Article 260(3) TFEU – Application for the imposition of a lump sum and a periodic penalty payment – Criteria for determining the amount of the penalty – Discontinuance in part.
Case C-457/22.
ECLI identifier: ECLI:EU:C:2024:237
Case C‑457/22
European Commission
v
Republic of Slovenia
Judgment of the Court (Ninth Chamber) of 14 March 2024
(Failure of a Member State to fulfil obligations – Article 258 TFEU – Directive (EU) 2018/1972 – European Electronic Communications Code – Failure to transpose and to notify transposition measures – Article 260(3) TFEU – Application for the imposition of a lump sum and a periodic penalty payment – Criteria for determining the amount of the penalty – Discontinuance in part)
Actions for failure to fulfil obligations – Examination of the merits by the Court – Situation to be taken into consideration – Situation on expiry of the period laid down in the reasoned opinion
(Art. 258 TFEU)
(see paragraphs 24, 26)
Acts of the institutions – Directives – Implementation by Member States – Directive requiring a reference to be made to it in the national transposition measures in view of its transposition – Effect – Obligation for Member States to adopt a positive measure transposing the directive
(Arts 258 and 288, third para., TFEU; European Parliament and Council Directive 2018/1972, Art. 124(1))
(see paragraphs 25, 27, 32, operative part 1)
Member States – Obligations – Failure to fulfil obligations – National system pleaded as justification – Not permissible
(Art. 258 TFEU)
(see paragraph 30)
Actions for failure to fulfil obligations – Judgment of the Court establishing the failure of a Member State to fulfil its obligations – Failure to fulfil the obligation to notify measures transposing a directive – Financial penalties – Imposition of a lump sum payment – Purpose
(Art. 260(3) TFEU; European Parliament and Council Directive 2018/1972)
(see paragraph 64)
Actions for failure to fulfil obligations – Judgment of the Court establishing the failure of a Member State to fulfil its obligations – Failure to fulfil the obligation to notify measures transposing a directive – Financial penalties – Discretion of the Court – Criteria
(Art. 260(3) TFEU; European Parliament and Council Directive 2018/1972)
(see paragraphs 65-67)
Actions for failure to fulfil obligations – Judgment of the Court establishing the failure of a Member State to fulfil its obligations – Breach of the obligation to comply with the judgment – Financial penalties – Periodic penalty payment – Calculation of the amount – Criteria – Payment capacity – Gross domestic product of the Member State – Consideration of the institutional weight of the Member State concerned in the European Union – Not included
(Art. 260(3) TFEU; European Parliament and Council Directive 2018/1972, Art. 124(1))
(see paragraphs 68, 71-86, operative part 2)