19.1.2017 |
EN |
Official Journal of the European Union |
L 15/1 |
COMMISSION DELEGATED REGULATION (EU) 2017/90
of 31 October 2016
amending Delegated Regulation (EU) 2015/2195 on supplementing Regulation (EU) No 1304/2013 of the European Parliament and of the Council on the European Social Fund, regarding the definition of standard scales of unit costs and lump sums for reimbursement of expenditure by the Commission to Member States
THE EUROPEAN COMMISSION,
Having regard to the Treaty on the Functioning of the European Union,
Having regard to Regulation (EU) No 1304/2013 of the European Parliament and of the Council of 17 December 2013 on the European Social Fund and repealing Council Regulation (EC) No 1081/2006 (1), and in particular Article 14(1) thereof,
Whereas:
(1) |
The standard scales of unit costs and lump sums for reimbursement to Member States should be established on the basis of methods submitted by Member States and assessed by the Commission, including the methods set out in Article 67(5) of Regulation (EU) No 1303/2013 of the European Parliament and of the Council (2) and Articles 14(2) and 14(3) of Regulation (EU) No 1304/2013. |
(2) |
Taking into account the significant disparities between Member States, regarding the level of costs for a type of operation, the definition and amounts of standard scales of unit costs and lump sums may differ by type of operation and Member State in order to reflect their specificities. |
(3) |
Italy, Slovakia, the Netherlands, Malta and Germany have submitted methods for defining standard scales of unit costs for reimbursement of expenditure by the Commission. The Commission considers that those methods are appropriate for the reimbursement of expenditure to those Member States. |
(4) |
Further to the submission by the Czech Republic concerning types of operations not yet covered by Commission Delegated Regulation (EU) 2015/2195 (3), additional standard scales of unit costs should be defined for reimbursement of expenditure to the Czech Republic concerning these types of operations. |
(5) |
Delegated Regulation (EU) 2015/2195 should therefore be amended accordingly, |
HAS ADOPTED THIS REGULATION:
Article 1
Annex III to Delegated Regulation (EU) 2015/2195 is replaced by the text in Annex I to this Regulation.
Article 2
The text in Annex II to this Regulation is added as Annexes V to IX to Delegated Regulation (EU) 2015/2195.
Article 3
This Regulation shall enter into force on the twentieth day following that of its publication in the Official Journal of the European Union.
This Regulation shall be binding in its entirety and directly applicable in all Member States.
Done at Brussels, 31 October 2016.
For the Commission
The President
Jean-Claude JUNCKER
(1) OJ L 347, 20.12.2013, p. 470.
(2) Regulation (EU) No 1303/2013 of the European Parliament and of the Council of 17 December 2013 laying down common provisions on the European Regional Development Fund, the European Social Fund, the Cohesion Fund, the European Agricultural Fund for Rural Development and the European Maritime and Fisheries Fund and laying down general provisions on the European Regional Development Fund, the European Social Fund, the Cohesion Fund and the European Maritime and Fisheries Fund and repealing Council Regulation (EC) No 1083/2006 (OJ L 347, 20.12.2013, p. 320).
(3) Commission Delegated Regulation (EU) 2015/2195 of 9 July 2015 on supplementing Regulation (EU) No 1304/2013 of the European Parliament and of the Council on the European Social Fund, regarding the definition of standard scales of unit costs and lump sums for reimbursement of expenditure by the Commission to Member States (OJ L 313, 28.11.2015, p. 22).
ANNEX I
‘ANNEX III
Conditions for reimbursement of expenditure on the basis of standard scales of unit costs to the Czech Republic
1. Definition of standard scales of unit costs
Type of operations |
Indicator name |
Category of costs (1) |
Measurement unit for the indicator |
Amounts (in national currency CZK) |
||||||||||||||||||||
|
Newly created place in a new childcare facility |
|
Number of newly created places in a new childcare facility (2), |
20 053 incl. VAT, or 16 992 excl. VAT |
||||||||||||||||||||
|
Transformed place in a children's group (3) |
|
Number of transformed places in a children's group (4). |
9 518 incl. VAT, or 8 279 excl. VAT |
||||||||||||||||||||
|
Occupancy per place in a childcare facility |
|
Occupancy rate (5) |
628 (6) |
||||||||||||||||||||
|
Achievement of a qualification as caregiver in a childcare facility |
|
Number of persons who obtain a certification of professional qualification as caregiver in a childcare facility |
14 178 |
||||||||||||||||||||
|
Occupancy per place in a childcare facility |
|
Occupancy rate (7). |
56 (8) |
||||||||||||||||||||
|
One hour (60 minutes) of participation of an employee in an external training course on general information technologies (IT) |
All eligible costs, including:
|
Number of completed hours per employee. |
324 |
||||||||||||||||||||
|
One hour (60 minutes) of participation of an employee in an external training course on soft and managerial skills |
All eligible costs, including:
|
Number of completed hours per employee. |
593 |
||||||||||||||||||||
|
A period (45 minutes) of participation of an employee in external language training courses |
All eligible costs, including:
|
Number of completed periods per employee |
173 |
||||||||||||||||||||
|
One hour (60 minutes) of participation of an employee in a training course in specialised IT |
All eligible costs, inlcuding:
|
Number of completed hours per employee |
609 |
||||||||||||||||||||
|
One hour (60 minutes) of participation of an employee in an external training course in accountancy, economy and law |
All eligible costs, including:
|
Number of completed hours per employee |
436 |
||||||||||||||||||||
|
One hour (60 minutes) of participation of an employee in external technical and other professional training |
All eligible costs, including:
|
Number of completed hours per employee |
252 |
||||||||||||||||||||
|
One hour (60 minutes) of participation of an employee in a training course provided by an internal trainer in any of the following areas:
|
All eligible costs, including:
|
Number of completed hours per employee |
144 |
||||||||||||||||||||
|
0,1 full-time equivalent (FTE) worked as a school psychologist and/or a specialised school pedagogue per month |
All eligible costs, including, direct staff costs |
Number of 0,1 FTE worked per month |
5 607 |
||||||||||||||||||||
|
0,1 FTE worked by a school assistant and/or social pedagogue per month. |
All eligible costs, including direct staff costs |
Number of 0,1 FTE worked per month |
School assistant: 3 502 Social pedagogue: 4 695 |
||||||||||||||||||||
|
0,1 FTE worked by a nanny per month |
All eligible costs, including direct staff costs. |
Number of 0,1 FTE worked per month |
3 227 |
||||||||||||||||||||
|
Provision of a block of 16 lessons of extracurricular activities with a duration of 90 minutes per lesson provided to a group of at least 6 children/pupils of which 2 are at risk of school failure |
All eligible costs, including direct staff costs. |
Number of completed blocks of 16 lessons with a duration of 90 minutes per lesson provided to a group of at least 6 children/pupils of which 2 are at risk of school failure. |
17 277 |
||||||||||||||||||||
|
Provision of a block of 16 hours of tutoring to a group of at least 3 registered pupils at risk of school failure |
All eligible costs, including direct staff costs. |
Number of completed blocks of 16 hours provided to a goup of at least 3 registered pupils at risk of school failure. |
8 523 |
||||||||||||||||||||
|
Hours of professional training provided to pedagogues |
All eligible costs, including direct costs of providing training. |
Number of completed hours of training per pedagogue |
422 |
||||||||||||||||||||
|
Thematic meeting with a minimum of eight parents for a minimum duration of two hours (120 minutes). |
All eligible costs, including direct staff costs. |
Number of thematic meetings with a minimum of eight parents for a minimum duration of two hours (120 minutes) |
3 676 |
||||||||||||||||||||
|
Block of 30 hours of external mentoring/coaching to a group of between 3 and 8 pedagogues |
All eligible costs, including direct staff costs. |
Number of completed blocks of 30 hours mentoring/coaching to a group of between 3 and 8 pedagogues. |
29 698 |
||||||||||||||||||||
|
Training cycle of 15 hours of structured job-shadowing by a pedagogue |
All eligible costs, including direct staff costs. |
Number of completed training cycles of 15 hours per pedagogue undertaking a structured visit to another pedagogue in another school. |
4 246 |
||||||||||||||||||||
|
Cycle of 10 hours of training through mutual cooperation involving a group of at least 3 pedagogues |
All eligible costs, including direct staff costs. |
Number of completed training cycles of 10 hours involving a group of at least 3 pedagogues. |
8 068 |
||||||||||||||||||||
|
Tandem lesson (10) of 2,75 hours |
All eligible costs, including direct staff costs. |
Number of completed tandem lessons |
778 |
||||||||||||||||||||
|
Cycle of 19 hours of mutual cooperation and learning involving an expert and 2 pedagogues. |
All eligible costs, including direct staff costs. |
Number of completed cycles of 19 hours involving an expert and 2 other pedagogues. |
5 377 |
2. Adjustments of amounts.
(a) |
The rate for unit costs 6 – 11 may be adjusted by replacing the initial minimum wage rate in the calculation method that consists of the minimum wage, the cost for provision of training and indirect costs. The rate for unit cost 12 may be adjusted by replacing the initial direct staff costs, including social security and health contributions, and/or the wages for participants, including social security and health contributions in the calculation method that consists of direct staff costs, including social security and health contributions and/or the wages for participants, including social security and health contributions. Adjustments shall be based on the updated data as follows:
|
(b) |
The rate for unit costs 13 – 17 and 19 – 24 may be adjusted by replacing the initial direct staff costs, including social security and health contributions, in the calculation method that consists of direct staff costs, including social security and health contributions, plus indirect costs. The rate for unit cost 18 may be adjusted by replacing the wages for participants, including social security and health contributions in the calculation method that consists of the cost for provision of training plus wages for participants, including social security and health contributions, plus indirect costs. Adjustments shall be based on the updated data as follows:
|
(1) In each case listed below, the categories of costs mentioned cover all costs associated with that operation, except for types of operations 1 and 2, which may also include other categories of costs.
(2) Meaning a new place which is included in the capacity of the new childcare facility as recorded by national regulations, and which has proof of equipment for each new place provided.
(3) A children's group means it has been registered as a children's group pursuant to national legislation on the provision of childcare services in a children's group.
(4) Meaning a place in an existing facility which is newly registered as a children's group in accordance with national legislation and inlcuded in the official capacity of that group, and which has proof of equipment for each place.
(5) The occupancy rate is defined as the number of children attending the childcare facility per half day during 6 months divided by the maximum capacity of the facility per half day during 6 months, multiplied by 100.
(6) This amount shall be paid for each 1 % point of occupancy per place up to a maximum of 75 % points for a period of 6 months. If the occupancy rate is less than 20 % there shall be no reimbursement.
(7) The occupancy rate is defined as the number of children attending the childcare facility per half day during 6 months divided by the maximum capacity of the facility per half day during 6 months, multiplied by 100.
(8) This amount shall be paid for each 1 % point of occupancy per place up to a maximum of 75 % points for a period of 6 months. If the occupancy rate is less than 20 % there shall be no reimbursement.
(9) i.e. provided by an internal trainer.
(10) Tandem lesson is to be understood as two pedagogues cooperating to mutually strengthen their professional development by jointly planning, implementing and reflecting on teaching methods in a class.
ANNEX II
‘ANNEX V
Conditions for reimbursement of expenditure on the basis of standard scales of unit costs to Malta
1. Definition of standard scales of unit costs
Type of operations |
Indicators name |
Category of costs |
Measurement unit for the indicators |
Amounts (in EUR) |
||||||||
|
Employment aid paid per week to workers who are disadvantaged, severely disadvantaged or with disabilities (1). |
All costs related to the Employment Subsidy |
Number of weeks in employment per employee. |
|
2. Adjustment of amounts
The unit cost may be adjusted by replacing the initial minimum wage and/or the statutory bonus and/or social security contributions in the calculation method that consists of the lowest weekly rate of national minimum wage, the statutory bonus and social security contributions, and dividing this result by 2.
The national minimum wage is specified in national Subsidiary Legislation 452.71 (National Minimum Wage Standing Order).
The statutory bonuses and social security contributions emanate from Chapter 452 of the Maltese legislation on the Employment and Indistrial relations Act.
