WHAT IS THE AIM OF THE REGULATION?

  • The regulation aims to tackle the energy crisis and reduce the European Union’s (EU) dependence on Russian fossil fuels by accelerating the permit-granting process and the deployment of renewable energy projects.
  • The regulation targets technologies that are quick to implement in the short term, have considerable potential for reducing gas consumption and, because of their low operational cost, could help bring down energy bills.
  • It is an emergency measure based on Article 122 of the Treaty on the Functioning of the European Union.
  • Given the significant risks associated with the volatility of gas and electricity prices and security of supply, amending Regulation (EU) 2024/223 extends the application of some provisions of Regulation (EU) 2022/2257, initially due to expire on , to .

KEY POINTS

REPowerEU plan

Overriding public interest

  • Under the regulation, the planning, construction and operation of plants and installations for the production of renewable energy is presumed to be in the overriding public interest.
  • This allows such projects to benefit from a simplified assessment for a number of environmental rules included in specific EU directives.

Main elements

  • Solar energy equipment on artificial structures
    • The permit-granting process must not exceed 3 months.
    • Solar panels are exempted from environmental impact assessments.
    • Permits for solar energy equipment of a capacity up to 50 kW to be considered and tacitly agreed 1 month from their application if there are no issues of grid safety, stability or reliability.
  • Heat pumps
    • The permit-granting process must not exceed 1 month for the installation of heat pumps below 50 MW and 3 months for ground source heat pumps.
    • For certain categories of heat pumps, grid connections to the transmission or distribution grid are permitted following notification.
  • Repowering renewable energy power plants
    • The permit-granting process for repowering projects, including all relevant environmental assessments, must not exceed 6 months.
    • Where repowering results in an increase of up to 15% in the capacity of the power plant, grid connections will be permitted within 3 months.

Scope

  • The regulation applies to all permit-granting processes that have a starting date within its period of application, and it does not have an effect on national rules establishing shorter deadlines than those laid down in the regulation.
  • EU Member States are also allowed to apply the regulation to pending permit-granting processes that have not resulted in a final decision before , provided that the application shortens the process and that pre-existing third-party legal rights are preserved.

Amending Regulation (EU) 2024/223

Amending Regulation (EU) 2024/223 extends the application of some articles and introduces several changes.

  • A new article specifies that assessing alternatives in the context of the relevant environmental assessments should take into account any alternatives that ensure the achievement of the same objectives as the project in question in terms of deployment of renewable energy capacity using the same renewable technology, within the same or similar time frame and at no significantly higher cost. This article has applied since .
  • As of , the 6-month time limit for the permit-granting process for the repowering of renewable energy projects will only apply to renewable energy projects located in a dedicated renewable area.

FROM WHEN DOES THE REGULATION APPLY?

Regulation (EU) 2022/2577 has applied since . It was originally valid for 18 months and has been extended by Regulation (EU) 2024/223 following a review by the Commission.

BACKGROUND

For further information, see:

MAIN DOCUMENTS

Council Regulation (EU) 2022/2577 of laying down a framework to accelerate the deployment of renewable energy (OJ L 335, , pp. 36–44).

Council Regulation (EU) 2024/223 of amending Regulation (EU) 2022/2577 laying down a framework to accelerate the deployment of renewable energy (OJ L, 2024/223, ).

last update

Top