Judgment of the Court (Seventh Chamber) of 12 July 2007.
Commission of the European Communities v Kingdom of Belgium.
Failure of a Member State to fulfil obligations - Directive 2004/12/EC - Packaging and packaging waste - Failure to transpose within the prescribed period.
Case C-90/07.

European Court Reports 2007 I-00098*

ECLI identifier: ECLI:EU:C:2007:429





Judgment of the Court (Seventh Chamber) of 12 July 2007 – Commission v Belgium

(Case C‑90/07)

Failure of a Member State to fulfil obligations – Directive 2004/12/EC – Packaging and packaging waste – Failure to transpose within the prescribed period

1.                     Actions for failure to fulfil obligations – Examination of merits by the Court – Situation to be taken into consideration – Situation on expiry of the period laid down in the reasoned opinion (Art. 226 EC) (see para. 11)

2.                     Member States – Obligations – Implementation of directives – Failure to fulfil obligations – National system pleaded as justification – Not permissible (Art. 226 EC) (see para. 13)

Re:

Failure of a Member State to fulfil obligations – Failure to adopt, within the prescribed period, the measures necessary to comply with Directive 2004/12/EC of the European Parliament and of the Council of 11 February 2004 amending Directive 94/62/EC on packaging and packaging waste (OJ 2004 L 47, p. 26).

Operative part

The Court:

 

Declares that, by failing to adopt the laws, regulations and administrative provisions necessary to comply with Directive 2004/12/EC of the European Parliament and of the Council of 11 February 2004 amending Directive 94/62/EC on packaging and packaging waste, the Kingdom of Belgium has failed to fulfil its obligations under that directive.

 

Orders the Kingdom of Belgium to pay the costs.