‘ANNEX VI
Conditions for reimbursement of expenditure on the basis of standard scales of unit costs to Italy
1. Definition of standard scales of unit costs
Type of operations |
Indicators name |
Category of costs |
Measurement unit for the indicators |
Amounts (in EUR) |
||||||||||||||||||||||||||||||||||||||
|
Hourly rate for 1st guidance level support |
All eligible costs, including direct staff costs. |
Number of hours providing 1st guidance level support |
34,00 |
||||||||||||||||||||||||||||||||||||||
|
Hourly rate for specialist or 2nd guidance level support |
All eligible costs, including direct staff costs. |
Number of hours providing specialist or 2nd guidance level support |
35,50 |
||||||||||||||||||||||||||||||||||||||
|
|
All eligible costs, including direct staff costs and excluding any allowance paid to participants |
Number of hours per training course differentiated by type of class, and the number of hours per student. |
Type of class |
Hourly rate per course |
Hourly rate per student |
||||||||||||||||||||||||||||||||||||
C |
73,13 |
0,80 |
||||||||||||||||||||||||||||||||||||||||
B |
117,00 |
|||||||||||||||||||||||||||||||||||||||||
A |
146,25 |
|||||||||||||||||||||||||||||||||||||||||
|
New employment contracts as a result of job coaching |
All eligible costs, including direct staff costs |
Number of new employment contracts, differentiated by type of contract and profile classification (from low to very high) (4) |
Profile Classification |
Low |
Medium |
High |
Very high |
||||||||||||||||||||||||||||||||||
Open-ended contract and 1st and 3rd level apprenticeship contract |
1 500 |
2 000 |
2 500 |
3 000 |
||||||||||||||||||||||||||||||||||||||
2nd level apprenticeship, fixed-term and temporary contract ≥ 12 months |
1 000 |
1 300 |
1 600 |
2 000 |
||||||||||||||||||||||||||||||||||||||
fixed-term and temporary contract 6-12 months |
600 |
800 |
1 000 |
1 200 |
||||||||||||||||||||||||||||||||||||||
|
New regional/interregional/transnational traineeships |
All eligible costs including direct staff costs for providing a traineeship. |
Number of traineeships, differentiated by profile classification. |
|
Low |
Medium |
High |
Very high |
||||||||||||||||||||||||||||||||||
Regional/Interregional/Transnational |
200 |
300 |
400 |
500 |
||||||||||||||||||||||||||||||||||||||
|
Traineeships under interregional mobility |
For interregional mobility: all eligible costs, including travel, accomodation and meal, but excluding participant allowances |
Number of traineeships, differentiated by location and, for inter-regional mobility, the length of traineeship |
Inter-regional mobility as per the rates set out in point 3.4 Trans-national mobility as per the rates set in point 3.5 |
||||||||||||||||||||||||||||||||||||||
Traineeships under transnational mobility |
For transnational mobility: all eligible costs. |
|||||||||||||||||||||||||||||||||||||||||
|
30 hour block of general preparatory training for access to the Civil Service |
All eligible costs, including direct staff costs, excluding allowances and insurance. |
Number of participants completing the 30 hour block of training. |
90 |
||||||||||||||||||||||||||||||||||||||
|
Hourly rate of support for self-employment and self-entrepreneurship (5) |
All eligible costs, including direct staff costs., but excluding any allowance. |
Number of hours of support provided to participants |
40 |
||||||||||||||||||||||||||||||||||||||
|
|
All eligible costs (one off subsidy for travel, accommodation and meals, and an interview allowance), not including any additional allowances for disadvantaged people and any allowances for travel, accommodation or meals under inter-regional mobility provided by employer. |
Number of employment contracts or job interviews, differentiated by location |
|
||||||||||||||||||||||||||||||||||||||
|
Months spent working on PhD |
All eligible costs for the participant (salary and associated social secutiy contributions) and the institution providing the PhD (direct and indirect costs). |
Number of months spent working on PhD, according to location in Italy or abroad. |
Without a period spent abroad: 1 927,63 per month With a period spent abroad: 2 891,45 per month |
2. Adjustment of amounts
(a) |
For standard scale of unit costs 1-9, the amounts may be adjusted where the FOI index (consumer price index for blue and white collar worker households, excluding tobacco products) shows a monetary revaluation equal to or exceeding 5 %. In particular, having considered a given year y, the adjustment is made in case in a period y + t the difference between the benchmarking coefficients shown by the FOI index for such years is equal to or higher than 5 %. The base year taken into consideration — and on the basis of which the amounts were adjusted — is 2014. Where this rate is equal to or higher than 5 %, each unit cost may be adjusted accordingly. |
(b) |
For standard Scale of Unit Cost 10, the rate may be adjusted by replacing the montly scholarship and/or social security contributions in the calculation method that consists of monthly scholarship plus social security contributions plus an amount for all other costs. Updated data can be found in amendments to Minister's Decree of 18.6.2008 (which defines the total gross annual amount of PhD scholarships) and biannual adjustment of the rate of social security contributions (Circular letter No 13 of 29.1.2016 of the Director-General of INPS, the National Institute for Social Security). |
3.1 Inter-regional Travel Costs
Region of origin |
Travel costs |
||||||||||||||||||||
Destination region |
|||||||||||||||||||||
Valle d'Aosta |
PA Bolzano |
PA Trento |
Liguria |
Piemonte |
Lombardia |
Veneto |
Friuli Venezia Giulia |
Emilia-Romagna |
Toscana |
Marche |
Abruzzo |
Umbria |
Lazio |
Campania |
Molise |
Basilicata |
Puglia |
Calabria |
Sicilia |
Sardegna |
|
Abruzzo |
269,30 |
211,17 |
198,50 |
148,63 |
231,83 |
232,74 |
201,95 |
226,34 |
167,99 |
68,60 |
58,98 |
0,00 |
23,32 |
25,81 |
125,43 |
45,79 |
83,99 |
93,05 |
164,82 |
165,16 |
182,46 |
Basilicata |
271,11 |
236,02 |
227,31 |
236,81 |
294,55 |
239,98 |
259,23 |
264,89 |
201,50 |
176,59 |
97,35 |
83,99 |
142,75 |
67,92 |
33,96 |
31,24 |
0,00 |
55,47 |
71,43 |
114,33 |
224,18 |
Calabria |
369,32 |
285,04 |
273,72 |
242,02 |
351,32 |
340,51 |
304,28 |
304,39 |
270,32 |
238,63 |
243,15 |
164,82 |
178,18 |
139,01 |
90,33 |
85,58 |
71,43 |
69,05 |
0,00 |
75,62 |
280,55 |
Campania |
253,00 |
271,68 |
259,06 |
113,20 |
246,78 |
221,87 |
165,84 |
302,24 |
178,86 |
160,74 |
169,86 |
125,43 |
151,01 |
99,62 |
0,00 |
21,28 |
33,96 |
89,20 |
90,33 |
113,20 |
190,22 |
Emilia-Romagna |
146,48 |
81,50 |
74,71 |
38,26 |
129,05 |
92,82 |
63,39 |
55,47 |
0,00 |
54,34 |
62,26 |
167,99 |
52,07 |
131,31 |
178,86 |
160,52 |
201,50 |
140,37 |
270,32 |
292,06 |
188,94 |
Friuli Venezia Giulia |
129,05 |
103,24 |
82,30 |
120,22 |
175,52 |
99,62 |
37,36 |
0,00 |
55,47 |
70,18 |
163,01 |
226,34 |
162,50 |
113,20 |
302,24 |
218,87 |
264,89 |
241,12 |
304,39 |
325,00 |
279,13 |
Lazio |
230,31 |
172,06 |
160,74 |
129,05 |
210,55 |
201,50 |
165,27 |
113,20 |
131,31 |
99,62 |
70,18 |
25,81 |
54,34 |
0,00 |
99,62 |
29,21 |
67,92 |
113,20 |
139,01 |
138,10 |
156,65 |
Liguria |
53,66 |
113,94 |
105,11 |
0,00 |
36,22 |
49,81 |
106,41 |
120,22 |
38,26 |
67,47 |
118,07 |
148,63 |
75,50 |
129,05 |
113,20 |
152,03 |
236,81 |
250,17 |
242,02 |
231,61 |
224,15 |
Lombardia |
59,37 |
97,35 |
76,47 |
49,81 |
67,92 |
0,00 |
69,05 |
99,62 |
92,82 |
113,20 |
108,67 |
232,74 |
84,90 |
201,50 |
221,87 |
223,91 |
239,98 |
179,99 |
340,51 |
335,07 |
179,51 |
Marche |
200,25 |
84,90 |
76,98 |
118,07 |
119,99 |
108,67 |
70,18 |
163,01 |
62,26 |
108,11 |
0,00 |
58,98 |
43,92 |
70,18 |
169,86 |
75,96 |
97,35 |
107,54 |
243,15 |
216,21 |
251,20 |
Molise |
259,51 |
196,06 |
194,31 |
152,03 |
232,97 |
223,91 |
194,48 |
218,87 |
160,52 |
126,56 |
75,96 |
45,79 |
106,75 |
29,21 |
21,28 |
0,00 |
31,24 |
70,30 |
85,58 |
140,48 |
185,85 |
PA Bolzano |
118,58 |
0,00 |
36,22 |
113,94 |
151,35 |
97,35 |
96,22 |
103,24 |
81,50 |
110,94 |
84,90 |
67,92 |
127,01 |
172,06 |
271,68 |
196,06 |
236,02 |
138,10 |
285,04 |
310,17 |
273,47 |
PA Trento |
112,24 |
36,22 |
0,00 |
