    Commission Opinion of 4 December 2017 relating to the plan for the disposal of radioactive waste arising from the dismantling of reactors 1 & 2 of the Oskarshamn Nuclear Power Plant, located in Sweden

    C/2017/7959

    OJ C 413, 5.12.2017, p. 1–2 (BG, ES, CS, DA, DE, ET, EL, EN, FR, HR, IT, LV, LT, HU, MT, NL, PL, PT, RO, SK, SL, FI, SV)

    5.12.2017   

    EN

    Official Journal of the European Union

    C 413/1


    COMMISSION OPINION

    of 4 December 2017

    relating to the plan for the disposal of radioactive waste arising from the dismantling of reactors 1 & 2 of the Oskarshamn Nuclear Power Plant, located in Sweden

    (Only the Swedish text is authentic)

    (2017/C 413/01)

    The assessment below is carried out under the provisions of the Euratom Treaty, without prejudice to any additional assessments to be carried out under the Treaty on the Functioning of the European Union and the obligations stemming from it and from secondary legislation (1).

    On 13 June 2017, the European Commission received from the Government of Sweden, in accordance with Article 37 of the Euratom Treaty, General Data relating to the plan for the disposal of radioactive waste (2) arising from the dismantling of reactors 1 & 2 of the Oskarshamn Nuclear Power Plant.

    On the basis of these data and additional information requested by the Commission on 10 July 2017 and provided by the Swedish authorities on 4 September 2017, and following consultation with the Group of Experts, the Commission has drawn up the following opinion:

    (1)

    The distance between the site and the nearest border with another Member State, in this case Denmark, is 260 km.

    (2)

    During normal dismantling operations the discharge of gaseous and liquid radioactive effluents are not liable to cause an exposure of the population in another Member State that would be significant from the point of view of health, in respect of the dose limits laid down in the new Basic Safety Standards Directives (3).

    (3)

    Solid radioactive waste is temporarily stored on site before shipment to licensed treatment or disposal facilities located in Sweden.

    Non-radioactive solid waste and residual materials in compliance with clearance levels will be released from regulatory control for disposal as conventional waste or for reuse or recycling. This will be done in compliance with the criteria laid down in the Basic Safety Standards Directives.

    (4)

    In the event of unplanned releases of radioactive effluents that may follow the accidents of the type and magnitude considered in the General Data, the doses likely to be received by the population of another Member State would not be significant from the point of view of health, in respect of the reference levels laid down in the Basic Safety Standards Directives.

    In conclusion, the Commission is of the opinion that the implementation of the plan for the disposal of radioactive waste in whatever form, arising from the dismantling of reactors 1 and 2 of the Oskarshamn Nuclear Power Plant located in Sweden, both in normal operation and in the event of the accidents of the type and magnitude considered in the General Data, is not liable to result in a radioactive contamination, significant from the point of view of health, of the water, soil or airspace of another Member State, in respect of the provisions laid down in the Basic Safety Standards Directives.

    Done at Brussels, 4 December 2017.

    For the Commission

    Miguel ARIAS CAÑETE

    Member of the Commission


    (1)  For instance, under the Treaty on the Functioning of the European Union, environmental aspects should be further assessed. Indicatively, the Commission would like to draw attention to the provisions of Directive 2011/92/EU on the assessment of the effects of certain public and private projects on the environment, as amended by Directive 2014/52/EU; to Directive 2001/42/EC on the assessment of the effects of certain plans and programmes on the environment, as well as to Directive 92/43/EEC on the conservation of natural habitats and of wild fauna and flora and to Directive 2000/60/EC establishing a framework for Community action in the field of water policy.

    (2)  The disposal of radioactive waste in the meaning of point 1 of Commission Recommendation 2010/635/Euratom of 11 October 2010 on the application of Article 37 of the Euratom Treaty (OJ L 279, 23.10.2010, p. 36).

    (3)  Council Directive 96/29/Euratom of 13 May 1996 laying down basic safety standards for the protection of the health of workers and the general public against the dangers arising from ionising radiation (OJ L 159, 29.6.1996, p. 1) and Council Directive 2013/59/Euratom of 5 December 2013 laying down basic safety standards for protection against the dangers arising from exposure to ionising radiation, and repealing Directives 89/618/Euratom, 90/641/Euratom, 96/29/Euratom, 97/43/Euratom and 2003/122/Euratom (OJ L 13, 17.1.2014, p. 1) with effect from 6 February 2018.