This document is an excerpt from the EUR-Lex website
Document 32017R2196
Network code on electricity emergency and restoration
Regulation (EU) 2017/2196 establishing a network code on electricity emergency and restoration
The regulation establishes an electricity network code setting out requirements on:
The regulation particularly concerns:
The regulation covers procedures for:
System defence and restoration plans
Each TSO must design a system defence plan and a restoration plan, in consultation with relevant DSOs, SGUs, national regulatory authorities, and others. The plans include, for example:
Specific rules apply in the implementation of the system defence and restoration plans.
Each TSO needs to have in place the apropriate communication tools and to periodically assess and test the proper functioning of all equipment and capabilities involved in the system defence plan and the restoration plan.
Market activities
Subject to some conditions, a TSO may temporarily suspend market activities where:
Monitoring
Implementation of the regulation is monitored by ENTSO for Electricity.
Companion legislation
This regulation supplements and is an integral part of Regulation (EC) No 714/2009 on cross-border exchanges in electricity. References to Regulation (EC) No 714/2009 in other legal acts should be understood as also referring to this regulation.
The regulation is also a companion to Regulation (EU) 2017/1485: guideline on electricity transmission system operation.
It has applied since 18 December 2017.
See also:
Commission Regulation (EU) 2017/2196 of 24 November 2017 establishing a network code on electricity emergency and restoration (OJ L 312, 28.11.2017, pp. 54-85)
Successive amendments to Regulation (EU) 2017/2196 have been incorporated into the original document. This consolidated version is of documentary value only.
Commission Regulation (EU) 2017/1485 of 2 August 2017 establishing a guideline on electricity transmission system operation (OJ L 220, 25.8.2017, pp. 1-120)
Commission Regulation (EU) 2016/631 of 14 April 2016 establishing a network code on requirements for grid connection of generators (OJ L 112, 27.4.2016, pp. 1-68)
Commission Regulation (EU) 2016/1388 of 17 August 2016 establishing a Network Code on Demand Connection (OJ L 223, 18.8.2016, pp. 10-54)
Commission Regulation (EU) 2016/1447 of 26 August 2016 establishing a network code on requirements for grid connection of high voltage direct current systems and direct current-connected power park modules (OJ L 241, 8.9.2016, pp. 1-65)
Commission Regulation (EU) 2016/1719 of 26 September 2016 establishing a guideline on forward capacity allocation (OJ L 259, 27.9.2016, pp. 42-68)
Commission Regulation (EU) 2015/1222 of 24 July 2015 establishing a guideline on capacity allocation and congestion management (OJ L 197, 25.7.2015, pp. 24-72)
Commission Regulation (EU) No 543/2013 of 14 June 2013 on submission and publication of data in electricity markets and amending Annex I to Regulation (EC) No 714/2009 of the European Parliament and of the Council (OJ L 163, 15.6.2013, pp. 1-12)
Directive 2009/72/EC of the European Parliament and of the Council of 13 July 2009 concerning common rules for the internal market in electricity and repealing Directive 2003/54/EC (OJ L 211, 14.8.2009, pp. 55-93)
Regulation (EC) No 714/2009 of the European Parliament and of the Council of 13 July 2009 on conditions for access to the network for cross-border exchanges in electricity and repealing Regulation (EC) No 1228/2003 (OJ L 211, 14.8.2009, pp. 15–35)
last update 24.05.2019