105,11 |
147,22 |
76,47 |
19,02 |
82,30 |
74,71 |
99,62 |
76,98 |
198,50 |
120,44 |
160,74 |
259,06 |
194,31 |
227,31 |
132,44 |
273,72 |
308,24 |
247,26 |
Piemonte |
17,43 |
151,35 |
147,22 |
36,22 |
0,00 |
67,92 |
103,01 |
175,52 |
129,05 |
147,16 |
119,99 |
231,83 |
181,74 |
210,55 |
246,78 |
232,97 |
294,55 |
191,31 |
351,32 |
273,60 |
187,92 |
Puglia |
275,59 |
138,10 |
132,44 |
250,17 |
191,31 |
179,99 |
164,71 |
241,12 |
140,37 |
212,82 |
107,54 |
93,05 |
156,78 |
113,20 |
89,20 |
70,30 |
55,47 |
0,00 |
69,05 |
147,61 |
279,42 |
Sardegna |
205,36 |
273,47 |
247,26 |
224,15 |
187,92 |
179,51 |
248,56 |
279,13 |
188,94 |
189,41 |
251,20 |
182,46 |
210,98 |
156,65 |
190,22 |
185,85 |
224,18 |
279,42 |
280,55 |
185,82 |
0,00 |
Sicilia |
350,35 |
310,17 |
308,24 |
231,61 |
273,60 |
335,07 |
303,38 |
325,00 |
292,06 |
273,94 |
216,21 |
165,16 |
189,50 |
138,10 |
113,20 |
140,48 |
114,33 |
147,61 |
75,62 |
0,00 |
185,82 |
Toscana |
169,12 |
110,94 |
99,62 |
67,47 |
147,16 |
113,20 |
95,09 |
70,18 |
54,34 |
0,00 |
108,11 |
68,60 |
36,22 |
99,62 |
160,74 |
126,56 |
176,59 |
212,82 |
238,63 |
273,94 |
189,41 |
Umbria |
199,18 |
127,01 |
120,44 |
75,50 |
181,74 |
84,90 |
125,14 |
162,50 |
52,07 |
36,22 |
43,92 |
23,32 |
0,00 |
54,34 |
151,01 |
106,75 |
142,75 |
156,78 |
178,18 |
189,50 |
210,98 |
Valle d'Aosta |
0,00 |
118,58 |
112,24 |
53,66 |
17,43 |
59,37 |
155,03 |
129,05 |
146,48 |
169,12 |
200,25 |
269,30 |
199,18 |
230,31 |
253,00 |
259,51 |
271,11 |
275,59 |
369,32 |
350,35 |
205,36 |
Veneto |
155,03 |
96,22 |
19,02 |
106,41 |
103,01 |
69,05 |
0,00 |
37,36 |
63,39 |
95,09 |
70,18 |
201,95 |
125,14 |
165,27 |
165,84 |
194,48 |
259,23 |
164,71 |
304,28 |
303,38 |
248,56 |
3.2 Inter-regional Accommodation Costs (for more than 600 hours)
Region of origin |
Accomodation costs |
||||||||||||||||||||
Destination region |
|||||||||||||||||||||
Valle d'Aosta |
PA Bolzano |
PA Trento |
Liguria |
Piemonte |
Lombardia |
Veneto |
Friuli Venezia Giulia |
Emilia-Romagna |
Toscana |
Marche |
Abruzzo |
Umbria |
Lazio |
Campania |
Molise |
Basilicata |
Puglia |
Calabria |
Sicilia |
Sardegna |
|
Abruzzo |
803,84 |
1 153,94 |
788,70 |
741,25 |
695,62 |
1229,98 |
700,07 |
703,65 |
967,41 |
1 227,68 |
601,19 |
578,51 |
628,23 |
1 229,68 |
930,19 |
519,08 |
684,62 |
607,95 |
575,50 |
988,35 |
600,62 |
Basilicata |
803,84 |
1 153,94 |
788,70 |
741,25 |
695,62 |
1 229,98 |
700,07 |
703,65 |
967,41 |
1 227,68 |
601,19 |
578,51 |
628,23 |
1 229,68 |
930,19 |
519,08 |
684,62 |
607,95 |
575,50 |
988,35 |
600,62 |
Calabria |
803,84 |
1 153,94 |
788,70 |
741,25 |
695,62 |
1 229,98 |
700,07 |
703,65 |
967,41 |
1 227,68 |
601,19 |
578,51 |
628,23 |
1 229,68 |
930,19 |
519,08 |
684,62 |
607,95 |
575,50 |
988,35 |
600,62 |
Campania |
803,84 |
1 153,94 |
788,70 |
741,25 |
695,62 |
1 229,98 |
700,07 |
703,65 |
967,41 |
1 227,68 |
601,19 |
578,51 |
628,23 |
1 229,68 |
930,19 |
519,08 |
684,62 |
607,95 |
575,50 |
988,35 |
600,62 |
Emilia-Romagna |
803,84 |
1 153,94 |
788,70 |
741,25 |
695,62 |
1 229,98 |
700,07 |
703,65 |
967,41 |
1 227,68 |
601,19 |
578,51 |
628,23 |
1 229,68 |
930,19 |
519,08 |
684,62 |
607,95 |
575,50 |
988,35 |
600,62 |
Friuli Venezia Giulia |
803,84 |
1 153,94 |
788,70 |
741,25 |
695,62 |
1 229,98 |
700,07 |
703,65 |
967,41 |
1 227,68 |
601,19 |
578,51 |
628,23 |
1 229,68 |
930,19 |
519,08 |
684,62 |
607,95 |
575,50 |
988,35 |
600,62 |
Lazio |
803,84 |
1 153,94 |
788,70 |
741,25 |
695,62 |
1 229,98 |
700,07 |
703,65 |
967,41 |
1 227,68 |
601,19 |
578,51 |
628,23 |
1 229,68 |
930,19 |
519,08 |
684,62 |
607,95 |
575,50 |
988,35 |
600,62 |
Liguria |
803,84 |
1 153,94 |
788,70 |
741,25 |
695,62 |
1 229,98 |
700,07 |
703,65 |
967,41 |
1 227,68 |
601,19 |
578,51 |
628,23 |
1 229,68 |
930,19 |
519,08 |
684,62 |
607,95 |
575,50 |
988,35 |
600,62 |
Lombardia |
803,84 |
1 153,94 |
788,70 |
741,25 |
695,62 |
1 229,98 |
700,07 |
703,65 |
967,41 |
1 227,68 |
601,19 |
578,51 |
628,23 |
1 229,68 |
930,19 |
519,08 |
684,62 |
607,95 |
575,50 |
988,35 |
600,62 |
Marche |
803,84 |
1 153,94 |
788,70 |
741,25 |
695,62 |
1 229,98 |
700,07 |
703,65 |
967,41 |
1 227,68 |
601,19 |
578,51 |
628,23 |
1 229,68 |
930,19 |
519,08 |
684,62 |
607,95 |
575,50 |
988,35 |
600,62 |
Molise |
803,84 |
1 153,94 |
788,70 |
741,25 |
695,62 |
1 229,98 |
700,07 |
703,65 |
967,41 |
1 227,68 |
601,19 |
578,51 |
628,23 |
1 229,68 |
930,19 |
519,08 |
684,62 |
607,95 |
575,50 |
988,35 |
600,62 |
PA Bolzano |
803,84 |
1 153,94 |
788,70 |
741,25 |
695,62 |
1 229,98 |
700,07 |
703,65 |
967,41 |
1 227,68 |
601,19 |
578,51 |
628,23 |
1 229,68 |
930,19 |
519,08 |
684,62 |
607,95 |
575,50 |
988,35 |
600,62 |
PA Trento |
803,84 |
1 153,94 |
788,70 |
741,25 |
695,62 |
1 229,98 |
700,07 |
703,65 |
967,41 |
1 227,68 |
601,19 |
578,51 |
628,23 |
1 229,68 |
930,19 |
519,08 |
684,62 |
607,95 |
575,50 |
988,35 |
600,62 |
Piemonte |
803,84 |
1 153,94 |
788,70 |
741,25 |
695,62 |
1 229,98 |
700,07 |
703,65 |
967,41 |
1 227,68 |
601,19 |
578,51 |
628,23 |
1 229,68 |
930,19 |
519,08 |
684,62 |
607,95 |
575,50 |
988,35 |
600,62 |
Puglia |
803,84 |
1 153,94 |
788,70 |
741,25 |
695,62 |
1 229,98 |
700,07 |
703,65 |
967,41 |
1 227,68 |
601,19 |
578,51 |
628,23 |
1 229,68 |
930,19 |
519,08 |
684,62 |
607,95 |
575,50 |
988,35 |
600,62 |
Sardegna |
803,84 |
1 153,94 |
788,70 |
741,25 |
695,62 |
1 229,98 |
700,07 |
703,65 |
967,41 |
1 227,68 |
601,19 |
578,51 |
628,23 |
1 229,68 |
930,19 |
519,08 |
684,62 |
607,95 |
575,50 |
988,35 |
600,62 |
Sicilia |
803,84 |
1 153,94 |
788,70 |
741,25 |
695,62 |
1 229,98 |
700,07 |
703,65 |
967,41 |
1 227,68 |
601,19 |
578,51 |
628,23 |
1 229,68 |
930,19 |
519,08 |
684,62 |
607,95 |
575,50 |
988,35 |
600,62 |
Toscana |
803,84 |
1 153,94 |
788,70 |
741,25 |
695,62 |
1 229,98 |
700,07 |
703,65 |
967,41 |
1 227,68 |
601,19 |
578,51 |
628,23 |
1 229,68 |
930,19 |
519,08 |
684,62 |
607,95 |
575,50 |
988,35 |
600,62 |
Umbria |
803,84 |
1 153,94 |
788,70 |
741,25 |
695,62 |
1 229,98 |
700,07 |
703,65 |
967,41 |
1 227,68 |
601,19 |
578,51 |
628,23 |
1 229,68 |
930,19 |
519,08 |
684,62 |
607,95 |
575,50 |
988,35 |
600,62 |
Valle d'Aosta |
803,84 |
1 153,94 |
788,70 |
741,25 |
695,62 |
1 229,98 |
700,07 |
703,65 |
967,41 |
1 227,68 |
601,19 |
578,51 |
628,23 |
1 229,68 |
930,19 |
519,08 |
684,62 |
607,95 |
575,50 |
988,35 |
600,62 |
Veneto |
803,84 |
1 153,94 |
788,70 |
741,25 |
695,62 |
1 229,98 |
700,07 |
703,65 |
967,41 |
1 227,68 |
601,19 |
578,51 |
628,23 |
1 229,68 |
930,19 |
519,08 |
684,62 |
607,95 |
575,50 |
988,35 |
600,62 |
3.3 Inter-regional Subsistence Costs (for more than 600 hours)
Region of origin |
Meal costs |
||||||||||||||||||||
Destination region |
|||||||||||||||||||||
Valle d'Aosta |
PA Bolzano |
PA Trento |
Liguria |
Piemonte |
Lombardia |
Veneto |
Friuli Venezia Giulia |
Emilia-Romagna |
Toscana |
Marche |
Abruzzo |
Umbria |
Lazio |
Campania |
Molise |
Basilicata |
Puglia |
Calabria |
Sicilia |
Sardegna |
|
Abruzzo |
482,30 |
252,45 |
320,93 |
407,41 |
521,52 |
502,26 |
416,04 |
616,19 |
514,94 |
200,21 |
480,95 |
433,27 |
641,87 |
596,60 |
298,90 |
638,86 |
205,47 |
440,97 |
487,71 |
359,11 |
256,27 |
Basilicata |
482,30 |
252,45 |
320,93 |
407,41 |
521,52 |
502,26 |
416,04 |
616,19 |
514,94 |
200,21 |
480,95 |
433,27 |
641,87 |
596,60 |
298,90 |
638,86 |
205,47 |
440,97 |
487,71 |
359,11 |
256,27 |
Calabria |
482,30 |
252,45 |
320,93 |
407,41 |
521,52 |
502,26 |
416,04 |
616,19 |
514,94 |
200,21 |
480,95 |
433,27 |
641,87 |
596,60 |
298,90 |
638,86 |
205,47 |
440,97 |
487,71 |
359,11 |
256,27 |
Campania |
482,30 |
252,45 |
320,93 |
407,41 |
521,52 |
502,26 |
416,04 |
616,19 |
514,94 |
200,21 |
480,95 |
433,27 |
641,87 |
596,60 |
298,90 |
638,86 |
205,47 |
440,97 |
487,71 |
359,11 |
256,27 |
Emilia-Romagna |
482,30 |
252,45 |
320,93 |
407,41 |
521,52 |
502,26 |
416,04 |
616,19 |
514,94 |
200,21 |
480,95 |
433,27 |
641,87 |
596,60 |
298,90 |
638,86 |
205,47 |
440,97 |
487,71 |
359,11 |
256,27 |
Friuli Venezia Giulia |
482,30 |
252,45 |
320,93 |
407,41 |
521,52 |
502,26 |
416,04 |
616,19 |
514,94 |
200,21 |
480,95 |
433,27 |
641,87 |
596,60 |
298,90 |
638,86 |
205,47 |
440,97 |
487,71 |
359,11 |
256,27 |
Lazio |
482,30 |
252,45 |
320,93 |
407,41 |
521,52 |
502,26 |
416,04 |
616,19 |
514,94 |
200,21 |
480,95 |
