This document is an excerpt from the EUR-Lex website
Regulation (EU) 2017/1485 — guideline on electricity transmission system operation
As part of the EU’s Third Legislative Package in the field of energy, Regulation (EC) No 714/2009 sets out the rules governing access to the network for cross-border exchanges in electricity with a view to ensuring the proper functioning of the EU’s internal market in electricity. It creates the European Network of Transmission System Operators for electricity (ENTSOE) which, together with the Agency for the Cooperation of Energy Regulators, develops the European network codes and guidelines — i.e. the rules for the operation of the electricity and gas sectors, which are then adopted by the European Commission. These rules seek to ensure that Europe’s energy transmission systems meet the goals of security of supply, increased competitiveness and affordable energy.
In introducing a guideline on electricity transmission system operation, Commission Regulation (EU) 2017/1485 is a highly technical regulation and has five sections. This summary focuses on some of the content of the first section which lays down general aspects. It then provides an outline of the content of the technical sections.
GENERAL ASPECTS
Subject matter
The regulation lays down detailed guidelines on:
Scope
The regulation applies to all transmission systems, distribution systems and interconnections in the EU and regional security coordinators except those located in islands of EU countries of which the systems are not operated synchronously (i.e. interconnected) with Continental Europe (‘CE’), Great Britain (‘GB’), Nordic, Ireland and Northern Ireland (‘IE/NI’) or Baltic synchronous area.
Definitions
The regulation contains 159 — mostly technical — definitions.
TECHNICAL SECTIONS
The areas covered by the technical sections of the regulation concern:
Operational security:
Operational planning:
Load-frequency control and reserves:
The final section of the regulation is mainly concerned with application dates.
The general rules introduced by the regulation apply from 14 September 2017. However, Articles 41 to 53 (on data exchange between TSOs, between TSOs and DSOs with the TSO’s control area, between TSOs, DSOs and distribution-connected power generating modules, and between TSOs and transmission-connected demand facilities) apply from 14 March 2019 and Article 54(4) (compliance tests and simulations carried out by SGUs) from 18 August 2019.
For more information, see:
Commission Regulation (EU) 2017/1485 of 2 August 2017 establishing a guideline on electricity transmission system operation (OJ L 220, 25.8.2017, pp. 1-120)
Regulation (EC) No 714/2009 of the European Parliament and of the Council of 13 July 2009 on conditions for access to the network for cross-border exchanges in electricity and repealing Regulation (EC) No 1228/2003 (OJ L 211, 14.8.2009, pp. 15-35)
Successive amendments to Regulation (EC) No 714/2009 have been incorporated into the original document. This consolidated version is of documentary value only.