Case C-267/18: Request for a preliminary ruling from the Curtea de Apel București (Romania) lodged on 17 April 2018 — Delta Antrepriză de Construcții și Montaj 93 SA v Compania Națională de Administrare a Infrastructurii Rutiere SA
Case C-267/18: Request for a preliminary ruling from the Curtea de Apel București (Romania) lodged on 17 April 2018 — Delta Antrepriză de Construcții și Montaj 93 SA v Compania Națională de Administrare a Infrastructurii Rutiere SA
Case C-267/18: Request for a preliminary ruling from the Curtea de Apel București (Romania) lodged on 17 April 2018 — Delta Antrepriză de Construcții și Montaj 93 SA v Compania Națională de Administrare a Infrastructurii Rutiere SA
OJ C 249, 16.7.2018, p. 10–11
(BG, ES, CS, DA, DE, ET, EL, EN, FR, HR, IT, LV, LT, HU, MT, NL, PL, PT, RO, SK, SL, FI, SV)
Case C-267/18: Request for a preliminary ruling from the Curtea de Apel București (Romania) lodged on 17 April 2018 — Delta Antrepriză de Construcții și Montaj 93 SA v Compania Națională de Administrare a Infrastructurii Rutiere SA
Request for a preliminary ruling from the Curtea de Apel București (Romania) lodged on 17 April 2018 — Delta Antrepriză de Construcții și Montaj 93 SA v Compania Națională de Administrare a Infrastructurii Rutiere SA
(Case C-267/18)
2018/C 249/15Language of the case: RomanianReferring court
Curtea de Apel București
Parties to the main proceedings
Applicant: Delta Antrepriză de Construcții și Montaj 93 SA
Defendant: Compania Națională de Administrare a Infrastructurii Rutiere SA
Question referred
Can Article 57(4)(g) of Directive 2014/24/EU of the European Parliament and of the Council of 26 February 2014 on public procurement and repealing Directive 2004/18/EC ( 1 ) be interpreted as meaning that the termination of a public works contract on the ground that part of the works was subcontracted without the contracting authority’s authorisation constitutes a significant or persistent deficiency in the performance of a substantive requirement under a prior public contract leading to an economic operator being excluded from participation in a public procurement procedure?
( 1 ) OJ 2014 L 94, p. 65.