433,27 |
641,87 |
596,60 |
298,90 |
638,86 |
205,47 |
440,97 |
487,71 |
359,11 |
256,27 |
Liguria |
482,30 |
252,45 |
320,93 |
407,41 |
521,52 |
502,26 |
416,04 |
616,19 |
514,94 |
200,21 |
480,95 |
433,27 |
641,87 |
596,60 |
298,90 |
638,86 |
205,47 |
440,97 |
487,71 |
359,11 |
256,27 |
Lombardia |
482,30 |
252,45 |
320,93 |
407,41 |
521,52 |
502,26 |
416,04 |
616,19 |
514,94 |
200,21 |
480,95 |
433,27 |
641,87 |
596,60 |
298,90 |
638,86 |
205,47 |
440,97 |
487,71 |
359,11 |
256,27 |
Marche |
482,30 |
252,45 |
320,93 |
407,41 |
521,52 |
502,26 |
416,04 |
616,19 |
514,94 |
200,21 |
480,95 |
433,27 |
641,87 |
596,60 |
298,90 |
638,86 |
205,47 |
440,97 |
487,71 |
359,11 |
256,27 |
Molise |
482,30 |
252,45 |
320,93 |
407,41 |
521,52 |
502,26 |
416,04 |
616,19 |
514,94 |
200,21 |
480,95 |
433,27 |
641,87 |
596,60 |
298,90 |
638,86 |
205,47 |
440,97 |
487,71 |
359,11 |
256,27 |
PA Bolzano |
482,30 |
252,45 |
320,93 |
407,41 |
521,52 |
502,26 |
416,04 |
616,19 |
514,94 |
200,21 |
480,95 |
433,27 |
641,87 |
596,60 |
298,90 |
638,86 |
205,47 |
440,97 |
487,71 |
359,11 |
256,27 |
PA Trento |
482,30 |
252,45 |
320,93 |
407,41 |
521,52 |
502,26 |
416,04 |
616,19 |
514,94 |
200,21 |
480,95 |
433,27 |
641,87 |
596,60 |
298,90 |
638,86 |
205,47 |
440,97 |
487,71 |
359,11 |
256,27 |
Piemonte |
482,30 |
252,45 |
320,93 |
407,41 |
521,52 |
502,26 |
416,04 |
616,19 |
514,94 |
200,21 |
480,95 |
433,27 |
641,87 |
596,60 |
298,90 |
638,86 |
205,47 |
440,97 |
487,71 |
359,11 |
256,27 |
Puglia |
482,30 |
252,45 |
320,93 |
407,41 |
521,52 |
502,26 |
416,04 |
616,19 |
514,94 |
200,21 |
480,95 |
433,27 |
641,87 |
596,60 |
298,90 |
638,86 |
205,47 |
440,97 |
487,71 |
359,11 |
256,27 |
Sardegna |
482,30 |
252,45 |
320,93 |
407,41 |
521,52 |
502,26 |
416,04 |
616,19 |
514,94 |
200,21 |
480,95 |
433,27 |
641,87 |
596,60 |
298,90 |
638,86 |
205,47 |
440,97 |
487,71 |
359,11 |
256,27 |
Sicilia |
482,30 |
252,45 |
320,93 |
407,41 |
521,52 |
502,26 |
416,04 |
616,19 |
514,94 |
200,21 |
480,95 |
433,27 |
641,87 |
596,60 |
298,90 |
638,86 |
205,47 |
440,97 |
487,71 |
359,11 |
256,27 |
Toscana |
482,30 |
252,45 |
320,93 |
407,41 |
521,52 |
502,26 |
416,04 |
616,19 |
514,94 |
200,21 |
480,95 |
433,27 |
641,87 |
596,60 |
298,90 |
638,86 |
205,47 |
440,97 |
487,71 |
359,11 |
256,27 |
Umbria |
482,30 |
252,45 |
320,93 |
407,41 |
521,52 |
502,26 |
416,04 |
616,19 |
514,94 |
200,21 |
480,95 |
433,27 |
641,87 |
596,60 |
298,90 |
638,86 |
205,47 |
440,97 |
487,71 |
359,11 |
256,27 |
Valle d'Aosta |
482,30 |
252,45 |
320,93 |
407,41 |
521,52 |
502,26 |
416,04 |
616,19 |
514,94 |
200,21 |
480,95 |
433,27 |
641,87 |
596,60 |
298,90 |
638,86 |
205,47 |
440,97 |
487,71 |
359,11 |
256,27 |
Veneto |
482,30 |
252,45 |
320,93 |
407,41 |
521,52 |
502,26 |
416,04 |
616,19 |
514,94 |
200,21 |
480,95 |
433,27 |
641,87 |
596,60 |
298,90 |
638,86 |
205,47 |
440,97 |
487,71 |
359,11 |
256,27 |
3.4 Inter-regional allowances for Traineeships
No. of training hours |
Abruzzo |
Basilicata |
Calabria |
Campania |
Emilia Romagna |
Friuli Venezia Giulia |
Lazio |
Liguria |
Lombardia |
Marche |
Molise |
PA Bolzano |
PA Trento |
Piemonte |
Puglia |
Sardegna |
Sicilia |
Toscana |
Umbria |
Valle d'Aosta |
Veneto |
||
Region where the training is taking place |
Valle d'Aosta |
160 |
611,70 |
613,51 |
711,72 |
595,40 |
488,88 |
471,45 |
572,71 |
396,06 |
401,77 |
542,65 |
601,91 |
460,98 |
454,64 |
359,83 |
617,99 |
547,76 |
692,75 |
511,52 |
541,58 |
— |
497,43 |
161-200 |
613,84 |
615,65 |
713,86 |
597,54 |
491,02 |
473,59 |
574,85 |
398,20 |
403,91 |
544,79 |
604,05 |
463,12 |
456,78 |
361,97 |
620,13 |
549,90 |
694,89 |
513,66 |
543,72 |
— |
499,57 |
||
201-249 |
699,44 |
701,25 |
799,46 |
683,14 |
576,62 |
559,19 |
660,45 |
483,80 |
489,51 |
630,39 |
689,65 |
548,72 |
542,38 |
447,57 |
705,73 |
635,50 |
780,49 |
599,26 |
629,32 |
— |
585,17 |
||
250-300 |
804,30 |
806,11 |
904,32 |
788,00 |
681,48 |
664,05 |
765,31 |
588,66 |
594,37 |
735,25 |
794,51 |
653,58 |
647,24 |
552,43 |
810,59 |
740,36 |
885,35 |
704,12 |
734,18 |
— |
690,03 |
||
301-600 |
913,44 |
915,25 |
1.013,46 |
897,14 |
790,62 |
773,19 |
874,45 |
697,80 |
703,51 |
844,39 |
903,65 |
762,72 |
756,38 |
661,57 |
919,73 |
849,50 |
994,49 |
813,26 |
843,32 |
— |
799,17 |
||
> 600 |
1 555,44 |
1 557,25 |
1 655,46 |
1 539,14 |
1 432,62 |
1 415,19 |
1 516,45 |
1 339,80 |
1 345,51 |
1 486,39 |
1 545,65 |
1 404,72 |
1 398,38 |
1 303,57 |
1 561,73 |
1 491,50 |
1 636,49 |
1 455,26 |
1 485,32 |
— |
1 441,17 |
||
Bolzano |
160 |
585,59 |
610,44 |
659,45 |
646,09 |
455,92 |
477,65 |
546,48 |
488,35 |
471,77 |
459,31 |
570,48 |
— |
410,64 |
525,76 |
512,52 |
647,88 |
684,58 |
485,35 |
501,42 |
492,99 |
470,63 |
|
161-200 |
587,93 |
612,78 |
661,79 |
648,43 |
458,26 |
479,99 |
548,82 |
490,69 |
474,11 |
461,65 |
572,82 |
— |
412,98 |
528,10 |
514,86 |
650,22 |
686,92 |
487,69 |
503,76 |
495,33 |
472,97 |
||
201-249 |
681,53 |
706,38 |
755,39 |
742,04 |
551,86 |
573,60 |
642,42 |
584,29 |
567,71 |
555,26 |
666,42 |
— |
506,58 |
621,71 |
608,46 |
743,83 |
780,53 |
581,29 |
597,37 |
588,93 |
566,58 |
||
250-300 |
796,20 |
821,04 |
870,06 |
856,70 |
666,53 |
688,26 |
757,09 |
698,96 |
682,37 |
669,92 |
781,08 |
— |
621,25 |
736,37 |
723,13 |
858,49 |
895,19 |
695,96 |
712,03 |
703,60 |
681,24 |
||
301-600 |
915,54 |
940,39 |
989,40 |
976,05 |
785,87 |
807,60 |
876,43 |
818,30 |
801,72 |
789,27 |
900,43 |
— |
740,59 |
855,71 |
842,47 |
977,83 |
1 014,53 |
815,30 |
831,38 |
822,94 |
800,59 |
||
> 600 |
1 617,57 |
1 642,41 |
1 691,43 |
1 678,07 |
1 487,90 |
1 509,63 |
1 578,46 |
1 520,33 |
1 503,74 |
1 491,29 |
1 602,45 |
— |
1 442,62 |
1 557,74 |
1 544,50 |
1 679,86 |
1 716,56 |
1 517,33 |
1 533,40 |
1 524,97 |
1 502,61 |
||
Trento |
160 |
493,91 |
522,71 |
569,13 |
554,47 |
370,12 |
377,71 |
456,15 |
400,52 |
371,88 |
372,38 |
489,72 |
331,63 |
— |
442,63 |
427,85 |
542,67 |
603,65 |
395,02 |
415,85 |
407,65 |
314,43 |
|
161-200 |
495,75 |
524,56 |
570,97 |
556,31 |
371,97 |
379,55 |
458,00 |
402,36 |
373,72 |
374,23 |
491,56 |
333,48 |
— |
444,47 |
429,70 |
544,52 |
605,50 |
396,87 |
417,70 |
409,49 |
316,27 |
||
201-249 |
569,60 |
598,41 |
644,82 |
630,17 |
445,82 |
453,40 |
531,85 |
476,21 |
447,57 |
448,08 |
565,42 |
407,33 |
— |
518,32 |
503,55 |
618,37 |
679,35 |
470,72 |
491,55 |
483,35 |
390,12 |
||
250-300 |
660,07 |
688,88 |
735,29 |
720,63 |
536,29 |
543,87 |
622,32 |
566,68 |
538,04 |
538,55 |
655,88 |
497,80 |
— |
608,79 |
594,02 |
708,84 |
769,82 |
561,19 |
582,02 |
573,81 |
480,59 |
||
301-600 |
754,23 |
783,04 |
829,46 |
814,80 |
630,45 |
638,03 |
716,48 |
660,84 |
632,20 |
632,71 |
750,05 |
591,96 |
— |
702,95 |
688,18 |
803,00 |
863,98 |
655,35 |
676,18 |
667,98 |
574,76 |
||
> 600 |
1 308,13 |
1 336,93 |
1 383,35 |
1 368,69 |
1 184,34 |
1 191,93 |
1 270,37 |
1 214,74 |
1 186,10 |
1 186,61 |
1 303,94 |
1 145,85 |
— |
1 256,85 |
1 242,07 |
1 356,89 |
1 417,87 |
1 209,25 |
1 230,07 |
1 221,87 |
1 128,65 |
||
Liguria |
160 |
454,43 |
542,61 |
547,82 |
419,00 |
344,06 |
426,02 |
434,85 |
— |
355,61 |
423,87 |
457,83 |
419,74 |
410,91 |
342,02 |
555,97 |
529,95 |
537,41 |
373,27 |
381,30 |
359,46 |
412,21 |
|
161-200 |
456,34 |
544,52 |
549,73 |
420,91 |
345,97 |
427,93 |
436,76 |
— |
357,52 |
425,78 |
459,74 |
421,65 |
412,82 |
343,93 |
557,88 |
531,86 |
539,32 |
375,18 |
383,21 |
361,37 |
414,12 |
||
201-249 |
532,79 |
620,97 |
626,18 |
497,36 |
422,42 |
504,38 |
513,21 |
— |
433,97 |
502,23 |
536,19 |
498,10 |
489,27 |
420,38 |
634,33 |
608,31 |
615,77 |
451,63 |
459,66 |
437,82 |
490,57 |
||
250-300 |
626,44 |
714,63 |
719,83 |
591,01 |
516,07 |
598,03 |
606,86 |
— |
527,62 |
595,88 |
629,84 |
591,75 |
582,92 |
514,04 |
727,98 |
701,96 |
709,42 |
545,28 |
553,32 |
531,47 |
584,22 |
||
301-600 |
723,92 |
812,10 |
817,31 |
688,48 |
613,55 |
695,50 |
704,33 |
— |
625,09 |
693,35 |
727,31 |
689,22 |
680,39 |
611,51 |
825,46 |
799,43 |
806,89 |
642,75 |
650,79 |
628,94 |
681,69 |
||
> 600 |
1 297,29 |
1 385,47 |
1 390,68 |
1 261,86 |
1 186,92 |
1 268,88 |
1 277,71 |
— |
1 198,47 |
1 266,73 |
1 300,69 |
1 262,59 |
1 253,76 |
1 184,88 |
1 398,83 |
1 372,81 |
1 380,27 |
1 216,13 |
1 224,16 |
1 202,32 |
1 255,07 |
||
Piemonte |
160 |
555,86 |
618,58 |
675,35 |
570,81 |
453,08 |
499,55 |
534,58 |
360,26 |
391,95 |
444,02 |
557,00 |
475,38 |
471,25 |
— |
515,34 |
511,95 |
597,64 |
471,19 |
505,77 |
341,46 |
427,04 |
|
161-200 |
557,89 |
620,60 |
677,37 |
572,83 |
455,10 |
501,57 |
536,61 |
362,28 |
393,98 |
446,05 |
559,02 |
477,40 |
473,27 |
— |
517,36 |
513,98 |
599,66 |
473,22 |
507,80 |
343,49 |
429,07 |
||
201-249 |
638,90 |
701,61 |
758,38 |
653,84 |
536,11 |
582,58 |
617,62 |
443,29 |
474,98 |
527,06 |
640,03 |
558,41 |
554,28 |
— |
598,37 |
594,99 |
680,67 |
554,22 |
588,81 |
424,50 |
510,08 |
||
250-300 |
738,13 |
800,85 |
857,61 |
753,07 |
635,35 |
681,82 |
716,85 |
542,52 |
574,22 |
626,29 |
739,26 |
657,65 |
653,52 |
— |
697,61 |
694,22 |
779,90 |
653,46 |
688,04 |
523,73 |
609,31 |
||
301-600 |
841,42 |
904,13 |
960,90 |
856,36 |
738,63 |
785,10 |
820,14 |
645,81 |
677,50 |
729,58 |
842,55 |
760,93 |
756,80 |
— |
800,89 |
797,51 |
883,19 |
756,74 |
791,33 |
627,02 |
712,60 |
||
> 600 |
1 448,98 |
1 511,69 |
1 568,46 |
1 463,92 |
1 346,19 |
1 392,66 |
1 427,69 |
1 253,37 |
1 285,06 |
1 337,13 |
1 450,11 |
1 368,49 |
1 364,36 |
— |
1 408,45 |
1 405,07 |
1 490,75 |
1 364,30 |
1 398,88 |
1 234,57 |
1 320,15 |
||
Lombardia |
160 |
693,90 |
701,15 |
801,67 |
683,03 |
553,99 |
560,78 |
662,66 |
510,97 |
— |
569,83 |
685,07 |
558,51 |
537,63 |
529,08 |
641,15 |
640,67 |
796,23 |
574,36 |
546,06 |
520,54 |
530,21 |
|
161-200 |
696,78 |
704,03 |
804,55 |
685,92 |
556,87 |
563,66 |
665,54 |
513,85 |
— |
572,72 |
687,95 |
561,40 |
540,51 |
531,96 |
644,03 |
643,56 |
799,12 |
577,24 |
548,94 |
523,42 |
533,10 |
||
201-249 |
812,07 |
819,32 |
919,84 |
801,21 |
672,16 |
678,95 |
780,83 |
629,14 |
— |
688,01 |
803,24 |
676,69 |
655,80 |
647,26 |
759,32 |
758,85 |
914,41 |
692,54 |
664,24 |
638,71 |
648,39 |
||
250-300 |
953,31 |
960,55 |
1 061,07 |
942,44 |
813,39 |
820,18 |
922,06 |
770,37 |
— |
829,24 |
944,48 |
817,92 |
797,03 |
788,49 |
900,55 |
900,08 |
1 055,64 |
833,77 |
805,47 |
779,94 |
789,62 |
||
301-600 |
1 100,30 |
1 107,55 |
1 208,07 |
1 089,43 |
960,39 |
967,18 |
1 069,06 |
917,37 |
— |
976,23 |
1 091,47 |
964,91 |
944,03 |
935,48 |
1 047,55 |
1 047,07 |
1 202,63 |
980,76 |
952,46 |
926,94 |
936,61 |
||
> 600 |
1 964,98 |
1 972,23 |
2 072,75 |
1 954,11 |
1 825,07 |
1 831,86 |
1 933,74 |
1 782,05 |
— |
1 840,91 |
1 956,15 |
1 829,59 |
1 808,71 |
1 800,16 |
1 912,23 |
1 911,75 |
2 067,31 |
1 845,44 |
1 817,14 |
1 791,61 |
1 801,29 |
||
Veneto |
160 |
499,08 |
556,36 |
601,42 |
462,97 |
360,53 |
334,49 |
462,41 |
403,54 |
366,19 |
367,32 |
491,61 |
393,36 |
316,15 |
400,15 |
461,84 |
545,70 |
600,51 |
392,22 |
422,28 |
452,16 |
— |
|
161-200 |
500,94 |
558,22 |
603,27 |
464,83 |
362,38 |
336,35 |
464,26 |
405,40 |
368,04 |
369,18 |
493,47 |
395,21 |
318,01 |
402,00 |
463,70 |
547,56 |
602,37 |
394,08 |
424,13 |
454,02 |
— |
||
201-249 |
575,22 |
632,50 |
677,56 |
539,11 |
436,67 |
410,63 |
538,55 |
479,68 |
442,33 |
443,46 |
567,75 |
469,50 |
392,29 |
476,29 |
537,98 |
621,84 |
676,65 |
468,36 |
498,42 |
528,30 |
— |
||
250-300 |
666,22 |
723,50 |
768,56 |
630,11 |
527,67 |
501,63 |
629,55 |
570,68 |
533,33 |
534,46 |
658,75 |
560,49 |
483,29 |
567,29 |
628,98 |
712,84 |
767,65 |
559,36 |
589,42 |
619,30 |
— |
||
301-600 |
760,93 |
818,21 |
863,27 |
724,82 |
622,38 |
596,34 |
724,26 |
665,39 |
628,04 |
629,17 |
753,46 |
655,21 |
578,00 |
662,00 |
723,69 |
807,55 |
862,36 |
654,07 |
684,13 |
714,01 |
— |
||
> 600 |
1 318,06 |
1 375,34 |
1 420,39 |
1 281,95 |
1 179,51 |
1 153,47 |
1 281,39 |
1 222,52 |
1 185,17 |
1 186,30 |
1 310,59 |
1 212,33 |
1 135,13 |
1 219,13 |
1 280,82 |
1 364,68 |
1 419,49 |
1 211,20 |
1 241,26 |
1 271,14 |
— |
||
Friuli Venezia Giulia |
160 |
577,72 |
616,26 |
655,77 |
653,62 |
406,84 |
— |
464,57 |
471,59 |
450,99 |
514,38 |
570,24 |
454,61 |
433,67 |
526,89 |
592,49 |
630,50 |
676,37 |
421,56 |
513,87 |
480,42 |
388,73 |
|
161-200 |
579,91 |
618,46 |
657,96 |
655,81 |
409,04 |
— |
466,77 |
473,79 |
453,18 |
516,58 |
572,44 |
456,81 |
435,86 |
529,08 |
594,68 |
632,70 |
678,57 |
423,75 |
516,07 |
482,62 |
390,92 |
||
201-249 |
667,75 |
706,30 |
745,81 |
743,66 |
496,88 |
— |
554,61 |
561,63 |
541,03 |
604,42 |
660,28 |
544,65 |
523,71 |
616,93 |
682,53 |
720,54 |
766,41 |
511,60 |
603,91 |
570,46 |
478,77 |
||
250-300 |
775,36 |
813,91 |
853,41 |
851,26 |
604,49 |
— |
662,22 |
669,24 |
648,63 |
712,03 |
767,89 |
652,26 |
631,32 |
724,54 |
790,13 |
828,15 |
874,02 |
619,20 |
711,52 |
678,07 |
586,37 |
||
301-600 |
887,36 |
925,91 |
965,41 |
963,26 |
716,49 |
— |
774,22 |
781,24 |
760,63 |
824,03 |
879,89 |
764,26 |
743,31 |
836,54 |
902,13 |
940,15 |
986,02 |
731,20 |
823,52 |
790,07 |
698,37 |
||
> 600 |
1 546,18 |
1 584,73 |
1 624,24 |
1 622,09 |
1 375,31 |
— |
1 433,04 |
1 440,06 |
1 419,46 |
1 482,85 |
1 538,71 |
1 423,08 |
1 402,14 |
1 495,36 |
1 560,96 |
1 598,97 |
1 644,84 |
1 390,03 |
1 482,34 |
1 448,89 |
1 357,20 |
No. of training hours |
Abruzzo |
Basilicata |
Calabria |
Campania |
Emilia Romagna |
Friuli Venezia Giulia |
Lazio |
Liguria |
Lombardia |
Marche |
Molise |
PA Bolzano |
PA Trento |
Piemonte |
Puglia |
Sardegna |
Sicilia |
Toscana |
Umbria |
Valle d'Aosta |
Veneto |
||
Region where the training is taking place |
Emilia Romagna |
160 |
562,62 |
596,13 |
664,95 |
573,49 |
— |
450,10 |
525,95 |
432,89 |
487,46 |
456,89 |
555,15 |
476,14 |
469,35 |
523,68 |
535,00 |
583,58 |
686,69 |
448,97 |
446,71 |
541,11 |
458,03 |
161-200 |
565,09 |
598,60 |
667,42 |
575,96 |
— |
452,57 |
528,41 |
435,36 |
489,92 |
459,36 |
557,62 |
478,60 |
471,81 |
526,15 |
537,47 |
586,04 |
689,16 |
451,44 |
449,17 |
543,58 |
460,49 |
||
201-249 |
663,75 |
697,25 |
766,08 |
674,61 |
— |
551,23 |
627,07 |
534,02 |
588,58 |
558,02 |
656,28 |
577,26 |
570,47 |
624,81 |
636,13 |
684,70 |
787,81 |
550,09 |
547,83 |
642,24 |
559,15 |
||
250-300 |
784,60 |
818,11 |
886,94 |
795,47 |
— |
672,08 |
747,93 |
654,88 |
709,44 |
678,87 |
777,13 |
698,12 |
691,33 |
745,66 |
756,98 |
805,56 |
908,67 |
670,95 |
668,69 |
763,10 |
680,01 |
||
301-600 |
910,39 |
943,90 |
1 012,73 |
921,26 |
— |
797,87 |
873,72 |
780,67 |
835,23 |
804,66 |
902,92 |
823,91 |
817,12 |
871,45 |
882,77 |
931,35 |
1 034,46 |
796,74 |
794,48 |
888,88 |
805,80 |
||
> 600 |
1 650,33 |
1 683,84 |
1 752,66 |
1 661,20 |
— |
1 537,81 |
1 613,65 |
1 520,60 |
1 575,16 |
1 544,60 |
1 642,86 |
1 563,84 |
1 557,05 |
1 611,39 |
1 622,71 |
1 671,28 |
1 774,40 |
1 536,68 |
1 534,41 |
1 628,82 |
1 545,73 |
||
Toscana |
160 |
448,73 |
556,73 |
618,76 |
540,88 |
434,47 |
450,32 |
479,75 |
447,60 |
493,34 |
488,24 |
506,69 |
491,07 |
479,75 |
527,30 |
592,95 |
569,54 |
654,08 |
— |
416,36 |
549,26 |
475,22 |
|
161-200 |
451,11 |
559,10 |
621,14 |
543,26 |
436,85 |
452,70 |
482,13 |
449,98 |
495,71 |
490,62 |
509,07 |
493,45 |
482,13 |
529,67 |
595,33 |
571,92 |
656,46 |
— |
418,74 |
551,63 |
477,60 |
||
201-249 |
546,14 |
654,14 |
716,17 |
638,29 |
531,88 |
547,73 |
577,16 |
545,01 |
590,75 |
585,65 |
604,10 |
588,48 |
577,16 |
624,71 |
690,36 |
666,95 |
751,49 |
— |
513,77 |
646,67 |
572,63 |
||
250-300 |
662,56 |
770,55 |
832,59 |
754,71 |
648,30 |
664,15 |
693,58 |
661,43 |
707,16 |
702,07 |
720,52 |
704,90 |
693,58 |
741,12 |
806,78 |
783,37 |
867,91 |
— |
630,19 |
763,08 |
689,05 |
||
301-600 |
783,73 |
891,72 |
953,76 |
875,87 |
769,47 |
785,31 |
814,75 |
782,60 |
828,33 |
823,24 |
841,69 |
826,07 |
814,75 |
862,29 |
927,95 |
904,54 |
989,07 |
— |
751,35 |
884,25 |
810,22 |
||
> 600 |
1 496,48 |
1 604,48 |
1 666,51 |
1 588,63 |
1 482,22 |
1 498,07 |
1 527,50 |
1 495,35 |
1 541,08 |
1 535,99 |
1 554,44 |
1 538,82 |
1 527,50 |
1 575,04 |
1 640,70 |
1 617,29 |
1 701,83 |
— |
1 464,11 |
1 597,01 |
1 522,97 |
||
Marche |
160 |
347,07 |
385,44 |
531,24 |
457,95 |
350,35 |
451,10 |
358,27 |
406,16 |
396,76 |
— |
364,05 |
372,99 |
365,07 |
408,08 |
395,63 |
539,29 |
504,30 |
396,20 |
332,01 |
488,34 |
358,27 |
|
161-200 |
348,87 |
387,24 |
533,04 |
459,75 |
352,15 |
452,90 |
360,07 |
407,96 |
398,56 |
— |
365,85 |
374,79 |
366,87 |
409,88 |
397,43 |
541,09 |
506,10 |
398,00 |
333,81 |
490,14 |
360,07 |
||
201-249 |
420,89 |
459,27 |
605,07 |
531,77 |
424,17 |
524,92 |
432,10 |
479,98 |
470,59 |
— |
437,87 |
446,81 |
438,89 |
481,91 |
469,45 |
613,12 |
578,13 |
470,02 |
405,83 |
562,16 |
432,10 |
||
250-300 |
509,12 |
547,49 |
693,29 |
620,00 |
512,40 |
613,15 |
520,32 |
568,21 |
558,81 |
— |
526,10 |
535,04 |
527,12 |
570,13 |
557,68 |
701,34 |
666,35 |
558,25 |
494,06 |
650,39 |
520,32 |
||
301-600 |
600,95 |
639,32 |
785,12 |
711,83 |
604,23 |
704,98 |
612,15 |
660,04 |
650,64 |
— |
617,93 |
626,87 |
618,95 |
661,96 |
649,51 |
793,17 |
758,18 |
650,08 |
585,89 |
742,22 |
612,15 |
||
> 600 |
1 141,12 |
1 179,49 |
1 325,29 |
1 251,99 |
1 144,40 |
1 245,15 |
1 152,32 |
1 200,21 |
1 190,81 |
— |
1 158,10 |
1 167,04 |
1 159,11 |
1 202,13 |
1 189,68 |
1 333,34 |
1 298,35 |
1 190,24 |
1 126,06 |
1 282,39 |
1 152,32 |
||
Abruzzo |
160 |
— |
353,35 |
434,18 |
394,78 |
437,35 |
495,70 |
295,17 |
417,99 |
502,10 |
328,34 |
315,15 |
337,28 |
467,86 |
501,19 |
362,41 |
451,81 |
434,52 |
337,96 |
292,68 |
538,66 |
471,31 |
|
161-200 |
— |
355,04 |
435,86 |
396,47 |
439,03 |
497,39 |
296,85 |
419,67 |
503,78 |
330,02 |
316,83 |
338,96 |
469,54 |
502,88 |
364,09 |
453,50 |
436,20 |
339,64 |
294,36 |
540,35 |
472,99 |
||
201-249 |
— |
422,38 |
503,20 |
463,81 |
506,37 |
564,73 |
364,19 |
487,01 |
571,12 |
397,36 |
384,17 |
406,30 |
536,88 |
570,22 |
431,43 |
520,84 |
503,54 |
406,98 |
361,70 |
607,69 |
540,33 |
||
250-300 |
— |
504,87 |
585,69 |
546,30 |
588,86 |
647,22 |
446,68 |
569,51 |
653,61 |
479,85 |
466,66 |
488,79 |
619,37 |
652,71 |
513,92 |
603,33 |
586,03 |
489,47 |
444,19 |
690,18 |
622,82 |
||
301-600 |
— |
590,73 |
671,55 |
632,16 |
674,72 |
733,08 |
532,54 |
655,36 |
739,47 |
565,71 |
552,52 |
574,65 |
705,23 |
738,57 |
599,78 |
689,19 |
671,89 |
575,33 |
530,05 |
776,03 |
708,68 |
||
> 600 |
— |
1 095,77 |
1 176,60 |
1 137,21 |
1 179,77 |
1 238,12 |
1 037,59 |
1 160,41 |
1 244,52 |
1 070,76 |
1 057,57 |
1 079,70 |
1 210,28 |
1 243,61 |
1 104,83 |
1 194,24 |
1 176,94 |
1 080,38 |
1 035,10 |
1 281,08 |
1 213,73 |
||
Umbria |
160 |
361,45 |
480,87 |
516,31 |
489,14 |
390,20 |
500,63 |
392,46 |
413,63 |
423,03 |
382,05 |
444,88 |
465,14 |
458,57 |
519,87 |
494,91 |
549,11 |
527,63 |
374,35 |
— |
537,30 |
463,27 |
|
161-200 |
363,56 |
482,99 |
518,42 |
491,25 |
392,31 |
502,74 |
394,58 |
415,75 |
425,14 |
384,16 |
446,99 |
467,25 |
460,69 |
521,98 |
497,02 |
551,22 |
529,74 |
376,47 |
— |
539,42 |
465,38 |
||
201-249 |
448,09 |
567,52 |
602,95 |
575,78 |
476,85 |
587,27 |
479,11 |
500,28 |
509,67 |
468,70 |
531,52 |
551,78 |
545,22 |
606,52 |
581,56 |
635,76 |
614,27 |
461,00 |
— |
623,95 |
549,92 |
||
250-300 |
551,65 |
671,07 |
706,50 |
679,34 |
580,40 |
690,82 |
582,66 |
603,83 |
613,23 |
572,25 |
635,07 |
655,34 |
648,77 |
710,07 |
685,11 |
739,31 |
717,82 |
564,55 |
— |
727,50 |
653,47 |
||
301-600 |
659,42 |
778,85 |
814,28 |
787,11 |
688,18 |
798,60 |
690,44 |
711,61 |
721,00 |
680,03 |
742,85 |
763,12 |
756,55 |
817,85 |
792,89 |
847,09 |
825,60 |
672,33 |
— |
835,28 |
761,25 |
||
> 600 |
1 293,42 |
1 412,84 |
1 448,27 |
1 421,11 |
1 322,17 |
1 432,59 |
1 324,43 |
1 345,60 |
1 355,00 |
1 314,02 |
1 376,84 |
1 397,11 |
1 390,54 |
1 451,84 |
1 426,88 |
1 481,08 |
1 459,59 |
1 306,32 |
— |
1 469,27 |
1 395,24 |
||
Lazio |
160 |
512,01 |
554,12 |
625,21 |
585,81 |
617,51 |
599,40 |
— |
615,25 |
687,69 |
556,38 |
515,40 |
658,26 |
646,94 |
696,75 |
599,40 |
642,84 |
624,30 |
585,81 |
540,53 |
716,50 |
651,47 |
|
161-200 |
515,05 |
557,16 |
628,25 |
588,85 |
620,55 |
602,44 |
— |
618,28 |
690,73 |
559,42 |
518,44 |
661,30 |
649,98 |
699,79 |
602,44 |
645,88 |
627,34 |
588,85 |
543,57 |
719,54 |
654,51 |
||
201-249 |
636,60 |
678,71 |
749,80 |
710,40 |
742,10 |
723,99 |
— |
739,83 |
812,28 |
680,97 |
639,99 |
782,85 |
771,53 |
821,34 |
723,99 |
767,43 |
748,89 |
710,40 |
665,12 |
841,09 |
776,06 |
||
250-300 |
785,49 |
827,60 |
898,69 |
859,30 |
891,00 |
872,88 |
— |
888,73 |
961,18 |
829,87 |
788,89 |
931,75 |
920,43 |
970,24 |
872,88 |
916,33 |
897,79 |
859,30 |
814,02 |
989,99 |
924,96 |
||
301-600 |
940,47 |
982,58 |
1 053,67 |
1 014,27 |
1 045,97 |
1 027,86 |
— |
1 043,71 |
1 116,15 |
984,84 |
943,86 |
1 086,72 |
1 075,40 |
1 125,21 |
1 027,86 |
1 071,31 |
1 052,76 |
1 014,27 |
968,99 |
1 144,96 |
1 079,93 |
||
> 600 |
1 852,09 |
1 894,20 |
1 965,29 |
1 925,89 |
1 957,59 |
1 939,48 |
— |
1 955,33 |
2 027,77 |
1 896,46 |
1 855,48 |
1 998,34 |
1 987,02 |
2 036,83 |
1 939,48 |
1 982,93 |
1 964,38 |
1 925,89 |
1 880,61 |
2 056,58 |
1 991,55 |
||
Campania |
160 |
452,64 |
361,17 |
417,55 |
— |
506,07 |
629,46 |
426,83 |
440,41 |
549,08 |
497,07 |
348,49 |
598,89 |
586,27 |
573,99 |
416,41 |
517,43 |
440,41 |
487,96 |
478,22 |
580,21 |
493,05 |
|
161-200 |
454,68 |
363,22 |
419,59 |
— |
508,11 |
631,50 |
428,87 |
442,46 |
551,13 |
499,11 |
350,54 |
600,94 |
588,32 |
576,03 |
418,46 |
519,48 |
442,46 |
490,00 |
480,27 |
582,26 |
495,10 |
||
201-249 |
536,49 |
445,02 |
501,39 |
— |
589,92 |
713,30 |
510,68 |
524,26 |
632,93 |
580,92 |
432,34 |
682,74 |
670,12 |
657,84 |
500,26 |
601,28 |
524,26 |
571,80 |
562,07 |
664,06 |
576,90 |
||
250-300 |
636,69 |
545,23 |
601,60 |
— |
690,13 |
813,51 |
610,89 |
624,47 |
733,14 |
681,13 |
532,55 |
782,95 |
770,33 |
758,05 |
600,47 |
701,49 |
624,47 |
672,01 |
662,28 |
764,27 |
677,11 |
||
301-600 |
740,99 |
649,53 |
705,90 |
— |
794,42 |
917,81 |
715,18 |
728,77 |
837,44 |
785,42 |
636,85 |
887,25 |
874,63 |
862,34 |
704,77 |
805,79 |
728,77 |
776,31 |
766,58 |
868,57 |
781,41 |
||
> 600 |
1 354,52 |
1 263,05 |
1 319,43 |
— |
1 407,95 |
1 531,34 |
1 328,71 |
1 342,29 |
1 450,96 |
1 398,95 |
1 250,37 |
1 500,77 |
1 488,15 |
1 475,87 |
1 318,29 |
1 419,31 |
1 342,29 |
1 389,84 |
1 380,10 |
1 482,09 |
1 394,93 |
||
Molise |
160 |
354,06 |
339,51 |
393,85 |
329,55 |
468,79 |
527,14 |
337,48 |
460,30 |
532,18 |
384,23 |
— |
504,33 |
502,58 |
541,24 |
378,57 |
494,12 |
448,75 |
434,83 |
415,02 |
567,78 |
502,75 |
|
161-200 |
355,99 |
341,44 |
395,78 |
331,48 |
470,71 |
529,07 |
339,40 |
462,22 |
534,11 |
386,15 |
— |
506,26 |
504,50 |
543,16 |
380,49 |
496,05 |
450,68 |
436,75 |
416,94 |
569,71 |
504,67 |
||
201-249 |
433,05 |
418,51 |
472,84 |
408,55 |
547,78 |
606,14 |
416,47 |
539,29 |
611,17 |
463,22 |
— |
583,33 |
581,57 |
620,23 |
457,56 |
573,12 |
527,75 |
513,82 |
494,01 |
646,78 |
581,74 |
||
250-300 |
527,46 |
512,92 |
567,25 |
502,95 |
642,19 |
700,54 |
510,88 |
633,70 |
705,58 |
557,63 |
— |
677,73 |
675,98 |
714,64 |
551,97 |
667,52 |
622,15 |
608,23 |
588,42 |
741,18 |
676,15 |
||
301-600 |
625,72 |
611,18 |
665,51 |
601,21 |
740,45 |
798,81 |
609,14 |
731,96 |
803,84 |
655,89 |
— |
776,00 |
774,24 |
812,90 |
650,23 |
765,78 |
720,41 |
706,49 |
686,68 |
839,44 |
774,41 |
||
> 600 |
1 203,73 |
1 189,18 |
1 243,52 |
1 179,22 |
1 318,46 |
1 376,81 |
1 187,14 |
1 309,97 |
1 381,85 |
1 233,90 |
— |
1 354,00 |
1 352,25 |
1 390,90 |
1 228,24 |
1 343,79 |
1 298,42 |
1 284,50 |
1 264,69 |
1 417,45 |
1 352,42 |
No. of training hours |
Abruzzo |
Basilicata |
Calabria |
Campania |
Emilia Romagna |
Friuli Venezia Giulia |
Lazio |
Liguria |
Lombardia |
Marche |
Molise |
PA Bolzano |
PA Trento |
Piemonte |
Puglia |
Sardegna |
Sicilia |
Toscana |
Umbria |
Valle d'Aosta |
Veneto |
||
Region where the training is taking place |
Basilicata |
160 |
320,95 |
— |
308,39 |
270,92 |
438,46 |
501,85 |
304,88 |
473,77 |
476,94 |
334,31 |
268,20 |
472,98 |
464,27 |
531,51 |
292,43 |
461,14 |
351,29 |
413,55 |
379,71 |
508,07 |
496,19 |
161-200 |
322,44 |
— |
309,87 |
272,40 |
439,94 |
503,33 |
306,36 |
475,26 |
478,43 |
335,79 |
269,68 |
474,46 |
465,75 |
532,99 |
293,91 |
462,62 |
352,77 |
415,03 |
381,19 |
509,56 |
497,67 |
||
201-249 |
381,68 |
— |
369,11 |
331,64 |
499,18 |
562,57 |
365,60 |
534,50 |
537,67 |
395,03 |
328,92 |
533,70 |
524,99 |
592,23 |
353,15 |
521,86 |
412,01 |
474,27 |
440,43 |
568,80 |
556,91 |
||
250-300 |
454,25 |
— |
441,68 |
404,21 |
571,75 |
635,14 |
438,17 |
607,07 |
610,23 |
467,60 |
401,49 |
606,27 |
597,56 |
664,80 |
425,72 |
594,43 |
484,58 |
546,84 |
513,00 |
641,36 |
629,48 |
||
301-600 |
529,78 |
— |
517,21 |
479,74 |
647,28 |
710,67 |
513,70 |
682,60 |
685,77 |
543,13 |
477,02 |
681,80 |
673,09 |
740,33 |
501,25 |
669,96 |
560,11 |
622,37 |
588,53 |
716,90 |
705,01 |
||
> 600 |
974,08 |
— |
961,51 |
924,04 |
1 091,58 |
1 154,97 |
958,00 |
1 126,90 |
1 130,07 |
987,43 |
921,33 |
1 126,10 |
1 117,39 |
1 184,63 |
945,55 |
1 114,26 |
1 004,41 |
1 066,67 |
1 032,83 |
1 161,20 |
1 149,31 |
||
Puglia |
160 |
372,30 |
334,71 |
348,30 |
368,45 |
419,61 |
520,36 |
392,45 |
529,42 |
459,23 |
386,79 |
349,54 |
417,35 |
411,69 |
470,55 |
— |
558,67 |
426,86 |
492,06 |
436,03 |
554,83 |
443,95 |
|
161-200 |
374,04 |
336,46 |
350,04 |
370,19 |
421,36 |
522,11 |
394,19 |
531,16 |
460,98 |
388,53 |
351,29 |
419,09 |
413,43 |
472,30 |
— |
560,41 |
428,60 |
493,81 |
437,77 |
556,58 |
445,70 |
||
201-249 |
443,85 |
406,27 |
419,85 |
440,00 |
491,17 |
591,92 |
464,00 |
600,97 |
530,79 |
458,34 |
421,10 |
488,91 |
483,25 |
542,11 |
— |
630,22 |
498,41 |
563,62 |
507,58 |
626,39 |
515,51 |
||
250-300 |
529,37 |
491,79 |
505,37 |
525,52 |
576,69 |
677,44 |
549,52 |
686,49 |
616,31 |
543,86 |
506,62 |
574,42 |
568,76 |
627,63 |
— |
715,74 |
583,93 |
649,14 |
593,10 |
711,91 |
601,03 |
||
301-600 |
618,38 |
580,80 |
594,38 |
614,53 |
665,70 |
766,45 |
638,53 |
775,50 |
705,32 |
632,87 |
595,63 |
663,43 |
657,77 |
716,64 |
— |
804,75 |
672,94 |
738,15 |
682,11 |
800,92 |
690,04 |
||
> 600 |
1 141,97 |
1 104,38 |
1 117,97 |
1 138,12 |
1 189,28 |
1 290,03 |
1 162,11 |
1 299,09 |
1 228,90 |
1 156,45 |
1 119,21 |
1 187,02 |
1 181,36 |
1 240,22 |
— |
1 328,34 |
1 196,53 |
1 261,73 |
1 205,70 |
1 324,50 |
1 213,62 |
||
Calabria |
160 |
447,87 |
354,48 |
— |
373,38 |
553,37 |
587,45 |
422,06 |
525,07 |
623,56 |
526,20 |
368,63 |
568,09 |
556,77 |
634,37 |
352,10 |
563,61 |
358,67 |
521,68 |
461,23 |
652,37 |
587,33 |
|
161-200 |
449,64 |
356,25 |
— |
375,15 |
555,14 |
589,22 |
423,83 |
526,84 |
625,33 |
527,97 |
370,40 |
569,86 |
558,54 |
636,14 |
353,87 |
565,38 |
360,44 |
523,45 |
463,00 |
654,14 |
589,10 |
||
201-249 |
520,40 |
427,01 |
— |
445,92 |
625,90 |
659,98 |
494,59 |
597,60 |
696,09 |
598,74 |
441,16 |
640,62 |
629,30 |
706,90 |
424,64 |
636,14 |
431,20 |
594,21 |
533,76 |
724,90 |
659,86 |
||
250-300 |
607,09 |
513,70 |
— |
532,60 |
712,59 |
746,66 |
581,28 |
684,29 |
782,77 |
685,42 |
527,85 |
727,31 |
715,99 |
793,58 |
511,32 |
722,82 |
517,89 |
680,89 |
620,44 |
811,58 |
746,55 |
||
301-600 |
697,31 |
603,92 |
— |
622,82 |
802,81 |
836,88 |
671,50 |
774,51 |
873,00 |
775,64 |
618,07 |
817,53 |
806,21 |
883,81 |
601,54 |
813,04 |
608,11 |
771,12 |
710,67 |
901,81 |
836,77 |
||
> 600 |
1 228,03 |
1 134,64 |
— |
1 153,54 |
1 333,53 |
1 367,61 |
1 202,22 |
1 305,23 |
1 403,72 |
1 306,36 |
1 148,79 |
1 348,25 |
1 336,93 |
1 414,53 |
1 132,26 |
1 343,77 |
1 138,83 |
1 301,84 |
1 241,39 |
1 432,53 |
1 367,49 |
||
Sicilia |
160 |
523,88 |
473,06 |
434,34 |
471,93 |
650,78 |
683,72 |
496,83 |
590,33 |
693,80 |
574,94 |
499,21 |
668,89 |
666,97 |
632,33 |
506,34 |
544,54 |
— |
632,67 |
548,22 |
709,08 |
662,10 |
|
161-200 |
526,13 |
475,30 |
436,59 |
474,17 |
653,02 |
685,96 |
499,07 |
592,57 |
696,04 |
577,18 |
501,45 |
671,14 |
669,21 |
634,57 |
508,58 |
546,79 |
— |
634,91 |
550,46 |
711,32 |
664,34 |
||
201-249 |
615,81 |
564,98 |
526,27 |
563,85 |
742,70 |
775,65 |
588,75 |
682,26 |
785,72 |
666,86 |
591,13 |
760,82 |
758,89 |
724,25 |
598,26 |
636,47 |
— |
724,59 |
640,15 |
801,00 |
754,02 |
||
250-300 |
725,67 |
674,84 |
636,13 |
673,71 |
852,56 |
885,51 |
698,61 |
792,12 |
895,58 |
776,72 |
700,99 |
870,68 |
868,75 |
834,11 |
708,12 |
746,33 |
— |
834,45 |
750,01 |
910,86 |
863,88 |
||
301-600 |
840,01 |
789,18 |
750,47 |
788,05 |
966,91 |
999,85 |
812,96 |
906,46 |
1 009,92 |
891,06 |
815,33 |
985,02 |
983,10 |
948,46 |
822,46 |
860,67 |
— |
948,80 |
864,35 |
1 025,21 |
978,23 |
||
> 600 |
1 512,62 |
1 461,79 |
1 423,08 |
1 460,66 |
1 639,52 |
1 672,46 |
1 485,57 |
1 579,07 |
1 682,53 |
1 563,67 |
1 487,94 |
1 657,63 |
1 655,71 |
1 621,07 |
1 495,08 |
1 533,28 |
— |
1 621,41 |
1 536,96 |
1 697,82 |
1 650,84 |
||
Sardegna |
160 |
410,58 |
452,31 |
508,68 |
418,35 |
417,07 |
507,25 |
384,77 |
452,27 |
407,64 |
479,33 |
413,98 |
501,59 |
475,39 |
416,05 |
507,55 |
— |
413,94 |
417,53 |
439,11 |
433,48 |
476,69 |
|
161-200 |
412,01 |
453,73 |
510,10 |
419,77 |
418,49 |
508,68 |
386,20 |
453,70 |
409,06 |
480,75 |
415,40 |
503,02 |
476,81 |
417,47 |
508,97 |
— |
415,37 |
418,96 |
440,53 |
434,91 |
478,11 |
||
201-249 |
469,04 |
510,76 |
567,14 |
476,80 |
475,52 |
565,71 |
443,23 |
510,73 |
466,09 |
537,78 |
472,43 |
560,05 |
533,84 |
474,50 |
566,00 |
— |
472,40 |
475,99 |
497,56 |
491,94 |
535,15 |
||
250-300 |
538,90 |
580,63 |
637,00 |
546,67 |
545,39 |
635,57 |
513,09 |
580,59 |
535,96 |
607,65 |
542,30 |
629,91 |
603,71 |
544,37 |
635,87 |
— |
542,26 |
545,85 |
567,43 |
561,80 |
605,01 |
||
301-600 |
611,61 |
653,34 |
709,71 |
619,38 |
618,10 |
708,29 |
585,80 |
653,31 |
608,67 |
680,36 |
615,01 |
702,63 |
676,42 |
617,08 |
708,58 |
— |
614,98 |
618,56 |
640,14 |
634,51 |
677,72 |
||
> 600 |
1 039,35 |
1 081,07 |
1 137,45 |
1 047,11 |
1 045,83 |
1 136,02 |
1 013,54 |
1 081,04 |
1 036,40 |
1 108,09 |
1 042,74 |
1 130,36 |
1 104,15 |
1 044,81 |
1 136,31 |
— |
1 042,71 |
1 046,30 |
1 067,87 |
1 062,25 |
1 105,46 |
3.5 Allowances for Traineeships under Transnational Mobility
Country |
Months |
SA (7) |
MA (8) |
GA (9) |
|||||
1 |
2 |
3 |
4 |
5 |
6 |
||||
Austria |
1 617 |
2 312 |
3 094 |
4 082 |
4 732 |
5 382 |
162,5 |
650,2 |
22 733 |
Belgium |
1 501 |
2 183 |
2 841 |
3 719 |
4 305 |
4 890 |
151,0 |
585,3 |
21 575 |
Bulgaria |
990 |
1 413 |
1 831 |
2 583 |
2 980 |
3 377 |
99,2 |
396,7 |
13,97 |
Cyprus |
1 342 |
1 854 |
2 499 |
3 316 |
3 957 |
4 495 |
134,5 |
538,2 |
18,94 |
Czech Republic |
1 365 |
1 876 |
2 522 |
3 369 |
4 018 |
4 564 |
136,5 |
546,17 |
19,51 |
Germany |
1 477 |
2 114 |
2 751 |
3 749 |
4 344 |
4 939 |
148,7 |
594,67 |
21,24 |
Denmark |
1 973 |
2 840 |
3 707 |
5 080,5 |
5 889 |
6 698 |
202,1 |
808,5 |
28,88 |
Estonia |
1 504 |
2 226 |
2 949 |
3 765 |
4 366 |
4 968 |
150,3 |
601,33 |
21,48 |
Spain |
1 552 |
2 199 |
2 860 |
3 894 |
4 514 |
5 133 |
154,8 |
619,17 |
22,11 |
Finland |
1 806 |
2 587 |
3 351 |
4 537 |
5 260 |
5 982 |
180,6 |
722,5 |
25,80 |
France |
1 771 |
2 533 |
3 295 |
4 451 |
5 162 |
5 873 |
177,8 |
711 |
25,39 |
United Kingdom |
1 972 |
2 820 |
3 668 |
4 950 |
5 737 |
6 525 |
196,9 |
787,67 |
28,13 |
Hungary |
1 255 |
1 790 |
2 324 |
3 223 |
3 727 |
4 231 |
126,1 |
504,33 |
18,01 |
Greece |
1 402 |
2 000 |
2 598 |
3 674 |
4 251 |
4 828 |
144,2 |
576,83 |
20,60 |
Ireland |
1 788 |
2 559 |
3 330 |
4 493 |
5 210 |
5 927 |
179,3 |
717,3 |
25,62 |
Iceland |
1 614 |
2 312 |
3 011 |
4 062 |
4 710 |
5 358 |
162 |
648 |
23,14 |
Liechenstein |
1 978 |
2 817 |
3 656 |
4 968 |
5 758 |
6 547 |
197,4 |
789,5 |
28,20 |
Lithuania |
1 145 |
1 639 |
2 133 |
2 912 |
3 420 |
3 882 |
115,6 |
462,3 |
16,51 |
Luxembourg |
1 501 |
2 148 |
2 794 |
3 802 |
4 406 |
5 010 |
151 |
604 |
21,57 |
Latvia |
1 204 |
1 721 |
2 238 |
3 104 |
3 589 |
4 074 |
121,2 |
484,8 |
17,32 |
Malta |
1 315 |
1 883 |
2 452 |
3 362 |
3 891 |
4 420 |
132,3 |
529 |
18,89 |
Netherlands |
1 597 |
2 350 |
3 058 |
4 144 |
4 805 |
5 466 |
165,3 |
661,2 |
23,61 |
Norway |
2 129 |
3 035 |
3 942 |
5 341 |
6 189 |
7 036 |
211,9 |
847,7 |
30,27 |
Poland |
1 232 |
1 758 |
2 284 |
3 174 |
3 669 |
4 165 |
123,9 |
495,5 |
17,70 |
Portugal |
1 371 |
1 959 |
2 548 |
3 492 |
4 041 |
4 591 |
137,4 |
549,5 |
19,63 |
Romania |
1 056 |
1 507 |
1 958 |
2 745 |
3 170 |
3 596 |
106,3 |
425,3 |
15,19 |
Sweden |
1 771 |
2 533 |
3 288 |
4 452 |
5 161 |
5 871 |
177,3 |
709,3 |
25,33 |
Slovenia |
1 363 |
1 945 |
2 526 |
3 465 |
4 011 |
4 556 |
136,3 |
545,3 |
19,48 |
Slovakia |
1 293 |
1 850 |
2 408 |
3 308 |
3 827 |
4 346 |
129,8 |
519,2 |
18,54 |
Turkey |
1 194 |
1 706 |
2 218 |
3 071 |
3 552 |
4 033 |
120,3 |
481 |
17,18 |
Switzerland |
1 879 |
2 579 |
3 279 |
4 670 |
5 370 |
6 070 |
175,0 |
700,0 |
25,00 |
Croatia |
1 157 |
1 589 |
2 021 |
2 953 |
3 385 |
3 817 |
108 |
432 |
15,43 |
3.6 Allowance for interview(s)
Place or country of Destination |
Distance (KM) |
Amount (EUR) |
|
Travel and Accommodation |
Daily Subsistence Allowance (DSA) |
||
Any EU-28 and EFTA/EEA country (Iceland and Norway) |
0 - 50 |
0 |
50/day (> 12 hours) 25/ Day (> 6 - 12 hours) Max 3 Days |
> 50 - 250 |
100 |
||
> 250 - 500 |
250 |
||
> 500 |
350 |
3.7 Allowance to move to another Member State (work placement)
Country of Destination |
Amount (EUR) |
Austria |
1 025 |
Belgium |
970 |
Bulgaria |
635 |
Croatia |
675 |
Cyprus |
835 |
Czech Republic |
750 |
Denmark |
1 270 |
Estonia |
750 |
Finland |
1 090 |
France |
1 045 |
Germany |
940 |
Greece |
910 |
Hungary |
655 |
Iceland |
945 |
Ireland |
1 015 |
Italy |
995 |
Latvia |
675 |
Lithuania |
675 |
Luxembourg |
970 |
Malta |
825 |
Netherlands |
950 |
Norway |
1 270 |
Poland |
655 |
Portugal |
825 |
Romania |
635 |
Slovakia |
740 |
Slovenia |
825 |
Spain |
890 |
Sweden |
1 090 |
United Kingdom |
1 060 |
‘ANNEX VII
Conditions for reimbursement of expenditure on the basis of standard scales of unit costs to Slovakia
1. Definition of standard scales of unit costs
Type of operations |
Indicators name |
Category of costs |
Measurement unit for the indicators |
Amounts (in EUR) |
|||||||
|
45-minute period of foreign language training per employee |
|
Number of completed 45-minute periods per employee. |
8,53 |
|||||||
|
ECDL certification |
|
Number of ECDL certificates awarded, differentiated by profile and module (10) |
Certificate Name |
Price |
||||||
ECDL Profile — 1 Base/Standard exam |
31,50 |
||||||||||
ECDL Profile — 2 Base/Standard exams |
59,00 |
||||||||||
ECDL Profile — 3 Base/Standard exams |
76,50 |
||||||||||
ECDL Profile — 4 Base/Standard exams |
92,00 |
||||||||||
ECDL Profile — 5 Base/Standard exams |
111,50 |
||||||||||
ECDL Profile — 6 Base/Standard exams |
127,00 |
||||||||||
ECDL Profile — 7 Base/Standard exams |
142,50 |
||||||||||
ECDL Profile — 8 Base/Standard exams |
163,00 |
||||||||||
ECDL Profile — 1 Advanced exam |
39,10 |
||||||||||
ECDL Profile — 2 Advanced exams |
74,30 |
||||||||||
ECDL Profile — 3 Advanced exams |
99,40 |
||||||||||
ECDL Profile — 4 Advanced exams |
122,50 |
||||||||||
|
Creation and occupation of new posts in inclusive teams |
|
Number of months during which a newly created post in an inclusive team is occupied |
School psychologist — 1 235 per month Special pedagogue/social pedagogue — 1 440 per month |
|||||||
|
Creation and occupation of new posts for pedagogical assistants |
|
Number of months during which a newly created post for a pedagogical assistant is occupied |
1 005 per month |
2. Adjustment of amounts
Not Applicable.
‘ANNEX VIII
Conditions for reimbursement of expenditure on the basis of standard scales of unit costs to Germany
1. Definition of standard scales of unit costs
Type of operations |
Indicators name |
Category of costs |
Measurement unit for the indicators |
Amounts (in EUR) |
||||||||||
|
Participants who successfully complete the training. |
All eligible costs (personnel costs, other direct and indirect costs). |
Number of participants who:
|
4 702,60 |
||||||||||
|
Participants who attend the workshop on inclusive school development. |
All eligible costs (personnel costs, other direct and indirect costs). |
Number of participants who have participated in the eight-hour workshop and have received a certificate on this basis. |
33,32 |
||||||||||
|
Participants who successfully complete the training. |
All eligible costs (personnel costs, other direct and indirect costs). |
Number of participants who:
|
11 474,14 |
||||||||||
|
Participants who successfully complete the training. |
All eligible costs (personnel costs, other direct and indirect costs). |
Number of participants who:
|
1 698,24 |
||||||||||
|
Participants who successfully complete the training. |
All eligible costs (personnel costs, other direct and indirect costs). |
Number of participants who:
|
246,20 |
||||||||||
|
Participants who successfully complete the training. |
All eligible costs (personnel costs, other direct and indirect costs). |
Number of participants who:
|
14 678,40 |
||||||||||
|
Participants who successfully complete the training. |
All eligible costs (personnel costs, other direct and indirect costs). |
Number of participants who:
|
7 268,34 |
||||||||||
|
Participants who successfully complete the training. |
All eligible costs (personnel costs, other direct and indirect costs). |
Number of participants who:
|
14 105,51 |
2. Adjustment of amounts
Not applicable.
‘ANNEX IX
Conditions for reimbursement of expenditure on the basis of standard scales of unit costs to the Netherlands
1. Definition of standard scales of unit costs
Type of operations |
Indicators name |
Category of costs |
Measurement unit for the indicators |
Amounts (in EUR) |
||
|
Calendar days of participation of a detainee during the period of intervention (11), in the sector Prison Services (GW). |
All eligible costs (personnel costs, other direct and indirect costs). |
Number of calendar days of participation of a detainee in the period of intervention |
14,50 |
||
|
Calendar days of participation of a detainee during the period of intervention in the sector forensic care (Forzo) |
All eligible costs (personnel costs, other direct and indirect costs). |
Number of calendar days of participation of a detainee in the period of intervention. |
21,00 |
||
|
Calendar days of participation of a juvenile offender and a young person during the period of intervention in the sector Juvenile offenders and youth in custodial institutions under civil law (JI) |
All eligible costs (personnel costs, other direct and indirect costs). |
Number of calendar days of participation of a juvenile offender and a young person in the period of intervention. |
26,50 |
2. Adjustment of amounts
The amounts of standard scales of unit costs (SCO) set out for types of operation 1 to 3 shall be adjusted yearly in line with the Dutch consumer price index (CPI): https://www.cbs.nl/nl-nl/conversie/uitgelicht/de-consumentenprijsindex. Index figures can be found on CBS Statline.
The first indexation shall be calculated in 2017. The baseline year for the amounts of SCO set out in this annex is 2015. (CPI 2015 = 100).
Every year (N), as from 2017, the amounts shall be indexed by applying the CPI of the year N-1 with the year 2015 as baseline. The following formula shall be used for calculating the amounts of SCO to be applied in a given year:
SCO amounts in year N = SCO amounts included in this annex * CPI in year N-1 (with baseline 2015 = 100)/100
(1) As defined in Regulation (EU) No 651/2014.
(2) For unit cost number 3 relating to training for self-employment and self-entrepreneurship, the amount will be reimbursed only in the case of group formation of 4 or more students.
(3) The definition of the classes is in accordance with the provisions of Ministerial Circular no. 2 of 2 February 2009. This Circular defines the classes according to the type of teachers providing training.
(4) The young person will be profiled according to one of the four classes (low, medium, high, very high) provided on the basis of the following variables:
— |
Age; |
— |
Gender; |
— |
Education; |
— |
Employment status one year before; |
— |
Region and Province where the competent body which took in charge the young is based; |
— |
Language skills (only for non-nationals who have not obtained the educational qualification in Italy), for the evaluation of which will be used the already developed methodology for the issuance of an EC residence permit for long-term residents. |
Based on the variables identified for the young, a ‘disadvantage coefficient’ is calculated, with a value between 0 and 1.
(5) For unit cost number 8 relating to support for self-employment and self-entrepreneurship, the amount will be reimbursed only in the case of individual or individualised training (meaning a maximum of 3 students)
(6) The amounts in table 3.4 are the maximum allowance payable. Where an employer provides an allowance to cover travel, accommodation or meals, the allowance mentioned in point 3.4 will be reduced by:
— |
the amount mentioned in point 3.1 for travel (depending on location) |
— |
the amount mentioned in point 3.2 for accommodation (depending on location) |
— |
the amount mentioned in point 3.3 for meals (depending on location). |
The amounts mentioned in tables 3.1, 3.2 and 3.3. will also be payable in a situation where the beneficiary pays only the categories of allowances mentioned in those tables.
(7)
SA |
= |
Additional Week |
MA |
= |
Additional Month |
GA |
= |
Additional Day |
(10) There are two possible modules — 1) Base/Standard and 2) Advanced.